Sei sulla pagina 1di 63

PLUMBING

TAKE-OFF SHEETS

SHEET NAME SUBJECT

BOQ-P01 Piping - Cast Iron

BOQ-P02 Piping - Steel

BOQ-P03 Piping - Polypropylene / Polyethylene

BOQ-P04 Piping - Copper

BOQ-P05 Piping - uPVC

BOQ-P06 Pipe Insulation

BOQ-P07 Jacketing on Pipe Insulation

BOQ-P08 Waste Disposal and Drainage Accessories (1/2)

BOQ-P09 Waste Disposal and Drainage Accessories (2/2)

BOQ-P10 Rain Water Accessories

BOQ-P11 Equipment

BOQ-P12 Components & Accessories (Except Fire & Gases)

BOQ-P13 Sanitary and Rain Water Drainage outside the Building (Underground Structure)

BOQ-P14 Fire Fighting Accessories

BOQ-P15 Pumps

BOQ-P16 LP Gas System

BOQ-P17 Compressed Air System

BOQ-P18 Vacuum System

BOQ-P19 Medical Vacuum System

BOQ-P20 Medical Compressed Air System

BOQ-P21 Medical Gases (Nitrous Oxide System)

BOQ-P22 Medical Gases (Oxygen)

BOQ-P23 Water Treatment Equipment

BOQ-P24 Solar System

BOQ-P25 Swimming Pool Equipment

BOQ-P26 Fixtures

BOQ-P27 Kitchen Equipment

BOQ-P28 Laundry Equipment

BOQ-P29 Workshop Equipment

BOQ-P30 Incineration and Rubbish Collection System

BOQ-P31 Electrical Works

PRC-ME-01 REV 1
BOQ-P32 Plumbing Accessories

PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.: of


Checked by
Subject: Piping System:

Unit No.:
FERROUS PIPES

MATERIAL: CAST IRON CAST IRON: 3A (HUB & SPIGOT) CAST IRON: 3B (HUBLESS)

PIPE RUNNING ABOVE GROUND UNDER GROUND


SIZE TOTAL +10%

50

75

100

125

200

250

300

350

400

PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.: of


Checked by
Subject: Piping System:

Unit No.:
FERROUS PIPES
WELDED
GAL STEEL: 1SCH. 40
SEAMLESS
MATERIAL: STEEL
WELDED WELDED
BLACK STEEL: 2A SCH. 40 BLACK STEEL: 2B SCH. 80
SEAMLESS SEAMLESS

PIPE RUNNING ABOVE GROUND UNDER GROUND


SIZE TOTAL +10%

15

20

25

32

40

50

65

75

100

125

150

200

250

300

350

400

450

500

600

PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.: of


Checked by
Subject: Piping System:

Unit No.:
NON FERROUS PIPES

MATERIAL POLYPROPYLENE POLYETHYLENE

PIPE RUNNING ABOVE GROUND UNDER GROUND


SIZE TOTAL +10%

15

20

25

32

40

50

65

80

110

125

160

200

250

PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.: of

Subject: Piping System: Checked by

Unit No.:
NON FERROUS PIPES

MATERIAL: COPPER SPECIFY STANDARD:

PIPE RUNNING ABOVE GROUND UNDER GROUND


SIZE TOTAL +10%

12

15

22

28

35

42

54

67

76

108

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.: of

Subject: Piping System: Checked by

Unit No.:
NON FERROUS PIPES

MATERIAL: uPVC SPECIFY STANDARD:

PIPE RUNNING ABOVE GROUND UNDER GROUND


SIZE TOTAL +10%

15

20

25

32

40

50

80

110

125

160

200

250

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.: of

Subject: Pipe Insulation System: Checked by

Unit No.:

MATERIAL:

THICKNESS SIZE QTY QTY QTY QTY QTY QTY QTY QTY QTY +10%

15

20

25

32

40

50

65

75

100

125

150

200

250

300

350

400

450

500

600

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.: of

Subject: Jacketing on Pipe Insulation System: Checked by

Unit No.:

MATERIAL:

THICKNESS SIZE QTY QTY QTY QTY QTY QTY QTY QTY QTY +10%

15

20

25

32

40

50

65

75

100

125

150

200

250

300

350

400

450

500

600

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of
Checked by
Subject: Waste Disposal and Drainage
System:
Accessories (1/2)

FD-1 : : : : : : : FD-2 : : : : : : :

FD-3 : : : : : : : FD-4 : : : : : : :

FD-5 : : : : : : : (FBD-1) : : : : : : :

(FBD-2) : : : : : : : (GD-1) : : : : : : :

(GD-2) : : : : : : : (GRD-1) : : : : : : :

(GRD-2) : : : : : : :

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by
Drawing No.: Rev. No.: of
Subject: Waste Disposal and Drainage Checked by
System:
Accessories (2/2)

TRD-1 : : : : : : : TRD-2 : : : : : : :

GRATING w: w: w: w: w: w: w: GRATING w: w: w: w: w: w: w:

GULLY TRAP : : : : : : : GULLY TRAP : : : : : : :

FCO : : : : : : : AAV : : : : : : :

WCO : : : : : : : WVC : : : : : : :

RVC : : : : : : :

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by
Drawing No.: Rev. No.: of
Checked by
Subject: Rain Water Accessories System:

RD-1 : : : : : : : RD-2 : : : : : : :

RD-3 : : : : : : : BD-1 : : : : : : :

BD-2 : : : : : : : (TD-1) : : : : : : :

(TD-2) : : : : : : :

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of

Subject: Equipment System: Checked by

Remarks:
EWH-1 QTY EWH-2 QTY EWH-3 QTY EWH-4 QTY EWH-5 QTY EWH-6 QTY

QTY QTY QTY QTY QTY QTY

QTY QTY QTY QTY QTY QTY

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of
Subject: Components&Accessories Checked by
System:
(Except Fire & Gases)
Remarks:
BALL VALVE :15 :20 :25 :32 :40 :50

TOTAL
GATE VALVE : : : : : : : : : : : : : : : :

TOTAL
GLOBE VALVE : : : : : : : : : : : : : : : :

TOTAL
CHECK VALVE : : : : : : : : : : : : : : : :

TOTAL
PRESSURE RED. : : : : : : : : : : : : : : : :

TOTAL
BALANCING VALVE : : : : : : : : : : : : : : : :

PRC-ME-01 REV 1
TOTAL

PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of
Subject: Sanitary and Rain Water Drainage- Checked by
System:
Outside the Building (Underground Structure)

Remarks:
MANHOLE QTY NEUTR. PIT QTY OIL INTER. QTY INSPEC. CHAMB. QTY SAND TRAP QTY GREASE TRAP QTY
MH- NP- IC-
MH- IC-
MH- IC-

TOTAL
LINT INTER. QTY VALVE BOX QTY GREASE INTER. QTY
VB- GI-

PRC-ME-01 REV 1
TOTAL

PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
FIRE Sheet No. Prepared by

Drawing No.: Rev. No.:


of

Subject: Fire Fighting Accessories System: Checked by

Remarks:
SPRINKLERS QTY QTY QTY QTY QTY QTY QTY TOTAL
SP-1
SP-2
SP-3
SP-4
SP-5
FIRE EXTING. QTY QTY QTY QTY QTY QTY QTY QTY
FE-1
FE-2
FE-3
AUT. FIRE EXTING. QTY QTY QTY QTY QTY QTY QTY QTY
AFE-1
AFE-2
FIRE HOSE CAB. QTY QTY QTY QTY QTY QTY QTY QTY
FHC-1
FHC-2
FHC-3
FIRE HOSE REEL QTY QTY QTY QTY QTY QTY QTY QTY
FHR-1
FHR-2
FHR-3
SIAMMESE CON. QTY QTY QTY QTY QTY QTY QTY QTY
TYPE SC-1
TYPE SC-2
FM 200 SYST. QTY QTY QTY QTY QTY QTY QTY QTY

WATER CURTAIN QTY QTY QTY QTY QTY QTY QTY QTY
TYPE
TYPE
FIRE VALVES
GATE VALVE : : : : : : : TEST & DRAIN : : : : : : :

TOTAL TOTAL
WATER FLOW
ALARM CHECK : : : : : PRESSURE RED. : : : ALARM SWITCH : : :

