CALCULO DE FLETE

A) POR PESO

MATERIALES UNIDAD CANTIDAD PESO.UNIT. PESO.TOTAL


CEMENTO BL. 2,922.00 42.50 124,185.00
ALAMBRES,FIERRO, CLAV. ETC KG 4,631.00 1.00 4,631.00
MADERA P2 96,842.00 1.50 145,263.00
CLAVO GALVANIZADO, PERNO UN 345.00 0.10 34.50
LADRILLO KG 94,348.80 0.51 48,117.89
YESO BL 1,590.00 20.00 31,800.00
PINTURA, IMPERM GAL 37.00 4.50 166.50
TRIPLAY KG 8.00 10.00 80.00
SEALES PREVENTIVAS KG 20.00 15.00 300.00
OTROS KG 84,305.00 32.65 2,752,558.25
PESO TOTAL 3,107,136.14

B) POR VOLUMEN

VOLQUETE 6X4
CAPACIDAD
15 M3

EN AGREGADOS
DESCRIPC. UNIDAD CANTIDAD SIN IGV
ARENA GRUESA M3 140.18 42.95
ARENA FINA M3 19.48 55.08
PIEDRA CHANCADA 1/2" M3 180.67 46.61
PIEDRA MEDIANA M3 11.75 44.92
PIEDRA GRANDE P/ZANJA M3 62.85 49.15
TIERRA DE CHACRA M3 1.40 31.20
HORMIGON M3 155.61 59.32

VOLUMEN TOTAL 416.70 270.05


CAPACIDAD DEL CAMION (M3) 6.00
NUMERO DE VIAJES 45.01
REDONDEO 45.01
EN TUBERIA
UNIDAD DE (2.20 M. x 3.00 M.) DE CARROCERIA, CON H= 1.50 M.
CAPACIDAD DEL CAMION EN TUBOS / VIAJE ML N de tubos N VIAJES
TUB PVC SAP PARA DESAGUE UND 5,040.00 38.00 0.01
CODO PVC SAL UND 3,360.00 310.00 0.09
TEE PVC SAP UND 1,690.00 24.00 0.01
TRAMPA "P" PVC UND 994.00 262.00 0.26
YEE PVC UND 470.00 274.00 0.58
TUBERIA ELECTRICA UND 259.00 89.00 0.34
TUBERIA PVC-SEL 3/4 UND 110.00 7.00 0.06
CURVAS PVC-SEL 3/4" (20mm) UND 65.00 34.00 0.52
UNION UNIVERSAL PVC-SAP C/R 1 1/2" UND 50.00 10.00 0.20
VALVULAS UND 80.00 36.00 0.45
NUMERO TOTAL DE VIAJES 2.52
REDONDEO 2.75
TUBERIA EN VOLUMEN 37

2- FLETE TERRESTRE

UNIDAD DE TRANSPORTE
UNIDAD QUE DA COMPROBANTE UNIDAD QUE NO DA COMPROBANTE
CAPACIDAD DEL CAMION ( M3 ) 15.00 CAPACIDAD DEL CAMION /M3 15.00
COSTO POR VIAJE S/. 550.00 COSTO POR VIAJE S/. 550.00
CAPACIDAD DEL CAMION (KG) 25,000.00 CAPACIDAD DEL CAMION / KG25,000.00
FLETE POR KG 0.02 36.67

AFECTO IGV SIN IGV


FLETE POR PESO 62,142.72

FLETE POR VOLUMEN


AGREGADOS 24,755.50
TUBERIA 1,512.50
COSTO TOTAL FLETE TERR. 63,655.22 24,755.50