Error Message: Bad public user Name or password. SQL Server Error:
[DBNETLIB][ConnectionOpen(Connect()).]SQL Server does not exist or access denied.
Error message: Bad public user name or password. SQL Server Error:
[DBNETLIB][ConnectionOpen (Invalid Instance()).] Invalid connection.;
Error Message: Bad public user name or password. Database Server Error: Login
failed for user pubuser.
CAUSE 1:
Incorrect hostname, instance or database name
Bad public user Name or password. SQL Server Error: [DBNETLIB
[ConnectionOpen(Connect()).]SQL Server does not exist or access denied.;
The default configuration entries for a standalone installation
are localhost\primavera for the server host name and PMDB$primavera for the
database name.
FIX 1:
Click back to the Database Configuration and correct the database name or hostname
or instance.
CAUSE 2:
Connecting to an existing SQL Server 2005 (or SQL Server 2005 Studio Express)
instance and there were no network protocols enabled for the instance.
FIX 2:
Enable the TCP/IP in the SQL Server Configuration Manager.
Click Start, All Programs, Microsoft SQL Server 2005, Configuration Tools, SQL
Server Configuration Manager.
Select your instance of SQL Server 2005 (or SQL Server 2005 Studio Express) instance
in the SQL Server 2005 Network Configuration left-hand section.
Double-click on TCP/IP in the right-hand section and set Enabled to Yes then
click Apply and OK.
Restart the Service by going to Start, Run and typing in Services.msc and clicking OK.
In the Services window locate the SQL Server. Entry for your instance then right-click
it and select Restart.
CAUSE 3:
Firewall is enabled on either the client or server preventing communication between
the application and database.
FIX 3:
Disable the firewall on the machine or create an exception within the firewall to allow
the ports /or programs to properly communicate. (ensure the machine has other anti-
virus/firewall software) . You will then find the connection will be successful.
Default port for SQL is 1433. Default Port for Oracle is 1521. An exception can be
added to the firwewall for pm.exe and dbconfig.exe
CAUSE 4:
On a machine that does not have a network cable plugged in, localhost is not
recognized as a valid replacement for the machine name. (This is common in a stand
alone environment.)
FIX 4:
Replace localhost with the actual machine name in the db alias connection
information
CAUSE 5:
User made a typo in the server name. Accidentally typed / (forward slash) instead of
the correct \ (back slash) or didnt enter the right name of the Instance.
FIX 5:
Enter the server name correctly. (Example: <hostname>\<Instance Name> where
<hostname> is the machine name where SQL Server is installed and <Instance Name>
is the name of the Instance where the P6 database is located. Example:
localhost\Primavera )
CAUSE 6:
Databases were not created during standalone installation. To verify:
Click Start, All Programs, Microsoft SQL Server 2005, SQL Server Management
Studio/ SQL Server Management Studio Express.
Log in either with Authentication set to Windows Authentication or using Login: sa
and Password: Prima123Vera with SQL Server Authentication.
FIX 6:
For P6.0 and P6.1 run the ConfigAsst.exe from CD1 to create databases: (See admin
guide pg. 36)
CAUSE 7:
Check the Status of the SQL Server Management Studio/SQL Server Management
Studio Express service by going to Start, Run and typing in Services.msc and
clicking OK.
Locate the SQL Server .. service entry for your instance (for example
MSSQLSERVER) and examine the Status column:
FIX 7:
Double-click on the Service to open its Properties and set the service to Automatic so it
will restart after a shutdown of the machine:
CAUSE 8:
If running full Microsoft SQL Server 2005, Authentication setting is set to Windows
Only.
FIX 8:
Click Start, All Programs, Microsoft SQL Server 2005.
Within Server Management, right click on the Server icon and select Properties. On
the Security tab, set Authentication to SQL Server and Windows Authentication
Mode:
CAUSE 9:
FIX 9: (to be done from the machine that cant connect to the database)
The application was installed using the Client Applications whereas the intention was
to install the Stand-alone version of the software, which installs a database locally for
the client to connect to.
FIX 10:
Uninstall the software and re-install, choosing Stand-alone rather than Client
applications
CAUSE 11:
If it still continues to generate the issue, utilize a TCP/IP method to connect to the
database instead of shared memory:
CAUSE 12:
The SQL Database Server TCP port was changed and the Server was never restarted.
FIX 12:
CAUSE 13:
The SQL Server Browser service is not running on the Server machine hosting the
database. All SQL Server named instances register its port with the SQL Server
Browser service when it is running, so when a P6 client connection uses
MachineName\InstanceName to connect to the sql server, the client will talk with SQL
Server Browser first to get the named instance port, then connect to that named
instance by this port. If SQL Server Browser is disabled, client connections could fail
with the reported error since it doesnt understand the TCP/IP connection that should
be made.
FIX 13:
On the database Server go to Start, Run and typing in Services.msc and click OK.
Locate the SQL Browser Service, right-click it and select Start. Then double-click on
the Service to open its Properties and set the service to Automatic so it will restart after
a shutdown of the machine.
Once the service is running, reattempt connection to the server with the database
configuration wizard.
CAUSE 14:
The SQL Server Primavera service is not starting as the Local System Account. This
may be causing an OS 5: Access is denied message when attempting to start the
service.
FIX 14:
CAUSE 15:
or
P6 clients installed on Windows 2008
FIX 15:
For Windows 2008 use Fix 9 above and supply a period for the hostname field, i.e.
just: .
CAUSE 16:
FIX 16:
DEP can either be disabled (set to essential windows programs and services only), or
the sql programs would have to be added to the list.
CAUSE 17:
IP Address is being used in the alias to connect to the Database Server host, and
because DHCP is enabled, workstation hosting the database server caused the IP
Address to change, resulting in an incorrect host entry.
FIX 17:
Replace the host name variable with the new IP assigned to the database server (OR)
use the fully qualified hostname in replace of an IP Address (so long as the host is
registered with the DNS Server, and accessble via hostname. See your network
administrator for further information).
NOTE: For issues relating to the native MS SQL server client; registry entries
specifically pointing to a sql instance and port while accessing either a different named
instance or a different port.
Refer to Microsoft article: http://support.microsoft.com/kb/328383
Under key
HKEY_LOCAL_MACHINE\SOFTWARE\Microsoft\MSSQLServer\Client\SNI9.0, add
string value=<servername or ip>\instance name data=DBMSSOCN,<servername or
ip>\instancename,port
CAUSE 18:
FIX 18:
3. Click on Tasks.
4. Click on Shrink.
5. Click on Database.
6. This screen will give the available free space. Click ok, if you want to continue.
CAUSE 19:
Database was restored and has not had the public and private database logins re-
synced.
FIX 19:
Re-sync the public and private database logins using the following syntax:
Example:
USE PMDB
CAUSE 20:
The SQL Server database may be set to auto-close. When trying to log in, the database
may not be ready to accept the connection.
FIX 20:
Change auto-close setting to false: