Sei sulla pagina 1di 2

Ac tivity ID Activity Name Time Start Finis h Predecessors 2018 2019 2020

(days ) Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oc t Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
767 Oct-16-17 Mar-27-20 Mar-27-20, PASIG SPORTS ARENA
PASIG SPORTS ARENA
PROJECT GEN INFO 0 Oct-16-17 Oct-16-17 Oct-16-17, PROJECT GEN INFO

A1000 NOTICE TO PROCEED (NTP) 0 Oct-16-17 Oct-16-17 NOTICE TO PROCEED (NTP)


A1010 PROJECT START OFF 0 Oct-16-17 Oct-16-17 PROJECT START OFF
A1020 PROJECT SITE TURNOVER to PHESCO 0 Oct-16-17 Oct-16-17 PROJECT SITE TURNOVER to PHESCO
A1030 PROJECT COMPLETION 0 Oct-16-17 Oct-16-17 A1010 PROJECT COMPLETION
PROJECT PRELIMINARIES 70 Oct-16-17 Jan-04-18 Jan-04-18, PROJECT PRELIMINARIES

A1040 Temporary Fence 30 Oct-16-17 Nov-18-17 Temporary Fenc e


A1050 Bunk house/Bodega 30 Oct-16-17 Nov-18-17 A1040 Bunkhouse/Bodega
A1060 Clearing & Grubbing 60 Oct-16-17 Dec-23-17 A1050 Clearing & Grubbing
A1070 Lay-out & Staking 60 Oc t-27-17* Jan-04-18 A1060 Lay-out & Staking

