Sei sulla pagina 1di 19

CONSTRUCTION SCHEDULE

& MONITORING TOWER-1 (R.1)


ZONE-1 ZONE-2
LANTAI MASTER MASTER MASTER
PLAN INTERNAL ACTUAL PLAN INTERNAL ACTUAL
SCHEDULE SCHEDULE SCHEDULE
TYPICAL
LMR+ROOF LMR 2/24/2018 5/16/2018 3/6/2018 5/16/2018 3/10/2018

ROOF/25 2/21/2018 5/6/2018 2/23/2018 5/9/2018 2/26/2018

24 2/13/2018 4/26/2018 2/15/2018 4/29/2018 2/18/2018

23 2/5/2018 4/16/2018 2/7/2018 4/19/2018 2/10/2018

22 1/28/2018 4/6/2018 1/30/2018 4/9/2018 2/2/2018

21 1/20/2018 3/27/2018 1/22/2018 3/30/2018 1/25/2018

20 1/12/2018 3/17/2018 1/14/2018 3/20/2018 1/17/2018

19 1/4/2018 3/7/2018 1/6/2018 3/10/2018 1/9/2018

18 12/27/2017 2/25/2018 12/29/2017 2/28/2018 1/1/2018

17 12/19/2017 2/15/2018 12/21/2017 2/18/2018 12/24/2017

16 12/11/2017 2/5/2018 12/13/2017 2/8/2018 12/16/2017

15 12/3/2017 1/26/2018 12/5/2017 1/29/2018 12/8/2017

14 11/25/2017 1/16/2018 11/27/2017 1/19/2018 11/30/2017

13 11/17/2017 1/6/2018 11/19/2017 1/9/2018 11/22/2017

12 11/9/2017 12/27/2017 11/11/2017 12/30/2017 11/14/2017

11 11/1/2017 12/17/2017 11/3/2017 12/20/2017 11/6/2017

10 10/24/2017 12/7/2017 10/26/2017 12/10/2017 10/29/2017

9 10/16/2017 11/27/2017 10/18/2017 11/30/2017 10/21/2017

8 10/8/2017 11/17/2017 10/10/2017 11/20/2017 10/13/2017

7 9/29/2017 11/7/2017 10/2/2017 11/10/2017 10/5/2017

6 9/20/2017 10/28/2017 9/23/2017 10/31/2017 9/26/2017

5 9/11/2017 10/18/2017 9/14/2017 10/21/2017 9/17/2017

NON TYPICAL

4/PODIUM 9/21/2017 10/8/2017 9/26/2017 10/16/2017 10/1/2017

P4 9/8/2017 9/24/2017 9/13/2017 10/2/2017 9/18/2017


P3 8/26/2017 9/9/2017 8/31/2017 9/17/2017 9/5/2017

P2 8/13/2017 8/25/2017 8/18/2017 9/3/2017 8/23/2017

P1 7/31/2017 8/10/2017 8/5/2017 8/19/2017 8/10/2017

GF 7/18/2017 7/25/2017 7/28/2017 7/23/2017 7/27/2017 8/1/2017 7/28/2017

BASEMENT 7/5/2017 6/12/2017 6/12/2017 7/10/2017 6/26/2017 6/12/2017 7/15/2017


TION SCHEDULE
NG TOWER-1 (R.1)
ZONE-3
PLAN INTERNAL ACTUAL

5/16/2018

5/11/2018

5/1/2018

4/21/2018

4/11/2018

4/1/2018

3/22/2018

3/12/2018

3/2/2018

2/20/2018

2/10/2018

1/31/2018

1/21/2018

1/11/2018

1/1/2018

12/22/2017

12/12/2017

12/2/2017

11/22/2017

11/12/2017

11/2/2017

10/23/2017

10/19/2017

10/5/2017
9/20/2017

9/6/2017

8/22/2017

7/29/2017 8/6/2017

7/10/2017 6/12/2017
KEY DATE
TOWER 1 (R-1)
(Milestone Floor to Floor)

