Sei sulla pagina 1di 132

Making Relay Testing

The NEW SMRT46D Multi-Phase Relay Test System


is equipped with a 4th Voltage Channel to expand
your testing capabilities.

The word Megger is a registered trademark.

Megger's New SMRT46D Multi-Phase Relay Test System expands your testing abilities by
adding a powerful 4th voltage channel to make relay testing easier 4 you.

The fourth voltage channel provides a number of different testing options including functioning
as a synchronizing reference voltage or as a battery simulator. With the voltage channels
converted to currents, a three-channel unit can provide 6 currents for testing three-phase current
differential relays, including harmonic restraint transformer differential relays. These options are
designed to simplify the relay testing process to help you keep the power on.

us.megger.com/smrt46D
TABLE OF CONTENTS

C O VER S T O RY FEAT URES

7 Presidents Desk
Ron Widup, Shermco Industries
NETA President
58 Using Test Plans as a Tool for Protection
7HVWLQJ6SHFLFDWLRQV
Benton Vandiver, OMICRON electronics Corp. USA

74 Lessons Learned from a 400kV Busbar


Misoperation Using the IEC 61850 Standard
Dhanabal Mani, Vijay Shanmugasundaram,
and Jason Buneo, Megger

66
66 Going Beyond Automated
Relay Testing: Using Power
System Models
74
Automated testing is often used to test protective
relays, but special cases exist that cannot be
adequately covered. This article presents three
examples that illustrate how to test protection
functions using simple model power systems
and symmetrical components.
Steve Turner, Beckwith Electric Company, Inc.

TABLE OF CONTENTS NETAWORLD 3


TABLE OF CONTENTS

IN EVERY ISSUE SPECIFICATIONS AND STANDARDS

11 NFPA 70E and NETA 100 ANSI/NETA Standards Update


Electrical Risk Management
104 ASTM F18 Committee Report
Ron Widup and Jim White, Shermco Industries
Jim White, Shermco Industries
18 No-Outage Corner
Using No-Outage Testing Techniques for
Post-Natural Disaster Triage NETA NEWS
Don A. Genutis, Halco Testing Services
22 Tech Quiz 46 NETA 2016 Alliance Recognition Award
Protective Relaying for Electrical Power Systems Honoree: Finley Ledbetter
Jim White, Shermco Industries Carla Kalogeridis, NETA
28 Tech Tips 51 PowerTest 2016 Deep in the Heart of
Grounding in the Solar Industry Texas, PowerTest 2016 Comes to Fort Worth
Jeff Jowett, Megger
82 NETA 2016 Outstanding Achievement Award
34 Safety Corner Honoree: Jim Cialdea
Arc-Rated Clothing and Electrical Carla Kalogeridis, NETA
Hazard Footwear
Paul Chamberlain, American Electrical Testing Co., Inc. 108 NETA Members and Alliance Partners
Gather in Fort Worth, Texas
39 Relay Column Jill Howell, NETA
Improving System Protection Reliability
and Security
Steve Turner, Beckwith Electric Company, Inc.
NETA NEWS SETTING THE STANDARD

INDUSTRY TOPICS
24 NETAs Electrical Testing Technical
&HUWLFDWLRQ3URJUDP6HWWLQJWKH
89 The Evolution of Circuit Breakers Standard, Energizing the Future
Paul H. Grein, Circuit Breaker Sales Co., Inc. Kristen Wicks, NETA
97 Establishing Maintenance Zero for Large
Power Transformers in Todays Electrical 118 NETA Standards Review Council Appoints
Utility Sector New Members
Ray Curry, American Transmission Company Kristen Wicks, NETA

ADVANCEMENTS IN TECHNOLOGY NETA NEWS IMPORTANT LISTS

112 Time is Ticking to Address Grid 124 NETA Accredited Companies


Interconnection Standards 130 Advertiser List
Mark Siira, ComRent International

4 SUMMER 2016 TABLE OF CONTENTS


3050 Old Centre Avenue, Suite 102
Portage, MI 49024
Toll free: 888.300.NETA (6382)
Phone: 269.488.NETA (6382)
Fax: 269.488.6383
neta@netaworld.org
www.netaworld.org
EXECUTIVE DIRECTOR: Missy Richard

NETA Ofcers
PRESIDENT: Ron Widup, Shermco Industries
FIRST VICE PRESIDENT: Jim Cialdea, Three-C Electrical Co., Inc.
SECOND VICE PRESIDENT: Scott Blizard, American Electrical Testing Co., Inc.
SECRETARY: Mose Ramieh, Power & Generation Testing, Inc.
TREASURER: John White, Sigma Six Solutions

NETA Board of Directors


Ken Bassett (Potomac Testing, Inc.)
Eric Beckman (National Field Services)
Scott Blizard (American Electrical Testing Co., Inc.)
Jim Cialdea (Three-C Electrical Co., Inc.)
Lorne Gara (Orbis Engineering Field Services, Ltd.)
Dan Hook (Western Electrical Services, Inc.)
David Huffman (Power Systems Testing)
Alan Peterson (Utility Service Corporation)
Mose Ramieh (Power & Generation Testing, Inc.)
Bob Sheppard (Southwest Energy Services, LLC)
John White (Sigma Six Solutions)
Ron Widup (Shermco Industries)

NETA World Staff


TECHNICAL EDITORS: Roderic L. Hageman, Tim Cotter
ASSISTANT TECHNICAL EDITORS: Jim Caldea, Dan Hook,
Dave Huffman, Bob Sheppard
ASSOCIATE EDITOR: Resa Pickel
MANAGING EDITOR: Jayne Tanz, CMP
ADVERTISING MANAGER: Laura McDonald
DESIGN AND PRODUCTION: Hour Custom Publishing

NETA Committee Chairs


CONFERENCE: Ron Widup; MEMBERSHIP: Ken Bassett;
PROMOTIONS/MARKETING: Scott Blizard; SAFETY: Scott Blizard and Jim White;
TECHNICAL: Alan Peterson; TECHNICAL EXAM: Ron Widup;
CONTINUING TECHNICAL DEVELOPMENT: David Huffman;
TRAINING: Kerry Heid; FINANCE: John White;
NOMINATIONS: Alan Peterson; STRATEGY: Mose Ramieh;
Delivering Powerful Reliability Solutions ALLIANCE PROGRAM: Jim Cialdea

Copyright 2016, NETA


 Power System Acceptance Testing
NOTICE AND DISCLAIMER
 Commissioning and Start-up NETA World is published quarterly by the InterNational Electrical Testing Association.
Opinions, views and conclusions expressed in articles herein are those of the authors and not
 Maintenance necessarily those of NETA. Publication herein does not constitute or imply endorsement of
any opinion, product, or service by NETA, its directors, officers, members, employees or
agents (herein NETA).
 Life-Cycle Extension
All technical data in this publication reflects the experience of individuals using specific tools,

 Troubleshoot and Repair products, equipment and components under specific conditions and circumstances which may
or may not be fully reported and over which NETA has neither exercised nor reserved control.
Such data has not been independently tested or otherwise verified by NETA.
 Training and Engineering Services NETA MAKES NO ENDORSEMENT, REPRESENTATION OR WARRANTY AS TO
ANY OPINION, PRODUCT OR SERVICE REFERENCED OR ADVERTISED IN THIS
 Planning and Operations Support PUBLICATION. NETA EXPRESSLY DISCLAIMS ANY AND ALL LIABILITY TO ANY
CONSUMER, PURCHASER OR ANY OTHER PERSON USING ANY PRODUCT

 Project Management OR SERVICE REFERENCED OR ADVERTISED HEREIN FOR ANY INJURIES OR


DAMAGES OF ANY KIND WHATSOEVER, INCLUDING, BUT NOT LIMITED TO
ANY CONSEQUENTIAL, PUNITIVE, SPECIAL, INCIDENTAL, DIRECT OR INDIRECT
DAMAGES. NETA FURTHER DISCLAIMS ANY AND ALL WARRANTIES, EXPRESS
OF IMPLIED, INCLUDING, BUT NOT LIMITED TO, ANY IMPLIED WARRANTY OF
FITNESS FOR A PARTICULAR PURPOSE.

Sigma Six Solutions, Inc. ELECTRICAL TESTING SHALL BE PERFORMED ONLY BY TRAINED ELECTRICAL
PERSONNEL AND SHALL BE SUPERVISED BY NETA CERTIFIED TECHNICIANS/
LEVEL III OR IV OR BY NICET CERTIFIED TECHNICIANS IN ELECTRICAL TESTING
2200 West Valley Hwy North, Suite 100 | Auburn, WA 98001 TECHNOLOGY/LEVEL III OR IV. FAILURE TO ADHERE TO ADEQUATE TRAINING,
SAFETY REQUIREMENTS, AND APPLICABLE PROCEDURES MAY RESULT IN LOSS
2IFH|6DOHV OF PRODUCTION, CATASTROPHIC EQUIPMENT FAILURE, SERIOUS INJURY
OR DEATH.
ZZZVLJPDVL[FRP
PRESIDENTS DESK

SAFETY IN THE SUMMERTIME


The last time we talked was at the beginning of PowerTest 2016 in Fort Worth, and
wasnt that a fantastic event? Many thanks to all of the presenters, sponsors, subject
matter experts, industry leaders, and suppliers of goods and services who helped us
break attendance records as well as achieve high marks for overall satisfaction with
the conference. I extend a special shout-out to all of the NETA staff who worked
tirelessly to put the event together.
Mark your calendars for next years PowerTest event in Anaheim, California,
February 27 March 3, 2017. Its sure to be a great one.

Summertime means fun time fun at work and fun at home. With the summer
heat come longer days, and hopefully, more work for us all. So take a little extra
time to think about the small stuff that makes us all work a little safer.

As you go about your daily activities this summer, whether at work or home,
please do so with an extra thought of caution. At Shermco, we have an initiative
focused on human performance that is, trying to understand better why we
do what we do the way we do it. An important part of it is managing elements
of human performance to make sure we always do things the right way with
the least amount of risk. Its a good topic for all of us to think about.

So buckle your seatbelt, wear your helmet when riding bicycles and
motorcycles, keep that ladder in good condition, and be careful on
the roof of your house.

And, oh yeah even though its a little hot, wear all


that arc-rated PPE stuff at work.

Sincerely,

Ron Widup
President
NETA InterNational Electrical Testing Association

PRESIDENTS DESK
the test equipment answer

We support testing
Protective Relays and Metering

Batteries and UPS

Transformers

VLF, Tan Delta and Partial Discharge

Cable fault location

Substations & High Voltage Circuit Breakers

SF6 Analysis

Low & Medium Voltage Circuit Breakers

Motors and Rotating Apparatus

Power Monitoring

rental | support | logistics


888.902.6111 | info@intellirentco.com | intellirentco.com
THE NFPA 70E AND NETA

B Y R O N W I D U P AND J AM ES R. WH IT E, Shermco Industries

Risk assessment is a critical function for keeping us safe on


the job. Assessing risk happens every day whether driving a
car, walking across a street, or participating in sports, risks are
associated with all of them. When it comes to assessing risks on
the job, though, we become unsure about what we need to do.
STARTING AT THE BEGINNING
Typically, companies have a Job Safety Analysis or Job Hazard Analysis that documents the method
used to determine the risks, the work practices, and the PPE needed for a particular task. NFPA
70E, Standard for Electrical Safety in the Workplace provides guidance for assessing risk in Article 130.

To begin the process of assessing risk:

Perform a visual examination of the equipment.


Look at the condition of the equipment, the environment, whether
it is indoors or outdoors, whether there is room to safely perform the
task, and the presence of a recent maintenance test or calibration
decal as recommended by NFPA 70B and ANSI/NETA MTS-
2015. For example, look for the presence of rodent droppings or
other signs of varmints. If theyre in your switchgear room,
they are probably in your switchgear. They are unpredictable and
could cause a fault at any time.

Review appropriate company SOPs and policies concerning Figure 1: Rodents and other varmints
the task(s) about to be performed. Non-contact inspections, can cause faults in switchgear.
such as infrared thermography, can be conducted without the
use of arc-rated clothing and PPE, provided the equipment is in normal operating
condition and the worker remains outside the restricted-approach boundary However,
per Table 130.7(C)(15)(A)(a), the above guidance does not include opening of doors
or covers.

Understand how various systems are aected. When the circuit or system is deenergized,
will it affect critical or safety systems? Is temporary power needed for those systems? What
needs to be done to prevent back-feeding of other equipment? Examples of critical systems

ELECTRICAL RISK MANAGEMENT NETAWORLD 11


THE NFPA 70E AND NETA
are emergency alarm systems or PPE and other safety procedures are
lighting in stairwells. Normal operating appropriate to minimize the risks. An
condition means that equipment doors energized electrical work permit (EEWP) as
and panels are properly installed and specified by NFPA 70E is one method to
secured, theres no evidence of im- accomplish this. An example form is in NFPA
pending failure, and the equipment has 70E Informative Annex J.
been properly maintained Without
NFPA 70E Section 130.2 Electrically Safe
access to test and maintenance records,
Work Conditions directs us to place
proper maintenance can be difficult
electrical conductors and circuit parts into
to determine. Its not practical to review
an electrically safe work condition if we are
hundreds, possibly thousands, of records
within the restricted-approach boundary or
to determine if the equipment about to
the arc-flash boundary, or when interacting
be worked on is properly maintained.
with equipment in a manner that could cause
However, ANSI/NETA MTS 2015,
failure. Interacting does not include normal
Standard for Maintenance Testing
operation of equipment but does include
Specifications for Electrical Power
such tasks such as racking circuit breakers
Equipment & Systems and NFPA 70B- and installing and removing MCC buckets or
2016, Recommended Practice for Electrical bus plugs.
Equipment Maintenance both contain
requirements for a test or calibration decal NFPA 70E Section 130.2(B) Energized
system such as that shown in Figure 2. Electrical Work Permit (EEWP) is part of the
required documentation for any energized
Understand the Test and Maintenance electrical task. There are exceptions listed
Decal System NFPA 70B Section 11.27, in 130.2(B)(3), but an EEWP is part of the
shows that a red label indicates the electrical risk assessment process for most
equipment has severe issues that could tasks. Voltage testing and troubleshooting
affect safety or operation, while a yellow are two exceptions to completing an EEWP,
label indicates a defect that should not but an EEWP could assist in evaluating the
affect safety or operation but should be risks and hazards associated with the task.
addressed as soon as practical. A white The approval process is not necessary, but
label indicates the equipment has no the EEWP records the information needed
identified defects and is fully operational to assess the risk and the steps needed to
and ready for continued service. safeguard the worker and others. The EEWP
in Informative Annex J is considered non-
mandatory information, which means it can
be modified to more closely fit the needs and
circumstances of a company or task.

NFPA 70E Section 130.4(A) Shock Risk


Figure 2: Test or Calibration Decals Assessment would include determining
the nominal phase-to-phase voltage of the
Technicians must use all their senses to detect system, along with the approach boundaries
unusual odors, sounds, scorched paint on the (limited and restricted) and shock-protective
equipment, discoloration of components, and PPE required.
hot spots or other conditions that may indicate
a potential problem. To perform an arc-flash risk assessment in
accordance with 130.5, first determine if
Collect all of the important information an arc-flash hazard exists. An arc-flash risk
needed to assess the risk and decide which exists if the technician is exposed to energized

12 SUMMER 2016 ELECTRICAL RISK MANAGEMENT


THE NFPA 70E AND NETA
electrical conductors or circuit parts. The
amount of risk will vary with the tasks
being performed. The hazard is the available
short-circuit current, the voltage, and the
clearing time of the overcurrent protective
device (OCPD). The arc-flash boundary,
working distance, condition of maintenance
of the equipment or circuit, arc-flash
protective clothing, and PPE such as shown
in Figure 3 will also have to be determined.

Figure 4: Safety Barrier Tape Used as a


Boundary Marker

If necessary, ground the equipment and use


a means to account for temporary personal
protective grounds and equipment, such as
tags and specialized forms like those shown in
Figure 5.

Figure 3: Arc-Rated Clothing and Panel


Removal

Refer to Table H.3(b) in NFPA 70E Informative


Annex H if an arc-flash-hazard warning label
is present on the equipment. Do not use
Table 130.7(C)(16) to determine the required
arc-rated clothing and PPE. If there is
no label, use the table method [Tables
130.7(C)(15)(A)(a), 130.7(C)(15)(A)(b) and
130.7(C)(16)]. If the limits of Table 130.7(C)
(15)(a)(b) are exceeded, an incident energy
analysis must be conducted. Figure 5: Grounding Awareness Tags
(Coutesy of BP American, Inc.)
Determine what is needed to protect
unqualified workers from the risks of shock Other items to review include:
or arc flash. This usually involves setting up Inspect all tools and equipment prior to
safety barriers or signage, but may require the start of work, including test
the use of an attendant, in accordance with instruments, leads and accessories, live-
130.7(E) Alerting Techniques. The safety line tools, insulated tools, rubber
barrier or barricade is set up at the limited- insulating blankets, shielding or gloves,
approach boundary or the arc-flash boundary, arc-rated clothing and PPE, as required.
whichever is farther out, according to 130.7(E) Inspect everything, even if it is known to
(2) Barricades (Figure 4). be good.

ELECTRICAL RISK MANAGEMENT NETAWORLD 13


THE NFPA 70E AND NETA
Determine whether a safety backup is rubber-insulating shields, but the associated
required, as well as the training, experience, risk will never be zero as long as the equipment
and PPE required for the safety backup. is energized.
All these items should be documented.
The risk that remains after all appropriate
Determine whether temporary insulating steps have been taken is referred to as the
shielding is needed on nearby energized residual risk, which must be evaluated. If
electrical circuits or whether other means the residual risk is still too great, the work
are required to guard nearby equipment cannot be performed while the equipment is
to prevent incidental contact. energized. If a trained and experienced (read:
qualified) technician carefully evaluates the
Document the installation or removal of risk and believes it can be done safely, then
any specialized test instruments that that task can be done energized. However,
may be required, such as circuit analyzers if the technicians experience indicates that
or recorders. the conditions look too risky, or if they do
If troubleshooting, the equipment may have to not have the correct training or experience,
be de-energized or operated to allow opening then the energized task cannot proceed.
the door. Since it is no longer operating
normally, arc-rated clothing and PPE will A different approach to accomplish the task
be required even to operate the overcurrent would need to be formulated, which would
protective device to remove it from service. probably include de-energizing the equipment.
Refer to the arc-flash risk assessment for the
proper protection. SUMMARY
When the cause of the malfunction is Assessing risk is a vital part of safety not just
determined, repair may be required to return electrical safety, but all work-site safety issues.
the equipment or circuit to service. Repair The employer can only do so much. It is the
includes any task using tools, such as removing employee at the scene, observing the equipment
and installing components, tightening or and conditions, who ultimately must determine
replacement of conductors, and so on. the level of risk.

It would be wise to evaluate the condition of One good adage: Always be responsible for your
the equipment before repairs begin, as the risks personal safety. Relying on others could result
will be greater when energized conductors or in a less-than-satisfactory outcome. Listen to
circuit parts are being handled or replaced. your gut feelings. Often, accidents could have
been avoided if the worker stopped when that
The task work on energized electrical conductors and little voice in their ear said, I wouldnt do
circuit parts, including voltage testing in Table that, if I were you. Step back and re-evaluate
130.7(C)(15)(A)(a) indicates that arc-rated the situation because maybe something was
PPE is always required, which would include missed. Having a second look or asking for a
troubleshooting. second opinion is never a bad thing.

A huge part of the risk-assessment equation


ALL E LE C T RIC A L TASKS is how well the personnel performing the task
INVOLVE RIS K are trained. If workers are not following the
The hazard is present whenever the equipment appropriate policies or procedures, it is often
or circuit is energized, and therefore, so is a lack of training thats at fault. Check-the-box
an element of risk. Risk can be reduced training may satisfy the paper trail, but does
considerably by operating the equipment little or nothing to promote safety or safe work
remotely or by covering adjacent circuits with practices. Employees must be trained and show

14 SUMMER 2016 ELECTRICAL RISK MANAGEMENT


they understand the importance of what they Ron Widup and Jim White are
do and how to do it. People must understand NETAs representatives to NFPA Technical
Committee 70E (Electrical Safety
why it needs to be done the right way instead
Requirements for Employee Workplaces).
of a more convenient way. Both gentlemen are employees of Shermco
Industries in Dallas, Texas, a NETA
Be careful out there. Accredited Company. Ron Widup is
Ron Widup CEO of Shermco and has been with the
company since 1983. He is a Principal
member of the Technical Committee on Electrical Safety
in the Workplace (NFPA 70E) and a Principal member
of the National Electrical Code (NFPA 70) Code Panel
11. He is also a member of the technical committee
Recommended Practice for Electrical Equipment
Maintenance (NFPA 70B), and a member of the NETA
Board of Directors and Standards Review Council.
Jim White is nationally recognized for
technical skills and safety training in
the electrical power systems industry. He
is the Training Director for Shermco
Industries, and has spent the last twenty
years directly involved in technical skills
and safety training for electrical power
Jim White system technicians. Jim is a Principal
member of NFPA 70B representing
Shermco Industries, NETAs alternate member of NFPA
70E, and NETAs Principal representative to the ASTM F18
Committee Electrical Protective Equipment for Workers.
WERE MORE THAN JUST PARTS.
WERE PART OF THE
SOLUTION.

When your electrical equipment is failing, getting the parts you need shouldnt be part of the problem.
With a huge inventory of new, surplus and repurposed electrical circuit breaker and switchgear products,
National Switchgear can be a big part of your solution. We have millions of parts, but we also have the
expertise to see the whole picture, to understand your problem and to recommend the best total solution.
Of course, if you already know exactly what you need, we make it easy to buy online on our constantly
updated website, where youll also discover hard-to-nd resources like installation manuals, wiring
diagrams and more. If you need advice, customized equipment, remanufacturing or reconditioning,
were ready to share our expertise. Because integrity is always in stock.

800-322-0149
nationalswitchgear.com
Industrial Electric Testing, Inc.

{xU{ i}iV-iVi


*/
  / 
/ -/  , *,
U
>Li U66-Vi U,iVi
U66
V i>i U,i>/i U-}iii
U,>}>Vi U

ii U
>>V
Uii U`}-i U >ii
U>V/>vi-Vi U/>vi U`>-i
U-V}i>>`-VL>` U>}` U i>`
iLi U/i}>V-i /i}


" -1/   , - ,6
-
U>`-`i U>Vi}>
U/>i6>}i,iV`}>`> U,i>Viiv>}`
U iV>}iVi` /i} U*i>V-`i

7i LiiU>Vi]`>xU{nn
7iiU>>`>i]`>Ux{{x
NO-OUTAGE CORNER

USING NO-OUTAGE
TESTING TECHNIQUES FOR
POST-NATURAL
TRIAGE B Y D O N A . G E N U TI S ,
Halco Testing Services

A few weeks ago here in Southern California, we were in the


midst of a battering string of El Nio storms that created
widespread surface flooding. During this same timeframe, we
experienced a 4.5-magnitude earthquake, the Mississippi River
was flooding its banks, and the Eastern U.S. was hit with one
of the worst snowstorms in modern history. Natural disasters
force us to consider how to best conduct electrical equipment
assessment and maintain reliability when confronted with these
challenging attacks from nature.
There are many types of natural disasters and interrelated events that can potentially wreak havoc
upon our electrical systems. For example, flooding from freshwater rivers and saltwater storm
surges can submerge outdoor substations and low-lying indoor equipment. Water is one of the top
killers of electrical equipment. Floods and precipitation can cause insulation flash-over resulting in
insulation damage. High-humidity conditions can damage insulation through moisture absorption
in organic insulation and cause conductor corrosion, even if the exposure duration is relatively
brief. Corrosion problems can potentially cause long-term difficulty in high-resistance conductor
connections, and salt water can significantly accelerate this corrosion process. Particulates suspended
in flood waters can settle between moving apparatus components and create future mechanical
operational problems with moving parts.

18 SUMMER 2016 USING NO OUTAGE TESTING TECHNIQUES FOR POST-NATURAL DISASTER TRIAGE
NO-OUTAGE CORNER

Outdoor insulation is designed to function in Energized equipment should not be ignored.


wet weather, but extreme weather conditions Equipment may still be operational but close
can initiate and accelerate failures of marginal to failure, and no-outage testing techniques
insulation. Precipitation from rain, snow, and can often identify these looming failures. The
sleet can potentially compromise outdoor best no-outage methods for these assessments
insulation and challenge equipment's are typically visual inspections and partial-
weatherproofing integrity. Damp, heavy discharge (PD) detection using TEV and
snow and sleet can accumulate on overhead ultrasonics, infrared inspection, and insulating
lines and other outdoor equipment, adding fluid testing.
greater weight to lines and creating excessive
mechanical stresses to all related structural Ultrasonic PD inspections are perhaps the
components. best method for detecting medium- and high-
voltage surface-related insulation problems.
In addition to water-related challenges, high TEV PD inspections are very effective for
winds from storms, tornados, and hurricanes detecting elusive medium-voltage internal
can damage overhead lines and outdoor insulation defects. Infrared technology is a great
substations. Also, earthquakes can physically technique for spotting conductor damage at all
jolt indoor and outdoor equipment, creating voltage levels, and insulating fluid sampling
damaging mechanical stresses. Mechanical and testing can help ensure the integrity of
problems due to high winds and earthquakes transformers and other fluid-insulated devices.
can break or deform insulation or conductors Experienced technicians with a careful eye can
and mechanisms. Mechanical forces produced fill in most of the remaining gaps to detect
by these weather events can break or crack other problems.
insulators, and ceramic insulators may be at
much greater risk due to their more brittle We must adapt our daily practices to better
structural properties. High winds can also consider environmental conditions and also
propel projectiles that can damage equipment prepare ourselves for the inevitable task of
and enclosures. Equipment enclosures sealed assessing electrical equipment after natural
adequately during normal conditions may fail disasters strike. No-outage inspection
to keep out sand and dirt from extreme winds techniques are the most efficient methods to
that can subsequently contaminate insulation or provide equipment condition assessment and
migrate their way into operating mechanisms. ensure future reliability. However, equipment
exposed to natural disasters must also be
Extreme heat can also contribute to monitored for future long-term problems that
overheating and cause other equipment to be may result from abnormal conditions.
indirectly stressed due to increased heat-related
load demands. Thermal stresses can lead to
immediate failure and cause hidden long- Don A. Genutis holds a BSEE and was a
term effects by reducing overall equipment life NETA Certified Technician for more than
expectancy. 15 years. He has held various principal
If equipment is de-energized due to a direct positions during his 30-year career in the
or indirect fault, the opportunity to perform electrical testing field. He primarily focused
traditional outage-based inspections, testing, on advancing no-outage testing techniques
and field reconditioning and repairs must be for the last 15 years. Don presently serves as President of
seized. No-outage techniques should then be Halco Testing Services in Los Angeles, California.
used after the outage-based work has been
completed and power has been restored to help
ensure success.

USING NO OUTAGE TESTING TECHNIQUES FOR POST-NATURAL DISASTER TRIAGE NETAWORLD


NETAWORLD 19
THE EXPERTS IN
ELECTRICAL RELIABILITY

Comprehensive Electrical Predictive and Preventive


Testing and Maintenance Maintenance
Commissioning and Startup Partial Discharge Testing
Services and Monitoring
Engineering Services 24/7 Emergency Service
Power System and
Coordination Studies

FAILURE IS NOT AN OPTION.