PROJECT CONSTRUCTION WORKS 767 Oct-16-17 Mar-27-20 Mar-27-20, PROJECT CONSTRUCTION WORKS

MOBILIZATION & DEMOBILIATION 569 Oct-16-17 Aug-09-19 Aug-09-19, MOBILIZATION & DEMOBILIATION
A059 Mobilization 15 Oct-16-17 Nov-01-17 Mobilization
A060 Demobiliation 15 Jul-24-19* Aug-09-19 Demobiliation
DEMOLITION WORKS 42 Oct-21-17 Dec-08-17 Dec-08-17, DEMOLITION WORKS
A061 Dis mantling of Old Existing Light Tower 14 Oct-21-17 Nov-06-17 A059 Dismantling of Old Existing Light Tower
A062 Demolition of Ext'g Bldgs 42 Oct-21-17 Dec-08-17 A061 Demolition of Ext'g Bldgs
DEWATERING WORKS 1 Oct-16-17 Oct-16-17 Oct-16-17, DEWATERING W ORKS
A02 Dewatering 1 Oct-16-17 Oct-16-17 Dewatering
EARTHWORKS 186 Oct-25-17 May-29-18 May-29-18, EARTHW ORKS
A03 Soil Poisoning 91 Jan-31-18* May-17-18 Soil Pois oning
A04 Damp Proofing Polyethylene Sheet (6 mills) 90 Feb-13-18* May-29-18 A03 Damp Proofing Polyethylene Sheet (6 mills)
A05 Excavation for pile cap 45 Oct-25-17 Dec-15-17 A059 Exc avation for pile c ap
CIVIL & STRUCTURE WORKS 666 Nov-11-17 Dec-27-19 Dec -27-19, CIVIL & STRUCTURE WORKS
SUBSTRUCTURE 276 Nov-11-17 Sep-28-18 Sep-28-18, SUBSTRUCTURE
PILE CAP 164 Nov-11-17 May-21-18 May-21-18, PILE CAP
1st Cre w 164 Nov-11-17 May-21-18 May-21-18, 1st Crew
A1136 Pile Hack ing (32 Piles) 96 Nov-11-17 Mar-02-18 A05 Pile Hac king (32 Piles)
A1137 Removal & Disposal of debris 32 Feb-02-18 Mar-10-18 A1136 Removal & Dis posal of debris
A1138 Back filling, Compaction and testing of foundation bed 32 Feb-10-18 Mar-19-18 A1137 Back filling, Compaction and testing of foundation bed
A1139 Blinding of conc rete 10 Mar-14-18 Mar-24-18 A1138 Blinding of conc rete
A1140 Installation of pile cap rebar & dowels 32 Apr-03-18 May-09-18 A1139 Installation of pile cap rebar & dowels
A1141 Shuttering works 10 May-04-18 May-15-18 A1140 Shuttering works
A1142 Conc reting 10 May-10-18 May-21-18 A1141 Concreting
2nd Cre w 164 Nov-11-17 May-21-18 May-21-18, 2nd Crew
A1071 Pile Hack ing (32 Piles) 96 Nov-11-17 Mar-02-18 A05 Pile Hac king (32 Piles)
A1072 Removal & Disposal of debris 32 Feb-02-18 Mar-10-18 A1071 Removal & Dis posal of debris
A1073 Back filling, Compaction and testing of foundation bed 32 Feb-10-18 Mar-19-18 A1072 Back filling, Compaction and testing of foundation bed
A1074 Blinding of conc rete 10 Mar-14-18 Mar-24-18 A1073 Blinding of conc rete
A1075 Installation of pile cap rebar & dowels 32 Apr-03-18 May-09-18 A1074 Installation of pile cap rebar & dowels
A1076 Shuttering works 10 May-04-18 May-15-18 A1075 Shuttering works
A1077 Conc reting 10 May-10-18 May-21-18 A1076 Concreting
3rd Crew 164 Nov-11-17 May-21-18 May-21-18, 3rd Crew
A1078 Pile Hack ing (32 Piles) 96 Nov-11-17 Mar-02-18 A05 Pile Hac king (32 Piles)
A1079 Removal & Disposal of debris 32 Feb-02-18 Mar-10-18 A1078 Removal & Dis posal of debris
A1080 Back filling, Compaction and testing of foundation bed 32 Feb-10-18 Mar-19-18 A1079 Back filling, Compaction and testing of foundation bed
A1081 Blinding of conc rete 10 Mar-14-18 Mar-24-18 A1080 Blinding of conc rete
A1082 Installation of pile cap rebar & dowels 32 Apr-03-18 May-09-18 A1081 Installation of pile cap rebar & dowels
A1083 Shuttering works 10 May-04-18 May-15-18 A1082 Shuttering works
A1084 Conc reting 10 May-10-18 May-21-18 A1083 Concreting
4th Crew 164 Nov-11-17 May-21-18 May-21-18, 4th Crew
A1085 Pile Hack ing (32 Piles) 96 Nov-11-17 Mar-02-18 A05 Pile Hac king (32 Piles)
A1086 Removal & Disposal of debris 32 Feb-02-18 Mar-10-18 A1085 Removal & Dis posal of debris
A1087 Back filling, Compaction and testing of foundation bed 32 Feb-10-18 Mar-19-18 A1086 Back filling, Compaction and testing of foundation bed
A1088 Blinding of conc rete 10 Mar-14-18 Mar-24-18 A1087 Blinding of conc rete
A1089 Installation of pile cap rebar & dowels 32 Apr-03-18 May-09-18 A1088 Installation of pile cap rebar & dowels
A1090 Shuttering works 10 May-04-18 May-15-18 A1089 Shuttering works
A1091 Conc reting 10 May-10-18 May-21-18 A1090 Concreting
5th Crew 164 Nov-11-17 May-21-18 May-21-18, 5th Crew
A1092 Pile Hack ing (32 Piles) 96 Nov-11-17 Mar-02-18 A05 Pile Hac king (32 Piles)
A1093 Removal & Disposal of debris 32 Feb-02-18 Mar-10-18 A1092 Removal & Dis posal of debris
A1094 Back filling, Compaction and testing of foundation bed 32 Feb-10-18 Mar-19-18 A1093 Back filling, Compaction and testing of foundation bed
A1095 Blinding of conc rete 10 Mar-14-18 Mar-24-18 A1094 Blinding of conc rete
A1096 Installation of pile cap rebar & dowels 32 Apr-03-18 May-09-18 A1095 Installation of pile cap rebar & dowels
A1097 Shuttering works 10 May-04-18 May-15-18 A1096 Shuttering works
A1098 Conc reting 10 May-10-18 May-21-18 A1097 Concreting
6th Crew 164 Nov-11-17 May-21-18 May-21-18, 6th Crew
A1099 Pile Hack ing (32 Piles) 96 Nov-11-17 Mar-02-18 A05 Pile Hac king (32 Piles)
A1100 Removal & Disposal of debris 32 Feb-02-18 Mar-10-18 A1099 Removal & Dis posal of debris
A1101 Back filling, Compaction and testing of foundation bed 32 Feb-10-18 Mar-19-18 A1100 Back filling, Compaction and testing of foundation bed
A1102 Blinding of conc rete 10 Mar-14-18 Mar-24-18 A1101 Blinding of conc rete
A1103 Installation of pile cap rebar & dowels 32 Apr-03-18 May-09-18 A1102 Installation of pile cap rebar & dowels
A1104 Shuttering works 10 May-04-18 May-15-18 A1103 Shuttering works
A1105 Conc reting 10 May-10-18 May-21-18 A1104 Concreting
7th Crew 164 Nov-11-17 May-21-18 May-21-18, 7th Crew
A1106 Pile Hack ing (32 Piles) 96 Nov-11-17 Mar-02-18 A05 Pile Hac king (32 Piles)
A1107 Removal & Disposal of debris 32 Feb-02-18 Mar-10-18 A1106 Removal & Dis posal of debris
A1108 Back filling, Compaction and testing of foundation bed 32 Feb-10-18 Mar-19-18 A1107 Back filling, Compaction and testing of foundation bed
A1109 Blinding of conc rete 10 Mar-14-18 Mar-24-18 A1108 Blinding of conc rete
A1110 Installation of pile cap rebar & dowels 32 Apr-03-18 May-09-18 A1109 Installation of pile cap rebar & dowels
A1111 Shuttering works 10 May-04-18 May-15-18 A1110 Shuttering works
A1112 Conc reting 10 May-10-18 May-21-18 A1111 Concreting
8th Crew 164 Nov-11-17 May-21-18 May-21-18, 8th Crew
A1113 Pile Hack ing (32 Piles) 96 Nov-11-17 Mar-02-18 A05 Pile Hac king (32 Piles)
A1114 Removal & Disposal of debris 32 Feb-02-18 Mar-10-18 A1113 Removal & Dis posal of debris
A1115 Back filling, Compaction and testing of foundation bed 32 Feb-10-18 Mar-19-18 A1114 Back filling, Compaction and testing of foundation bed
A1116 Blinding of conc rete 10 Mar-14-18 Mar-24-18 A1115 Blinding of conc rete
A1117 Installation of pile cap rebar & dowels 32 Apr-03-18 May-09-18 A1116 Installation of pile cap rebar & dowels
A1118 Shuttering works 10 May-04-18 May-15-18 A1117 Shuttering works
A1119 Conc reting 10 May-10-18 May-21-18 A1118 Concreting
TIE BEAM 127 May-04-18 Sep-28-18 Sep-28-18, TIE BEAM
A08 Excavation 30 May-04-18 Jun-07-18 A1076, A1083, A1090, A1097, A110 4, A1111, A1118 Exc avation
A09 Installation of rebars 60 May-22-18 Jul-30-18 A08 Installation of rebars
A10 Shuttering Works 60 Jun-26-18 Sep-03-18 A09 Shuttering Works
Ac tivity ID Activity Name Time Start Finis h Predecessors 2018 2019 2020
(days ) Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oc t Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
A11 Conc reting 10 Aug-29-18 Sep-08-18 A10 Concreting
A12 Deshuttering work s 10 Sep-18-18 Sep-28-18 A11 Deshuttering works
SUPERSTRUCTURE 407 Sep-10-18 Dec-27-19 Dec -27-19, SUPERSTRUCTURE
1st FLOOR 147 Sep-10-18 Feb-27-19 Feb-27-19, 1st FLOOR
COLUMNS 92 Sep-10-18 Dec-25-18 Dec -25-18, COLUMNS
A016 Installation of rebar 50 Sep-10-18 Nov-06-18 A11 Installation of rebar