LANTAI ZONE - 1 ZONE 2 ZONE 3 Work Duration

Plan Actual Plan Actual Plan Actual (Days)

ROOF LMR 12-Feb-18

LMR 5-Feb-18

ROOF +90600 25-Jan-18 29-Jan-18 1-Feb-18

24th +87000 19-Jan-18 23-Jan-18 26-Jan-18

23rd +83600 13-Jan-18 17-Jan-18 20-Jan-18

22nd +80200 7-Jan-18 11-Jan-18 14-Jan-18

21st +76800 1-Jan-18 5-Jan-18 8-Jan-18

20th +73400 26-Dec-17 30-Dec-17 2-Jan-18

19th +70000 20-Dec-17 24-Dec-17 27-Dec-17

18th +66600 14-Dec-17 18-Dec-17 21-Dec-17

17th +63200 8-Dec-17 12-Dec-17 15-Dec-17

16th +59800 2-Dec-17 6-Dec-17 9-Dec-17

15th +56400 26-Nov-17 30-Nov-17 3-Dec-17

14th +53000 20-Nov-17 24-Nov-17 27-Nov-17

13rd +49600 14-Nov-17 18-Nov-17 21-Nov-17

12nd +46200 8-Nov-17 12-Nov-17 15-Nov-17

11st +42800 2-Nov-17 6-Nov-17 9-Nov-17

10th +39400 27-Oct-17 31-Oct-17 3-Nov-17

9th +36000 21-Oct-17 25-Oct-17 28-Oct-17

8th +32600 15-Oct-17 19-Oct-17 22-Oct-17

7th +29200 8-Oct-17 13-Oct-17 17-Oct-17

6th +25800 30-Sep-17 5-Oct-17 9-Oct-17

5th +22400 21-Sep-17 26-Sep-17 30-Sep-17

NON TYPICAL
4th/Podium+19000 11-Sep-17 14-Sep-17 16-Sep-17

P4 +14550 3-Sep-17 6-Sep-17 8-Sep-17

P3 +11350 26-Aug-17 26-Aug-17 29-Aug-17 31-Aug-17

P2 +8150 18-Aug-17 20-Aug-17 21-Aug-17 22-Aug-17 23-Aug-17

P1 +4950 8-Aug-17 9-Aug-17 12-Aug-17 13-Aug-17 14-Aug-17 15-Aug-17


9
GF 0.000 25-Jul-17 28-Jul-17 27-Jul-17 1-Aug-17 29-Jul-17 6-Aug-17
55
BASE -3.800
12-Jun-17
====> START PABRIKASI TABLE FORM
CONSTRUCTION SCHEDULE
& MONITORING TOWER-1 (R.1)
ZONE-1 ZONE-2
LANTAI MASTER MASTER MASTER
PLAN INTERNAL ACTUAL PLAN INTERNAL ACTUAL
SCHEDULE SCHEDULE SCHEDULE
TYPICAL
LMR + ROOF LMR 2/24/2018 3/1/2018 3/6/2018 3/6/2018 3/10/2018

ROOF/25 2/21/2018 2/22/2018 2/23/2018 2/26/2018 2/26/2018

24 2/13/2018 2/16/2018 2/15/2018 2/20/2018 2/18/2018

23 2/5/2018 2/10/2018 2/7/2018 2/14/2018 2/10/2018

22 1/28/2018 2/4/2018 1/30/2018 2/8/2018 2/2/2018

21 1/20/2018 1/29/2018 1/22/2018 2/2/2018 1/25/2018

20 1/12/2018 1/23/2018 1/14/2018 1/27/2018 1/17/2018

19 1/4/2018 1/17/2018 1/6/2018 1/21/2018 1/9/2018

18 12/27/2017 1/11/2018 12/29/2017 1/15/2018 1/1/2018

17 12/19/2017 1/5/2018 12/21/2017 1/9/2018 12/24/2017

16 12/11/2017 12/30/2017 12/13/2017 1/3/2018 12/16/2017

15 12/3/2017 12/24/2017 12/5/2017 12/28/2017 12/8/2017

14 11/25/2017 12/18/2017 11/27/2017 12/22/2017 11/30/2017

13 11/17/2017 12/12/2017 11/19/2017 12/16/2017 11/22/2017

12 11/9/2017 12/6/2017 11/11/2017 12/10/2017 11/14/2017

11 11/1/2017 11/30/2017 11/3/2017 12/4/2017 11/6/2017

10 10/24/2017 11/24/2017 10/26/2017 11/28/2017 10/29/2017

9 10/16/2017 11/17/2017 10/18/2017 11/21/2017 10/21/2017

8 10/8/2017 11/10/2017 10/10/2017 11/14/2017 10/13/2017

7 9/29/2017 11/3/2017 10/2/2017 11/7/2017 10/5/2017

6 9/20/2017 10/26/2017 9/23/2017 10/30/2017 9/26/2017

5 9/11/2017 10/17/2017 9/14/2017 10/21/2017 9/17/2017

NON TYPICAL

4/PODIUM 9/21/2017 10/8/2017 9/26/2017 10/16/2017 10/1/2017

P4 9/8/2017 9/24/2017 9/13/2017 10/2/2017 9/18/2017


P3 8/26/2017 9/9/2017 8/26/2017 8/31/2017 9/17/2017 9/5/2017

P2 8/13/2017 8/25/2017 8/19/2017 8/18/2017 9/3/2017 8/22/2017 8/23/2017

P1 7/31/2017 8/10/2017 8/8/2017 8/5/2017 8/19/2017 8/12/2017 8/10/2017

GF 7/18/2017 7/25/2017 7/28/2017 7/23/2017 7/27/2017 8/1/2017 7/28/2017

BASEMENT 7/5/2017 6/12/2017 6/12/2017 7/10/2017 6/26/2017 6/12/2017 7/15/2017


TION SCHEDULE
NG TOWER-1 (R.1)
ZONE-3
PLAN INTERNAL ACTUAL

3/10/2018

3/1/2018

2/23/2018

2/17/2018

2/11/2018

2/5/2018

1/30/2018

1/24/2018

1/18/2018

1/12/2018

1/6/2018

12/31/2017

12/25/2017

12/19/2017

12/13/2017

12/7/2017

12/1/2017

11/24/2017

11/17/2017

11/10/2017

11/2/2017

10/24/2017

10/19/2017

10/5/2017
9/20/2017

9/6/2017

8/22/2017 8/15/2017

7/29/2017 8/6/2017

7/10/2017 6/12/2017
SCHEDULE MINGGUAN
TOWER 1
PERIODE : 28 AGUST - 3 SEPTEMBER 2017
DURASI
NO ITEM PEKERJAAN Agustus September
21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8
LANTAI P2
ZONE 3
1 COR KOLOM ZONE 3 LT P1 -P2 (3 UNIT)
2 PASANG BEGISTING ZONE 3 AS T1.11-T1.12/T1.A-
3 PASANG BESI ZONE 3 AS T1.11-T1.12/T1.A-T1.C
4 COR LANTAI ZONE 3 AS T1.11-T1.12/T1.A-T1.C

LANTAI P3
ZONE 1
1 PASANG BEGISTING SLAB DAN BALOK LT P3 ZONE
2 PASANG BESI SLAB DAN BALOK LT P3 ZONE 1
3 COR LANTAI ZONE 1 AS T1.1 - T1.5 / T1.A - T1.C
4 COR KOLOM DAN SW ZONE 1 LT P3 - P4

ZONE 2 & 3
5 PASANG BEGISTING SLAB DAN BALOK LT P3 ZONE
6 PASANG BESI SLAB DAN BALOK LT P3 ZONE 2
7 COR LANTAI ZONE 2 AS T1.5 - T1.11 / T1.A - T1.
L
8 COR KOLOM DAN SW ZONE 2 LT P3 - P4
I
B
LANTAI P4 U
ZONE 1 R
1 PASANG BEGISTING SLAB DAN BALOK LT P4 ZONE
2 PASANG BESI SLAB DAN BALOK LT P4 ZONE 1
3 COR LANTAI ZONE 1 AS T1.1 - T1.5 / T1.A - T1.C
4 COR KOLOM DAN SW ZONE 1 LT P4 - PODIUM (LT

ZONE 2
5 PASANG BEGISTING SLAB DAN BALOK LT P4 ZONE
6 PASANG BESI SLAB DAN BALOK LT P4 ZONE 2
7 COR LANTAI ZONE 2 AS T1.5 - T1.10 / T1.A - T1.
8 COR KOLOM DAN SW ZONE 2 LT P4 - PODIUM (LT

ZONE 3
9 PASANG BEGISTING SLAB DAN BALOK LT P4 ZONE
10 PASANG BESI SLAB DAN BALOK LT P4 ZONE 3
11 COR LANTAI ZONE 3 AS T1.10 - T1.12 / T1.A - T1
12 COR KOLOM ZONE 3 LT P4 - PODIUM (LT 4)
CONSTRUCTION SCHEDULE
& MONITORING TOWER-1 (R.1)
ZONE-1 ZONE-2
LANTAI MASTER OWNER SCHEDULE OWNER SCHEDULE
ACTUAL
SCHEDULE SCHEDULE LAPANGAN SCHEDULE LAPANGAN
TYPICAL
LMR + ROOF LMR 2/24/2018 3/21/2018 2/12/2018 3/26/2018 2/12/2018

ROOF/25 2/21/2018 3/13/2018 1/25/2018 3/18/2018 1/29/2018

24 2/13/2018 3/6/2018 1/19/2018 3/11/2018 1/23/2018

23 2/5/2018 2/27/2018 1/13/2018 3/4/2018 1/17/2018

22 1/28/2018 2/20/2018 1/7/2018 2/25/2018 1/11/2018

21 1/20/2018 2/13/2018 1/1/2018 2/18/2018 1/5/2018

20 1/12/2018 2/6/2018 12/26/2017 2/11/2018 12/30/2017

19 1/4/2018 1/30/2018 12/20/2017 2/4/2018 12/24/2017

18 12/27/2017 1/23/2018 12/14/2017 1/28/2018 12/18/2017

17 12/19/2017 1/16/2018 12/8/2017 1/21/2018 12/12/2017

16 12/11/2017 1/9/2018 12/2/2017 1/14/2018 12/6/2017

15 12/3/2017 1/2/2018 11/26/2017 1/7/2018 11/30/2017

14 11/25/2017 12/26/2017 11/20/2017 12/31/2017 11/24/2017

13 11/17/2017 12/19/2017 11/14/2017 12/24/2017 11/18/2017

12 11/9/2017 12/12/2017 11/8/2017 12/17/2017 11/12/2017

11 11/1/2017 12/5/2017 11/2/2017 12/10/2017 11/6/2017

10 10/24/2017 11/28/2017 10/27/2017 12/3/2017 10/31/2017

9 10/16/2017 11/21/2017 10/21/2017 11/26/2017 10/25/2017

8 10/8/2017 11/13/2017 10/15/2017 11/18/2017 10/20/2017

7 9/29/2017 11/5/2017 10/8/2017 11/10/2017 10/13/2017

6 9/20/2017 10/27/2017 9/30/2017 11/1/2017 10/5/2017