Ensuring the reliability of your electrical distribution system.
As the leading independent electrical testing, maintenance, and
engineering service company, you can rely on Emersons High
Voltage Maintenance to exceed your electrical equipment
performance goals. From testing for problems that could disable
your system, to complete turnaround execution, youll quickly
understand how we are your single source solution for all of your
electrical reliability needs. With a service geography across the
Midwest and Eastern Seaboards, our service team puts experienced
professionals where and when you need them.

For more information:


High Voltage Maintenance (866) HVM-TEAM
EN G
PM IN
T
UI NT SOLID STATE
EQ RE
ST W

INDUSTRIAL ELECTRONICS
TE O
N

We Buy, Sell, Trade, Calibrate, Repair


Featuring quality, reliable, on-time service and support for all brands
and types of solid state power electronics.
Power electronics are our business
Let us suppoort you with our quality repair, calibration and servicing
of your solid state equipment. We also buy, sell and trade:
Communications devices for power equipment
Protective relays
Circuit breaker trip devices
Motor overload relays
Rating plugs

Toll Free
877-TRIP-FIX

4701 Spartan Drive Denton, TX 76207


(877-874-7349) Phone: 940-243-3731 Fax: 940-387-8277
Email: info@solidstaterepair.com Web: www.solidstaterepair.com
TECH QUIZ

No. 114

James R. (Jim) White


is the Training Director
of Shermco Industries,
PROTECTIVE RELAYING FOR
Inc., in Dallas, Texas.
He is the principal
member on the NFPA
ELECTRICAL POWER SYSTEMS
B Y JI M W H I TE , Shermco Industries
technical committee
Recommended Practice
for Electrical Equipment
Maintenance (NFPA
This issues Tech Quiz looks at protective relaying for electrical power systems.
70B). Jim represents Testing protective relays is a huge part of the protection scheme, and, if not done
NETA as an alternate accurately, can cause false tripping or worse a no-trip condition. Most protective
member of the NFPA relays today are digital and have eliminated many of the problem areas associated
Technical Committee
Electrical Safety with electromechanical relays, but they still need to have the calibration and
in the Workplace functions verified.
(NFPA 70E) and
represents NETA 1. Match the device number with the relay 3. What type of protective relay requires two
on the ASTM F18 function: voltages that can have their magnitudes and
Committee Electrical a. 50 ____ 1. Differential phase angles varied from each other?
Protective Equipment
For Workers. Jim is an b. 86 ____ 2. Undervoltage a. Undervoltage
IEEE Senior Member c. 87 ____ 3. Instantaneous overcurrent b. Overvoltage
and in 2011 received the d. 27 ____ 4. Lockout c. Percent differential
IEEE/PCIC Electrical e. 25 ____ 5. Directional overcurrent d. Synch check
Safety Excellence
award. Jim is a past
f. 67 ____ 6. Synch check e. Directional power
Chairman (2008) of the 2. A percentage differential relay with a 25 4. A type 21 protective relay would be a:
IEEE Electrical Safety
Workshop (ESW).
percent slope characteristic has 4.9 A in one a. Distance
restraint coil and 4.2 A in the other. b. ac reclosing
a. What is the calculated imbalance? c. Pilot wire
______ percent d. Ground detector
b. Will this relay operate with this imbalance? e. Excitation
Yes / No
c. Based on its characteristic, what is this relay
most likely protecting? ______ or ______
See answers on page 120.

22 SUMMER 2016 TECH QUIZ


S ELECTRICAL TESTING

CERTIFICATION PROGRAM:
SETTING
S E THE STANDARD, ENERGIZING THE FUTURE
BY K RIST EN WICK S, N E TA

An organization is only as strong as the people association. Each person who holds NETA
who belong to it. NETAs reputation as a technical Certified credentials is responsible for
leader in the electrical power systems industry representing what it means to test to the ANSI/
is built firmly on a long tradition of excellence NETA standards, assuring that the intent of
driven by the pursuit of quality, reliability, and these documents does not merely exist between
safety. This culture is a direct reflection of each the covers, but is implemented each day in the
individual who chooses to participate in NETAs field. It is a badge of honor to hold a NETA
many programs, from companies seeking NETA Certification at any level, and this is due largely
Accreditation as third-party electrical testing to the stringent requirements for certification.
firms, to implementing the use of ANSI/NETA
In the year 2000, NETAs exam blueprints
standards when field testing electrical power
became an official American National Standard
systems and equipment, to individuals who
with the publication of the ANSI/NETA ETT
elect to take the path toward becoming a NETA
Standard for Certification of Electrical Testing
Certified Technician. If NETAs Accredited
Technicians,, and are the industry standard for
Technicians
Companies are the foundation on which the
defining the required knowledge, skills, and
association is built, then NETAs Certified
abilities commensurate with competency as a
Technicians are the keystone that locks
qualified electrical testing technician. As with
everything into place. all things in life, the only constant is change.
In addition to representing their NETA In order to meet the needs of a constantly
Accredited Companies, NETA Certified evolving industry, it is necessary to refresh
Technicians are the face of NETA as an the certification program and infuse it with
new examination materials to assure that the
certification program remains robust and
consistent in its integrity as a true reflection of
the practice of electrical testing technicians.

In March of 2015, NETAs Board of Directors


approved a project to increase the associations
efforts toward certification program
development and maintenance. This project
kicked off in April of 2015 and is nearing the
final stages of the first phase of completion now

24 SUMMER 2016 NETAS ELECTRICAL TESTING TECHNICIAL CERTIFICATION PROGRAM:


SETTING THE STANDARD, ENERGIZING THE FUTURE
almost exactly a year later in May of 2016. The NETA is extremely fortunate to have members
project has seen the participation of over two- who are willing to donate one of the most
thirds of NETA Accredited Companies, whose valuable assets: their time. Their efforts assure
technicians participated in the job analysis survey continued growth and success for NETA,
in the summer of 2015. Those survey results its NETA Accredited Companies,
were the framework for a fresh look at NETAs and most of all, its NETA Certified
certification examinations. A team of 18 subject Technicians. To each company that takes
matter experts, under the leadership of NETAs
on the challenging process of applying
exam development committee, confirmed the
for NETA Accreditation, and to each
revised blueprints, and have been in the process
technician who elects to follow the path
of developing new exam questions to complete
toward certification, thank you. Your
the revised examinations for technicians Level 2,
Level 3, and Level 4. commitment to quality, reliability, and
safety is something to be proud of, and
July 2016 will be the first administration of the assures a bright future for all whose lives
new exam content based upon the redesigned are powered by the electrical equipment
blueprints. More information about the and systems in your care. Coming together is the
exam redesign project and requirements for beginning. Keeping together
certification are available on the NETA website Kristen Wicks is NETAs Technical Services is progress. Working together
at www.netaworld.org. Director. is success. Henry Ford.

RESPONSIBLE FOR ELECTRICAL POWER SYSTEM COMMISSION?


Get the ANSI/NETA Standard for Acceptance Testing and BUNDLE YOUR ORDER
the ANSI/NETA Standard for Electrical Commissioning. AND SAVE!

New!

Save 28% when you purchase the ANSI/NETA ATS 2013 and ANSI/NETA ECS 2015 together.
To order: visit www.netaworld.org, call 888.300.6382, or email neta@netaworld.org
TWO NEW SELF-PACED TECHNICAL SEMINARS
(SPTS)

Maintenance and Testing of Battery Systems Risk Assessment Techniques Using NFPA 70E: A Primer

ADDITIONAL Learn at your own pace. Advance your knowledge. Ask about
continuing education. Earn CTD*Credits for NETA Level III
COURSES and IV Technicians. Order online at: www.netaworld.org or
AVAILABLE call 888-300-6382 (NETA)
*CTDs awarded when participant receives a passing score on the prociency exam.
228 Merrick Road 601 Union Street
Lynbrook, NY 11563 Brooklyn, NY 11215
(631) 589-6343/Fax (516) 596-3680 (718) 786-4900
TECH TIPS

IN THE SOLAR INDUSTRY


BY J EFF J OWET T, Megger

Solar energy is a rapidly developing and expanding segment of the


electrical power industry, spurred by the need for additional sources
and green (i.e., environmentally friendly) generation.
In photovoltaic power generation, a miniscule contacts any of the protected equipment, the
fraction of the limitless energy of the sun is current is provided with a low impedance path
chemically converted to usable electricity. to ground that effectively shunts it around
Solar generation can provide power directly personnel while inciting protective devices to
to homes and commercial facilities and is also trip. Accordingly, the National Electrical Code
integrated into the larger power grid. The (NEC) states that exposed non-current-carrying
basic unit of generation is the solar panel metal parts of module frames, equipment, and
(module), where the suns energy is converted conductor enclosures shall be grounded. This
to electricity. The individual modules can then requirement applies to all PV systems.
be tied together into arrays, sometimes covering
vast areas of land to enhance total output. The equipment-grounding conductor runs
alongside the other conductors in the PV
Like the more common parts of the electrical circuitry. It is defined by the NEC as the
system, solar generation must be grounded. conductive path installed to connect normally
In Photovoltaic Design & Installation by Ryan non-current-carrying metal parts of equipment
Mayfield (John Wiley & Sons), Mayfield together and to the system-grounded conductor
refers to grounding as the most confusing, or to the grounding-electrode conductor, or
debatable, and fun topic in the photovoltaic both. Electrical components such as combiner
world. Just as in other segments of the grid, boxes, inverters, disconnects, battery boxes, and
effective ground protection consists of two any metallic box holding electrical equipment
distinct and inter-related parts: bonding can have a properly sized conductor connected
and grounding. Bonding (also referred to to the ground lug on the equipment and then
as equipment grounding) is the connecting to the grounding system, thereby creating an
of individual pieces of equipment in an equipment-grounding conductor (EGC). Every
equipotential network. System grounding is module must be connected to an EGC. There
the termination of the equipment grounding is often a connection point on the frame for this
at an electrode buried in the earth. This article purpose, usually in the middle of the long edge,
will examine equipment grounding first. but necessary hardware and instructions have
been reported as frequently lacking.
E QUIP M E NT GR OUNDI NG
The purpose of equipment grounding is to Two means of connection are most employed:
maintain all electrically conductive components at ground lugs and grounding clips. A ground lug
ground potential. If a live conductor accidentally (Figure 1a) is a metallic screw-type clamp. It can

28 SUMMER 2016 GROUNDING IN THE SOLAR INDUSTRY


TECH TIPS
be placed at the manufacturers suggested point After all components are bonded together,
on the module. The EGC is then screwed tight to a single EGC can be bonded to one of the
the lug. The same EGC can be run from lug rails and brought to the combiner box. This
to lug, thereby connecting the whole array. The method is not as labor-intensive, but the clips
lug must be rated for outdoor use and direct must be placed precisely as specified by the clip
burial. This option, however, can be tedious and manufacturer. Full contact with the module
time-consuming. and rack must be verified; otherwise, there is
the possibility of an open or weak bond that
would defeat the purpose of ground protection
of the array. Similarly, if a module is removed,
it must be done without disrupting the ground
continuity of any other part of the structure. If
the lug method uses a continuous conductor,
then the structure remains protected. Proper
rail bonding assures similar protection where
the clip method has been used.

The equipment-grounding conductor must


Figure 1a: Ground Lug be sized properly to accommodate maximum
prospective current. Again, the requirements
Alternatively, a grounding clip (Figure 1b) can are set forth in the NEC and are based on the
be placed between the module and the racking over-current protection device (OCPD) for the
system that composes the structure upon which system. A ground fault protection device (GFP)
the modules are mounted. The clip pierces the should also be installed in the system. Article
module frame and the racking system, metallically 690.45 provides a table that specifies the gauge
bonding the two and making the mounting rails of the EGC based on the amperage rating of the
the EGC. Be certain all the rails are connected OCPD. Not all PV systems require OCPDs.
together, which can be done prior to installation In that case, the grounding conductor is sized
of the modules. based on the short-circuit current. The same
table can be used, substituting the short-circuit
current for the OCPD of the same rating,
but no gauge smaller than 14 AWG should ever
be used.

If there is no ground fault protection device


(GFP) installed in the system, the EGC is sized
with an ampacity at least twice that of what is
called the conditions of use ampacity for the
current-carrying conductors. These parameters
are given in Tables 310.15(B)(2)(a), 310.15(B)
(2)(c), 310.16, and 310.17 of the NEC.
However, these are last-option measures, and
it is highly advantageous to have an installed
GFP. Fortunately, all grid-direct inverters come
standard with built-in GFPs, and for battery-
based systems, they are easy to integrate.

In addition to considering the potential damage


to undersized conductors from over-currents,
Figure 1b: Grounding Clip the possibility of physical damage should also

GROUNDING IN THE SOLAR INDUSTRY NETAWORLD


NETAWORLD 29
TECH TIPS
be taken into account. If such risk exists, the idea that the foundation steel already in place
EGC can be protected in conduit or be at least would serve.)
6 AWG, as the heavier gauge will withstand
physical abuse that might damage a lighter GROUNDING ELECTRODE
gauge. In the PV industry, EGCs are most CONDUCTOR
commonly bare copper. Within conduit, either The second essential element in system
bare copper or insulated ground conductors are grounding is the grounding electrode
used. Using building wiring for ground wire in
conductor (GEC).This is a conductor that
conduit is acceptable.
connects the rod(s) or Ufer to a point where
Finally, all the current-carrying protection all the other grounded conductors can be
of equipment grounding will be lost if not connected. A good example is a 6 AWG or
connected to adequate system grounding. 4 AWG wire from the grounding electrode
Currents traveling on the grounding conductors at one end to the ground busbar inside the main
must be diverted to earth at low impedance distribution panel (MDP) at the other end.
to not exploit unwanted paths through Article 690.47 is the principal NEC reference.
equipment and personnel. This function
If the PV system is utility-interactive, either
requires an adequate grounding electrode (GE)
grid-direct or battery-based, the PV system
making contact with the surrounding earth.
grounding is then paralleled with the existing
The most commonly recognized electrode
utility system ground. Electrically separate
is the ground rod, often a copper rod driven
grounds can develop voltage gradients between
eight feet into the earth. For a better ground,
them that will behave counter to the purpose
or in poorly conductive soil, a deeper rod can
of the grounding system, causing ground
be driven. Also, extra rods can be added and
currents to flow into an electrical system.
paralleled together with a conductor. To avoid
Paralleling them together brings them to the
the two rods behaving as only one, the second
same potential. There are two common ways
rod is added at a horizontal distance slightly to make the system-grounding connection in a
greater than its depth. A second rod will utility-interactive system.
generally decrease ground resistance by about
40 percent, but additional rods invoke the Law One is to connect an additional ground rod
of Diminishing Returns, as increments become or two to the inverter system grounding (6
progressively smaller. AWG GEC recommended) and parallel it to
the existing utility electrode (Figure 2 top).
The solar industry also uses the Ufer This must be done with a GEC of the same
ground. For roof-mounted arrays, the steel gauge as the existing utility GEC. A second
reinforcement of the concrete foundation may method is to run a GEC from the inverter to
be used to make contact with the earth. It is the existing utility electrode (Figure 2 bottom).
a good idea, however, to augment this with a This conductor would be sized according to
parallel ground rod, as lightning strikes can NEC requirements. For stand-alone, battery-
damage foundations by vaporizing the trapped based systems (the solar array is providing the
moisture in the concrete. (Historical note: Ufer sole source of electricity to the ac load), a utility
is not an acronym, as sometimes reported. It ground is unavailable, so a new grounding
is actually the name of Herbert G. Ufer, the electrode must be installed. Two 6 AWG or
electrical engineer who pioneered the method. 4 AWG GECs must then be connected, one
During WWII, a method was needed to safely from the dc wiring enclosure where the inverter
ground ammunition bunkers at obvious connects to the battery bank and the other
risk and it was Ufer who came up with the from the ac MDP.

30 SUMMER 2016 GROUNDING IN THE SOLAR INDUSTRY


For utility-interactive systems, a GEC will
already be in place from the original contractor.
Stand-alone, battery-based systems require the
installation of a new GE and GEC. The GE is
installed as close to the MDP as possible. If the
GEC is run outside without conduit, it should
be at least 6 AWG. The robustness of this gauge
is considered sufficient to provide physical
protection. If the GEC can be run without
exposure to physical damage, an 8 AWG
conductor for the dc side may be adequate.

Jeffrey R. Jowett is a Senior Applications


Engineer for Megger in Valley Forge,
Figure 2: Two Common Ways to Make Pennsylvania, serving the manufacturing
System-Grounding Connection in a Utility- lines of Biddle, Megger, and multi-Amp
Interactive System for electrical test and measurement
instrumentation. He holds a BS in Biology
As to sizing the GEC, Article 250.66 of the and Chemistry from Ursinus College. He was employed for
NEC describes the requirements for the ac 22 years with James G. Biddle Co. which became Biddle
side, and Article 250.166 covers the dc side. Instruments and is now Megger.

ANSI/NETA MTS - 2015 UPDATED EDITION

To learn more about the newest edition of the

ORDER NOW! ANSI/NETA MTS Standard for Maintenance Testing


Specifications, visit netaworld.org/standards.
CALL FOR SPONSORS
A premier reservation.
Sponsorships are now available.
+ Reach hundreds of leading
decisionmakers at PowerTest
+ Receive advertising and press reaching
24,000+ industry professionals before,
during, and after the event
+ Available in all price ranges

A N A H E I M C A L I F O R N I A POWERTEST.ORG 888.300.6382

February 27 - March 3 2017 THE PREMIER ELECTRICAL MAINTENANCE & SAFETY EVENT

DISNE Y L A ND HO T E L
NEW eBOOK
PACKED FULL OF TECHNICAL INFORMATION!

ELECTRICAL CIRCUIT BREAKERS,


FUSES AND PROTECTIVE RELAYS
by L.W. Brittian

900+ pages

200+ pictures

125+ Charts and Tables

Reliable Power System Solutions Only $5.99


We deliver optimum system reliability and performance while reducing the
chances of costly unplanned power outages. Whether you need acceptance
testing or preventive maintenance, depend on EnerGTest to keep the power on.
Achieve specialist level knowledge
of Circuit Breakers, Fuses, and
Protective Relays with this
ener es

Accredited Company
convenient take-anywhere eBook.
Serving clients in Pennsylvania, Delaware, New Jersey,
Maryland, Washington, DC and New England. AVAILABLE NOW ON AMAZON.COM
204 Gale Lane Kennett Square, PA 19348 484.731.0200 enerGtest.com
IN THE KINDLE STORE
SAFETY CORNER

AND ELECTRIC
A CAL HAZARD FOOTWEAR
B Y PA U L CH AM BERL AIN, American Electrical Testing Co., Inc.

Everyone wears clothes. However, not everyone needs to wear


clothes designed to protect from the inherent hazards in their job.
If employees work on electric power generation, transmission,
and distribution equipment, then special clothing is necessary
for certain tasks.
Per OSHA Regulation 29 CFR 1910.269, could ignite the employees clothing,
employers need to assess a workplace and 3. Molten metal or electric arcs from faulted
whether an employee will be exposed to the conductors in the work area could ignite
hazards of flames or electric arcs. Upon finding the employees clothing, or
a potential for exposure, the employer must 4. The incident heat energy exceeds 2.0 cal/
estimate the potential incident heat energy cm2.
the employee could be exposed to and provide
the employee with the appropriate personal Per NFPA 70E 2015 Standard for Electrical Safety
protective equipment (PPE). In addition, if in the Workplace, the employer must provide
employees will be exposed to flames and arcs, arc-rated (AR) clothing for potential arc-flash
the employer must ensure that the material hazards in an atmosphere not regulated by
worn by employees is not untreated meltable the OSHA 1910.269 standard. Section 130.4
fabric (e.g., polyester, rayon, fleece, natural and 130.6 of NFPA 70E clearly states that it is
fiber blended with meltable fibers, etc.). the employers responsibility to identify the
Available materials are listed in ASTM F1506 hazards and provide the necessary AR clothing
Flame Resistant and Arc Rated Textile Materials to mitigate those hazards. It also instructs
for Wearing Apparel for Use by Electrical the employee in proper inspection of that PPE.
Workers Exposed to Momentary Electric Arc
and Related Thermal Hazards. Once it is determined that flame-resistant clothing
is required, the employer must provide clothing
Further, in regulation 1910.269, OSHA states: that is appropriately rated for the potential
The employer shall ensure that the outer layer of hazard. In 1910.269, OSHA further states:
clothing worn by an employee, except for The employer shall ensure that each employee
clothing not required to be arc rated, is flame exposed to hazards from electric arcs wears
resistant under any of the following conditions: protective clothing and other protective
1. The employee is exposed to contact with equipment with an arc rating greater
energized circuit parts operating at more than or equal to the heat energy estimated
than 600 volts, whenever that estimate exceeds 2.0 cal/cm2.
2. An electric arc could ignite flammable This protective equipment shall cover the
material in the work area that, in turn, employees entire body, except as follows:

34 SUMMER 2016 ARC-RATED CLOTHING AND ELECTRICAL HAZARD FOOTWEAR


SAFETY CORNER

1. Arc-rated protection is not necessary for the


employees hands when the employee is
wearing rubber insulating gloves with
protectors, or, if the estimated incident
energy is no more than 14 cal/cm2,
heavy-duty leather work gloves with a
weight of at least 407 gm/m2 (12 oz/yd2),
2. Arc-rated protection is not necessary for
the employees feet when the employee
is wearing heavy-duty work shoes or boots,
3. Arc-rated protection is not necessary
for the employees head when the
employee is wearing head protection The other aspect to employee training is
meeting 1910.135 if the estimated care of their PPE. If it is worn, damaged, or
incident energy is less than 9 cal/cm2 deteriorated, then it cannot adequately protect
for exposures involving single-phase arcs them from potential hazards. Employees must
in open air or 5 cal/cm2 for other exposures, learn to inspect all PPE prior to and after
4. The protection for the employees head use. A guideline in the inspection and care of
may consist of head protection meeting AR clothing is found in ASTM F1449
1910.135 and a face shield with a Standard Guide for Industrial Laundering of
minimum arc rating of 8 cal/cm2 if Flame, Thermal, and Arc Resistant Clothing
the estimated incident-energy exposure is and ASTM F2757 Standard Guide for Home
less than 13 cal/cm2 for exposures involving Laundering Care and Maintenance of Flame,
single-phase arcs in open air or 9 cal/cm2 Thermal and Arc Resistant Clothing.
Clothing. These
for other exposures, and ASTM standards are a requirement for
5. For exposures involving single-phase arcs management of AR clothing, whether laundered
in open air, the arc rating for the at home or commercially. Many AR clothing
employees head and face protection may manufacturers offer helpful online aids to
be 4 cal/cm2 less than the estimated provide guidance to employees on the proper
incident energy. use, care, and maintenance of AR clothing.

As the potential incident energy increases,


so must the protection level provided to the
employee. Again, it is the employers
responsibility to assess the workplace, identify
potential hazards, and provide adequate
protection to the hazard.

Training employees in the proper use and


care of the PPE provided is very important.
Employees ability to identify electrical
hazards, their knowledge of electrical equipment
and its nominal voltage, and understanding
when proper PPE is required are vitally If they will be exposed to the hazard of flames
important and will go a long way in ensuring or electrical arc, employees must also wear
that they are protecting themselves from heavy-duty work boots or shoes. Per OSHA
potential hazards. 29 CFR 1910.136(a): Each affected employee

ARC-RATED CLOTHING AND ELECTRICAL HAZARD FOOTWEAR NETAWORLD 35


SAFETY CORNER
shall wear protective footwear when working in Proper care of footwear is also very important.
areas where there is a danger of foot injuries due Exposed toe caps indicate a breakthrough
to falling or rolling objects, or objects piercing the in the leather of the boot, providing less arc
sole, and where such employees feet are exposed to and flame protection. Simple things such as
electrical hazards. broken, missing, or overly long laces can pose
a simple trip hazard, which can cause serious
Likely, the boot or shoe will also need to be injury. Wear in the sole of the boot exposes the
safety-toed and meet ASTM F2413 Standard employee to step potential during a ground
Specification for Performance Requirements fault. Spilled flammable materials can soak into
for Protective (Safety) Toe Cap Footwear.
Footwear. a leather boot, possibly causing a flame hazard.
Additionally, the boots must be electrical Therefore, cleaning and maintaining boots and
hazard-rated footwear (EH). EH footwear is shoes used for protection is highly important.
manufactured with non-conductive, electrical-
shock-resistant soles and heels. The outsole Wearing the correct AR clothing and boots
provides a secondary source of electric-shock- protects employees from many potential
resistance protection to the wearer against hazards. Ensuring that this equipment is clean
the hazards from an incidental contact with and well maintained is an important step in
live electrical circuits, electrically energized providing adequate protection to the wearer.
conductors, parts, or apparatus. It must be Knowledge of how to inspect, clean, and
capable of withstanding the application of maintain these garments and footwear must
18,000 volts at 60 hertz for one minute with be given to the employee by the employer to
no current flow or leakage current in excess of ensure a safe and productive workplace.
one milliampere under dry conditions. Should
the assessed potential exceed this, protection
such as rubber dielectric over boots or shoes Paul Chamberlain has been
will be required. the Safety Manager for American
Electrical Testing Co., Inc. since
2009. He has been in the safety field
for the past 17 years, working for
various companies and in various
industries. He received a bachelor
of science degree from Massachusetts
Maritime Academy.

36 SUMMER 2016 ARC-RATED CLOTHING AND ELECTRICAL HAZARD FOOTWEAR


1 965-2
965-201
015
5

Electro Rent is Now


Electro Now a NETA
NETA Go Gold
ld
Electro
Electr o Rent Tur
urns
ns 50 YEARS
Corpor
Cor poraate Alliance Par
artner
tner

Electro Rent answers


your every test need.
Largest inventory
NOW IN HOUSTON
Consistent, reliable delivery service
Immediate availability Electro Rent is proud to
introduce its new Regional
ISO and ANSI accredited labs Service Center, serving your
test needs better and faster
than ever with experienced
customer support 24x7. If it
Learn more at:
www.electr
www .electror
orent.com/electr
ent.com/electrica
ical-po
l-pow
wer tests, weve got it and were
800.304.4744 | sales@electrorent.com ready to deliver in Houston.

Vanguard Instruments Company, Inc.


www.vanguard-instruments.com
RELAY COLUMN
The users, owners, and operators of the bulk should not coordinate with a distance element;
power system within these areas account for while the distance element has a fixed reach,
virtually all the electricity supplied in the the effective reach of the overcurrent element
United States, Canada, and a portion of Baja is dependent upon the strength of the source.
California Norte, Mxico. NERC released
an official report in May 2013 that featured Misoperations due to setting errors can be
statistics for protection misoperations across reduced using the following techniques:
the entire country. Peer reviews
Increased training
Major disturbances are ranked using a Daily More extensive fault studies
Severity Risk Index. These include the following Standard-setting templates for standard
blackouts: schemes
1989 Quebec Solar Flare Periodic review of existing settings when
1996 Western Disturbance there is a change in system topography
2003 Eastern Interconnection Blackout
Remember that the greater the complexity
Primarily, misoperations resulted due to the of the protection scheme, the greater risk of
following reasons (Figure 2): misoperation. Simplicity is elegance.
Incorrect settings/logic/design errors
Communication failure MI SOPERATI ON ANALY SIS
Relay failure or malfunction 87 Generator Phase Dierential Protection
The customer reported a questionable generator
These events include human error during protection relay trip. There are two main
testing and maintenance activities. These errors protection relays provided by different
result in protection system activation that has manufacturers, but only one operated.
contributed to large disturbance events.
Review of the relay settings revealed that the
relay that did not trip had a higher pickup
setting by a factor greater than four times. The
CTs have a knee point of 100 volts or less,
which is low, and there was the presence of
heavy dc offset in the C-Phase current (Figure 3).

Figure 2: NERC 2012 Misoperation Table

Most of these misoperations contribute to


increasing Security Risk Index (SRI) and indicate
that the number of transmission element outages
is increasing.

C OR R E C T IVE AC TI ONS Figure 3: C-Phase Neutral Side CT Excitation


Applications requiring coordination of Characteristic
functionally different relay elements should
be avoided. This type of coordination is Figures 4A and 4B show the high levels of dc offset
almost always problematic and is the cause of present in C-Phase current during the event.
numerous misoperations reported in the study In fact, dc offset current is the number-one
period. For example, an overcurrent element cause of CT saturation.

40 SUMMER 2016 IMPROVING SYSTEM PROTECTION RELIABILITY AND SECURITY


RELAY COLUMN
The blue triangle in Figure 6 corresponds to the
C-Phase operating point, which was just on the
boundary of operation. The misoperation occurred
when the current was coming out of saturation.

Figure 4A: Generator C-Phase Current

Figure 6: 87 Phase Differential Operating Characteristic

The dc offset present in fault current exponentially


decays as shown in Figure 7. The digital Fourier
transform algorithm cannot fully reject it.

Figure 4B: Generator C-Phase Differential Current

Here is the minimum pickup for the relay that


did not operate:

TapO87P = (4.4 amps)(0.3) = 1.32 amps

As shown in Figure 5, the customer copied the


settings from an arbitrary example in the
Figure 7: DC Offset Current
manufacturer relay instruction book. The relay
that tripped was more than four times as sensitive.
Best Practice: If the dc offset from transformer
inrush (e.g., black start) or fault condition can
cause CT saturation, then the following are
appropriate for generator phase differential
protection settings:
Minimum pickup up to 0.5 amps secondary
Slope of 20 percent
Time delay up to 5 8 cycles

Detailed calculations are necessary for generator


differential protection to determine if CTs can
saturate; do not simply copy settings from the
relay instruction book without actual verification.

Higher C-class CTs can help to mitigate saturation


Figure 5: Nominal Current Calculations (Figure 8).

IMPROVING SYSTEM PROTECTION RELIABILITY AND SECURITY NETAWORLD 41


RELAY COLUMN
operating conditions. If failure occurs in the
lower voltage portion of winding near neutral, a
generator trip will not typically occur until some
other relay protection detects a problem (e.g.,
arcing becomes so widespread that other portions
of winding become involved). 27TN sees stator
ground faults very close to the machine neutral as
shown in Figure 10.

Figure 8: CT Saturation Calculation

VCTMAX = 2(RCT + 2Rlead + Rburden)

The factor of 2 accounts for a fully offset current


waveform, which is worse case.

27TN Third Harmonic Neutral Undervoltage


A utility experienced several misoperations when
Figure 10: 27TN and 59N Zones of Stator
system voltage was low. However, the trip shown
Ground Fault Protection
in Figure 9 occurred when the machine was
under-excited and drawing vars from the system.
Third-harmonic neutral voltage changes as a
function of load. The pickup setting is typically
set equal to one-half of the minimum value
measured during normal operation. Figure 11
illustrates how complex it can be to securely set
27TN protection through the blocking functions.

Figure 9: Machine Real and Reactive Power at


Time of 27TN Trip

The machine nominal power is 746.5 watts


secondary.
Figure 11: 27TN Settings
Conventional protection (59N) cannot detect
grounds in the last five to 10 percent of the stator The solution for this particular machine is
winding. Actually, 27TN is not always reliable to block on low-forward power as this is the
and may have to be blocked during specific prevailing system condition when the nuisance

42 SUMMER 2016 IMPROVING SYSTEM PROTECTION RELIABILITY AND SECURITY


trip occurs. The main drawback to this solution
is no protection for stator ground faults close to
neutral during this operating condition.

Best Practice: The customer was urged to


considering installation of 100 percent stator
ground fault protection using sub-harmonic
voltage injection (64S), which they did (Figure 12).

Figure 13B: Core and Winding Damage Burned


Open Bar in a Slot

Figure 12: 64S Protection Connection


Recent experience with four such failures in
large generators demonstrates that lack of proper
protection can be disastrous. Each of the four
failures caused massive damage to generators and Figure 13C: Burned Away Copper - Fractured
collectively had total cost, including repair and Connection Ring
loss of generation, close to $500 million. This
demonstrates that the failure of stator windings
64S provides the following advantages:
in the last five percent of the winding is not
Detects stator ground when winding
uncommon. See Figures 13A, 13B and 13C.
insulation first starts to break down and trips
unit before catastrophic damage occurs.
Trips in order of cycles since 20 Hz signal is
decoupled from 60 Hz power system.
Detects grounds close to machine neutral
or even right at neutral providing 100
percent coverage of stator windings.
Detects grounds when machine is starting up
or offline.
Reliably operates with generator in various
operating modes (such as a synchronous
condenser) and at all levels of real and reactive
power output.
Commissions in less than one hour, assuming
Figure 13A: Winding Damage Broken there are no wiring errors. See Figure 14.
Stator Winding Conductor

IMPROVING SYSTEM PROTECTION RELIABILITY AND SECURITY NETAWORLD 43


Sequence of events:
40 operates on Z1 (positive-sequence
impedance).
40 measures incorrect impedance due to
wrong phase rotation setting.
40 trips each time customer attempts to
synch the generator to the grid.

The second misoperation was 78 out-of-step


protection (Figure 17).
Figure 14: Numerical Generator Relay 20 Hz
Metering

Incorrect Phase Rotation Settings


Numerical protection relays require a setting to
determine the correct phase rotation. Figure 15
illustrates ABC phase rotation; however, some
power systems are ACB.

Figure 17: 78 Out-of-Step Protection

Sequence of events:
78 operates on Z1 (positive-sequence
impedance).
Figure 15: ABC Phase Rotation 78 measures incorrect impedance due to
wrong phase rotation setting.
78 tripped during external event.
Two customers experienced generator protection
misoperations due to incorrect phase rotation How did either incorrect relay setting make it
settings. The first misoperation was 40 loss-of- past commissioning? Both elements (40 and
field protection (Figure 16). 78) were effectively operating on Z2 (negative-
sequence impedance) due to the incorrect
phase rotation settings.

Best Practice: Modern numerical relays have


built-in tools to determine the actual phase
rotation. Phase rotation can quickly be checked
using numerical relay metering.

CONCLUSI ON
The 2013 NERC report covered relay In the
2013 NERC report on relay misoperations
across the country, over one-third of the total
events were due to incorrect setting, logic,
testing, and design errors. Simplified software
Figure 16: 40 Loss-of-Field Protection

44 SUMMER 2016 IMPROVING SYSTEM PROTECTION RELIABILITY AND SECURITY


for complex applications and visualization
tools can enhance proper relay settings and Steve Turner, an IEEE Senior Member,
is a Senior Applications Engineer at
operation. And finally, correction actions Beckwith Electric Company. His previous
must be taken such as peer reviews, training, experience includes work as an application
analysis, the use of standards-setting templates, engineer with GEC Alstom, and as an
and periodic reviews. application engineer in the international
market for SEL, focusing on transmission
line protection applications. Steve worked for Duke Energy
(formerly Progress Energy), where he developed a patent
for double-ended fault location on overhead transmission
lines. He has a BSEE and MSEE from Virginia Tech.
Steve has presented at numerous conferences including
Georgia Tech Protective Relay Conference, Western Protective
Relay Conference, Energy Council of the Northeast
(ECNE), and Doble User Groups, as well as various
international conferences.
FINLEY LEDBETTER:
NETA Will Bring Together People
From All Over The World
BY CARL A K AL OG ERIDIS, NETA

Congratulations! Finley Ledbetter receives the 2016 Alliance Recognition Award from Jim Cialdea.

NETA 2016 Alliance Recognition Award honoree Systems. I believe he hired me to be quarterback, but
Finley Ledbetter is an ideas man, an entrepreneur at then made me coach and waterboy also, Schofield says.
heart. But as good as he is with numbers and
recognizing a great business opportunity, Ledbetter Schofield remembers the day he interviewed with
has always put people first. CBS. Finley was giving him a tour, and they happened
upon a delivery driver. Ledbetter had heard that the
Bill Schofield, president of Ledbetters flagship driver was in an on-the-job accident the day before.
company, Circuit Breaker Sales (CBS), has worked for Schofield was impressed by Ledbetters sincere concern
Ledbetter for 18 years. In July 1998, Ledbetter for the driver without a mention about the damage to
purchased Schofields former company, Astro Power the company truck. You could see the genuine concern
on his face making sure that the driver was OK, NETA into more of a worldwide organization. When
Schofield says. you look at how far its come to date, its certainly
possible, and its what needs to happen, he says. I see
The driver assured Ledbetter that he was fine, but the future of NETA as bringing together people from
confessed that the truck was messed up. Schofield recalls all over the world.
that Finley casually replied, Well, you were wanting a
new truck anyhow, so I guess you better go get one. A SOLUTI ONS-DRI VEN LEADER
I was very impressed with the fact that Finley only Finley Ledbetter has worked in power engineering for
cared about his people, not his stuff, Schofield says, 35 years, including serving as an applications engineer
and to this day, I think it is the same. and instructor for the Multi-Amp Institute. He was
instrumental in founding Shermco Engineering
Schofield says Finley is an excellent businessman and Services Division, a division of Shermco Industries,
has a great mind for numbers, ideas, and execution. which later became a NETA Accredited Company.
He is not afraid to take a chance, nor too proud to
admit when something is not working. In 1982, Ledbetter founded Group CBS, Inc.,
which now owns 12 circuit breaker service shops in
Over the last decade, Finley has hired lots of great, the United States. He is a member of IEEE and his
talented folks and given them the freedom to champion company, Circuit Breaker Sales Co., Inc., is a NETA
their own segments of the business, Schofield says. I Corporate Alliance Partner. In addition, Ledbetter is
am proud to call him my partner in several businesses a charter member and past president of Professional
and my friend in life. Electrical Apparatus Recyclers League (PEARL),
bringing to the organization the quality standards he
F U TU R E O F NE TA had already established at his own company. He was a
The Alliance Recognition Award is NETAs way of key contributor to the PEARL standards.
honoring worthy contributors to the electrical testing
industry people like Finley Ledbetter who have In presenting the NETA Alliance Award to Ledbetter
not only been dedicated supporters of NETA and the at PowerTest 2016, Jim Cialdea, Owner and CEO
work of the association, but also have furthered the of 3-C Electrical Company, underscored Ledbetters
industry and inspired others to do the same. Presented role in establishing the used equipment market.
annually at PowerTest, this years honor went to Finley worked to take the used equipment industry
Ledbetter in recognition of his example of how to to a higher standard of quality, Cialdea says. He
achieve personal success, take good care of employees was one of the first to put time, effort, and money
and customers, and still have time to devote to making into developing procedures that redefined the
the industry stronger. reconditioned, remanufactured industry.

Ledbetter accomplished much of his work for the As an ideas guy and an entrepreneur, Finley is motivated
industry as a long-time supporter of NETA, including when he sees a need to develop a product or service
presenting and sponsoring at PowerTest as well as solution, Cialdea says. He is a guy you can count on,
authoring articles. Ive come to all of the NETA someone who puts 150 percent into everything he does.
conferences since the second one in 1977, Ledbetter Schofield emphasizes that Finley is not looking for
says. I started as one of the youngest, and now Im awards or pats on the back; rather, he seeks a higher
one of the oldest. personal satisfaction. When one of our customers
Over the last 10 years, NETA has really upped its brags that we solved their problem when nobody
industry presence and leadership, Ledbetter says. else could or that we spent hours on R&D to figure
NETA has become a serious technical organization something out, that is what makes Finley smile,
where it doesnt matter who you are, but what you do, Schofield says. He is constantly thinking of new and
he explains. If you bring value to the group through innovative ways to approach things in our electrical
good ideas, youll have stature. segment. There is no other equivalent individual who
puts as much energy, effort, and brainpower into the
Ledbetter believes the next 10 years will develop industry as Finley does.
F OC U S E D ON FA M ILIES
Cialdea describes Ledbetter as laid back, un-
presumptuous, and softspoken, someone who likes to
have fun and is a huge basketball fan. He is husband to
Joni Ledbetter and father to three sons and a daughter.
All four of his children are involved with Group CBS
in different capacities and in different companies
although daughter Ashley McWhorter says he
gave us a lot of choices, and we all had opportunities
to go do other things.

Growing up, McWhorter remembers her father


traveling a great deal, building the Group CBS
companies. Now, working for him, you see how hard
he works and see him in a whole new light, she says.
It is amazing and enlightening to see all the things he
has accomplished over some 30 years, including how
he took care of our family growing up as well as the
hundreds of families that work for him.
Finley gets children involved in the business early.
McWhorter says her father is always busy and not one
to take stock of what he has accomplished or what he
contributes. He just keeps moving and creating, she
says. McWhorter adds that the Alliance Recognition
Award means a lot to him, and even though he doesnt
say much about it, you know what he is feeling.

McWhorter says her father is happiest when surrounded


by family especially when he and wife Joni are on
their way to the ranch for the weekend knowing all
the kids and grandkids will be heading there, too. He
loves to watch Mom driving her bulldozer, the kids
feeding the cows, and the grandkids chasing frogs,
she says. If he can find the elusive golden circuit Finley, Finley III, and daughter Ashley Ledbetter
breaker, that will be just the icing on the top. McWhorter at PowerTest 2016. Finley keeps his family
close. All of his children are involved in the Group CBS
Carla Kalogeridis is part of the NETA World Journal businesses and are SMEs.
editorial team.

Meet Finley Ledbetter, NETAs 2016 Alliance Partner Honoree


Over the years, Finley Ledbetter has started and sold more than 40 companies, including well-known
organizations like Instel and Sentinel Power Services. In fact, he is connected in one way or another to
numerous NETA Alliance Companies and industry suppliers.

Ledbetter graduated with a degree in electrical engineering from the University of Texas, Arlington.
While still in college, Ledbetter interned at Multi-Amp and later ADE, and was hired by the firm upon
graduation. From there he went to Round House, and then on to Shermco Industries where he
developed its Engineering Services Division. In 1982, he became a founding partner in Group CBS
and currently leads 17 Group CBS companies. Finley Ledbetter is still focused on coming up with the
next idea.
DONT SAY GOODBYE TO
YOUR OLD POWER/VAC
CIRCUIT BREAKERS
Extend their life, avoid downtime, and save $$$ with
NEW Encapsulated Pole replacement assemblies

EXTEND THE LIFE OF YOUR POWER/VAC CIRCUIT


BREAKERS WITH NEW ENCAPSULATED POLES
EPOXY-ENCASED POLES RESIST CONTAMINATION, MOISTURE,
AND OTHER ADVERSE ENVIRONMENTAL CONDITIONS

EXTENDS THE LIFE OF YOUR BREAKER, ALLOWING RE-USE OF


TRUSTED USA-MADE MECHANISM
FUTURE MODELS WILL ACCOMMODATE ALL POWER/VAC
RATINGS UP TO 27 kV AND 63 kA

13765 BETA ROAD, FARMERS BRANCH, TEXAS 75244 | 214-442-5877


VACUUMINTERRUPTERSINC.COM | INFO@VACUUMINTERRUPTERSINC.COM

One of these is a brand new vacuum interrupter.


The other two are 30-year-old hand grenades.

Need a
vacuum interrupter
from
We have it in stock.
And replacements for every
other vacuum breaker Which one is in your circuit breaker?
ever made too!
MAC-TS4
The worlds rst predictive test system for vacuum interrupters
13765 BETA ROAD, FARMERS BRANCH, TEXAS 75244 | 214-442-5877
LEARN
VACUUMINTERRUPTERSINC.COM | INFO@VACUUMINTERRUPTERSINC.COM MORE AT
VACUUMTESTING.COM
US PATENT NO. 9,031,795 B1 Replacement vacuum interrupters | Vacuum interrupter test systems | Portable circuit breaker timer test systems
Years of Experience
25 Years of Reliability

FULL SERVICE INDEPENDENT ELECTRICAL TESTING

Acceptance Testing Services


Low, Medium, and High Voltage
 4VCTUBUJPOT t %JTUSJCVUJPO TXJUDIHFBSt 5SBOTGPSNFST t $BCMFT t 3FMBZT
Preventative Maintenance & Testing
Switchgear
 *OGSBSFETVSWFZTt$JSDVJUCSFBLFSTt3FMBZUFTUJOHBOEDBMJCSBUJPO
 5SBOTGFSTXJUDIFTt$PNQMFUFNBJOUFOBODFPG"$#T0$#T4'$#T
 614TUBUJPOCBUUFSZNBJOUFOBODFt(FOMPBEUFTUT
Transformers
 553t1PXFSGBDUPSUFTUJOHt0JMUFTUJOHBOEFMEBOBMZTJT
 0JMSFDPOEJUJPOJOHSFDMBJNJOHtFMESFQMBDFNFOUT
Engineering Services
 "SDBTI TIPSUDJSDVJU BOEDPPSEJOBUJPOTUVEJFT
 1PXFSGBDUPSDPSSFDUJPOt1PXFSRVBMJUZBOEIBSNPOJDTUVEJFT
 -PBETVSWFZTt(SPVOEJOHTZTUFNEFTJHO
5SVTU VT UP LFFQ ZPVS CVTJOFTT VQ BOE SVOOJOH $BMM GPS B GSFF DPOTVMUBUJPO UPEBZ
781-767-0888
Email: infrared.ma@verizon.net
152 Centre Street
Holbrook, MA 02343
www.Infraredbps.com

Independent Electrical Testing and Preventive Maintenance


PROFESSIONAL SERVICES
(JJLW[HUJL;LZ[PUN ;YHUZMVYTLY6PS(UHS`ZPZ=HJ\\T
7SHUULK,SLJ[YPJHS;LZ[PUNHUK7YL]LU[P]L +LNHZZPUNHUK9LWHPY
4HPU[LUHUJL7YVNYHTZ *PYJ\P[)YLHRLY9L[YV[HUK9LWHPY
7V^LY-HJ[VY;LZ[PUN 7V^LY.LULYH[PVU:`Z[LTZ;LZ[PUN
*HISL;LZ[PUN 3VHKHUK7V^LY8\HSP[`9LJVYKPUN(UHS`ZPZ
9LSH` 4L[LY*HSPIYH[PVU *OPSSLY:`Z[LTZ;LZ[PUN
.YV\UK9LZPZ[HUJL;LZ[PUN 0UMYHYLK0UZWLJ[PVUZ
609-890-8300 www.easternhighvoltage.com
(:.VSK+YP]L9VIIPUZ]PSSL51 
Ron Widup, PowerTest Conference Chair, welcomes a packed opening session.

DEEP IN THE HEART OF TEXAS, POWERTEST


2016 COMES TO FORT WORTH
As they say, Everythings bigger in Texas, which have traveled its winding history to build a stronger
this year, included the opportunities for learning at electrical power industry with technicians, engineers,
PowerTest 2016, held in the states fifth-largest city, and professionals fiercely committed to education
Fort Worth. and improving the industry. This years technical
session line-up helped industry professionals grab the
PowerTest attendance continues to grow each year, bull by the horns and ride to the top of their game.
with record numbers in 2016. Individuals attending
PowerTest are the boots on the ground as well as
POWERTEST MONDAY
the messengers who take information, technology,
Monday morning, the registration area is energized
and solutions gathered at PowerTest back home to
as attendees converge for a week of high-powered
their companies. PowerTest is recognized as one of
learning, networking, and a fabulous breakfast
the best educational and networking events in the
sponsored by Circuit Breaker Sales. After filling
electrical power testing industry.
up on omelets and coffee, attendees sauntered
Fort Worth shares several common traits with the into the Welcoming Address from Conference
electrical power testing industry. For example, Fort Chair Ron Widup. Ron reminded everyone to
Worth is a community ready to take on modern be safe, explained the weeks order of events, and
challenges for expansion and growth. Its cattle and introduced Keynote Speaker Gary Norland.
oil heritage is interwoven with an array of diverse
industries that make the city an exciting place to live Gary Norland, survivor of a horrific 12,500 volt
and visit. 200 amp overhead power line shock, shared his
unforgettable story to a filled room. Gary emphasized
Similarly, this premier electrical maintenance and his message that hard work and dedication to your
safety event brings together industry experts who job should be a focus but not your only focus.
The impact of an injury goes beyond the physical Alliance Committee Chair, and member of the
challenges, impacting not only you but your Membership Review Committee, Technical Exam
friends and family in ways you cannot imagine. Committee, and Standards Review Council.
He wants people to understand that if you dont
take safety seriously, your life could resemble his Attendees reconvened in the main ballroom for
in less than a second. the New Product Forum before heading upstairs
to the 11 excellent hospitality suites hosted
Following the opening sessions, attendees by BCS Switchgear, Inc.; Doble Engineering
broke into smaller segments for a total of 28 Company; Electric Power Systems; Electro Rent
technical presentations available in five different Corporation; Group CBS, Inc.; IBEW LU 269;
tracks: Electrical Safety, Reliability, Equipment, Megger and AVO Training Institute, Inc.; Protec
Circuit Breakers, and Electrical Commissioning. Equipment Resources; RESA Power Solutions;
These tracks pack a lot of information into Shermco Industries; and SMC International.
each 45-minute presentation, in addition to Each year, suite hosts up the ante with more
a four-hour symposium where attendees can creative ideas to entice attendees through their
participate in discussion led by a moderator and doors, and this year was no exception. A winner-
panel of subject matter experts. This year, Ron takes-all casino night, performances from Patsy
Widup led the Technical Reports Symposium, Cline and Dolly Parton entertainer look-a-likes,
providing attendees an opportunity to interact
with subject-matter experts on technical report
writing, structure, readability, and professional
style and framework.

In the midst of this packed schedule, NETA


Members and Alliance Partners find a little time
to relax and enjoy a meal together during the
NETA Member and Alliance Luncheon. This
event features technical roundtable discussions
that are summarized and reported on during
dessert. This is also the venue that hosts the
annual NETA Alliance Recognition Award PowerTest attendees participate in Mondays
for an Alliance Partner who has demonstrated technical tracks.
exceptional dedication to bettering the industry
through service to NETA. This year, Finley
a kick-up-your-heels-and-dance blues band, and
Ledbetter, founder of Group CBS, Inc., was called
the Dallas Mav ManiAACs were just some of
to the stage and recognized for his many years of
the thrilling attractions this year. Attendees had
dedication to the industry and his contributions
a lot of fun while creating new relationships and
to NETA.
reconnecting with business associates and friends,
Additionally, the NETA Outstanding Achievement making this night a favorite among attendees and
Award is presented to a NETA Member who, hosts alike.
despite daily responsibilities at a full-time job,
has created time in his schedule to advance the POWERTEST TUESDAY
association toward fulfilling NETAs mission. These Tuesday, attendees gathered again for a day of
contributions can be technical or organizational, technical discussions with another breakfast
and are often both. Jim Cialdea, Owner and Chief sponsored by Group CBS, which flowed right
Executive Officer of 3-C Electrical, was honored to into four panel sessions: Electrical Safety,
accept this award for his role on the NETA Board Cable Testing, Circuit Breaker Maintenance,
of Directors, and as NETAs First Vice President, and Protection and Control. Panelists worked
THANK YOU TO NETAS
CORPORATE ALLIANCE PARTNERS!
POWERTEST 2016 SPOTLIGHT
STAGE PRESENTATIONS

AVO TRAINING INSTITUTE


TITLE: HOW IMPORTANT IS ELECTRICAL
EQUIPMENT MAINTENANCE?

BCS SWITCHGEAR
TITLE: NEWS ON MOLDED CASE AND
INSULATED CASE SWITCHGEAR

CIRCUIT BREAKER SALES


TITLE: CHANGES IN THE CONSTRUCTION &
DURABILITY OF CIRCUIT BREAKERS: FROM
STICKS & STONES TO CARBON FIBER.

COMRENT INTERNATIONAL
TITLE: HIGH-DEFINITION
COMMISSIONING PART 2

DOBLE ENGINEERING
TITLE: IMPROVING ELECTRICAL SYSTEM
ASSESSMENTS THROUGH IN-SERVICE
SURVEYING SOLUTIONS

ELECTRO RENT
TITLE: TEST EQUIPMENT
ACQUISITION METHODS, INCLUDING
A FINANCIAL PERSPECTIVE
The PowerTest 2017 Trade Show featured over 100
INTELLIRENT
booths displaying the latest in leading technology. TITLE: THE LATEST AND GREATEST IN
ELECTRICAL TESTING
in tandem with attendees during these sessions,
MEGGER
creating lively conversation to address real- TITLE: TRAX TRANSFORMER AND SUBSTATION
world problems faced in the field and providing TEST SYSTEM
real-world solutions to take home and apply. OMICRON
Rooms were filled with people engaging in TITLE: A GUIDED WORKFLOW APPROACH TO
Q&A and learning from each other. TRANSFORMER DIAGNOSTIC TESTING

PROTEC EQUIPMENT RESOURCES


Lunch was provided at the PowerTest Trade TITLE: BATTERY TESTING METHODOLOGIES
Show, where attendees dined on gourmet
sandwiches and desserts as they traversed the SMC INTERNATIONAL
TITLE: FIND OUT WHAT YOUR MICRO
carpeted aisles of the convention center. This OHMMETER IS MISSING
may be the biggest event of the entire conference
and where most business is conducted for UTILITY RELAY COMPANY
TITLE: ADVANCING LOW-VOLTAGE CIRCUIT
attendees and vendors alike. New products and BREAKER RETROFIT PROTECTION TECHNOLOGY
technologies waited around every corner, along
WEIDMANN
with knowledgeable sales reps eager to help. TITLE: MOISTURE IN INSULATION AND
TRANSFORMER DRYOUT
The PowerTest Trade Show was held at the
Fort Worth Convention Center, just across the Spotlight Stage Presentations can be
downloaded from the netaworld.org
street from the Omni Hotel. Each year, this website under the Corporate Alliance Tab
event features industry leaders at the Spotlight
An exciting evening of hospitality suites was hosted by 11 industry leaders.

Stage. Thirteen presentations were given by raffle that takes place at the end of the show. This
NETA's Corporate Alliance Partners. The year's winners were not disappointed with the
event included presentations by AVO Training excellent offerings from exhibitors as well as from
Institute, Inc.; BCS Switchgear, Inc.; Circuit NETA, including an Apple iPad and $500 cash.
Breaker Sales Co., Inc.; ComRent International;
Doble Engineering Company; Intellirent;, Following the PowerTest Trade Show, everyone
Megger; Protec Equipment Resources; SMC headed back to the hotel for the PowerBash
International; Utility Relay Company; and Awards Reception and Dinner, and the turnout
Weidmann Electrical Technology Inc. (Editors was impressive to say the least. Thanks go out to
note: For more information on the Spotlight Stage Karl Zimmerman and his band for providing
presentations, see sidebar.) the musical backdrop for a smorgasbord of food,
drinks, and desserts. Over 400 people attended
Each year, exhibitors raise the bar with their the event and were present to congratulate this
booths, and it is always a great time to meet new year's recipients of the awards for Technical
people and connect with old colleagues. One of Presentations, Trade Show Exhibitors, and
the highlights of the Trade Show is a door-prize Hospitality Suites. Congratulations to all!