A018 Shuttering Works 50 Oct-03-18 Nov-29-18 A016 Shuttering Works
A019 Conc reting 10 Nov-24-18 Dec-05-18 A018 Concreting
A020 Deshuttering Works 10 Dec-14-18 Dec-25-18 A019 Des huttering W ork s
BEAMS 72 Dec-06-18 Feb-27-19 Feb-27-19, BEAMS
A021 Installation of rebars 50 Dec-06-18 Feb-01-19 A019 Installation of rebars
A022 Shuttering works 30 Dec-29-18 Feb-01-19 A021 Shuttering works
A023 Conc reting 10 Jan-28-19 Feb-07-19 A022 Conc reting
A024 Deshuttering work s 10 Feb-16-19 Feb-27-19 A023 Deshuttering work s
2nd Floor 147 Feb-08-19 Jul-29-19 Jul-29-19, 2nd Floor
COLUMN 92 Feb-08-19 May-25-19 May-25-19, COLUMN
A1120 Installation of rebar 50 Feb-08-19 Apr-06-19 A023 Installation of rebar
A1121 Shuttering Works 50 Mar-04-19 Apr-30-19 A1120 Shuttering Works
A1122 Conc reting 10 Apr-25-19 May-06-19 A1121 Concreting
A1123 Deshuttering Works 10 May-15-19 May-25-19 A1122 Des huttering W ork s
BEAM 72 May-07-19 Jul-29-19 Jul-29-19, BEAM
A1124 Installation of rebars 50 May-07-19 Jul-03-19 A1122 Installation of rebars
A1125 Shuttering works 30 May-30-19 Jul-03-19 A1124 Shuttering works
A1126 Conc reting 10 Jun-28-19 Jul-09-19 A1125 Concreting
A1127 Deshuttering work s 10 Jul-18-19 Jul-29-19 A1126 Deshuttering works
3RD FLOOR 147 Jul-10-19 Dec-27-19 Dec -27-19, 3RD FLOOR
COLUMN 92 Jul-10-19 Oct-24-19 Oct-24-19, COLUMN
A1128 Installation of rebar 50 Jul-10-19 Sep-05-19 A1126 Installation of rebar
A1129 Shuttering Works 50 Aug-02-19 Sep-28-19 A1128 Shuttering Works
A1130 Conc reting 10 Sep-24-19 Oct-04-19 A1129 Concreting
A1131 Deshuttering Works 10 Oct-14-19 Oct-24-19 A1130 Deshuttering Works
BEAM 72 Oct-05-19 Dec-27-19 Dec -27-19, BEAM
A1132 Installation of rebars 50 Oct-05-19 Dec-02-19 A1130 Installation of rebars
A1133 Shuttering works 30 Oct-29-19 Dec-02-19 A1132 Shuttering works
A1134 Conc reting 10 Nov-27-19 Dec-07-19 A1133 Concreting
A1135 Deshuttering work s 10 Dec-17-19 Dec-27-19 A1134 Des huttering works
ELECTRICAL WORKS 350 Feb-02-19 Mar-16-20 Mar-16-20, ELECTRICAL WORKS
ROUGH-INS 350 Feb-02-19 Mar-16-20 Mar-16-20, ROUGH-INS
A044 15 mm PVC, Neltex or Atlanta, sch.40 350 Feb-02-19* Mar-16-20 A022 15 mm PVC, Neltex or Atlanta, sch.40
A045 15 mm IMC, MATSUSHITA, PANASONIC 350 Feb-02-19* Mar-16-20 A047 15 mm IMC, MATSUSHITA, PANASONIC
A046 65 mm PVC, Neltex or Atlanta, sch.40 350 Feb-02-19 Mar-16-20 A044 65 mm PVC, Neltex or Atlanta, sch.40
A047 110 mm PVC, Neltex or At lanta, s ch. 40 350 Feb-02-19 Mar-16-20 A044 110 mm PVC, Neltex or Atlanta, s ch.40
Chipping a nd restoration 317 Feb-02-19 Feb-06-20 Feb-06-20, Chipping and restoration
A048 Service Entrance Concrete Pedes tal to DPG ins ide 90 Feb-02-19 May-17-19 A046, A044, A045, A047 Service Entrance Concrete Pedestal to DPG inside
A049 Other access ories 317 Feb-02-19 Feb-06-20 A048 Other acc essories
GRINDING 350 Feb-02-19 Mar-16-20 Mar-16-20, GRINDING
A050 Ground Rod, 20mm x 3000mm Copper Clad 105 Feb-02-19 Jun-04-19 A044 Ground Rod, 20mm x 3000mm Copper Clad
A051 Bare wire 80mm2 350 Feb-02-19 Mar-16-20 A050 Bare wire 80mm2
A052 25 mm PVC, sch 40 180 Feb-02-19 Aug-30-19 A051 25 mm PVC, sc h 40
MECHANICAL WORKS 378 Jan-12-19 Mar-27-20 Mar-27-20, MECHANICAL WORKS
ROUGH-INS 378 Jan-12-19 Mar-27-20 Mar-27-20, ROUGH-INS
A053 Drainage Line & Collector Pipe (Catch Basin) 330 Feb-02-19 Feb-21-20 A044 Drainage Line & Collector Pipe (Catc h Basin)
A054 Collector of Perforated Pipe @ Mez zanine Area 300 Mar-09-19 Feb-21-20 A053 Collector of Perforated Pipe @ Mezz anine Area
A055 Threaded Plug for Clean-out 54 Feb-02-19 Apr-05-19 A053 Threaded Plug for Clean-out
A056 Pipe Hangers 318 Jan-12-19 Jan-17-20 A053 Pipe Hangers
A057 Sanitary Soil Stack 360 Feb-02-19 Mar-27-20 A053 Sanitary Soil Stack
A058 Water Supply 348 Feb-02-19 Mar-13-20 A053 Water Supply
PROJECT CLOSED-OUT 0