5 9/11/2017 10/18/2017 9/21/2017 10/23/2017 9/26/2017


NON TYPICAL
4/PODIUM 9/21/2017 10/8/2017 9/11/2017 10/16/2017 9/14/2017

P4 9/8/2017 9/24/2017 9/3/2017 10/2/2017 9/6/2017

P3 8/26/2017 9/9/2017 8/26/2017 8/26/2017 9/17/2017 8/29/2017

P2 8/13/2017 8/25/2017 8/18/2017 8/19/2017 9/3/2017 8/21/2017

P1 7/31/2017 8/10/2017 8/9/2017 8/8/2017 8/19/2017 8/12/2017

GF 7/18/2017 7/25/2017 7/25/2017 7/28/2017 7/27/2017 7/27/2017

BASEMENT 7/5/2017 6/12/2017 6/12/2017 6/26/2017


DULE
1 (R.1)
2 ZONE-3
MASTER OWNER SCHEDULE
ACTUAL ACTUAL
SCHEDULE SCHEDULE LAPANGAN

3/10/2018 4/1/2018 2/12/2018

2/26/2018 3/22/2018 2/1/2018

2/18/2018 3/15/2018 1/26/2018

2/10/2018 3/8/2018 1/20/2018

2/2/2018 3/1/2018 1/14/2018

1/25/2018 2/22/2018 1/8/2018

1/17/2018 2/15/2018 1/2/2018

1/9/2018 2/8/2018 12/27/2017

1/1/2018 2/1/2018 12/21/2017

12/24/2017 1/25/2018 12/15/2017

12/16/2017 1/18/2018 12/9/2017

12/8/2017 1/11/2018 12/3/2017

11/30/2017 1/4/2018 11/27/2017

11/22/2017 12/28/2017 11/21/2017

11/14/2017 12/21/2017 11/15/2017

11/6/2017 12/14/2017 11/9/2017

10/29/2017 12/7/2017 11/3/2017

10/21/2017 11/30/2017 10/28/2017

10/13/2017 11/22/2017 10/23/2017

10/5/2017 11/14/2017 10/17/2017

9/26/2017 11/5/2017 10/9/2017

9/17/2017 10/28/2017 9/30/2017


10/1/2017 10/19/2017 9/16/2017

9/18/2017 10/5/2017 9/8/2017

9/5/2017 9/20/2017 8/31/2017

8/22/2017 8/23/2017 9/6/2017 8/23/2017

8/12/2017 8/10/2017 8/22/2017 8/14/2017 8/15/2017

8/1/2017 7/28/2017 7/29/2017 7/29/2017 8/6/2017

6/12/2017 7/15/2017 7/10/2017 6/12/2017


CONSTRUCTION SCHEDULE
& MONITORING TOWER-1 (R.1)
ZONE-1 ZONE-2
LANTAI
CONTRACT SCHEDULE PLAN SCHEDULE ACTUAL CONTRACT SCHEDULE PLAN SCHEDULE ACTUAL
TYPICAL
LMR + ROOF LMR 3/21/2018 8 d 3/6/2018 8 d d 3/26/2018 8 d 3/6/2018 8 d d

ROOF/25 3/13/2018 7 d 2/21/2018 7 d d 3/18/2018 7 d 2/26/2018 5 d d

24 3/6/2018 7 d 2/14/2018 7 d d 3/11/2018 7 d 2/19/2018 5 d d

23 2/27/2018 7 d 2/7/2018 7 d d 3/4/2018 7 d 2/12/2018 5 d d

22 2/20/2018 7 d 1/31/2018 7 d d 2/25/2018 7 d 2/5/2018 5 d d

21 2/13/2018 7 d 1/24/2018 7 d d 2/18/2018 7 d 1/29/2018 5 d d

20 2/6/2018 7 d 1/17/2018 7 d d 2/11/2018 7 d 1/22/2018 5 d d

19 1/30/2018 7 d 1/10/2018 7 d d 2/4/2018 7 d 1/15/2018 5 d d

18 1/23/2018 7 d 1/3/2018 7 d d 1/28/2018 7 d 1/8/2018 5 d d

17 1/16/2018 7 d 12/27/2017 7 d d 1/21/2018 7 d 1/1/2018 5 d d

16 1/9/2018 7 d 12/20/2017 7 d d 1/14/2018 7 d 12/25/2017 5 d d

15 1/2/2018 7 d 12/13/2017 7 d d 1/7/2018 7 d 12/18/2017 5 d d

14 12/26/2017 7 d 12/6/2017 7 d d 12/31/2017 7 d 12/11/2017 5 d d

13 12/19/2017 7 d 11/29/2017 7 d d 12/24/2017 7 d 12/4/2017 5 d d

12 12/12/2017 7 d 11/22/2017 7 d d 12/17/2017 7 d 11/27/2017 5 d d

11 12/5/2017 7 d 11/15/2017 7 d d 12/10/2017 7 d 11/20/2017 5 d d

10 11/28/2017 7 d 11/8/2017 7 d d 12/3/2017 7 d 11/13/2017 5 d d

9 11/21/2017 8 d 11/1/2017 8 d d 11/26/2017 8 d 11/6/2017 5 d d

8 11/13/2017 8 d 10/24/2017 8 d d 11/18/2017 8 d 10/29/2017 5 d d

7 11/5/2017 9 d 10/16/2017 9 d d 11/10/2017 9 d 10/21/2017 5 d d

6 10/27/2017 9 d 10/7/2017 9 d d 11/1/2017 9 d 10/12/2017 5 d d

5 10/18/2017 10 d 9/28/2017 10 d d 10/23/2017 7 d 10/3/2017 5 d d


NON TYPICAL
4/PODIUM 10/8/2017 14 d 9/18/2017 13 d d 10/16/2017 14 d 9/21/2017 13 d d

P4 9/24/2017 15 d 9/5/2017 10 d d 10/2/2017 15 d 9/8/2017 10 d d

P3 9/9/2017 15 d 8/26/2017 8 d 8/26/2017 6 d 9/17/2017 14 d 8/29/2017 8 d 8/30/2017 7 d

P2 8/25/2017 15 d 8/18/2017 9 d 8/20/2017 11 d 9/3/2017 15 d 8/21/2017 9 d 8/23/2017 10 d

P1 8/10/2017 16 d 8/9/2017 15 d 8/9/2017 12 d 8/19/2017 23 d 8/12/2017 16 d 8/13/2017 12 d

GF 7/25/2017 43 d 7/25/2017 0 d 7/28/2017 46 d 7/27/2017 31 d 7/27/2017 0 d 8/1/2017 50 d

BASEMENT 6/12/2017 6/12/2017 0 6/26/2017 6/12/2017


TION SCHEDULE
NG TOWER-1 (R.1)
ZONE-3

CONTRACT SCHEDULE PLAN SCHEDULE ACTUAL

4/1/2018 10 d 3/6/2018 8 d d

3/22/2018 7 d 3/2/2018 4 d d

3/15/2018 7 d 2/23/2018 4 d d

3/8/2018 7 d 2/16/2018 4 d d

3/1/2018 7 d 2/9/2018 4 d d

2/22/2018 7 d 2/2/2018 4 d d

2/15/2018 7 d 1/26/2018 4 d d

2/8/2018 7 d 1/19/2018 4 d d

2/1/2018 7 d 1/12/2018 4 d d

1/25/2018 7 d 1/5/2018 4 d d

1/18/2018 7 d 12/29/2017 4 d d

1/11/2018 7 d 12/22/2017 4 d d

1/4/2018 7 d 12/15/2017 4 d d

12/28/2017 7 d 12/8/2017 4 d d

12/21/2017 7 d 12/1/2017 4 d d

12/14/2017 7 d 11/24/2017 4 d d

12/7/2017 7 d 11/17/2017 4 d d

11/30/2017 8 d 11/10/2017 4 d d

11/22/2017 8 d 11/2/2017 4 d d

11/14/2017 9 d 10/25/2017 4 d d

11/5/2017 8 d 10/16/2017 4 d d

10/28/2017 9 d 10/7/2017 4 d d
10/19/2017 14 d 9/24/2017 13 d
d
10/5/2017 15 d 9/11/2017 5 d
d
9/20/2017 14 d 9/6/2017 14 d
d
9/6/2017 15 d 8/23/2017 9 d
d
8/22/2017 24 d 8/14/2017 16 d 16 Agust & 26 Agus 10
d
7/29/2017 19 d 7/29/2017 0 d 8/6/2017 55
d
7/10/2017 6/12/2017