PowerBash 2016
was an evening
of grand food,
best of the show
awards, dancing,
and professional
comradery.
TRADE SHOW EXHIBITION WINNERS
MOST INNOVATIVE MADDOX INDUSTRIAL TRANSFORMER
MOST VISITED CIRCUIT BREAKER SALES CO., INC.
BEST IN SHOW MEGGER/AVO TRAINING INSTITUTE, INC.

PowerBash marks the end of the first two TECHNICAL PRESENTATIONS WINNERS
whirlwind days of technical and social events, SAFETY ARC-FLASH MITIGATION BY TRANSFORMER
and the beginning of three more days of DIFFERENTIAL RELAY PROTECTION
technical seminars. It's sort of the seventh- PRESENTERS: MOSE RAMIEH III, PGTI, A CE POWER COMPANY,
inning stretch of PowerTest, the pause before AND RANDALL SAGAN, MBUSI
the more intense educational innings to come.
RELIABILITY IMPROVING SAFETY THROUGH
PO W E R T E ST W E DNE SDAY, PARTIAL DISCHARGE SURVEYING
T H U R S D AY, AND F RIDAY PRESENTER: TONY MCGRAIL, DOBLE ENGINEERING COMPANY
Wednesday and Thursday have always featured
four-hour technical seminars that offer CIRCUIT BREAKERS VACUUM INTERRUPTERS:
attendees a more thorough exploration of PRESSURE VS. AGE A STUDY OF VACUUM LEVELS IN
various subject matters. Attendees gain hands- 314 SERVICE AGE VACUUM BREAKERS
PRESENTER: FINLEY LEDBETTER, GROUP CBS, INC.
on experience applying and troubleshooting
relays for transformers and distribution lines.
EQUIPMENT UNDERSTANDING TRANSFORMER
On Friday, Doble Engineering Company added DIFFERENTIAL PROTECTION
one more day of learning with its Laboratory PRESENTER: WILL KNAPEK, OMICRON ELECTRONICS CORP. USA
Seminar. The seminar offered attendees an
interactive experience, combining theoretical COMMISSIONING ELECTRICAL COMMISSIONING TIPS AND
background with practical experience and TRENDS FOR ADVANCED CRITICAL FACILITIES APPLICATIONS
PRESENTER: CORY DOZHIER, ORACLE
hands-on examples, including case studies
illustrating common problems found in the
field. People were eager to participate in this BEST OVERALL HOW DISRUPTIONS IN DC AND
COMMUNICATIONS AFFECT PROTECTION
event, and more than 60 people attended.
PRESENTER: KARL ZIMMERMAN, SCHWEITZER ENGINEERING
LABORATORIES, INC.

HOSPITALITY SUITE WINNERS


MOST CREATIVE SHERMCO INDUSTRIES
MOST APPETIZING PROTEC EQUIPMENT RESOURCES
MOST TECHNICAL GROUP CBS, INC.
MOST ENTERTAINING BCS SWITCHGEAR, INC.
MOST HOSPITABLE MEGGER/AVO TRAINING INSTITUTE, INC.

POWERTEST 2016 SELFIE-PHOTO


CONTEST WINNERS
GRAND PRIZE WINNER:
MOSE RAMIEH III, PGTI, A CE POWER COMPANY

SECOND PLACE WINNERS:


TOM WARNING, SHERMCO INDUSTRIES
ELECTRO RENT POWERTEST 2016 TEAM
SARAH BAUMANN, MEGGER
Tuesdays panel sessions featured lively discussions on Electrical Safety, Cable Testing, Circuit Breaker
Maintenance, and Protection & Control.

P OW E RT E ST 2016 Next year is already shaping up to be a heck of


PowerTest 2016 was the best yet. PowerTest a conference, as PowerTest heads to Anahiem,
attendees, speakers, sponsors, and exhibitors all California, on February 27 March 3, 2017. Mark
contributed to making the event a tremendous your calendars, and make plans to join us next year!
success. NETA would like to thank each and
every one of you who contributed to this success
by participating, speaking up, and energizing your
future at PowerTest 2016.

CHOOSE BETWEEN KEEPING MAINTENANCE COSTS DOWN


AND KEEPING UP WITH PRODUCTION DEMANDOR DO BOTH.

THATS THE
CRITICAL DIFFERENCE.
NETA certied experts at Electrical Reliability Services will keep you in perfect balance.
To ensure the reliability of your electrical power, you have to balance the need to reduce maintenance costs
and Double Helix Design are trademarks and service marks of Emerson Electric Co.
Emerson, Business-Critical Continuity, Emerson Network Power and the Emerson

with the need to perform regular maintenance. Only the team from Electrical Reliability Services delivers
cost-effective services and system expertise to keep you up and running 24/7.

ElectricalReliability.com
Sertec Can Bring That Relay Back to Life
Sertec Relay Services buys and sells protective relays and specializes in extending the life of obsolete electromechanical
relays by providing quality repair, remanufacture, and retrot services for relays of all types and manufacture. We also service
specialty electronics used in electrical power systems.

sInstantaneous Overcurrent Relays sDifferential Relays


sTime Overcurrent Relays sReverse Power Relays
sDirectional Overcurrent Relays sPhase Balance Relays

sUndervoltage Relays
sFrequency Relays
sDistance/Impedance Relays

RELAY MANUFACTURERS
sGeneral ElectricTM sBaslerTM
sWestinghouseTM sSchweitzer-SELTM
sABBTM sGE MultiLinTM, and more!

* Third-party trademarks are the property of their respective owners

Emergency support 24/7


www.sertecrelayservices.com 203-888-7500
WALLINGFORD, CT P:(203) 888-7500 SERTEC@CBSALESNE.COM For more emergency contact phone numbers, visit:
cbsalesne.com/services/eld-services
FEATURE

AS A TOOL FOR PROTECTION TESTING


SPECIFICATIONSB Y B E N T ON VANDIV ER III, OMICRON electronics Corp. USA

Over the past 30-plus years, I have had numerous conversations


with technicians, engineers, and managers on how to create the best
test plan for many of the relays, protection schemes, and protection-
and-control (PAC) systems used in the utility industry.
The discussion generally turned into a lengthy physically on the device. In the newest digital
laundry list of what they actually wanted to technologies, this has been supplanted by
accomplish during their test process. Some of software programming of the parameters and
the tasks mentioned included: firmware updates, self-diagnostics, observational
testing, logs, and reports.
Proof of calibration
Proof of proper settings Most often, what was actually desired from the
Proof of the ac system components test plan was the least amount of work to satisfy
Proof of the dc system components a testing compliance requirement. In addition,
Verify the interconnections they wanted an assurance that the testing
Verify the functions performed was sufficient for the task(s) that
Verify the scheme logic the tester executed, and that the test procedure
Verify the overall protection system coordination was correct, accurate, and repeatable. It was a
bonus if the test procedure was self-instructing
For these tasks, the test plan comprised a or automated so that training was minimized,
specific list of the test methods and steps the ultimate goal being the one-button test.
required to accomplish them. For the proof-of
tasks in electromechanical devices and systems, In the past, a working test plan for a PAC device
the steps were essentially specified by the or system was not automatically delivered with
manufacturer in the device instruction manual it, nor was it made by accident. It evolved from
and any special publications dealing with three distinct steps driven by the utility user:
maintenance tasks or calibration. For newer 1) The test philosophy implemented by the user
technologies, these specifications evolved to 2) The users protection philosophy and a generic
more black-box testing designed to prove the test plan structure developed from it
device specifications or troubleshoot the devices 3) The users final configuration/settings of the
components and calibration, since typically, the Intelligent Electronic Device (IED) or system
setting parameters were directly set or displayed (Figure 1)

58 SUMMER 2016 USING TEST PLANS AS A TOOL FOR


PROTECTION TESTING SPECIFICATIONS
FEATURE
living document continually updated based
on current PAC devices and systems in use,
compliance requirements, training requirements,
and performance expectations.

When a specific protection philosophy was


applied, it refined the definition of what was to
be tested. Using a basic four-zone step distance
scheme as an example, we could construct a
generic four-zone step distance test plan of the
functions (reclosing, loss of potential, etc.);
protection elements (21P, 21G, 50/51, 59, etc.);
Figure 1: An IED-Specific Test Plan interfaces (physical I/O, control, etc.); and logic
(permissive overreach transfer trip {POTT} and
A users test philosophy is often based on breaker failure, etc.) that should be tested and
operational history usually scenarios of should include the test equipment, tolerances, and
specific device misoperations from a variety test methods stated in our test specification.
of causes as well as compliance issues, At this point, the test plan could be used as a
manufacturer guidelines, and industry standards. functional test specification (Figure 2) for this
Often, the philosophy was known but not type PAC device or system because the What,
always documented effectively and was Why, and How questions should now be known.
internally perpetuated through on-the-job
knowledge (e.g., We always test at 2x, 3x, 4x
pickup.) As PAC technology changed, the
testing philosophy adapted slowly or not at all,
resulting in unnecessary or improper testing
of the new PAC device or system. This also
extended to:

Test equipment used


Tolerance definitions and performance
expectations
Test methods applied
Proper training (knowledge and skills)
Documentation of the objectives (compliance,
calibration, etc.) Figure 2: Test Specifications

Some examples would be using a one-phase However, we still do not have an executable
test set on a relay using three-phase algorithms test plan because we are missing the specific
and logic; using electromechanical tolerances manufacturer device(s) used, the specific
on a precision digital device; step-change configuration parameters, and the specific
injections expecting dynamic performance; or protection settings that finally dictate the exact
no PC/software user skills and expecting one- testing to be performed. For instance, the
day training to master the PC-controlled test specific line being protected may not require
kit. The proactive user would take all these a fourth zone element, so the configuration
points into consideration and craft a protection information would indicate it is not used or
system specification(s) that would clearly required. This would mean only three zone
convey how the devices and systems should elements need to be tested, and any scheme,
be applied, the test philosophy employed, function, or logic associated with only the
and how it was to be achieved. It was a fourth zone would be ignored.

USING TEST PLANS AS A TOOL FOR NETAWORLD 59


PROTECTION TESTING SPECIFICATIONS
FEATURE
So a mechanism to get these configuration Some may disagree, citing that a good generic
parameters/protection settings into the generic test specification can be written from a
test plan was needed, as these were typically entered common denominator (generic) practice,
manually (today, of course, they are possibly an approach that in turn can generate the
imported electronically.) Often, the parameters required test plan. But I see this as a chicken-
used in a specific PAC device vary from and-the-egg discussion or Schrodingers cat
manufacturer to manufacturer, even when they situation: If you do not know the actual device
perform identical functionality. Further, the actual details, how can you possibly test it? Even in
parameters used to define the test method can the case of the simplest network model, you
be a different data type or mathematical equivalent. must understand how it works, its limitations,
So translation of these specific device parameters and the data it requires to function correctly.
into test method parameters was another task However, there is no argument in the industry
necessary to create the executable test plan. that device technology dictates the test tools
and techniques required and that the objective
Today, many utilities have lost expertise and
is the proof of the device as applied in situ.
cannot follow these steps; they increasingly
So taking the device out of its commissioned
rely on other sources to bridge these gaps.
state to make functional or element tests
With modern software solutions, the specific
indicates lack of good specifications and
IED can be data modeled and parameters
systems engineering. A properly engineered
imported, then recalculations made and
IED or PAC system will be testable with the
mapped to the functional test module
performing the specific defined testing task, correct tools and simulations.
including the required hardware interfaces The fact is, there is nothing to test until there
(Figure 3). Additionally, modern test software is a device or system design, and no design
can use purpose-built test modules or a until there is a specification to build it a certain
power system mathematical model to relieve way. So we are back to the specification again.
the task of defining individual test methods for Naturally, one would conclude that whatever
each function, element, or logic scheme. this specification is, it should then be used to
Since the beginning of my career and regardless define the test plan. If we are talking design
of the protection devices and/or systems and absolutes like the strength of an I-beam made
technology used, there has never been a perfect from different materials, then yes, it could
tool for creating such test plans. The fact is that be. For instance, a 10-foot-long oak I-beam
it requires a deep knowledge and understanding may have a design-loading factor of 100
of what it is you are testing. Whether it is pounds, whereas one made from cold steel
an auxiliary dc relay or a modern HV digital might be 1,000 pounds. To prove the design,
line protection IED, or an application like a a simple test would anchor one end of the
permissive overreach transfer trip scheme over beam and apply an increasing dead load at the
fiber, understanding what it is designed to do other end until the beam failed. This would
and how it does it is necessary for organizing be destructive, but necessary to prove the
any of the previous testing tasks successfully. design and specification, and many industries
perform these tests.

In PAC systems, we do not typically test


them until they fail (we let Murphy take
care of that), but we do need to apply best
practices in verifying their design and
operation prior to implementation and
during service life. The other consideration
for PAC systems and their devices is the
Figure 3: The Hardware Setting Parameters variable nature of designing/applying them.

60 SUMMER 2016 USING TEST PLANS AS A TOOL FOR


PROTECTION TESTING SPECIFICATIONS
FEATURE
Most of todays devices are digital, use
communications, and are programmable in
configuration and scheme logic, making
their testing dependent on their intended
application and the specific parameters used
(Figure 4). The device specification cannot be
used directly for defining the test plan because
there are too many variables, overlapping
functions, and implementations unique to
the manufacturer.

Figure 5: IED Test Results Distance Zone Elements


Figure 4: IED Test Plans Adapting to Actual Settings
DEVELOPMENT METHODOLOGY
and Creating Specific Functional Tests
TEST SPECIFICATION
Further, when we take multiple devices and use The multifunctional design of modern numerical
them together in PAC systems, the aggregate protection devices usually requires different
specifications of all those devices could create methods to test the different functions integrated
conflicting test requirements across the system in each of them. It is obvious that to define the
and, in some cases, damage them if not properly test specification, we need to start with the type
considered. The specific settings/parameters of protection being tested.
applied based on the intended application As mentioned, the test specification depends on
restricts them and blends these devices to work the users testing philosophy and the regulators
together within the PAC system. This provides compliance requirements. It defines what types of
the details necessary for developing the test tests need to be performed for different types of
plan. Once the test plan is derived according function elements, schemes, or applications as well
to our required task list and proven against the as any characteristics of the test method used depending
PAC system configuration, then it can be the on the purpose of the test: type, acceptance,
basis for extracting the test specification for this commissioning, maintenance, etc. (Figure 6).
specific PAC system implementation.

This methodology could be seen as backwards


but for one key point: With the knowledge of
the application and the specific parameters of
the configured devices, we are able to define a
white-box testing environment, one in which
we know the output based on the internal
responses of the system based components/
devices from known application-based input
simulations. In other words, we have a detailed
understanding of the devices and system, and
therefore, can prepare a proper test plan to
prove it. (Figure 5) Figure 6: IED Zone Characteristic Test Results

USING TEST PLANS AS A TOOL FOR NETAWORLD


NETAWORLD 61
PROTECTION TESTING SPECIFICATIONS
Based on the testing philosophy, a generic test The test modules (methods) to be executed
plan can be structured that defines the required as required by the testing philosophy
test hardware and specific implementation
considerations based on the PAC device or Such an approach allows improvement of
protection IED dependent: the testing process efficiency by defining the
required hardware configuration only once
Interfaces: hardwired voltage, current, I/O
at the beginning of the test specification. The
or IEC 61850 GOOSE, or sampled values hardware configuration represents the signal
Bay configuration (for example, breaker- path between the testing tool and the test object
and-a-half) or application configuration and contains complete information about:
(two- ended line model) The assignments between the inputs and
outputs of the test software and the test
Once the generic test specification for a protection
object terminals
type is created as a generic test plan, it can be
The used test hardware as well as its
customized to meet the specific functionality of
configuration
a selected manufacturers IED used for the protection
The wiring between the test hardware and
type under consideration and represented then by
the test object terminals
an IED-specific test plan (Figure 7).
The setting parameters of the test object are
also not specified individually for each test
module, but only once at the beginning
of the executable test plan configuration
(Figure 8). The same applies to the generation
of a single test report that covers all test
results. Any number and type of test
modules can be combined into one central
document to form a complete test plan that
matches the requirements of the functions tested.

Figure 7: Completed IED-Specific Test Plan

The test specifications must define:


The functionality of the tested
multifunctional protection IED represented
by different protection function elements,
such as distance, differential, overcurrent, etc.
The required test devices needed to execute
the tests
The interfaces between the test equipment
and the test object Figure 8: IED Functional Model with Specific
Configuration and Settings

62 SUMMER 2016 USING TEST PLANS AS A TOOL FOR


PROTECTION TESTING SPECIFICATIONS
The test plan can be executed as an automatic tool knowledge with the existing SCL data,
sequence. When running it, the defined test test plans could be defined directly. Expansion
functions of each selected module are executed of the SCL to include test devices described
before the program automatically switches to as logical nodes with data objects and data
the next one, until all the modules have been attributes would enable the goal of creating test
completed. After the completion of the test, plans and test specifications.
the software enters the results into the test
plan document, which creates a comprehensive A utility using the IEC 61850 data model can
overall test report. define the single line diagram, all functions
used, and their logical nodes/data types.
The test report still contains all of the test From this, a device-independent specification
settings (protection device parameters, test can be made using the System Specification
modules used, test points, etc.). Using a Description (SSD) file with a top-down
protection IED-specific test specification for design that will constrain vendors and system
testing several relays that differ only in their integrators to the utilitys system specification.
parameter settings (e.g. relays of the same type This means the supplier is not free to make a
on different feeders) is substantially simplified non-conformant, bottom-up design using their
since a test plan, once created, only needs own tags and architecture. Further, with test
minor adjustments. tool/device extensions of the SCL, the utility
could also include the test plan from the SSD
The fundamental difference between a test plan with all test processes defined (what to test
and a test specification is that a test plan not with expected values) and then easily formalize
only tells us how to perform the test, but it also a conformant test specification from it (an
has knowledge of what the test results should be. annotated report).
A generalized test specification cannot contain
the specific expected results, only relative
parameters like tolerances. When describing to CONCLUSIONS
a technician, contractor, or test company via a The ability to create a properly constrained test
test specification, the information must be as specification that has value has always been a
specific as possible and derived by extracting challenge, but IEC 61850 is poised to deliver
that specification from successful test plans. on a long-awaited capability creating a test
specification from the top down that includes
If an independent way existed to describe all the the functional test plan, too.
devices, interfaces, communications, logic, and
settings used in PAC systems, then our industry The best specification is one that:
could evolve engineering tools to define its Exists
many unique applications in a standardized Describes what, not how
way. In fact, it would be possible to not only Cites relevant industry standards
self-describe the PAC system as designed, but Clearly defines testing tasks such as
also provide a mechanism to self-define its test acceptance, commissioning, routine, and
plan based on those defined relationships. You maintenance
guessed it: Thats IEC 61850. Has only one interpretation
Is available to all parties
Although long-coming, IEC 61850 (Ed 2) is Is the spec agreed to by all parties involved
approaching a new level of maturity. In Part 6, Only includes what is necessary
the Substation Configuration Language (SCL) Is consistent (avoid using it or which
has grown to encompass more information on and clearly specify what)
PAC devices. This substantially increases the Defines the jargon and abbreviations
self-description details where the key data and common within the industry
relationships of the configured devices from the Describes the test objectives so a novice
SCL can be used. If combining application/test can understand them

USING TEST PLANS AS A TOOL FOR NETAWORLD


NETAWORLD 63
PROTECTION TESTING SPECIFICATIONS
7(&+1,&$/ 6$)(7<
TRAINING

ENGINEERING SERVICES TECHNICAL SERVICES COMMISSIONING


Protection Systems Design, Commissioning, Relays
1DWLRQDO&HUWLHG&DEOH6SOLFLQJ&DEOH7HVWLQJ $QDO\VLVXVLQJ | |

9/)9/)7$1'HOWDDQG3DUWLDO'LVFKDUJH
/DUJH0RWRU*HQHUDWRU 7UDQVIRUPHU0DLQWHQDQFH7HVWLQJ2LO+DQGOLQJ /HDN5HSDLUV (310) 816-3130
7URXEOHVKRRWLQJ3RZHU&RQWURO6\VWHPVDQG3RZHU4XDOLW\$XGLWV ZZZWGHLQFFRP
131 W F Street
Wilmington, CA 90744
CA LICENSE #315448 Los Angeles Area

www.youtube.com/tdeinc2 www.twitter.com/tdeinc www.facebook.com/tdeinc www.linkedin.com/company/tony-demaria-electric

1965-20
19 65-2015
15

Electro Rent is Now a NETA Gold


Electro Rent Turns 50 YEARS
Corporate Alliance Partner

Electro Rent answers


your every test need.
Count on Electro Rent to get the test equipment you need fast,
with experienced customer support you can rely on, 24x7. From
motor test equipment to borescopes: if it tests, weve got it and
were ready to meet your need.

Largest inventory
Consistent, reliable delivery service
Immediate availability
ISO and ANSI accredited labs

Learn more at:


www.electr
www .electror
orent.com/electr
ent.com/electrica
ical-po
l-pow
wer
800.304.4744 | sales@electrorent.com Vanguard Instruments Company, Inc.
www.vanguard-instruments.com
FEATURE

G O I N G B EY O N D AUT OMAT E D

USIN G P OW ER S Y S T E M M O D E LS
B Y S TE V E TU R NER, Beckwith Electric Company, Inc.

Automated testing is often used to test A shunt-connected zigzag transformer provides


a zero-sequence current sink for ungrounded
protective relays, but special cases exist that systems by establishing a connection from
cannot be adequately covered. This article ground to neutral (Figure 1). During ground
presents three examples that illustrate how to faults, zero-sequence current (I0) flows up
through the neutral of the zigzag transformer.
test protection functions using simple model By applying the zigzag transformer as a ground
power systems and symmetrical components. source, it is now simple to apply non-directional
overcurrent protection for the detection of
Model power systems calculate test signals single line-to-ground faults. If the system is left
that are equivalent to the actual steady-state ungrounded, very low current is produced on
fault conditions when precise test signals are the faulted phase during single line-to-ground
required. The ability to calculate test signals faults, due only to the capacitance-to-ground
rather than solely relying upon software is a of the unfaulted phases. Conventional ground
valuable skill for testing protective relays. over-current protection is useless.
The three examples given are: A zigzag transformer consists of three 1:1 ratio
Zigzag transformer inside transformer transformers. Each leg of the zigzag transformer
differential zone consists of two windings that are 120 degrees
Sensitive ground directional overcurrent out of phase. Windings are wound around
protection for ungrounded systems the core such that zero-sequence current flows
Directional power for intertie protection through the bank when system unbalance exists
(i.e., ground fault). Only exciting current flows
ZIG ZAG T R ANF ORMER through a zigzag transformer during balanced
INS IDE T R ANSF ORMER system conditions; positive- and negative-
DIF F E RE NT IA L Z ONE sequence current cannot flow since they are
The first example demonstrates how zero- 120 degrees out of phase. The grounding
sequence current elimination is applied for transformer appears as the leakage reactance of
transformer differential protection. the core during a ground fault.

66 SUMMER 2016 GOING BEYOND AUTOMATED RELAY TESTING


USING POWER SYSTEM MODELS
FEATURE

Figure 2: Ungrounded System with Zigzag Transformer for Ground Current

Zero-Sequence Current Elimination (Figure 2)

IA = IB = IC

IA = IB = IC =

The currents shown above are taken directly


from the CT secondary and have been divided
by the tap setting for the delta winding to
convert them into per unit. If zero-sequence
current elimination is selected (Figure 3),
Figure 1: Zigzag Transformer Three-Line then the numerical relay calculates the ground
Diagram current as follows:

IG = IA + IB + IC
A grounding resistor is sometimes used to
IG =
limit ground faults to lower levels than with
the zigzag transformer solidly grounded.
Typically, the zigzag transformer is sized such IA, IB and IC are the internally compensated
that its impedance is 100 percent on its own currents:
base; 400 amps primary is the 10-second IA = IA + IB = IB + IC= IC +
rating commonly applied throughout the
United States.

If the zigzag transformer is located inside the IA = - =0 I B = 0 IC = 0


zone of transformer differential protection,
as in the delta-connected windings shown
in Figure 2, then the zero-sequence current
contribution during external ground faults
must be eliminated or a misoperation can
occur. Here is one method showing how
numerical transformer protection relays can
reliably remove the ground current. Figure 3: Zero-Sequence Current Elimination (Relay Settings)

GOING BEYOND AUTOMATED RELAY TESTING NETAWORLD


NETAWORLD 67
USING POWER SYSTEM MODELS
FEATURE
Figure 4 shows the transformer differential
operating characteristic. Point A is the filtered
operating point for an external ground fault,
and Point B is unfiltered.

Figure 4: Transformer Differential Operating


Characteristic

Note that custom settings that properly


account for the phase shift can also be used for
this application.

Zigzag Transformer Impedance Model and


Symmetrical Component Calculations
Figure 5a shows the zero-sequence model for
the zigzag transformer. Note that it does not
appear in either the positive- or negative-
sequence networks.

Figure 5b: Symmetrical Component Diagram

Figure 5c shows the ground-current distribution


for a single phase-to-ground fault. Note the
current magnitudes are normalized to the total
zero-sequence current (3I0).
Figure 5a: Zigzag Transformer Zero-Sequence
Impedance Model

Figure 5b shows the symmetrical component


diagram for the two-winding wye-delta
transformer with the zigzag transformer
connected to the delta side. Note that the load
is connected wye and solidly grounded at the
neutral. The CTs for the delta side are shown as
well. ZT is the impedance of the two-winding
wye-delta transformer, and ZZig is the impedance
of the zigzag transformer. The zigzag transformer
provides 400 amps primary during a ground-
fault current when the system is unloaded. Figure 5c: Ground Current Distribution

68 SUMMER 2016 GOING BEYOND AUTOMATED RELAY TESTING


USING POWER SYSTEM MODELS
FEATURE

Figure 5d: Base Values and Impedances (Mathcad)

Figure 5d shows the base values and impedances


used for this particular example.

SENSITIVE GROUND
DIRECTIONAL OVERCURRENT Figure 6: SEF Pickup Setting Range
PROTECTION FOR
UNGROUNDED SYSTEM Figure 7 illustrates how the operating current
The first example was for an ungrounded power is commonly measured for distribution feeders.
system grounded via a zigzag transformer. Note that IG is the ground current input. A
Remember, as stated previously in regards to an toroidal CT is also used but is only applicable
ungrounded power system: If the system is left at lower voltages since all the phase conductors
ungrounded, high magnitude voltage appears must pass through the center opening.
on the unfaulted phases during single line-
to-ground faults and conventional ground-
overcurrent protection is useless due to the very
low magnitude ground current.

It is possible to protect the feeders for single


line-to-ground faults using sensitive-earth-fault
(SEF) protection. SEF protection can detect
ground-fault current in the order of milli-amps
secondary. Figure 6 shows the pickup range for
an SEF element. If the CT ratio is 100:5 then
the range in primary is 0.5 to 20 amps. Figure 7: SEF Current Input

GOING BEYOND AUTOMATED RELAY TESTING NETAWORLD


NETAWORLD 69
USING POWER SYSTEM MODELS
FEATURE
Figure 8 shows a single line-to-ground fault on a
distribution feeder supplied via an ungrounded
wye winding. The power system is grounded
through the total stray capacitance to ground
(XC0g).