TOTAL TOTAL TOTAL


ZONE VALVE : : : : : : : CHECK VALVE : : : : : : :

PRC-ME-01 REV 1
TOTAL TOTAL

PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of

Subject: Pumps System: Checked by

Unit:
PUMPS QTY PUMPS QTY PUMPS QTY PUMPS QTY PUMPS QTY

PRC-ME-01 REV 1
TOTAL

PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of
Subject: LP Gas System System: Checked by

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

PIPES
: : : : :

VALVES
: : : : :

PRESSURE REGULATING VALVES


: : : : :

GAS TANKS
Size

GAS CYLINDERS
Litres

EMERGENCY SHUT-OFF VALVES


: : : : :

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of
Subject: Compressed Air System System: Checked by

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

PIPES
15 20 25 32 40

50

COMPRESSORS
Type AC- AC- AC-

AUTOMATIC DRAIN TRAPS


15 20 25

VALVES
15 20 25 32 40

50

COMPRESSED AIR OUTLETS

MISCELLANEOUS

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of
Subject: Vacuum System System: Checked by

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

PIPES
15 20 25 32 40

50

VACUUM UNIT
Type VAC- VAC-

AUTOMATIC DRAIN TRAPS


15 20 25

VALVES
15 20 25 32 40

50

VACUUM OUTLETS

MISCELLANEOUS

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of
Subject: Medical Vacuum System System: Checked by

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

PIPES
15 22 28 35 42

54 67 76 108

BALL VALVES
15 22 28 35 42

54

MEDICAL VALVE BOXES


Type MVB- MVB- MVB- MVB- MVB-

GAUGE PANELS

ALARM PANELS

PACKAGED MEDICAL VACUUM UNIT INCLUDING RECEIVER


Type MVU- MVU-

MISCELLANEOUS

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of
Subject: Medical Compressed Air System System: Checked by

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

PIPES
15 22 28 35 42

54 67 76 108

BALL VALVES
15 22 28 35 42

54

MEDICAL VALVE BOXES


Type MVB- MVB- MVB- MVB- MVB-

GAUGE PANELS

ALARM PANELS

MEDICAL AIR COMPRESSORS INCLUDING RECEIVER


Type MCAV- MCAV-

MISCELLANEOUS

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of
Subject: Medical Gases: Checked by
System:
(Nitrous Oxide System)

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

PIPES
15 22 28 35 42

54 67 76 108

BALL VALVES
15 22 28 35 42

54

MEDICAL VALVE BOXES


Type MVB- MVB- MVB- MVB- MVB-

GAUGE PANELS

ALARM PANELS

GAS CYLINDERS

MISCELLANEOUS

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of

Subject: Medical Gases: (Oxygen) System: Checked by

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

PIPES
15 22 28 35 42

54 67 76 108

BALL VALVES
15 22 28 35 42

54

MEDICAL VALVE BOXES


Type MVB- MVB- MVB- MVB- MVB-

GAUGE PANELS

ALARM PANELS

GAS CYLINDERS

MISCELLANEOUS

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of

Subject: Water Treatment Equipment System: Checked by

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

PIPES
: : : : :

VALVES
: : : : :

WATER SOFTENERS
WS-1 WS-2 WS-3 WS-4

FILTERS
SF-1 SF-2 SF-3 SF-4

PUMPS
P- P- P- P-

MISCELLANEOUS

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of

Subject: Solar System System: Checked by

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

PRC-ME-01 REV 1
TOTAL

PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of

Subject: Swimming Pool Equipment System: Checked by

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

uPVC PRESSURE PIPES


20 25 32 40 50

65 80 110 125 160

PUMPS
Type P- P- P- P- P-

FILTERS
Type F- F- F- F- F0

BALANCING TANKS
Type T- T- T- T- T-

CHLORINATION EQUIPMENT
Soda/Ash Hypochlorite

FITTINGS & ACCESSORIES


Gutter
Skimmers
Vacuum
Supply Nozzles

MISCELLANEOUS

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of
Checked by
Subject: Fixtures System:

Remarks:

