Daily Activity Report

BLCP Outage 2017 Unit#1 Shutdown Project


Date of Daily Activty Report : 4/11/2017
08:00-09:00 09:00-10:00 10:00-11:00 11:00-12:00 13:00-14:00 14:00-15:00 15:00-16:00 16:00-17:00 17:00-18:00 18:00-19:00 19:00-20:00
Weather Report S S S S S S S S S S S
Remarks: Sunny : S Clouded : C Rainy :R Heavy Rains : HR

Item Last day Item Today Item Next day

Piping Activity
1 Start machine beveling support TA MHPS stub tube. 1 Machine beveling support TA MHPS stub tube 1 Fit up & weld stub tube 4 joint.

2 Continues Tube Instaiiation fit up and weld (RHS top) 2 Continues Tube Instaiiation fit up and weld (RHS top) 10 joint 2 Continues Tube Instaiiation fit up and weld (RHS top)
3 Continues cut on RH tubes inside of boiler (RHS top) 3 Continues cut on RH tubes inside of boiler (RHS top) 3 Continues cut on RH tubes inside of boiler (RHS top) 30 joint
4 Continues cut on RH tubes inside of boiler (LHS top) 4 Continues cut on RH tubes inside of boiler (LHS top) 4 Continues cut on RH tubes inside of boiler (LHS top) 20 joint
5 Tube RH fit up & weld inside boiler (LHS top) 5 Continues tube RH fit up & weld inside boiler (LHS top) 10 joint 5 Continues tube RH fit up & weld inside boiler (LHS top)
6 Continues cut on RH tubes inside of boiler (Front side Bottom) 100% 6 Preparation spare part tube laydown area & Stock tube (for fit up Tube RH LHS top) 6 Preparation spare part tube laydown area & Stock tube (for fit up Tube RH LHS top)
7 Preparation spare part tube laydown area (for fit up Tube RH LHS top) 7 Machine beveling tube RHS/LHS top. 7 Continues machine beveling tube RHS/LHS top.

Item Position Day Night Today Piping Activity Photo


MANPOWER
1 Site Engineer 1 0 1
2 QA Engineer 1 1 2
3 Safety 1 2 3
4 QA,QC Superviser 1 1 2
5 Superviser 6 2 8
6 Admin Staff 1 0 1
7 Welder 17 3 20
8 Fitter A,B 29 9 38
9 Electricain 1 2 3
10 Fire Watch 5 2 7
11 Store/General 4 0 4
12 Rigger 6 0 6
73 22 95
Piping Activity Photo
Total (Man-Day)
The TJEL manpower combine foe SPC Sub-Contact

Note : Progress Erection


Outdate information
No. Description Fit up Weld RT
7 11 11 7
1
2
RHS top (145 joints)
LHS top (145 joints) 2 7
7
2 7 2 4
0
3 Front side (297 joints) 0 0 0

Total 9 18 9 18 9 4

Note : Progress Cut tube


No. Description Joint Cut Balance
1 RHS top 145 82 63
2 LHS top 145 125 20
3 Front side 297 0 297

Total 587 207 380

Weigthtage percent Attribute calculate percent completed = [((18*0.4)+(18*0.5)+(9*0.1))/1174]*100 = 1.45%


Fit-up = 40%
Welding = 50%
RT = 10%