Figure 9b: SEF Directional Operating


Characteristic

Calculate the ground fault current (Ig) as


follows:

Ig = 3I0
Figure 8: Single Line-to-Ground Fault on
Ungrounded System Where:
1
Directionality makes SEF secure since ground I0 = (per unit)
current flows in the unfaulted phases for the 2ZT+Zc0+3RF
non-faulted feeders as shown in Figure 9a.
ZT = distribution transformer impedance

Zc0 = -jXc0

1
Xc0 =
2Cg

f = nominal frequency

Cg = total stray capacitance to ground

RF = ground fault resistance

Figure 9a: Ground Current in Unfaulted Note that the impedance of the distribution
Feeder(s) feeder can be ignored since the impedance
of the stray capacitance is so high. This
Figure 9b shows the SEF directional operating calculation does not take any load into
characteristic. The maximum torque angle account. You can increase the fault resistance
between the zero-sequence voltage and ground until the ground fault current is equal to
current is 90 degrees leading, since the voltage the minimum pickup setting to test the
drop behind the relay in the zero-sequence maximum sensitivity of the SEF protection.
network is across the total stray capacitance to Figure 10 shows the symmetrical-component
ground (XC0g). zero-sequence network.

70 SUMMER 2016 GOING BEYOND AUTOMATED RELAY TESTING


USING POWER SYSTEM MODELS
FEATURE
based on the Nominal Voltage and Nominal
Current setting, as shown in Figure 12.

Figure 12: Relay Configuration


Figure 10: Zero-Sequence Network
Use the forward over-power function to limit
the amount of power flow into the utility if
DIRECTIONAL POWER FOR the DG is allowed to supply power to the
INTERTIE PROTECTION utility (export). Use the reverse under-power
The last example demonstrates how to calculate function to ensure that the DG is importing
test signals for directional power protection a minimal amount of power from the utility
(Figure 11). Note that this type of protection for peak shaving applications when no
typically operates on real power (W). export of power from the DG to the utility
Power protection may be useful to detect the is allowed.
loss of utility supply, depending upon the Nominal Power
size of the distributed generator (DG) and its Here is how one particular numerical relay
load, feeder load, and the local utility import/ internally calculates the nominal power (Pnom):
export restrictions. Forward power is defined
as power exported from a DG to a utility. VT Configuration Line-Ground (L-G)
Reverse power is defined as power imported Nominal Power = 3VnomInom
by a DG from a utility. VT Configuration Line-Line (L-L)
Nominal Power = 3VnomInom

Pickup Setting
Suppose, for example, the utility requires that
the directional power (32) elements trips at 50
kW primary.

VT Ratio = 4160/120 = 35 (Open Delta)


Vnom = 120 volts L-L
Figure 11: Directional Power
CR Ratio = 400/5 = 80 (Wye)
It is convenient to set the pickup in per- Inom = 5 amps
unit (PU) based upon the numerical relay
Note: The values above were arbitrarily selected
nominal power. The choice of the base PU
but are typical.
is typically taken from the kVA rating of
the interconnection transformer, the DG Pickup = (50 kW)/(VTRCTR) = 18 watts
aggregate generating capacity, or some other secondary
value agreed upon by the DG and the utility. Pickup = (18 watts)/(3120V5A) = 0.02
Normalized PU power flow measurements are per unit

GOING BEYOND AUTOMATED RELAY TESTING NETAWORLD 71


USING POWER SYSTEM MODELS
Absolute confidence. Every time.
You can count on us for specialized experience in healthcare, data center, oce complex, and commercial
acceptance and maintenance testing. Absolutely. Power generation, petrochemical, oil & gas, and heavy
industries also look to us for high demand services such as start-up commissioning, maintenance testing,
shut-down and turnarounds, and breaker shop repair. Get started today.

Toll free: 832.467.4446


6829 Guhn Road, Houston, Texas 77040
Email: Alan Postiglione apost@absolutetesting.com
absolutetesting.com Like us on:
FEATURE

From A 400kV
Busbar Misoperation Using The
IEC 61850 STANDARD
B Y D H A N A B A L M A N I , V IJ AY SH ANM UG ASUNDARAM , AND J ASON BUNEO , Megger

The implementation of IEC 61850 standard for substation design


and commissioning is rapidly becoming the dominant method of
defining grid protection schemes throughout the world. The
protection logic that involves dc control circuits is executed internally
in the intelligent electronic devices (IEDs) and effectively communicated
between the IEDs via Generic Object Oriented Substation Events
(GOOSE) messages. Any error in the mapping of GOOSE signals
will result in undesired operation of the protection schemes.

The main buses in power substations are scheme. This incident happened when a zone
designed to carry load currents through the two fault occurred on one of the 400 kV line
individual feeders as well as high amplitude feeders, immediately triggering a breaker-
currents during bus fault conditions. Any delay failure condition. Under a normal trip scenario,
in fault isolation or improper relay operation the zone two timer will time out and the line
could result in severe damage to the substation IED will issue a trip signal to the line breaker
buses and the equipment connected to them. to isolate the fault. The line IED will also then
Therefore, proper design and testing of the bus- issue a breaker-failure initiate (BFI) signal to
bar protection scheme is required to ensure safe bus-bar IEDs through GOOSE messages. The
and reliable operation of the substation. The breaker-failure condition is only declared when
complex protection schemes such as bus-bar the line breaker fails to trip within a specified
and breaker-failure protection are relatively breaker-failure time. However, in this case, the
easy to design using the modern IEC 61850 breaker-failure condition was initiated before
standard. However, the implementation of the zone two timer expired instead of after.
these schemes in the real world poses certain
unique challenges. An investigation was carried out to determine
the reason for declaring a breaker-failure
This article discusses the investigation of condition even before zone two tripping of the
the tripping of a 400 kV substation due to line IED. Further analysis of the IEC 61850
improper operation of a bus-bar protection network and GOOSE configurations led to

74 SUMMER 2016 LESSONS LEARNED FROM A 400kV BUSBAR


MISOPERATION USING THE IEC 61850 STANDARD
FEATURE
the conclusion that the BFI signal was mapped A protection scheme is implemented by
incorrectly. The bus-bar IEDs were configured configuring the IEDs to send or receive
to receive a BFI signal through GOOSE GOOSE messages from other substation
messaging for a fault pick-up signal instead of a equipment. Depending upon the complexity
fault-trip signal by protection IEDs. This minor of the protection scheme implemented,
error caused the entire substation to be out of a GOOSE message could pass through a
service. This article discusses testing methods number of switches until the destination
that would help prevent this situation. IED is reached. After analyzing the received
message, further actions are carried out by the
I N T R OD U CT ION destination IED. A redundant network in LAN
The protection schemes used in substations design prevents data loss by re-routing the path
are implemented through protective relays taken by the messages. Numerous network
from various manufacturers. Legacy systems topologies have been adopted to maintain an
that use electro-mechanical relays share critical un-interrupted data flow from the source IED
information such as breaker status, interlock to the destination IED.
signals, etc., through a network of copper wires
monitored by some control center. With the An IED in the substation can send or receive
advent of IEDs, data sharing between protective GOOSE messages to or from many different
relays and control centers has become possible IEDs in the network. The proper mapping of
by using Ethernet and fiber optic cables. This GOOSE messages between IEDs is essential for
has reduced the amount of copper necessary in execution of a protection scheme. The number
substations, making them cheaper to produce of signals mapped depends on the number
and maintain. However, the interoperability of IEDs and the elements of the protection
between different relay manufacturers has become scheme being implemented in the substation.
increasingly difficult, as many IED manufacturers The IEC 61850 standard ensures that the
have adopted proprietary standards for data control functions and message flags seen on
representation and interpretation. In 2005, a the communication network will be the same
common standard was first published by a shared no matter which manufacturer device is used.
effort from IEC 60870-5-101, -103, -104, and However, mapping the IEDs internal logic
Utility Communication Architecture 2.0 (UCA to the IEC 61850 standard can be tricky, and
2.0), and called IEC-61850. great attention to detail must be maintained.

The IEC-61850 standard allowed direct THE SYSTEM


communication between IEDs from multiple A newly constructed 400kV IEC 61850
vendors in a substation. The IEDs in a substation substation was fully commissioned prior to the
followed an abstract model for data definition, work on this article. It consists of six
which could be interpreted by all the compliant D-configuration systems, referred to as a DIA by
manufacturers. A local area network (LAN) the customer, and is provided with a distributed
switch connected between IEDs passed the data busbar protection scheme as per Figure 1.
as GOOSE messages. These messages contain
essential information such as control signals A D-configuration system has three circuit
and acknowledgements. The implementation of breakers with two outgoing circuits; one circuit
the IEC-61850 standard through LAN-based is for line and the other circuit is for transformer
architecture considerably increased the reliability or bus reactor. Both circuits could be lines as
and speed of peer-to-peer communication. well. For circuit breaker maintenance of any
Also, a complex protection scheme could be line, the load gets tranferred automatically
implemented easily through the LAN-based from one bus to the other bus. No changeover
design without increasing the complexity of of the line from one bus to another is required.
physical wiring. For any bus-fault conditions or scheduled

LESSONS LEARNED FROM A 400kV BUSBAR NETAWORLD


NETAWORLD 75
MISOPERATION USING THE IEC 61850 STANDARD
FEATURE
maintenance, all interconnections will be on
the healthy bus, and no disturbance will come
to the other circuits. Even if both buses become
dead, circuits can remain in service through the
tie circuit breaker. This is very advantageous in
maintaining system stability.

Figure 2: Bay and Station Level IEC 61850


Communication Architecture

This busbar protection scheme is implemented


for Main Bus I and Main Bus II. All bay control
units are connected with fiber optic cable to
their main busbar relay for transmitting each
bays load current values, isolator, and breaker
statuses. An equivalent single-line digram of
the substation is configured in the busbar main
Figure 1: 400kV Substation One-Line Diagram IEDs for proper replication of the substation
and for ensuring correct decision making in the
The IEC 61850-based substation automation protective scheme. In the case of a bus-fault or
system (SAS) architecture used in this substation breaker-failure condition, the main busbar IEDs
is shown in Figure 2. This architecture is defined make the decision to isolate the faulty feeders by
in two levels as station level and bay level. sending a trip command to the bay IEDs and, in
A redundant PC-based human-to-machine turn, the bay IEDs trip the respective bay circuit
interface (HMI) is used to control the subsation breakers. This data sharing occurs within the
at station level, which supports communication busbar protection relay network; these trip signals
over IEC 61850-8-1 bus as an IEC 61850 are also sent as GOOSE messages over the IEC
client. An IEC 61850-8-1 inter-bay bus provides 61850 bus.
station-to-bay and bay-to-station exchanges. In
this case, an Ethernet LAN is set up with ring
configuration to maintain reliability, availabilty, IED ENGINEERING AND SYSTEM
and interoperability requirements of the system. LEVEL ENGINEERING
Reduntant gateways are used to exchange the The IED engineering process involves configuring
information to remote network control centers the protection functions, interlock logic, metering
using IEC 60870-5-101 protocol. functions, etc., in each of the IEDs. This process
is shown in Figure 3. The IED configuration
The bay level system consists of all circuit breakers, description (ICD) file is then exported from
current and potential transformers, power each IED, into the substation configuration
transformers, and protective relays. IEDs in the language (SCL) file. The SCL output contains
bay level perform all functions including control, the IEDs capabilities (logical devices, logical
monitoring, and protection. The data exchange nodes). It also reports the control blocks
between bay level and station level happens with available in the ICD files that are used as
fiber optic ring connection according to IEC inputs in the system-level engineering design.
61850-8-1 protocol. Configuration tools are used to set up the

76 SUMMER 2016 LESSONS LEARNED FROM A 400kV BUSBAR


MISOPERATION USING THE IEC 61850 STANDARD
FEATURE
communication between various devices. The the bus of the faulty feeder. Fault selection is
transmission of the data sets is decided by the processed by the busbar main protection IED
report control blocks. Also, GOOSE messages with isolator staus [1].
are configured in the system-level engineering
tool with GOOSE control blocks.

Figure 4: Breaker Failure Scheme Operation Logic


Figure 3: Engineering Process for Configuring
IEDs in a GOOSE-Enabled Substation 4 0 0 k V SUBSTATI ON
COMMI SSI ONI NG
During commissioning of the substation, the
Ethernet switch configurations are then protection IEDs operation, busbar protection,
defined and downloaded into the switches. In and all other trip logic were verified to be in
this IEC 61850 network, GOOSE messages proper working order. Later, an additional bay
have priority over other messages, so Ethernet was added to the existing system. All of the
switches are necessary to support the IEEE protection schemes associated with the new bay
802.1P standard for priority tagging. Finally, were verified as well.
once the system-level engineering is completed,
the SCL file is re-imported back into IEDs, After successful commissioning of the new bay,
where all the configured GOOSE inputs a feeder was connected to Bus-I. Subsequently,
coming from other IEDs are connected to there was a zone two line fault on the newly added
the correct functions. Once the configuration 400kV line. Both Main I and Main-II distance
is downloaded to the individual IEDs, the protection relays in the substation sensed the fault
complete system architecture is defined. correctly on zone two and started the zone-two
timer. The zone-two trip timer is set for 300 ms.
Using the isolator logic, the busbar relay is It was observed that the busbar protection relay
capable of identifying and isolating respective operated within 200 ms for this fault and tripped
feeders connected with the faulty bus. Also, the feeeders connected with Bus-I and Bus-II,
this busbar scheme is combined with breaker thereby causing the entire 400kV substation to be
failure protection. Any protection trip of taken out of service.
respective bay protection IEDs will send a
trip signal to respective busbar bay IEDs to After careful physical inspection of the substation
initiate the breaker failure protection (Figure and busbar protection relays, it was determined
4). If the breaker fails to trip, this action will that there was no real bus fault, and the busbar
cause a breaker-failure protection trip with BFI relay had misoperated due to improper breaker-
initiation and timer timeout. In IEC 61850 failure protection. The BFI signal was sent to
substations, a BFI signal may be configured as the busbar IEDs through a GOOSE signal.
a GOOSE message from the protection IEDs After careful analysis of the IED GOOSE
to the breaker failure protection relays. The configuration, it was found that the newly added
busbar IED will trip all feeders connected with bay had distance-protection GOOSE messages

LESSONS LEARNED FROM A 400kV BUSBAR NETAWORLD 77


MISOPERATION USING THE IEC 61850 STANDARD
configured with a start signal for breaker-failure
initiation instead of a trip signal. Since the
breaker-failure initiation started the function
block timer with a start input, its timer operated
within 150 ms instead of waiting for the 300 ms
zone two timer to expire first. This caused the Figure 6: Example of Incorrect IED GOOSE
breaker failure to trip before the zone two timer. Configuration
Due to this small mistake, both the Main-I and
Main-II protection operated, leading to an entire
substation blockout. The erroneous logic is shown
in Figure 5.

Figure 7: Example of Correct IED GOOSE


Configuration
It is necessary to test the IEDs protection schemes
and GOOSE signals properly before commissioning
the IEC 61850 substation or adding additional
bays in the existing IEC 61850 substations. It
is fairly easy to verify copper wire schemes for
breaker-failure protection schemes or other
protection schemes when adding additional bays
into service in a conventional substation. In the
Figure 5: Breaker Failure Scheme Operation case of IEC 61850 substations, it requires special
Logic with Improper Configuration care. GOOSE-monitoring software can test an
IEDs GOOSE configurations before putting
IEDs and bays into service. Importing the SCL
file of the IED under test into the GOOSE
Figures 6 and 7 show the signal configuration of
monitoring software can assist in verifying the
the GOOSE assignment for the breaker-failure
GOOSE signals as required.
initiation sent to busbar protection IEDs. This
signal configuration is defined in the IED-level Figure 8 shows one of the trip GOOSE signals
engineering and in the main-line protection from a distance protection IED. The purple font
IEDs. Figure 6 shows a simulation example of the in this particular data set indicates the non-
wrong GOOSE configuration for breaker-failure operation of the distance function and that
initiation. In this case, the zone two start signal its signal status is low. This means that this
has been assigned to breaker-failure protection GOOSE signal will be seen by other relays in
initiation as a GOOSE output. Whenever a zone the substation as non-operative.
two fault occurs, the zone two start signal will
send a BFI and cause a breaker-failure trip before
the zone two timer completes and clears the fault.
Figure 7 shows the simulation example of the
corrected GOOSE configuration for breaker-
failure initiation. In this scenario, if there is a zone
two fault, the breaker-failure protection will not
send any GOOSE signal to the busbar IEDs from
the main protection IEDs to initiate the breaker-
failure trip. The IED will send a GOOSE signal
to the bus bar IEDs only when there is a trip Figure 8: GOOSE Monitoring, No Operation
issued by the protection IEDs. of Protection Function

78 SU
SUMMER
UMM
MER
R 2016
6 LESSONS LEARNED FROM A 400kV BUSBAR
MISOPERATION USING THE IEC 61850 STANDARD
Figure 9 provides an example where the when adding additional bays into service within
GOOSE signal color is red. It indicates that this existing IEC 61850 substations. As always,
signal is high and that the protection function additional care is required at the commissioning
has operated; therefore, this GOOSE will stage for any substation.
register when the distance protection trip goes
high. The mapped IEDs that use this GOOSE REFERENCES
signal will process and operate accordingly. Krishnan, Rajiv and Bapuji Palki. First Experiences with Design
and Engineering of IEC 61850 Based Substation Automation
Systems in India, CEPSI 2006 Conference, Mumbai, India,
November 6 - 10, 2006.

Dhanabal Mani received his Bachelor


of Electrical and Electronics Engineering
from Bharathiyar University, India,
in 2001. He commissioned the first
400kV IEC61850 substation in
India in Madhya Pradesh as a Lead
Commissioning Engineer of the
Substation Automation Group at ABB
India Ltd. He has also developed custom
relay applications as a R&D engineer at ABB Ltd, Sweden.
Dhanabal joined Megger India as an Application Manager
in August 2009 and is presently based in Dallas. He has
over 13 years of field experience in protective relaying and
commissioning, and has published numerous articles and
presented at various international conferences on the subject.
Figure 9: GOOSE Monitoring, Operation
of Protection Function Vijay Shanmugasundaram received
his Bachelor of Technology with
distinction in Electrical and Electronics
With reference to Figure 8 and Figure 9, any Engineering from Amrita University,
GOOSE used in protection schemes can be India, in 2008. He joined the Defense
tested and verified without any risk of Research and Development Organization
(DRDO) of India as a junior research
misoperation of the relays or unwanted fellow, specializing in the performance
interruption of the substations. The BFI GOOSE optimization of induction motors. In
signals have been corrected from a start signal to a 2011, Vijay received his Master of Science in Electrical
trip and downloaded to the distance protection Engineering focusing on power systems, from North Carolina
State University. As a part of this program, he worked on
IEDs. Since there is no change in data sets, IEC61850 substation development in Siemenss Energy
it is not required to update the system-level and Automation department. Vijay joined Megger as an
engineering in the substation level (Figure 3). Applications Engineer in December 2012 and is currently
working on developing IEC61850 applications. He is
Necessary validation of signal mapping and an active member of IEEE and EPRI, participating in
GOOSE configuration in line with substation conferences and contributing to the working groups.
configuration is required in any IEC 61850
Jason Buneo received his B.S and M.S in
substation when adding new bay/feeders into Electrical Engineering from the University
the existing substation. of Buffalo. In 2005, he joined GE Energy
Services as a Field Service Engineer. He
specialized in arc-flash coordination
C ON C L U S I ON studies, protective relay testing and
IEC 61850 substations are increasing in use calibration, and low-/medium-voltage
throughout the world. Necessary testing switchgear repair. In 2008, he joined Megger
as an Applications Engineer where he assisted Meggers customer
procedures, such as one of the methods base in their relay testing needs. He became the Applications
discussed in this article to validate IEC Development Manager in 2012 and now specializes in
61850 GOOSE mappings, are required to developing automated testing applications for protective relays.
Jason continues to work closely with utility and industrial
follow the commissioning of those stations customers to develop new testing solutions. Jason has published
for proper operation. More challenges lie several technical papers in industry journals and conferences
ahead in IEC 61850 substations, especially and is active in the IEEE Power Systems Relaying Committee.

LESSONS LEARNED FROM A 400kV BUSBAR NETAWORLD


NETAWORLD 79
MISOPERATION USING THE IEC 61850 STANDARD
SAFETY TRAINING

Who does your training?


So you thought school was out? Training topic examples:
:VTL[PTLZ`V\KVU[RUV^^OH[`V\KVU[RUV^
(UKZVTL[PTLZ[OH[PZYLHSS`HWYVISLTLZWLJPHSS` )HZPJ,SLJ[YPJHS-\UKHTLU[HSZ
^OLYL LSLJ[YPJHS ZHML[` HUK ILZ[ THPU[LUHUJL )HZPJ,SLJ[YPJHS;LJOUPJHS:RPSSZ
WYHJ[PJLZHYLJVUJLYULK:OLYTJV0UK\Z[YPLZPZ[OL ,SLJ[YPJHS7YPU[9LHKPUN
SLHKPUN PUKLWLUKLU[ 5VY[O (TLYPJHU WYV]PKLY VM ,SLJ[YPJHS:HML[`MVY8\HSPMPLK,SLJ[YPJHS>VYRLYZ
LSLJ[YPJHSWV^LYZ`Z[LTTHPU[LUHUJLYLWHPY[LZ[PUN ,SLJ[YPJHS:HML[`MVY4HUHNLYZ
HUK[YHPUPUN6YPNPUHSS`KL]LSVWLK[V[YHPUV\YV^U *)4HPU[LUHUJL6WLYH[PVU *VU[YVSZ
Z[HMM [OLZL [YHPUPUN ZLY]PJLZ HYL UV^ H]HPSHISL :WSPJPUN ;LYTPUH[PVUVM4LK=VS[HNL*HISLZ
HJYVZZ 5VY[O (TLYPJH PU IV[O JSHZZYVVT HUK 7YV[LJ[P]L9LSH`4HPU[LUHUJLHUK*HSPIYH[PVU
VUZP[L]LU\LZ*VU[PU\PUN,K\JH[PVU<UP[Z*,<Z 7YVNYHTTHISL3VNPJ*VU[YVSSLYZ
HYL L]LU H]HPSHISL [OYV\NO HU HSSPHUJL ^P[O (YJ-SHZO:LTPUHY
3V\PZPHUH ;LJO <UP]LYZP[` :OLYTJV OHZ HJ[P]L :\IZ[H[PVU4HPU[LUHUJL
TLTILYZ VU T\S[PWSL [LJOUPJHS JVTTP[[LLZ
6WLYH[PVUZHUK:HML[`MVY>PUK.LULYH[PVU:P[LZ
PUJS\KPUN 5-7(, HUK ) 5,* 0U[LY5H[PVUHS
<UKLYZ[HUKPUN5-7(,
,SLJ[YPJHS ;LZ[PUN (ZZVJPH[PVU (:;4 0,,, HUK
(TLYPJHU >PUK ,ULYN` (ZZVJPH[PVU ;OPZ WLYZVUHS
WHY[PJPWH[PVUHZZ\YLZ[OH[V\YWYVNYHTZHYLHS^H`Z Training updated for
HJJ\YH[LHUK\W[VKH[L(SSVM[OLJSHZZVMMLYPUNZ lastest safety standards
JHU IL J\Z[VTPaLK [V TLL[ ZWLJPMPJ JVTWHU`
SVJH[PVUVYPUK\Z[Y`ULLKZ

:VIHJR[VZJOVVS[PTL:[H`J\YYLU[Z[H`ZTHY[
HUKZ[H`ZHML

2425 E Pioneer Drive +1.972.793.5523


Irving, TX US 75061 WWW.SHERMCO.COM
And Your Source for
NFPA 70E Compliant
Protective Gear
Metro NY/NJ/PA 800-220-2120
Calif (SF) 888-817-1412
Calif (LA) 800-296-2803
www.BurlingtonSafety.com
info@BurlingtonSafety.com
Buy Online Now!
2 0 16 NETA OUT STANDING ACH IEV EM ENT AWARD

Jim Cialdea,
Cialdea
3C Electrical
Electrica
owner
ow
wner
neer and
an
and
CEO, alway
always
JIM CIALDEA: a technician
at heart.
EVERYONE SHOULD
BE PART OF THE
ASSOCIATIONS
THAT SHAPE
THEIR INDUSTRY
B Y CA R L A K A L OG ERIDIS, NETA

NETA 2016 If hes asked or hired to do something, hes going another one of those things that Jim Cialdea did
to get it done sometimes painfully but hes right. It has been an excellent choice, an important
Outstanding going to do it right no matter how long it takes, one in helping us to grow our business, he says.
Achievement says Jims son Steve Cialdea, who has worked part- Everyone should be a part of the associations
time for his father since age 16 and came on full- that shape their industry. Cialdea and Picciolo
Award honoree time a couple of years ago after earning his masters worked hard to build 3-C Electrical into a NETA
Jim Cialdea has in electrical engineering. Accredited Company.
a motto, one I always wanted to work with him, says Steve, NETAs Outstanding Achievement Award is given
that applies to an engineer with his fathers firm, 3-C Electrical in recognition of an individuals commitment
Company, named for Jims father and his two to NETA and leadership through service to the
every aspect of brothers who started the company in 1971 to association. It is always a difficult decision to
his personal and service, install, and maintain electrical power make since every single member contributes to
distribution equipment. Today, the organization the growth and advancement of our industry
professional life: each day that they are in the field serving clients
has grown to 60 employees with offices in
If youre going Massachusetts and Maine. All of 3-C and participating throughout the industry in
volunteer efforts, says Ron Widup, CEO
to do it, you Electricals technicians are NETA certified.
and President of Shermco Industries
might as well 3-C was a NETA member company and President of the NETA Board of
back in the 1970s for a while when Jims Directors, who presented Cialdea with
do it right. father was running the company, until the Outstanding Achievement Award
their focus became more construction. at this years PowerTest conference. The
When Jim Cialdea and Alex Picciolo conference ran March 14 18, 2016, at
took over, they started moving the business again the Omni Fort Worth Hotel in Fort Worth,
toward testing and maintenance. I have been to Texas.
every NETA PowerTest conference since the early
PowerTest 2016 represents the largest gathering
1990s, Cialdea says. It was Jayne Tanz who first of electrical power systems professionals
came up in her very convincing way and in the industry and is the only conference
suggested that we re-join. and trade show specifically designed for the
Joining NETA again falls under the category of electrical testing industry. As it is every year,

82 SUMMER 2016 JIM CIALDEA: EVERYONE SHOULD BE PART OF


THE ASSOCIATIONS THAT SHAPE THEIR INDUSTRY
the Outstanding Achievement Award was Alex Piccioli, COO and Co-owner of 3-C
presented by NETAs President at the Member Electrical Company, has worked with Jim Cialdea
and Alliance Luncheon on PowerTest Monday. for more than three decades. Jim is very well
respected in the electrical power industry and
It is quite an honor to receive this acknowledgement related community by building long-lasting
knowing who received the award in the past and relationships, and devotion to family and
understanding all the people who do so much for employees, says Piccioli, as well as his ability to
NETA says Jim Cialdea. It was a surprise.
provide engineered solutions to clients, passion
Widup acknowledged that it is a tough task to for promoting education and supporting those
choose an honoree because so many members work institutions, and commitment to foster the growth
tirelessly to keep the business of the association and continued participation in state and national
moving forward and usually outside of regular code panels and organizations.
business hours. It is also a humbling experience to
take stock of all the work that gets done by people
who have the drive, determination, and heart to
make this all possible, Widup adds.