EWC-1 QTY EWC-2 QTY EWC-3 QTY EWC-4 QTY

AWC-1 QTY AWC-2 QTY B-1 QTY B-2 QTY

LAV-1 QTY LAV-2 QTY LAV-3 QTY LAV-4 QTY

BT-1 QTY BT-2 QTY MS-1 QTY MS-2 QTY

SH-1 QTY SH-2 QTY SH-3 QTY ESH-1 QTY

UR-1 QTY UR-2 QTY UR-3 QTY KS-1 QTY

KS-2 QTY KS-3 QTY S-1 QTY S-2 QTY

S-3 QTY LS-1 QTY LS-2 QTY DF-1 QTY

DF-2 QTY WC-1 QTY WC-2 QTY FT- QTY HD-1 QTY

EW
HD-2 QTY WT QTY HB QTY (EYE WASH) QTY BPH QTY

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of

Subject: Kitchen Equipment System: Checked by

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of

Subject: Laundry Equipment System: Checked by

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of

Subject: Workshop Equipment System: Checked by

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

PRC-ME-01 REV 1
TOTAL

PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of
Subject: Incineration and Rubbish Checked by
System:
Collection System

Unit:
ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY ITEM QTY

PRC-ME-01 REV 1
PRC-ME-01 REV 1
Project No. Date
QUANTITY TAKE-OFF
SHEET
PLUMBING Sheet No. Prepared by

Drawing No.: Rev. No.:


of
Checked by
Subject: Electrical Works System:

Unit:

MOTOR CONTROL CENTRES QTY ITEM QTY ITEM QTY ITEM QTY
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MCC-
MOTOR CONTROL PANELS QTY ITEM QTY ITEM QTY ITEM QTY
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-
MCP-

PRC-ME-01 REV 1
MCP-
MCP-

PRC-ME-01 REV 1
Project No. Date

QUANTITY TAKE-OFF
SHEET Sheet No. Prepared by

of
Checked by
Subject: Plumbing Accessories

CW HW WASTE VENT
FIXTURE
INCH MM INCH MM INCH MM INCH MM
EWC (FT) 1/2" 12 - - 4" 100 2" 50
EWC (FV) 1 1/4" 32 - - 4" 100 2" 50
AWC (FT) 1/2" 12 - - 4" 100 2" 50
AWC (FV) 1 1/4" 12 - - 4" 100 2" 50
B 1/2" 12 1/2" 12 1 1/2" 40 1 1/4" 32
BT 1/2" 12 1/2" 12 2" 50 1 1/4" 32
SH 1/2" 12 1/2" 12 2" 50 1 1/4" 32
FD - - - - 3" 80 1 1/2" -
HB 3/4" 20 - - - - - -
DF 1/2" 12 - - 1 1/4" 32 1 1/4" 32
US 1/2" 12 1/2" 12 1 1/2" 40 1 1/4" 32
CS 1/2" 12 - - 1 1/2" 40 1 1/4" 32
SCS 1/2" 12 1/2" 12 4" 100 2" 50
LS - - - - 1 1/2" 40 1 1/4" 32
WT 1/2" 12 1/2" 12 1 1/2" 40 1 1/4" 32
MS 1/2" 12 1/2" 12 3" 80 1 1/2" 40
KS 1/2" 12 1/2" 12 2" 50 1 1/4" 32
UR (FT) 1/2" 12 - - 2" 50 1 1/4" 32
UR (FV) 1 1/4" 25 - - 2" 50 1 1/4" 32
LAV 1/2" 12 1/2" 12 1 1/2" 40 1 1/4" 32
S (ALL TYPES) 1/2" 12 1/2" 12 1 1/2" 40 1 1/4" 32

FROM FINISHING FLOOR


WASTE WATER
FIXTURE
INCH CM. INCH CM.

EWC (FT) 20 8 1/2" 20


EWC (FV) 60
B 20 20
BT 27 1/2" 70
SH 54" 140
WT, HB 40
DF 50 50
MS, S 10 1/2" 30 35 1/2" 90
SINK 23 1/4" 60 35 1/2" 90
UR (FT) 16 1/2" 40
UR (FV) 17" 45
FHC 120
LAV 17" 43 20" 50
LOW LEVEL (VENT) 120

PRC-ME-01 REV 1
LOW LEVEL (WATER) 50

PRC-ME-01 REV 1