This year was no exception. Widup says Jim


Cialdea was selected as the 2016 recipient
because he embodies all the qualities that this
award represents by being committed to the
advancement of NETA from a business as well as a
technical perspective.

Jim is always willing to pitch in and lead or


contribute to a new initiative or breathe life into Early Days at 3C Electrical Jim and his uncle plot a course
an existing program that needs a helping hand, for success.
says Widup.
Jim was extremely appreciative of the
Widup says Cialdea gives the impression of not
acknowledgement from his NETA colleagues,
taking things too seriously, but adds, Under that
adds wife Doreen Cialdea. NETA is a great
calm exterior is a mind committed to asking the
organization, and participating in NETA is very
tough questions, creating solutions, and getting it
important to him. He says NETA improves the
done the right way instead of the easy way.
industry, and he has enjoyed building many close
Steve Cialdea says his father is greatly respected relationships over the years.
among his employees because he leads by
example. Hes a workaholic, and if theres ON HI S DOWNTI ME
trouble, hes not afraid to be in the field with Jim Cialdea is a Registered Professional Engineer,
the guys taking care of things, he says. Hes a Licensed Master Electrician, a Licensed
respected because everyone knows that he can Construction Supervisor, and a Level IV NETA
do the job of any one of his employees. Certified Technician. Like his son, Jim followed
in his own fathers footsteps and now has
Steve says his fathers excellent reputation over 30 years of experience in the electrical
spreads from his company to the industry as testing industry.
well. They keep giving him awards, so he must
be doing something right, he laughs. Hes In addition to several other volunteer
extremely involved in professional societies and positions he holds with other organizations,
has the utmost respect and admiration of his Cialdea is the First Vice President of NETA,
industry colleagues. has served as a member of the NETA Board

JIM CIALDEA: EVERYONE SHOULD BE PART OF NETAWORLD


NETAWORLD 83
THE ASSOCIATIONS THAT SHAPE THEIR INDUSTRY
Always a positive influence, Jim and Doreen Cialdea Relaxing at his favorite pastime
willing to do whatever it takes
to make it happen.
of Directors since 2011, is a Membership Review A SEAT AT THE TABLE
Committee member, one of the newest members of In making his presentation to Jim Cialdea at
the NETA Standards Review Council, chair of the PowerTest, Widup commended him for his
Alliance Committee, and a member of the Exam dedication to improving the industry and the
Review Committee. world around him.
Cialdea has many hobbies and passions outside Looking ahead, Cialdea, who was recently
of electrical testing and technology, including appointed to the Standards Review Council,
photography, history, boating, and traveling. His
is looking forward to helping write the ANSI/
wife would add music and wine to that list.
NETA standards. He says he is very honored to
He is just an all-around nice guy who is always be sitting at the table with this group of very smart
ready with a kind word, a smile, and a laugh, people and is looking forward to expanding his
says Widup. And hes always up for an adventure relationship through NETA and sharing and
or just kicking back with a beer and some good exchanging ideas.
conversation.
It is important to contribute, to improve the
There has never been a want for excitement standards, Cialdea says. Getting involved not
when working with and having many a fun time only makes the industry better, but helps make
with Jim over the past 33+ years, says your company better, and makes us all better
Piccioli. We have had the very good professionals. Sharing information and ideas
fortune to start together in the family helps us make everyone better.
business, and sustaining the companys
growth with the beliefs of safety, quality, Carla Kalogeridis is part of the NETA World
and value for our employees and clients. Journal editorial team.

Secretary of the IEEE PES Boston Chapter Receiving Outstanding Training 3C Technicians
Achievement Award From
NETA President, Ron Widup
84 SUMMER 2016 JIM CIALDEA: EVERYONE SHOULD BE PART OF
THE ASSOCIATIONS THAT SHAPE THEIR INDUSTRY
JAMES G. CIALDEA,
NETAs 2016 Outstanding Achievement Award Honoree
Jim Cialdea, P.E., is Owner and Chief Executive Ofcer of 3C preventative maintenance programs, and performing related technical
Electrical Company, Inc., in Westborough, Massachusetts. and support services designed to add quality and value for
Jim began working at 3C Electrical under the tutelage and 3Cs customers.
training of his father, Giulio Cialdea,in 1984. He took over Jim is a Registered Professional Engineer, Licensed
the business in 1988 and, under his able leadership, 3C Master Electrician, Licensed Construction Supervisor,
M
Electrical has achieved marked success in performing g and NETA Certied Test Technician Level IV. He holds
a
a broad range of engineering activities and a B.S. in Electrical Engineering, Power Option, from
endeavors, including facilitating and implementing Worcester Polytechnic Institute. Jim brings an inherent
W
new plant and systems designs for supply-side knowledge of the practical aspects of electrical power
and demand-side customers, expanding and engineering with over 30 years experience managing
affecting improvements to the complex and executing projects. In addition to serving on the
electrical systems at existing customer NETA Board of Directors and several NETA committees,
facilities, implementation of all manner of JJim holds several volunteer positions including IEEE Power
and Energy Society Boston Chapter Secretary, member
a
of the Commonwealth of Massachusetts Electrical Code
Advisory Sub-Committee, and MECA Past President.
We put the we
in Empower

Get Empowered with Doble.


Learn more about our in-service testing tools which help you to identify and locate electrical partial
discharge, low-voltage arcing and mechanical system defects before they lead to
asset failure.
www.doble.com/NETA

Empowering the industry with services, solutions and unmatched knowledge.


For nearly a century, Doble has been amassing an unprecedented amount of knowledge and practical experience
in preventing asset failure. We share this knowledge through our products, services and training programs.
We make sure you have the tools and information you need to perform your job and meet the needs of your customers.
HVI - The Worlds Source for
High Voltage Test Equipment

+1.518.329.3275 |

NEW!
VLF & TD from High Voltage, Inc. HVI with the newest designs available
offering the most in control, communications and data reporting.

To
Te
ut
Outp

st C
VLF
HV
< VLF-34E Solid State Design TD-34E

ab
le
0 34 kVac peak, sinusoidal or square wave
0.5 +F 5.0 +F @ 0.1 Hz 0.01 Hz
+/- 34 kVdc, Sheath Testing, Load Burn
USB Port for data collection and removal Full
nd
Gr
ou Remote Control Wireless with XBee
XBee for Reliable Wireless - no Bluetooth

< VLF-65E Solid State Design TD-65E


0 65 kVac peak, sinusoidal or square wave
1.0 +F 10.0 +F @ 0.1 Hz 0.01 Hz
+/- 65 kVdc, Sheath Testing, Load Burn
USB Port for data collection and removal Full
Remote Control Wireless with XBee
XBee for Reliable Wireless - no Bluetooth

All HVI Products are


Made in the USA
ISO 9001 2008
HIGH VOLTAGE, INC. &RXQW\5W$&RSDNH1<7HO  )D[  sales@hvinc.com www.hvinc.com

Company

Up Your Production And Stay In The Game!


PQ Analyzers with Remote Wireless Communications
Control your Dranetz HDPQ from your smartphone, tablet, or computer!

732.287.3680
1000 New Durham Road
Edison, New Jersey 08817
sales@dranetz.com www.dranetz.com
INDUSTRY TOPICS

Of Circuit Breakers
B Y PA U L H . G REIN, Circuit Breaker Sales Co., Inc.

This article examines the changes to medium voltage circuit


breaker testing over three generations spanning 70 years from
1945 to today. It discusses the challenges and driving forces
that evolved circuit breaker testing, including technological
advances in circuit breaker technology, safety practices, and
test equipment.

Figure 1: The Evolution of Cicuit Breakers


Photo courtesy of Brian Kaylor

In May 1945, World War II ended; that and how technological and safety advancements
same year, Westinghouse introduced its first have led up to the testing they perform today.
medium-voltage air-magnetic circuit breakers,
and the first American standard for ac power THE OI L YEARS, 1 9 4 5-1975
circuit breakers was published. Circuit breakers The Golden Years is often the moniker used
of the day were heavy, expensive, unreliable to describe the period following World War
devices that required regular upkeep to ensure
II. Regulatory intervention from federal and
they performed as expected. Early technicians
local governments was minimal, and the power
worked in hazardous environments where
profits often trumped employee safety. Over equipment industry benefited immensely from
three generations spanning 70 years, circuit an era of rapid growth. Between the years 1946
breaker technology has advanced and safety and 1947 alone, power usage grew almost 15
practices have improved. This article examines percent, creating an avid demand for power
three generations of circuit breaker technicians, equipment and men qualified to operate

THE EVOLUTION OF CIRCUIT BREAKERS NETAWORLD


NETAWORLD 89
INDUSTRY TOPICS
and maintain it. The demand for electric In 1963, Westinghouse introduced the DH-P
power and advances in productivity created a type air-magnetic Porcel-line circuit breaker
need for circuit breakers with higher current and switchgear, with all live parts insulated to
ratings and interrupting capacities. Growth ground by high-strength porcelain insulation
continued for decades, at a diminishing versus the paper phenolic insulation used in
rate, until it stagnated in the tumultuous the DH designs, but by this time the oil-
1970s to the average 7 percent we see today. generation circuit breaker technician was
While the golden years may delineate the certainly eyeing retirement.
economic growth that drove the circuit
breaker industry, the oil years better describes Safety in the Oil Years
the breaker technology that ruled the era. Safety was not a priority in industrial
environments until the Occupational Safety
Circuit Breakers in the Oil Years and Health Administration (OSHA) was
Before and in the decades immediately created in 1970 when the Williams-Steiger
following World War II, the most common Act was signed into law. Electrical safety was
medium-voltage circuit breaker technology not emphasized until 1979 when the National
used was oil-tank circuit breakers. Many of Fire Protection Association (NFPA) published
the switchgear manufacturers that served the NFPA 70E, Standard for Electrical Safety in
American market during World War II remain the Workplace, at OSHAs request. Prior to
in business today, including General Electric, OSHA and NFPA 70E, responsibility for
Westinghouse (now Eaton Cutler-Hammer), maintaining safe work practices fell on the
and ABB. This article bases its discussion on technician, and electrically safe work practices
Westinghouses introduction of circuit breaker were anything but. Electrical safety in the
technology with the understanding that beginning of the oil generation can be
competing manufacturers may have innovated summed up by this excerpt from the American
the technology earlier or later. Electricians Handbook of 1942, which is
The 1940s saw the beginning of a major comical by todays standards:
transition from oil-tank to air-magnetic 158. Electricians often test for the presence
circuit breakers, but oil-tank technology of voltage by touching the conductors with the
remained the workhorse of American utilities fingers. This method is safe where the voltage
and factories. Despite the introduction of air- does not exceed 250 and is often convenient to
magnetic technology, Westinghouse continued
locate a blown-out fuse or for ascertaining whether
manufacturing its type B and type F oil-
or not a circuit is alive. Some men can endure
tank circuit breakers into the early 1950s.
the electric shock that results without discomfort
However, extinguishing the arcs produced
whereas others cannot. Therefore, the method
from larger interrupting currents in insulating
is not feasible in some cases.
oil was reaching its technological limit; for
the Westinghouse model B-28-B to achieve Which are the outside wires and which is the
maximum ratings of 15kV, 500MVA, 2000A, neutral of a 115/230-volt, three-wire system can
the breaker had swollen to over 2,000 pounds. be determined in this way by noting the intensity
To meet the continually increasing demand for of the shock that results by touching different pairs
higher ratings, Westinghouse introduced its of wires with the fingers. Use the method with
DH-type medium-voltage air-magnetic circuit rc
caution and be certain the voltage of the circuit
breakers and switchgear in 1939. Initially, the does not exceed 250 before touching the conductors.
to
DH line was limited to 5kV up to 150MVA,
but by 1946, the maximum voltage
olt of the DH The precautions
p uti listed in circuit breaker
eak
was extended to 15kV; over time,
me the maximum instruction and installation books of the day
nstruction an d
rated interrupting capacity of th
the DH breaker were largely written
w to protect the equipment
me
reached 1,000 MVA. from
rom being damaged
d rather than protecting
cti

90 SUMMER 2016 TTHE EVOLUTION OF CIRCUIT


CU BREAKERS
AKER
INDUSTRY TOPICS
personnel from injury. The equipment was technological advances and safety environment
designed for increased operating safety when we experience today took root in the air years
compared to previous generation designs; the between 1965 and 1995.
primary circuits were isolated via steel barriers
rather than exposed, and interlocking was From Oil to Air
integrated into the racking mechanism. As mentioned previously, the transition from
oil-tank to air-magnetic circuit breakers
Advanced safety features aside, working with began in the 1940s, but the first generation
oil-tank circuit breakers was a risky endeavor; of air circuit breakers was limited to light-
the breakers were formidable devices whose duty applications with maximum ratings of
bulk made them difficult to install and 5kV, 50MVA, 1200A. However, customer
maintain, and their insulation systems were interest for the new technology and the
antiquated and often toxic. Combining these technological limitations of oil-tank designs
factors with the early manufacturing capabilities encouraged manufacturers to increase ratings
of the day resulted in unreliable operation, quickly. In 1946, air magnetic circuit breaker
especially compared to todays standards. ratings were extended up to 15kV, 500MVA,
When oil circuit breaker failures occurred, 2,000A applications. The first generation of
the consequences were usually catastrophic. Westinghouse air-magnetic breakers reached
their technological limit in 1958 with the
Circuit Breaker Testing in the Oil Years
model 150-DH-1000, 3,000A circuit breaker.
The majority of circuit breaker testing
To reach the extended 1,000MVA interrupt
performed in the oil years was a mechanical
and 3,000A continuous current ratings, the
process analogous to performing maintenance
breaker design had bloated to 3,908 pounds
on an automobile rather than maintaining
with each arc chute weighing in at over
electrical equipment. Maintenance consisted
600 pounds!
of testing, cleaning, and changing the oil then
physically inspecting the operating mechanism, The introduction of air magnetic technology
contact condition, connections, and looking brought many advantages over the oil-tank
for signs of carbonization. Maintenance was breakers they replaced, including:
performed by in-house technicians with Removal of the oil and the associated
limited specialized training or test equipment. chemical and fire hazards
If available, dedicated test equipment was Higher contact breaking speeds and faster
limited to dielectric test sets that measured the arc quenching
insulating oil resistance and high-potential test Smaller arc duration allowing extended
sets for the solid insulation. Test equipment and service life of contacts
practices did improve through the oil years, but Extended interrupt and continuous current
advancements were adopted slowly. It wasnt until ratings
the next generation that circuit breaker testing Smaller size and weight at a given rating
would begin to resemble what we see today. Much less maintenance

Westinghouse introduced its second generation


T H E A I R Y E AR S, 1945-1975 DH-P Porcel-line model air-magnetic circuit
The economic good times experienced during breakers in 1963. Initially, the breakers were
thee golden years following World War II rated up to 15kV, 750MVA interrupt, and
would
ou not last forever. A combination of ,
2,000A continuous current ratings; by 1974,
macroeconomic
ac events includingding the oil the maximum cucurrent ratings were increased to
embargo
mb of 1973 stalled the eeconomy,
ecoonomy, but
b 00
1,000MVA, 3,000A.
growth
ow in thehe power equipment inindustry
nddustry crept
d crep
along
on at 7 per
percent. While the economic
no setting
n The innovations in
introduced in second-generation
of the
t period
io may have been w wanting, the
th ake technology stemmed from
air circuit breaker

THE
HE EVOLUTION
E ON OF CIRCUIT BREAKERS
S NETAWORLD 91
INDUSTRY TOPICS
advancements in design, m materials, and during
ur the air i years. After the Williams-Steiger
ir iiaa
manufacturing. Rather than paperp phenolic Act
cctt was signed
gnn into law in 1970, 70 creating
insulation used in early generation
ne circuit OSHA,
SSHA,
HA, iin
n 119
1979
9979
79 th
thee NFPA
NFPAP p publish
published
ublish NFPA
breakers, the DH-P relied on porcelain to 70E, the firstt nationally
n accepted standard that
insulate all live parts from ground.
ound Porcelain aaddressed
ddressed eelelectrical
l safety requirements for
and similar advanced insulation material employee workplaces.
technologies are non-tracking, non-combustible,
and non-hygroscopic. The reduction of insulation The first edition of NFPA 70E included
tracking and non-hygroscopic properties installation work practices; since that first
allowed circuit breakers to become more edition, the document has continuously
compact and lowered the risk of failure from improved. Published in 1981, the second
flash-over, increasing reliability and safety. edition added safety-related work practices. In
Technician safety was also improved by 1983, safety-related maintenance requirements
replacing antiquated materials that could be were included as well. At the end of the air
toxic when mishandled. years in 1995, the fifth edition of NFPA
70E introduced arc-flash hazards. Since their
Early air circuit breaker designs were furnished partnership began, OSHA and NFPA have
with a solenoid operated mechanism with cast worked together to establish standards and
parts and monolithic pole assemblies. By the codes documenting safe work practices to ensure
late 1960s, stored-energy spring mechanisms employee safety in the workplace and levy
had phased out the solenoid operator, markedly fines when those standards are not followed.
increasing operating speeds. By 1968, cast
mechanisms were replaced with machined and The air years established the advancement of
modern fabricated mechanisms. Finally, after technician safety through the foundation of
1970, monolithic pole units were phased out by standardized and enforced safety practices,
the post-insulator pole unit, the single/isolated which in turn impacted how breaker testing
pole designs employed today. These and other was performed.
advancements to circuit breaker design had an
enormous impact on circuit breaker reliability Air Years Circuit Breaker Testing
so much so that it is common to find From generation to generation, circuit breaker
equipment commissioned in the 1960s still in testing requirements have expanded in scope
use today, over 50 years later. and scale. The introduction of new circuit
breaker technology and the advancement of test
At the end of the air years, vacuum circuit equipment and safety practices brought forth
breaker technology was arriving in American both new types of tests and testing requirements.
utilities, factories, and distribution systems.
The first-generation vacuum breakers, such as The transition between circuit breaker technologies
the Westinghouse DVP introduced in 1978, was a gradual process requiring technicians to
were directly interchangeable with the air- maintain the equipment of current and
circuit breakers they would eventually replace. previous generations. The growing knowledge
The improvements that accelerated during the and experience required to effectually test
air years were not limited to circuit breaker the rapidly expanding arena of circuit
technology. Test equipment and especially breaker technologies led to the increased
safety practices developed considerably during use of specialized breaker technicians, often
the air years. employed from outside testing companies versus
in-house technicians. Outsourcing circuit breaker
T H E A IR S AF E T Y ERA testing introduced new challenges, the largest
The safety environment that many of us take of which was ensuring that testing was
for granted today was pioneered a generation performed consistently and accurately by
ago as workplace and electrical safety originated suitably experienced and trained technicians.

92 SUMMER 2016 THE EVOLUTION OF CIRCUIT BREAKERS


INDUSTRY TOPICS
A group of electrical testing business owners THE VACUUM GENERATI ON:
recognized the need to standardize electrical 1 9 8 5-TODAY
testing to combat the inconsistent testing For much of America, the 1970s was a
and safety practices that were commonplace. tumultuous time and the 1980s were not
In 1972, the National Electrical Testing free from hardships, but most would agree
Association (NETA) was formed with that history has shown the decade to be a
the goal of establishing uniform testing turning point for the country economically
procedures for electrical equipment. In 1977, and technologically. Driven in part by the
NETA published ATS-1977, Acceptance Testing intense competition between the United
Specifications for Electrical Power Distribution States and the Soviet Union, technological
Equipment and Systems. ATS-1977 illustrates innovation and other advancements exploded
how circuit breaker testing has expanded in the vacuum generation. Many of the most
since the 1940s. Comparing the maintenance significant circuit breaker advancements took
recommendations from circa 1940s and 1950s place during the vacuum generation.
maintenance manuals to the ATS-1977 test
Vacuum Circuit Breakers
recommendations for like equipment gives an In 1978, Westinghouse introduced the DVP
indication of how the types of testing continue type in 500 and 750 MVA, its first vacuum
to grow. Apart from the basic mechanical circuit breaker model. The DVP was not a new
inspections predominant in the oil years, all of line of switchgear; it was an introduction to
the following tests either took root or became vacuum technology used with its existing DHP
expected during the air years: Porcel-line switchgear (directly interchangeable,
1. Visual and mechanical inspections identically-rated DH-Ps). Competing manufacturers
Contact alignment and condition took a similar approach to introducing vacuum
Lubrication interruption technology. In 1981, Westinghouse
Tightness of bolted connections introduced its VCP line of vacuum circuit
2. Contact resistance breakers and associated VacClad switchgear in
3. Travel time test ratings up to 15kV and 1,000 MVA. VCP was
4. Sample insulating liquid Westinghouses first generation of modern
Dielectric strength vacuum circuit breakers.
Acidity
Interfacial tension Vacuum interruption is arguably the most
Color significant innovation in medium-voltage circuit
5. Minimum pickup voltage tests breaker technology. Vacuum interruption has
Close numerous advantages over previous generation
Trip equipment, including:
6. Insulation resistance testing Breaker size and weight are significantly
7. AC and/or dc over-potential testing reduced, allowing two-high stacking
8. Control wire insulation testing construction and making them physically
9. Power factor testing easier to remove and transport for maintenance.
Removal of air-magnetic arc chutes eliminates
The expanding knowledge requirement was associated maintenance and handling issues.
not limited to understanding the idiosyncrasies Contact upkeep is reduced to monitoring
of the various types of breaker technology versus maintenance.
not to mention the various manufacturers and Vacuum insulation strength greatly reduces
models but also included the theory and the required contact gap, allowing breaker
application of new testing requirements. Testing operating mechanisms to become faster to
was beginning to see a gradual transition from operate, more reliable, and easier to maintain.
corrective to preventative maintenance, a trend Interrupting arcs are contained, making
that would accelerate in generations to come. them non-explosive.

THE EVOLUTION OF CIRCUIT BREAKERS NETAWORLD


NETA WORLD 93
INDUSTRY TOPICS
The mechanisms require significantly less Despite the progression of safety afforded by
stored kinetic energy during operation, procedural and technological advancements,
making them safer to maintain. the modern technician faces many of the
same risks as those of previous generations.
In 1986, Westinghouse introduced the second The implementation of new technology in
generation VCP-W line of vacuum circuit the power industry is a slow process. There
breaker and associated VacClad-W switchgear are countless installations across the United
in ratings up to 15kV at 1,500 MVA and 38kV States that still use air-magnetic and even
at 40kA. VCP-W included product improvements oil-tank circuit breaker technology that has
in manufacturing design and performance. In been in service for over 40 or even 50 years.
1995, an arc-resistant version of the VCP-W The continually expanding knowledge and
brand was introduced: VCP-W is Eatons current experience level required to safely maintain
switchgear offering in medium voltage. power equipment technology spanning three
generations may be the greatest challenge to
The most recent innovations in medium-
present-day maintenance technicians.
voltage circuit breaker technology involve
the operating mechanism rather than the Testing Technicians Today
interrupting medium. Several manufacturers So far, three generations of circuit breakers have
have introduced magnetic-actuator operating been discussed the oil, air, and vacuum
mechanisms that have few moving parts, require eras as well as how technology and safety
no maintenance or adjustments over the life of advancements have affected circuit breaker
the product, and are warranteed for five years testing. The primary challenge that todays
versus the industry standard of one year. technicians face is the overwhelming level
of expertise needed to effectively and safely
M ODE RN S AF E T Y evaluate three generations of equipment.
During the air years, the largest contributor
to technician safety was the development and Over the last 70 years, four or five major and
enforcement of modern safety practices. In several minor switchgear manufacturers have
the vacuum generation, safety practices were collectively produced over 100 combinations
further enhanced by OSHAs institution of of models and ratings of medium voltage
lock-out/tag-out procedures in 1989, the circuit breakers. Medium-voltage circuit
recognition of arc-flash hazards by the NFPA breakers have been the focus of this article,
in 1994, and subsequent efforts to reduce but electrical maintenance personnel and
exposure to arc flash. Recent efforts to reduce technicians are also responsible for testing the
or remove the risk of arc flash include arc-flash entire lineup of electrical equipment, including
studies, the implementation of remote and low-voltage circuit breakers, motor starters,
integrated racking devices, and use of advanced transformers, cables, motors, metering, relays,
personal protective equipment. and ground fault systems. To overcome these
During the vacuum generation, the most challenges, technicians have evolved from
significant contributor to safety was technological mechanics to electrical maintenance personnel
innovation. The advantages of vacuum circuit to technicians who specialize in narrow fields
breaker technology partnered with modern of expertise. Specialized technicians may have
manufacturing capabilities and materials have some experience on the entire spectrum, but
dramatically increased the reliability of modern have focused expertise and training that is
power equipment operation and safety features. limited to a few and sometimes a single
Increased equipment reliability results in category of electrical equipment. No matter
longer maintenance cycles and fewer failures, what their specific category of expertise
which in turn reduces maintenance technicians may be, all technicians must be trained and
exposure to the hazards. proficient in safe work practices.

94 SUMMER 2016 THE EVOLUTION OF CIRCUIT BREAKERS


INDUSTRY TOPICS
L O O K IN G F ORWAR D REFERENCES
The greatest changes to the industry are and ABB (2014). AMVAC. Medium Voltage Indoor Circuit
will continue to be driven by globalization Breakers Descriptive Bulletin,
Bulletin, pp. 6-7. Lake Mary: ABB.
and advancements to circuit breaker and Croft, T (1942). American Electricians' Handbook, 5th
Edition. New York: McGraw-Hill Book Company.
manufacturing technologies. These and other
Eaton (2013). Medium Voltage Switchgear. In
factors have driven costs down to where it CA08100014E Aftermarket, Renewal Parts and
almost makes more sense to replace equipment Life Extension Solutions Catalog, pp. V12-T17-53 -
rather than maintain it, and modern breaker 64. Eaton.
designs encourage that practice. Howell, J (2014). NETA Setting the Standard.
NETA World Journal, pp. 1-4.
Circuit breaker designs are becoming modular. Jooma, Z. (2016). History of the NFPA 70E.
The trend began with plug-and-play parts Retrieved from Electricity and Control:
such as coils and motors, but now, complete http://www.eandcspoton.co.za/resources/docs/
Hazardous/History_of_the_NFPA.pdf
mechanisms and interrupting assemblies are
Littelfuse (2005). Electrical Safety Hazards Handbook.
designed to be quickly and easily replaced in Des Plaines: Littelfuse Inc.
the field. Opinions will vary on whether the NETA (1977). Acceptance Testing Specifications for
philosophy of make it fast over make it last Electrical Power Distribution Equipment & Systems.
is an improvement, but most would agree that Meriden: National Electrical Testing Association.
it is unlikely that switchgear commissioned U.S. EIA (2016, January 15). History of Energy
today will still be in service in the year 2075. Consumption in the United States, 17752009.
Retrieved from U.S. Energy Information
Over the years, the means and methods of Administration's Today in Energy: https://www.eia.
electrical testing may have changed, but the gov/todayinenergy/detail.cfm?id=10#
Westinghouse (1941). Type "DH" "De-ion" Air Circuit
goal has remained the same: the upkeep and
Breakers Instruction Book. Pittsburgh: Westinghouse.
preservation of electrical equipment. Dramatic Westinghouse (1944). "Unitized" Heavy-Duty Metal-Clad
improvements to circuit breaker technology, Switchgear. Pittsburgh: Westinghouse Electric &
safety practices, and testing capabilities have Manufacturing Company.
resulted in continually increasing performance Westinghouse (1949). Instructions - High-Voltage Metal-
and reliability. Without question, modern Clad Switchgear with "F" and "B" Oil Circuit Breakers.
Pittsburgh: Westinghouse Electric Corporation.
equipment is easier and safer to maintain, and
Westinghouse (1949). Unitized Metal-Clad Switchgear
as the aging equipment of previous generation Light-Duty DH Type Descriptive Bulletin.
is slowly upgraded and industry innovations East Pittsburgh: Westinghose Electric Corporation.
continue, the risks and costs of maintaining it
will continue to decrease. Westinghouse (1958). Descriptive Bulletin Standardized
Metal-Clad Switchgear. East Pittsburgh: Westinghouse
Electric Corporation.
Paul Grein has been with Group CBS Westinghouse (1959). Instrcutions De-ion Air Circuit
since 2008, working primarily at Circuit Breaker Type 150-DH-1000. East Pittsburgh:
Breaker Sales in Gainesville, Texas. He Westinghouse Electric Corporation.
has worked with industrial electrical Westinghouse (1965). Porcel-line Metal-Clad Switchgear
equipment for 20 years, beginning in the
with Type DH-P Air Circuit Breakers Descriptive
Navy as a Nuclear-qualified Electrician
on the submarine USS Topeka SSN 754 Bulletin. East Pittsburgh: Westinghouse Electric
from 1996 through 2002, followed by Corporation, Switchgear Division.
positions in the steel industry through 2005. Paul has a
BSEE from the University of Texas at Dallas (2007) and
an MBA from the University of North Texas (2014).
He participates in the IEEE/ANSI PES C37 Standards
Committee, which publishes and maintains the design
and testing standards that govern the industrial power
equipment industry. Pauls primary responsibilities at CBS
and the Group include sales, engineering design, technical
expertise, standards, project management, and engineering
team management.

THE EVOLUTION OF CIRCUIT BREAKERS NETAWORLD


NET 95
SAVE THE DATE
Join us in the land
of golden promise.
February 27 through March 3

A N A H E I M C A L I F O R N I A POWERTEST.ORG 888.300.6382

February 27 - March 3 2017 THE PREMIER ELECTRICAL MAINTENANCE & SAFETY EVENT

DISNE Y L A ND HO T E L
INDUSTRY TOPICS

For Large Power Transformers


In Today's Electrical Utility Sector
B Y R AY CU R RY, American Transmission Company

Use the best of the past to build the future. Unknown


In the previous article (see NETA World Journal, Winter 2015), I
touched on items that affect transformer installation and testing.
Now, I want to focus on two items that have changed the field
assembly of these transformers. Both have their origin in the 1970s
and continue to have a strong influence today.

FA L L P R OT E C T ION A ND on top of the main tank for the placement of


C O N F IN E D S PA C E railing systems. Some manufacturers provide
First and foremost was the establishment of an attachment area for installing a may pole
OSHA, and in particular, CFR 1910. Perhaps (see picture). This pole is rated to have up to
four workers attached at one time and still
the most influential thing to happen in the
meet OSHA code.
1970s was the establishment of OSHA. The
development of OSHA Regulation CFR 1910
on Fall Protection and Confined Space has
had a major influence on how the assembly
of large power transformers is accomplished.

Before any assembly work is started, the


best practice is to ground the transformer to
the ground grid of the substation. It is also
a good practice to ground all cranes, lifts,
processing trailers, and tankers.

In the area of fall protection, enhancements


to and development of man lifts, work
platforms, and body harnesses are designed
to comply with OSHA regulations. When
assembling large transformers, workers
operate anywhere from 10 to 40 feet above the
ground. Some transformers have attachments

ESTABLISHING MAINTENANCE ZERO FOR LARGE POWER NETAWORLD


NETAWORLD 97
TRANSFORMERS IN TODAY'S ELECTRICAL UTILITY SECTOR
INDUSTRY TOPICS
Todays power transformer is designed with a When fully loaded, these large transformers
smaller main tank. The intent of this design is produce a tremendous amount of heat. To
to aid shipping the largest MVA transformer dissipate this heat, mineral oil is used with
over the road versus railroad shipment. The pumps and radiators. Silicone and other fluids
length and width of todays transformer has were developed through the 1970s, but mineral
not changed much, but the height has been oil still provides the best heat transfer in the
greatly reduced. This reduction creates two large transformer. However, mineral oil can
challenges for the assembly crew: (1) more have a negative impact on the environment.
field assembly on top of the transformers To counter this, new products for containment
main tank and (2) in most designs, very and engineered systems have been initiated for
restricted work space for any inside tank most transformers, new and old.
work required to connect the high- and low-
side bushings. To address the inside work, With respect to ancillary equipment,
draw lead bushings are sometimes used. Side Reinhausen developed the vacuum tap
wall access flanges allow employees to make changer and grew its world market share in
up winding connections on the bottom of the 1970s. Most distribution and transmission
the bushings. class transformers have load tap changers.
The vacuum tap changer requires far less
By OSHA regulation, should any assembly maintenance compared to older tap changers.
work be required inside of the main Likewise, companies such as Ohio Brass
transformer tank, this entry point and and Qualitrol, among others, developed and
workspace must be treated as a confined improved transformer products through the
space. The regulation states that the entry 1970s and 1980s. Microprocessor-based
is by permit only. Another part of the protective relays a vast improvement over
regulation requires that the contractor have the electro-mechanical relay now protect
extraction equipment present while workers this expensive capital equipment.
are in the permitted space.
Computer modeling software has also provided
design engineers with the ability to build a
DE SIGN A ND E NGI NEERI NG
transformer that operates with more efficiency,
C H ANG E S heavier load cycle, and longer operating life.
The second influential item of the 1970s affecting To gain this capability, field assembly and
transformer field assembly is design and oil processing has been improved from the
engineering changes. Advancements that began in 1970s to now. Companies such as Barron have
the 1970s have become global today. Transformer designed vacuum/oil processing trailers that
manufacturers must use the building blocks of are also computer controlled. All transformers
the past to compete successfully today. in the high-voltage class (50kV and above) are
The advancement of computer-aided design designed to withstand full vacuum. The high
(CAD), for example, gave rise to computer- vacuum is used to dry or pull moisture out of
aided engineering (CAE), which allowed the the transformer. In the 1970s, this processing
engineer to build with modeling software. equipment would attain 800 to 1,000 microns
These programs grew in many directions or 0.8 to one Torr. Todays equipment will
and gave birth to new support services and typically reach 40 to 200 microns. To put this
ancillary equipment. Start-up companies in better perspective:
provided polymers, epoxy resins, and new 1,000 microns = 1 Torr = 1 millimeter of mercury
dielectric insulations, which in turn allowed
the transformer to be built with a higher basic Because of improved design and assembly,
insulation level or basic impulse level (BIL), todays transformers use neoprene and nitrile
which led to higher kilovolt (kV) levels. rubber gaskets, compared to units built in the

98 SUMMER 2016 ESTABLISHING MAINTENANCE ZERO FOR LARGE POWER


TRANSFORMERS IN TODAY'S ELECTRICAL UTILITY SECTOR
INDUSTRY TOPICS
1960s and 1970s, which used cork or cork- An objective of every large power transformer
neoprene. On the older transformer, oil leaks assembly and installation is to maximize its
occurred early as the cork dried out, which in life cycle by establishing a sound maintenance
turn affected annual maintenance work. The program. A term used today is Maintenance
preferred gasket or O-ring rubber is Nitrile Zero. By obtaining the proper installation,
70 or Nitrile 90. Many transformers of the vacuum/oil processing, and detailed final in-
late 1980s are in service today with Nitrile 70 service testing, the transformer owner lays
and have had little or no oil leak issues caused the foundation for 40-plus years of useful
from degradation of the nitrile. When these transformer life. In the next article in this
units were first assembled and processed, the series, I will outline how power transformer
benefit of having the advanced gaskets and testing, test equipment, and record keeping
O-rings was a tighter transformer with respect have changed from the 1970s to today.
to vacuum/pressure leaks. In turn, this reduced
the vacuum processing time. There are challenges going forward. One is
maintaining a skilled workforce that can deliver
Even with the higher vacuum, the processing quality technical workmanship safely to the
and oil filling of a large transformer takes time. customer. Another is building a strong working
Typically, most of these transformers will hold relationship between the manufacturer and the
10,000 to 26,000 gallons of oil. As part of field assembler/processor/testing company. As
the processing, oil is heated and degassed as a result, many NETA Certified Companies
it flows through the processing equipment at have formed strong working relationships with
a rate of 20 to 30 gallons per minute, heated Hyundai, GE, ABB, and Siemens to name a
again, and injected into the transformer tank. few. These relationships are strengthened with
Some transformer manufacturers also require factory training, technical seminars, and new
oil recirculation to obtain lower moisture product engineering updates. With many of
levels. After all, in most installations, the todays transformers built overseas, reliability
manufacturer is providing a warranty that may to the end customer has taken on a whole new
last several years.
meaning and significance.
Another aspect of todays transformer is the
preservation of the oil. Many transformers of
the 1970s used a nitrogen blanket to control Ray Curry graduated from Penn
oil moisture buildup. Todays transmission State University in 1969. He joined
Westinghouse Electric in the East
class transformer will use the conservator oil Pittsburgh Division and the PCB
preservation system (COPS). With the use Division at Trafford, Pennsylvania. In
of COPS, todays transformer now has a very 1977, Ray relocated with Westinghouse
to St. Louis, Missouri, working in the
sensitive dissolved gas analyzer (DGA) system. E&ISD Division as a Field Service
With the use of another protective relay a Engineer specializing in high-voltage switchgear and
gas-sensing relay that will detect explosive construction/commissioning power substations. After
gases the transformer now has enhanced retiring from Westinghouse in 1994, Ray managed two
municipal electrical systems for the cities of Chanute and
protection against electrical faults that occur Garden City, Kansas, from 1994-2000. From 2007 to
inside the transformer main tank. the present, Ray has been a Commissioning Engineer
with American Transmission Company, building and
When an electric arc happens in an oil maintaining over 500 69kV-138kV to 345kV electrical
transformer, explosive gasses are produced; substations, including more than 200 power transformers
within the ATC Service Footprint. He sits on ATCs Safety
if allowed to accumulate, further damage or Committee and has maintained an active affiliation with
transformer failure may occur. NETA for six years.

ESTABLISHING MAINTENANCE ZERO FOR LARGE POWER NETAWORLD


NETAWORLD 99
TRANSFORMERS IN TODAY'S ELECTRICAL UTILITY SECTOR
SPECIFICATIONS AND STANDARDS ACTIVITY

ANSI/NETA STANDARDS UPDATE B Y K R IST EN W ICK S, NETA

2015
ANSI/NETA ECS-2015
ANSI/NETA ETT-2015

STANDARD FOR STANDARD FOR


ELECTRICAL CERTIFICATION
COM
CO MIS
MM SION
ISS NG
NG
ONIING OF ELEC TRI
RICC AL TES
TESTI
TIN
NG
S P E C I F I C AT I O N S TECHNICIANS
FOR ELECTRICAL POWER
EQUI ENT AND SYST
PME
UIPM SYSTEEMS
G SPECIFICATIONS

ANSI/NETA ATS-201X ANSI/NETA ECS-2015 instrumentation systems, and related


REVISION IN PROCESS FIRST EDITION AMERICAN components.
The ANSI/NETA Standard for Acceptance NATIONAL STANDARD
Testing Specifications for Electrical Power The ANSI/NETA ECS Standard for Voltage classes addressed include:
Equipment and Systems began the review Electrical Commissioning of Electrical Power Low-Voltage Systems (less than
and revision process in October 2014 at Equipment and Systems,
Systems, 2015 edition, 1,000 volts)
the Standards Review Council meeting. was approved as an American National Medium-Voltage Systems (greater
The initial ballot and draft document Standard on December 3, 2014. This new than 1,000 volts and less than
will be issued on April 22, 2016 with a standard is available for purchase in the 100,000 volts)
closing date of May 22, 2016. The draft NETA Bookstore online at netaworld.org. High-Voltage and Extra-High
document will be available for public Voltage Systems (greater than
comment from April 22, 2016 through The ANSI/NETA ECS describes the 100 kV and less than 1,000 kV)
June 6, 2016. The document is expected systematic process of documenting and
to be published as a revised ANSI placing into service newly installed or References
standard in the spring of 2017. retrofitted electrical power equipment ASHRAE, ANSI/NETA ATS, NECA,
and systems. This document shall be NFPA 70E, OSHA, GSA Building
The ANSI/NETA ATS covers the used in conjunction with the most recent Commissioning Guide
suggested field tests and inspections that edition of the ANSI/NETA Standard
are available to assess the suitability for for Acceptance Testing Specifications for ANSI/NETA MTS-2015
initial energization of electrical power Electrical Power Equipment and Systems.
Systems. NEW EDITION
equipment and systems. The purpose The individual electrical components The ANSI/NETA MTS Standard for
of these specifications is to assure that shall be subjected to factory and field tests, Maintenance Testing Specifications for
tested electrical equipment and systems as required, to validate the individual Electrical Power Equipment and Systems,
Systems,
are operational, are within applicable components. It is not the intent of these 2015 edition, was approved as an American
standards and manufacturers tolerances, specifications to provide comprehensive National Standard on December 3, 2014,
and are installed in accordance with details on the commissioning of and supersedes the ANSI/NETA MTS-
design specifications. mechanical equipment, mechanical 2011. This new standard is available

100 SUMMER 2016 ANSI/NETA STANDARDS UPDATES


for purchase in the NETA Bookstore online at Updated references to industry standards
netaworld.org. Many more revisions, all marked in the PARTICIPATION
margins for ease of use Comments and
The ANSI/NETA MTS contains specifications suggestions on any
that cover suggested field tests and inspections ANSI/NETA ETT-2015 of the standards are
available to assess the suitability for continued NEW EDITION always welcome and
service and reliability of electrical power ANSI/NETA ETT Standard for Certification should be directed to
equipment and systems. The purpose of these of Electrical Testing Technicians,
Technicians, 2015 edition, the NETA office at
specifications is to assure that tested electrical was approved as an American National Standard neta@netaworld.org
equipment and systems are operational and on December 3, 2014, and supersedes the or 888-300-6382.
within applicable standards and manufacturers ANSI/NETA ETT-2010. This new standard is To learn more about
tolerances, and that the equipment and systems available for purchase in the NETA Bookstore the NETA standards
are suitable for continued service. online at netaworld.org. review and revision
process, to purchase
Revisions include: The ANSI/NETA ETT establishes minimum these standards, or to
New numbering system for more accurate requirements for qualifications, certification, get involved, please visit
referencing training, and experience for the electrical www.netaworld.org or
Protective relays testing technician. It also provides criteria for call 888-300-6382.
Instrument transformers documenting qualifications for certification
Rotating machinery and details the minimum qualifications for an
New Table 100.11 independent and impartial certifying body to
Revised Table 100.1 certify electrical testing technicians.
CALL FOR EXHIBITORS
California
is calling.
+ Join 400+ electrical
testing professionals
+ Leading decision makers looking
for new products and services
+ For attendee profile and additional
information, visit www.powertest.org

A N A H E I M C A L I F O R N I A POWERTEST.ORG 888.300.6382

February 27 - March 3 2017 THE PREMIER ELECTRICAL MAINTENANCE & SAFETY EVENT

DISNE Y L A ND HO T E L
SPECIFICATIONS AND STANDARDS ACTIVITY

B Y J IM W H ITE , Shermco Industries

(Editors note: Stephen Hester attended the approach boundary table at <100 volts. Some
ASTM F18 Committee meeting, as Jim White members expressed concern since OSHAs
was on vacation.) guidance for de-energizing equipment is <50
volts ac or dc.
The ASTM F18 committee is responsible
for all rubber insulating PPE, as well as arc- F18.65.30 Discussed the changes to the
flash PPE, live-line tools, insulated tools, and arc-rated hood testing method. For example,
insulated bucket trucks. The F18 committee its already acknowledged that an 8 cal/cm2
met in Las Vegas, Nevada, from October 47, face shield is effective at approximately 25
2015. The next meeting is scheduled for San cal/cm2. Hugh Hoagland recommended an
Antonio, Texas, April 1013, 2016. additional test shot to demonstrate reliability
of the hood assembly at incident energy levels
The OSHA update was provided by Marcia
above the rated ATPV.
Eblen of Pacific Gas and Electric. Marcia
briefed the committee on the requirements for F18.65.23 Discussed the scope changes,
care and maintenance of arc-rated daily work removing obsolete information, and
wear. OSHA is emphasizing that employers are distinguishing between fabric manufacturers
responsible for the proper laundering of arc- and garment manufacturers since those who
rated clothing, whether it is laundered at home make the actual garments may not be the
by the individual worker or in a commercial ones making the fabric that goes in them.
facility such as Aramark or CINTAS. A lively debate ensued over the definition of
Additionally, workers must be trained in the word durability.
the specific requirements for laundering
their arc-rated clothing, and employers are F18.65 Discussed the status of standards
responsible for inspecting clothing to ensure under the jurisdiction of the subcommittee:
that laundering protocols are followed and to
ensure serviceability of the garments. F1506-10: Under review
F1891-12: Current
The NFPA 70E update was provided by Nestor F1958/1958M-12: Current
Kolcio. Members were briefed on the number F1959/1959M-12: Under review
of public inputs (PI) to the 2018 edition (over F2178-12: Current
400) and a couple of key proposals such as F2621-12: Current
moving the tasks table from 130.7(C)(15) to F2675/F2675M-13: Current
130.5 and keeping the lower limit of the dc F2676-09: Due for revision

104 SUMMER 2016 ASTM F18 COMMITTEE REPORT


SPECIFICATIONS AND STANDARDS ACTIVITY

Also discussed the balloting results on rated line voltage. Given the If its not
several revisions to F1506 where negative grounded, its not dead rule-of-thumb
votes were submitted with comments. For and the fact that applying grounds by
the most part, the comments were based on hand is allowed at 600 volts and below
extremely narrow interpretations of language this discussion may resurface in the
or individual words used in the standard and future.
were not accepted by the subcommittee. Apparently, some sticks have passed
testing with elongated or deformed rivets.
F18.35.37 Engaged in spirited discussions This indicates excessive mechanical stress
on testing live-line tools. Some key points: and is cause to remove the stick from
The portion of shotgun sticks below the service and repair or replace.
operating mechanism is not tested due to F18.15.03 Emphasized discussion that
the presence of metal parts. dielectric overshoe footwear (not EH-rated
Extendo sticks must be cleaned and waxed footwear) used as primary protection must
on the inside. The inner surfaces of these be inspected before use, maintained, and
sticks can collect dirt and moisture, which dielectrically tested every six months.
may, under the right conditions, create a
short inside the stick. F18.35.43 Discussed the issue of whether
Some committee members claimed that there should be dielectric testing and retesting
some testing organizations do not test requirements for insulated hand tools.
the sticks wet in violation of 1910.269.
If true, it would benefit those who do not
test their own sticks to know this. Jim White is nationally recognized
Some members from the utilities pointed for technical skills and safety training
out that rubber insulating gloves are not in the electrical power systems
required when using live-line tools as long industry. He is the Training Director
for Shermco Industries, and has
as all body parts are outside the minimum spent the last twenty years directly
approach distances in the NESC and involved in technical skills and safety
1910.269. Non-utility industry practice training for electrical power system technicians. Jim is a
is to use gloves in conjunction with live- Principal member of NFPA 70B representing Shermco
Industries, NETAs alternate member of NFPA 70E, and
line tools. The utility industry appears a member of ASTM F18 Committee Electrical Protective
still divided on the subject. Equipment for Workers.
Questions were raised about per-foot
testing versus end-to-end testing of live-
line tools. Of course, the big issues regard
the appropriate test equipment and the
duration for an end-to-end test. A 10-
or 12-foot stick presents a considerable
challenge when testing at 75 kV per foot,
given the test equipment currently in use.
Consensus favored continuing with the
current per-foot method.
Are hot sticks considered live-line tools
when applying personal protective
grounds? Some members argued no
since were not contacting conductors at

ASTM F18 COMMITTEE REPORT NETAWORLD


NETA WORLD 105
&MFDUSJD4FSWJDF$PNQBOZ
)FU[FM4U$JODJOOBUJ 0)
:PVLOPXIPXXFMMXFIBOEMFB 'BY
&NBJMFMTDP!GVTFOFU

USBOTGPSNFSFNFSHFODZ XXXFMFDUSJDTFSWJDFDPN

*NBHJOFIPXXFMMXFEP
XIFOJUTOPU

-BSHFTFMFDUJPOPG/FX$PQQFS8PVOE%SZ5ZQFT6OJUT
JO4UPDLL7"UISVL7""WBJMBCMFXJUI/&."*OEPPSBOE
/&."30VUEPPS&ODMPTVSFT:FBS8BSSBOUZ
0JM'JMMFE6OJUTJO4UPDL/FX1BE.PVOUTL7"UPL7"
/FXDPQQFSXPVOESPVOEDPJM
$BMMPS IJHIFGDJFODZESZUZQFT
NETA MEMBERS
ALLIANCE PARTNERS
FORT WORTH, TEXAS
BY J IL L H OWEL L , NETA

NETAs 2016 Annual Member and Member and The NETA Member Meeting, a meeting open only to
Alliance Meetings were held on March 13, 2016, in Fort NETA Accredited Companies, brings together
Worth, Texas, welcoming over 100 NETA Accredited representatives and technicians from the many NETA
Company representatives, Alliance Partners, and Accredited Companies that attend PowerTest to
Corporate Alliance participants. The event was held in provide an update on NETA business. The agenda
the Omni Fort Worth Hotel on the Sunday leading into included membership updates, nominations and
PowerTest 2016. The Annual Meeting kicks off elections of officers, recognition of volunteers and
PowerTest each year, transitioning into a week-long committee chairs, association news, and a review of
series of technical sessions, professional exchange, and program plans for the year.
networking opportunities. It brings together the This year, NETA recognized one member in particular
largest gathering of NETA Accredited Company who has served on the NETA Board since 1988. Rod
representatives and industry professionals who are Hageman, who recently stepped down from the Board,
aligned in their commitment to continually work to is the owner of PRIT Services, a NETA Accredited
improve safety, reliability, and quality across the Company since 1986. (PRIT Services was recently sold
electrical power systems industry. to Shermco Industries.) NETA and its members are

One hundred plus NETA Accredited Company Members and Alliance Partners gathered for this year's annual meeting
in Fort Worth, Texas.
The meeting included an overview
of NETA's program updates,
technical reports, and a series of
roundtable discussions.
NETA President Ron Widup opens the 2016 Annual
Member and Member and Alliance Meetings.

grateful for Rods commitment and service to NETA


over the years. Rod will continue his work with the
organization serving on the Standards Review Council
and as the Executive Editor for the NETA World Journal
(see inset).

The NETA Member and Alliance Meeting takes place


during the second half of the NETA Member Meeting.
Corporate Alliance and Alliance Partners were invited
to join the NETA Accredited Companies in the
afternoon for roundtable discussions, technical reporting,
NETA member volunteers are recognized for their contributions to
and NETA updates. Roundtable discussions were hosted
the association.
by each of NETAs 13 Corporate Alliance Partners with the
goal of providing an opportunity to exchange information

NETA SALUTES
and ideas. To name just a few roundtable topics:
Significant Changes and Opportunities in
Commissioning and Testing
Field Force Automation and Cybersecurity ROD HAGEMAN,
Best Practices for Compliance President and CEO of PRIT Service, Inc.,
Power Factor Opening Doors to Advanced for 27 years of service to the NETA Board of Directors.
Diagnostics Rod stepped down from the Board this year following
Shermco Industries acquisition of PRIT Service,
During the NETA Member and Alliance Meeting, announced in March 2016.
NETA Accredited Company Representatives also cover
Over the years, Rod has dedicated thousands of hours to the association. He plans to
the many technical resources available to Members continue serving the industry and NETA as Chief Editor and committee Chairman for
and Alliance Partners such as NETA publications, the NETA World Journal and as a member of NETAs Standards Review Council,
training, the online NETA discussion forum at Technical Exam Committee, and Co-Chair of the Technical Working Committee.
www.engtips.com, and the online technical library at
We all like to joke that when you volunteer for NETA, it is a lifetime commitment. PRIT
www.electricalmanuals.net. This particular segment of Service began in the late 1950s as a response to requests for information from several
the meeting brings subject matter experts together from large industrial companies. At that time, Lynn Hageman was a testing engineer for
across the electrical power industrys many business Commonwealth Edison. During testing of Commonwealth Edisons protective
sectors to create an open dialogue, with a level of equipment, Lynn regularly met with maintenance and engineering staff of these
companies who asked him for solutions to their power problems and recommendations
questions and technical discussion hard to find outside
for maintenance of their distribution equipment. It became apparent to Lynn that the
of this face-to-face forum. industry needed independent testing and engineering services, and thus PRIT Service began.
Throughout the week of PowerTest, many special events In 1972, Rod Hageman graduated from college and assumed leadership of the company.
are designed to promote the exchange of ideas and Over the last 30 years, PRIT has been part of a growing industry. In 1986, PRIT Service
information sharing. For upcoming Alliance Partner joined NETA and has enjoyed the benefits of being part of an organization that has a vast
events, watch your inbox for emails from NETA and amount of technical knowledge shared between members. Rod Hageman joined the
NETA Board of Directors in 1988 and has been a faithful contributor to the association
look for notices in the NETA World Journal. ever since. Thank you, Rod, for your vision, leadership, technical expertise, and your dedication
to NETA and improving the safety and reliability of the electrical power systems industry.
If you would like additional information about the NETA
Alliance Program or would like to enroll, visit netaworld.
ADVANCEMENTS IN TECHNOLOGY

TIME IS TICKING
TO ADDRESS
Gr id I n te r c on n e c ti on S tan dards
BY M ARK SIIRA , ComRent International

Standards have always been an important consideration in


the work of engineers and testing companies, but their role is
increasing with the deployment of smart grids and the changes
in how buildings interact with electricity. Some changes coming
in the next two years will impact the testing done on systems that
are interconnected to the electric power system (EPS).

WHY ARE THINGS CHANGING Fortunately for the sanity of engineers, a plan
NOW? exists for updating the standards to address
The electric power infrastructure is transforming these changes.
from a system of power interconnections to a
HOW THE SYSTEM WO R K S
diverse, interconnected, interdependent, and
Say a roof-mounted solar panel is being
adaptive system. As the smart grid develops,
installed and connected to the grid through an
interconnection standards will evolve to help
inverter. Power engineers can look to a host of
enable interoperability, interconnection and standards for guidance, including:
integration of disparate systems, information Article 690 of the National Electrical
technology,and communications. Code (NEC) minimizing electrical
hazards in installation and operation
The need for change is most notably caused
Underwriters Laboratory (UL) 1741
by the increasing use of renewable energy.
additional fire and safety considerations
Based on the experience in Europe, operations
regarding distributed generators that use a
improvements were needed to efficiently feed
dc power source like a solar panel
in solar and wind energy and minimize any IEEE 1547, Standard for Interconnecting
problems to the grid. The renewable energy Distributed Resources with Electric
production can be optimized by allowing the Power Systems for the basis of the
local utility operation to communicate with interconnection of the photovoltaic device
distributed energy resources and modify their itself to the power grid
power output characteristics. In addition, IEEE 1547.1, Standard Conformance Test
some changes are required due to the need to Procedures for Equipment Interconnecting
improve voltage and frequency stability as well Distributed Resources with Electric Power
as power quality. Systems for commissioning tests

112 SUMMER 2016 TIME IS TICKING TO ADDRESS GRID INTERCONNECTION STANDARDS


ADVANCEMENTS IN TECHNOLOGY
The installer has to be aware of the NEC and The IEEE 1547 family of standards is starting
how it is applied in the local area before projects a cycle of revisions needed due to the reasons
are considered. The inverter is type-tested to expressed above and to accommodate smart-
UL-1741 at a Nationally Recognized Testing grid functionality. This has started with the
Laboratory (NRTL), and then the project core standard, IEEE 1547, which was published
may be tested to IEEE 1547.1 standards by in 2003 to reflect the evolution in the industry.
the utility before interconnection. This usually A full revision of IEEE 1547 is underway and
depends on how large the system is relative to estimated to be published by 2018. In considering
other sources on the distribution system. the scope and intentions of a full revision of
IEEE 1547, a wide variety of stakeholders may
System-level standards are an area of focus change requirements for emerging technologies
for the Institute of Electrical and Electronic and applications such as energy storage,
Engineers (IEEE) regarding the smart grid,
microgrids, inverter communications, voltage,
with interconnection and interoperability
and frequency ride-through instead of
defined below (Figure 1).
disconnection, higher renewable penetrations,
and cyber security, among others.

FI RST GUI DE TO
I NTEROPERABI LI TY AND
SMART GRI D
IEEE 2030, Guide for Smart Grid Interoperability
of Energy Technology and Information Technology
Operation with the Electric Power System (EPS),
End-Use Applications, and Loads takes a similar
system-of-systems approach.
Figure 1: Relationships of Standards Related to
Interconnection More than 400 professionals from across
the global communications, IT, and power
Interconnection is a widely known concept industries collaborated in developing IEEE
and the fundamental area covered by the IEEE 2030, and when it was released in 2011,
1547 series of standards. Generally, it deals with it established the worlds first interface-by-
equipment and functions used to interconnect interface guide to interoperability across
a distributed energy resource unit to an area the electric power system. IEEE 2030 is a
electric power system (distribution network). technology-agnostic roadmap to the standards
and functional interfaces for securely integrating
Interoperability is the seamless interaction of EPS with communications and IT as well as
the communication and information technology facilitating data exchange across the smart grid.
systems and addresses the capability of multiple This is important because it provides the tools
networks, systems, devices, applications, or and information to allow increasing clarity
components to exchange and use information in the specifying requirements of systems for
securely and effectively. It is important to communication and power system functions.
understand two definitions related to these
standards: The smart grid is bringing definitive change
Information technology classifies the types to the way buildings relate with electricity.
and methods of information exchanged Whereas historically most buildings have only
between entities that interact with the ESS. been consumers of electricity, more and more
Communication technology deals with the buildings will also serve as points of value for
data network paths available to transport power generation in the smart grid. For example,
that information. integrating renewables with energy storage

TIME IS TICKING TO ADDRESS GRID INTERCONNECTION STANDARDS NETAWORLD


NETA WORLD 113
ADVANCEMENTS IN TECHNOLOGY
systems could allow for additional functions to requirements (See Figure 2).
support the utility, such as frequency regulation, The new rules will have both must-trip
power quality stabilization, and more and must-run regions.
sophisticated schemes to replace simple The new rules will require DERs to
disconnection when abnormal conditions exist. remain online during certain disturbances.
Momentary cessation is the mechanism
W H AT W ILL C H ANGE? for low-voltage ride-through.
Initially, the changes will be seen in IEEE Inverters would stop sourcing power,
1547, anticipated to be approved and but not trip.
published before 2018. It is intended to Would be allowed to come back online
standardize interconnections of distributed immediately when conditions return
generators to EPSs. The original standard to normal (no five-minute wait for
published in 2003 did not fully comprehend return-to-service).
the impact of inverters (from renewable Power Quality Requirements
sources) on the system. Inverters convert Interoperability requirements
the dc power from a solar array or wind o Requires information exchange capability
turbine into ac power that is exported to the using standard protocol
electric power system. As a result, inverter- o Addresses cybersecurity
based systems were subjected to additional o May require simulation and modeling data
scrutiny and occasional delays in project Unintentional Islanding
implementation. The standard is focused on o May have special treatment for micro
interconnections to medium-voltage distribution grids and energy storage systems
feeders; high-voltage bulk generation and
Please note that these are based on the current
transmission will not be addressed.
draft of the working group, and specific
The old rules require a distributed energy requirements could change before the
source to disconnect from the EPS within two document is published.
seconds and reconnect within five minutes of
Since the ride-through requirements are a
an abnormal condition being present (power new concept, we have included Figure 2 to
outage or voltage spike). The new rules are more graphically illustrate what could be frequency
complex and will likely require more testing. The or voltage on the vertical axis and time (event
requirements will apply when the EPS operator duration 0 to 20 seconds) on the horizontal
(the utility) determines they are needed. These axis. The figure describes typical ride-through
might be where there are a large number of concepts used: continuous operation, mandatory
renewable energy sources in a small area. operation, permissive operation, ride-through
Here are the topics where you may see the most trip allowed, and mandatory (shall) trip.
change :
Voltage and Reactive Power Control
Requirements
o Wider range of settings
o Distributed energy resource (DER) will
be required to adjust voltage by adjusting
power factor output
Response to Abnormal Voltage and
Frequency Conditions
Figure 2: The Ride-Through Concept
o The old rules had allowable voltage and
frequency ranges specified, and We hope this overview has convinced you that
recommended settings were relatively tight. there are major changes coming to what will
o The new rules include ride-through be tested in the future. We are beginning to see

114 SUMMER 2016 TIME IS TICKING TO ADDRESS GRID INTERCONNECTION STANDARDS


ADVANCEMENTS IN TECHNOLOGY
training on these concepts related to California Mark Siira is the Director of Technology
Rule 21, where many of these requirements have Strategy for ComRent International, a
leader in load testing solutions. He is a senior
become the standard already. More information member of IEEE, including a member
can be obtained from ComRent.com or California of the IEEE Standards Coordinating
Energy Commission Rule 21 Smart Inverter Committee 21, which establishes standards
Working Group Technical Reference Materials for grid interconnection and smart grid
interoperability; Working Group Chair
at www.energy.ca.gov/electricity_analysis/rule21/. of IEEE 2030.2 Guide for Interoperability of Energy Storage
Systems; Vice Chair for IEEE1547 Interconnection Standard
B E PA R T OF T H E F U T U RE Revision, focusing on interoperability, simulation and modeling,
Standards development driven by the emerging, and testing, and he is starting activity on IEEE1547.1
Test Procedures for Interconnection. Mark is also an active
real-world needs of facility engineers will help
participant in the IEEE Power Systems Relaying Committee;
ensure this transformation is achieved as simply, Vice Chair of committee K10 - SCC21 Distributed Resources
cost-effectively, and efficiently as possible. All Standard Coordination; and a member of committee I25
of the standards-making organizations need Substation Commissioning best practices report to NERC.
your help. If you want to get involved and Additionally, he is a member of the UL Standards Technical
Panels 1741 (Inverters), UL2200 (Generators) and 6171
help write the standard, sign up for the IEEE
(Wind farms interconnection), as well as Sub-Group Chair of
1547 ListServ at http://grouper.ieee.org/groups/ the EPRI Energy Storage Integration Council, which is leading
scc21/1547_revision/1547revision_index.html. an effort to define commissioning practices for energy storage
and PV systems. Mark has spent 20 years in the distributed
Then, you can join the working group by power generation industry developing products and solutions for
expressing your interest in the IEEE project an inverter and energy storage appliance, combined heat and
system. Identify yourself to sub-group leads to get power systems, critical power systems paralleling switchgear, and
microturbines. He has a BS in mechanical engineering from
involved in groups working on the specific topics
GMI Engineering and Management Institute (now Kettering
of interest to you. University) and an MBA from Harvard University.
FORT WORTH, TEXAS
OMNI FORT WORTH HOTEL
MARCH 14-18, 2016
www.powertest.org
888.300.6382 (NETA)

A special thanks to our Sponsors


We would like to acknowledge and thank our sponsors
for helping make PowerTest 2016 possible.
Premium

High Voltage

Medium Voltage Low Voltage

General Hospitality Suite Sponsors


BCS Switchgear, Inc. Protec Equipment Resources
Electric Power Systems RESA Power Solutions
Electro Rent Shermco Industries
Group CBS, Inc. SMC International
IBEW LU 269 Doble Engineering Company
Megger/AVO Training
Institute, Inc.

THE PREMIER ELECTRICAL MAINTENANCE AND SAFETY EVENT + HOSTED BY


NETA Standards Review Council, from left to right: Dave Huffman, Alan Peterson, Jim Cialdea, Ralph Patterson,
Leif Hoegberg, Missy Richard, Rod Hageman, Kristen Wicks, Dan Hook, Tim Cotter, Ron Widup, Lorne Gara.

NETA STANDARDS REVIEW COUNCIL


APPOINTS NEW MEMBERS
BY K RIST EN WICK S, NETA

NETAs Standards Review Council (SRC) met in Texas on February 19 -20,


2016, at Shermco Industries Irving office. The main focus was preparation
of the final draft document of the ANSI/NETA Standard for Acceptance
Testing Specifications for Electrical Power Equipment and Systems,
Systems, which
was subsequently put forth for initial balloting and public comment
in April 2016. Most of the preparatory work was accomplished at this
meeting, and the committee completed the outstanding review work
remotely following the meeting.
NETAs Standards Review Council serves as the remains technically accurate through its ANSI
executive technical committee for the association standards, the certification exams, and other
and has a history of committee members who are technically related programs and projects for the
deeply committed to assuring that NETAs voice association. It is a responsibility not taken lightly

118 SUMMER 2016 NETA STANDARDS REVIEW COUNCIL


APPOINTS NEW MEMBERS
and one that requires a great deal of time and few. It is incredibly gratifying to know that an
effort in person as well as remotely. increasing number of members and industry
partners see the value that their relationships
NETA is thrilled to announce the addition with NETA provide to the association, to the
of three new SRC members to the team: Jim industry, to their technicians, and to themselves.
Cialdea of 3C Electrical Company, Inc.; Leif There is definite truth to the statement, You
Hoegberg of Electrical Reliability Services; make a living by what you get; you make a life
and Dan Hook of Western Electrical Services. by what you give.
As the associations newly appointed Executive
Director, Missy Richard was welcomed as a NETA thanks its many volunteers for donating
committee member. Kristen Wicks, NETA their time and talents to the pursuit of a vision
staff liaison for the SRC, was appointed as an that is greater than the sum of its parts. If you are
official member of the committee by Technical interested in learning more about how you can
Chair Alan Peterson. This committee join the efforts being made to advance the
expansion comes at a perfect time to support electrical testing industry, contact the NETA
NETAs technical growth in support of the office at neta@netaworld.org or call (888)
associations mission. 300-6382.

Historically, NETA has been an organization Kristen Wicks is the Technical Services Director
that accomplishes much with the hands of at NETA.

HIGH VOLTAGE - HIGH CURRENT - HIGH POWER 1-301-746-8118


TEST SYSTEMS and COMPONENTS www.PhenixTech.com

info@phenixtech.com 75 Speicher Drive, Accident, MD 21520 USA

High Current Circuit Breaker Test Sets


Ideal for testing thermal, magnetic, and solid state relays, molded case circuit breakers and
ground fault trip devices, plus other applications requiring a high current source.

Taiwan
+886.2.2835.9738
info@phenixasia.com

Switzerland
+41.61.383.2770
info@phenixsystems.com

35+ Years
Experience Made for field testing. Mobile units offer:
Models up to 75,000 Amps. Manual or computer operation with numerous
C
Features: automated modes.
ISO RE 9001 Proven duty cycle Precise, repeatable current pulses, minimal distortion.
TIFIED
Auto-jog and current-hold capabilities. Current wave form display with WIN HC.
TECH QUIZ ANSWERS

No. 114
A N S W E R S
A NS W ERS
1. a. 50 3. Instantaneous overcurrent
b. 86 4. Lockout
c. 87 1. Differential
d. 27 2. Undervoltage
e. 25 6. Synch check
f. 67 5. Directional overcurrent

2. a. What is the calculated imbalance?


16.6 percent
b. Will this relay operate with this imbalance?
Yes / No Figure 1: Synch Check Relay Circle Characteristic
For this relay to operate, the percent slope characteristic
must be exceeded, which is not the case in this example.
The relay will restrain.
c. Based on its characteristic, what is this relay most likely
protecting? Transformer or generator

3. d. Synch check relays require two voltages. One voltage


is used as the nominal (rated) voltage and the other
voltage is varied. The characteristic in Figure 1 shows how
the two voltages are used to check the size of the circle.
For a relay rated at 120 V, one voltage is typically set to
120 V at zero degrees, while the second voltage is set to
120 V and the phase angle is varied to find its operating
angles. At the 60-degree circle setting (the largest of the
circles) and at 120 V, the relay will close its contacts at 60
degrees plus-or-minus the tolerance of the relay, which
is usually 10 percent. Note that 120 V is in the center of
the circle, and at zero-degree phase angle difference, the
relay contacts will flicker if the second voltage is increased Figure 2: Synch Check Timing Characteristic
to 480 V (with the first voltage at 120 V). The timing
test is performed by setting both voltages at zero-degree
phase angle. One voltage is usually set to 120 V (or rated
voltage), while the second voltage is set to zero V and the NFPA Disclaimer: Although Jim White is a member of the NFPA
relay timed (see Figure 2). Technical Committee for both NFPA 70E Standard for Electrical Safety
in the Workplace and NFPA 70B Recommended Practice for Electrical
Equipment Maintenance, the views and opinions expressed in this message
4. a. A type 21 relay is any type of distance relay, but not are purely the authors and shall not be considered an official position of the
blocking or unblocking relays. NFPA or any of its technical committees and shall not be considered to be,
nor be relied upon as, a formal interpretation or promotion of the NFPA.
Readers are encouraged to refer to the entire text of all referenced documents.

120 SUMMER 2016 TECH QUIZ


A FULL SERVICE Electrical Distribution System
NETA ACCREDITED
ELECTRICAL 7HVWLQJ5HSDLUDQG0DLQWHQDQFH
TESTING
COMPANY.

Acceptance Testing
Commissioning
Maintenance Testing
High Voltage Substations
Short Circuit and
Coordination Studies
Data Centers and
UPS Systems
Serving the Sacramento and
San Francisco Bay Area

916-853-6280
www.apparatustesting.com 24 Hour Emergency Services
(937) 439-9660
NETA ACCREDITED COMPANIES Setting the Standard

A&F Electrical Testing, Inc. ABM Electrical Power Solutions American Electrical Testing Co., Inc. Apparatus Testing and Engineering
80 Lake Ave. South, Ste. 10 5809 Departure Dr., Ste. 104 34 Clover Dr. 7083 Commerce Circle, Ste. H
Nesconset, NY 11767 Raleigh, NC 27616 South Windsor, CT 06074 Pleasanton, CA 94588
(631) 584-5625 Fax: (631) 584-5720 (919) 877-1008 Fax: (919) 501-7492 (860) 648-1013 Fax: (781) 821-0771 (925) 454-1363 Fax: (925) 454-1499
kchilton@afelectricaltesting.com www.ABM.com jpoulin@aetco.us info@apparatustesting.com
www.afelectricaltesting.com Rob Parton www.99aetco.com www.apparatustesting.com
Kevin Chilton Gerald Poulin Harold ( Jerry) Carr
ABM Electrical Power Solutions
A&F Electrical Testing, Inc. 317 Commerce Park Dr. American Electrical Testing Co., Inc. Applied Engineering Concepts
80 Broad St. 5th Floor Cranberry Township, PA 16066-6427 76 Cain Dr. 1105 N. Allen Ave.
New York, NY 10004 (724) 772-4638 Fax: (724) 772-6003 Brentwood, NY 11717 Pasadena, CA 91104
(631) 584-5625 Fax: (631) 584-5720 william.mckenzie@abm.com (631) 617-5330 Fax: (631) 630-2292 (626) 398-3052 Fax: (626) 398-3053
afelectricaltesting@afelectricaltesting.com www.ABM.com mschacker@aetco.us michel.c@aec-us.com
www.afelectricaltesting.com William (Pete) McKenzie www.99aetco.com www.aec-us.com
Florence Chilton Michael Schacker Michel Castonguay
ABM Electrical Power Solutions
ABM Electrical Power Solutions 4390 Parliament Place, Ste. S American Electrical Testing Co., Inc. BEC Testing
3602 East Southern Ave., Ste. 1 Lanham, MD 20706 50 Intervale Rd., Ste. 1 50 Gazza Blvd.
Phoenix, AZ 85040 (301) 967-3500 Fax: (301) 735-8953 Boonton, NJ 07005 Farmingdale, NY 11735
(602) 722-2423 www.ABM.com (973) 316-1180 Fax: (781) 316-1181 (516) 531-9136 Fax: (631) 249-6115
www.ABM.com Frank Ceci jsomol@aetco.us wfernandez@banaelectric.com
Doug Bukowski www.99aetco.com www.bectesting.com
ABM Electrical Power Solutions Jeff Somol William Fernandez
ABM Electrical Power Solutions 3600 Woodpark Blvd., Suite G
9800 E. Geddes Avenue, Unit A-150 Charlotte, NC 28206 American Electrical Testing Co., Inc. Burlington Electrical Testing Co., Inc.
Englewood, CO 80112 (704) 273-6257 Fax: (704) 598-9812 4032 Park 65 Dr. 300 Cedar Ave.
(303) 524-6560 Fax: (303) 524-6581 ernest.goins@abm.com Indianapolis, IN 46254 Croydon, PA 19021-6051
www.ABM.com www.ABM.com (317) 487-2111 Fax: (781) 821-0771 (215) 826-9400 (221)
Brian Smith Ernest Goins scanale@aetco.us Fax: (215) 826-0964
www.99aetco.com waltc@betest.com
ABM Electrical Power Solutions ABM Electrical Power Solutions Stephen Canale www.betest.com
2142 Rheem Drive 720 S. Rochester Ave., Suite A Walter P. Cleary
Pleasanton, CA 94588 Ontario, CA 91761 American Electrical Testing Co., Inc.
(408) 466-6920 (800) 597-1225 Fax: (909) 937-6798 Green Hills Commerce Center C.E. Testing, Inc.
www.ABM.com www.ABM.com 5925 Tilghman St., Ste. 200 6148 Tim Crews Rd.
John Marvulli Mike Bivens Allentown, PA 18104 Macclenny, FL 32063
(215) 219-6800 (904) 653-1900 Fax: (904) 653-1911
ABM Electrical Power Solutions Absolute Testing Services jmunley@aetco.us cetesting@aol.com
3940 Ruffin Rd., Ste. C 6829 Guhn Rd. www.99aetco.com Mark Chapman
San Diego, CA 92123 Houston, TX 77040 Jonathan Munley
(858) 754-7963 (832) 467-4446 Fax: (713) 849-3885 CE Power Solutions, LLC
www.ABM.com rgamble@absolutetesting.com American Electrical Testing Co., Inc. 4040 Rev Dr.
Christopher Smith www.texasats.com 12566 W. Indianola Ave. Cincinnati, OH 45232
Richard Gamble Avondale, AZ 85392 (513) 563-6150 Fax: (513) 563-6120
ABM Electrical Power Solutions (480) 383-9242 info@cepowersol.net
6280 South Valley View Blvd., Ste. 618 Accessible Consulting Engineers, Inc. dmadaglia@aetco.us www.cepower.net
Las Vegas, NV 89118 1269 Pomona Rd., Ste. 111 www.99aetco.com Rhonda Harris
(602) 300-2188 Fax: (602) 437-3894 Corona, CA 92882 Donald Madaglia
www.ABM.com (951) 808-1040 CE Power Solutions of Minnesota, LLC
Jason Black info@acetesting.com AMP Quality Energy Services, LLC 7674 Washington Ave. South
www.acetesting.com 4220 West Schrimsher SW Site W1 Eden Prairie, MN 55344
ABM Electrical Power Solutions Iraj Nasrolahi P.O. Box 526, Huntsville, AL 35804 (877) 968-0281 Fax: (952) 400-8772
814 Greenbrier Circle, Ste. E (256) 513-8255 jason.thompson@cepower.net
Chesapeake, VA 23320 Advanced Testing Systems Brian Rodgers www.cepower-mn.net
(757) 548-5690 Fax: (757) 548-5417 15 Trowbridge Dr. Jason Thompson
www.ABM.com Bethel, CT 06801 Apparatus Testing and Engineering
Mark Anthony Gaughan, III (203) 743-2001 Fax: (203) 743-2325 11300 Sanders Dr., Ste. 29 Control Power Concepts
pmaccarthy@advtest.com Rancho Cordova, CA 95742 353 Pilot Rd; Ste. B
ABM Electrical Power Solutions www.advtest.com (916) 853-6280 Fax: (916) 853-6258 Las Vegas, NV 89119
3700 Commerce Dr. #901-903 Pat MacCarthy info@apparatustesting.com (702) 448-7833 Fax: (702) 448-7835
Baltimore, MD 21227 www.apparatustesting.com www.controlpowerconcepts.com
(410) 247-3300 Fax: (410) 247-0900 American Electrical Testing Co., Inc. Harold ( Jerry) Carr John Travis
www.ABM.com 25 Forbes Blvd., Ste. 1
Bill Hartman Foxboro, MA 02035
(781) 821-0121 Fax: (781) 821-0771
sblizard@aetco.us
www.99aetco.com
Scott A. Blizard

124 SUMMER 2016 NETA ACCREDITED COMPANIES


NETA ACCREDITED COMPANIES Setting the Standard

Dude Electrical Testing LLC Electric Power Systems, Inc. Electric Power Systems, Inc. Electrical Reliability Services
145 Tower Dr., Unit# 9 2601 Center Rd., # 101 6141 Connecticut Ave. 1426 Sens Rd. Ste. 5
Burr Ridge, IL 60527 Hinckley, OH 44233 Kansas City, MO 64120 Houston, TX 77571
(815) 293-3388 Fax: (815) 293-3386 (330) 460-3706 Fax: (330) 460-3708 (816) 241-9990 Fax: (816) 241-9992 (281) 241-2800 Fax: (281) 241-2801
scott.dude@dudetesting.com www.epsii.com www.epsii.com www.electricalreliability.com
www.dudetesting.com
Scott Dude Electric Power Systems, Inc. Electric Power Systems, Inc. Electrical Reliability Services
56 Bibber Pkwy #1 2495 Boulevard of the Generals 4099 SE International Way, Ste. 201
DYMAX Service, LLC Brunswick, ME 04011 Norristown, PA 19403 Milwaukie, OR 97222-8853
46918 Liberty Dr. (207) 837-6527 (610) 630-0286 (503) 653-6781 Fax: (503) 659-9733
Wixom, MI 48393 www.epsii.com www.epsii.com www.electricalreliability.com
(248) 313-6868 Fax: (248) 313-6869
www.dymaxservice.com Electric Power Systems, Inc. Electric Power Systems, Inc. Electrical Reliability Services
Bruce Robinson 4100 Greenbriar Dr., Ste. 160 1129 East Hwy. 30 5909 Sea Lion Place, Ste. C
Stafford, TX 77477 Gonzalez, LA 70817 Carlsbad, CA 92010
DYMAX Service, LLC (713) 644-5400 (225) 644-0150 Fax: (225) 644-6249 (858) 695-9551
4213 Kropf Ave. www.epsii.com www.epsii.com www.electricalreliability.com
Canton, OH 44706
(330) 484-6801 Fax: (740) 333-1271 Electric Power Systems, Inc. Electric Power Systems, Inc. Electrical Reliability Services
www.dymaxservice.com 11861 Longsdorf St. 7925 Dunbrook Rd., Ste. G 8500 Washington Pl. NE, Ste. A-6
Chuck Baker Riverview, MI 48193 San Diego, CA 92126 Albuquerque, NM 87113
(734) 282-3311 (858) 566-6317 (505) 822-0237 Fax: (505) 822-0217
Eastern High Voltage www.epsii.com www.epsii.com www.electricalreliability.com
11A South Gold Dr.
Robbinsville, NJ 08691-1606 Electric Power Systems, Inc. Electrical & Electronic Controls Electrical Reliability Services
(609) 890-8300 Fax: (609) 588-8090 827 Union St., 6149 Hunter Rd. 1380 Greg Street, Ste. 217
joewilson@easternhighvoltage.com Salem, VA 24153 Ooltewah, TN 37363 Sparks, NV 89431
www.easternhighvoltage.com (540) 375-0084 Fax: (540) 375-0094 (423) 344-7666 (23) (775) 746-8484 Fax: (775) 356-5488
Joseph Wilson www.epsii.com Fax: (423) 344-4494 www.electricalreliability.com
eecontrols@comcast.net
ELECT, P.C. Electric Power Systems, Inc. Michael Hughes Electrical Reliability Services
7400-G Siemens Rd., P.O. Box 2080 915 Holt Ave., Unit 9 2275 Northwest Pkwy SE, Ste. 180
Wendell, NC 27591 Manchester, NH 03109 Electrical Energy Experts, Inc. Marietta, GA 30067
(919) 365-9775 Fax: (919) 365-9789 (603) 657-7371 Fax: 603-657-7370 W129N10818, Washington Dr. (770) 541-6600 Fax: (770) 541-6501
btyndall@elect-pc.com www.epsii.com Germantown, WI 53022 www.electricalreliability.com
www.elect-pc.com (262) 255-5222 Fax: (262) 242-2360
Barry W. Tyndall Electric Power Systems, Inc. bill@electricalenergyexperts.com Electrical Reliability Services
146 Space Park Dr. www.electricalenergyexperts.com 7100 Broadway, Ste. 7E
Electric Power Systems, Inc. Nashville, TN 37211 William Styer Denver, CO 80221-2915
21 Millpark Ct. (615) 834-0999 Fax: (615) 834-0129 (303) 427-8809 Fax: (303) 427-4080
Maryland Heights, MO 63043 www.epsii.com Electrical Equipment Upgrading, Inc. www.electricalreliability.com
(314) 890-9999 Fax: (314) 890-9998 21 Telfair Place, Savannah, GA 31415 Electrical Reliability Services
www.epsii.com Electric Power Systems, Inc. (912) 232-7402 Fax: (912) 233-4355 348 N.W. Capital Dr.
8515 Cella Alameda NE, Ste. A kmiller@eeu-inc.com Lee's Summit, MO 64086
Electric Power Systems, Inc. Albuquerque, NM 87113 www.eeu-inc.com (816) 525-7156 Fax: (816) 524-3274
557 E. Juanita Ave., #4 (505) 792-7761 Kevin Miller www.electricalreliability.com
Mesa, AZ 85204 www.epsii.com
(480) 633-1490 Fax: (480) 633-7092 Electrical Maintenance & Testing Inc. Electrical Reliability Services
www.epsii.com Electric Power Systems, Inc. 12342 Hancock St., Carmel, IN 46032 6900 Koll Center Parkway, Ste. 415
7140 Dean Martin Drive, Suite 900 (317) 853-6795 Fax: (317) 853-6799 Pleasanton, CA 94566
Electric Power Systems, Inc. Las Vegas, NV 89118 info@emtesting.com (925) 485-3400 Fax: (925) 485-3436
4436 Parkway Commerce Blvd. (702) 815-1342 www.emtesting.com www.electricalreliability.com
Orlando, FL 32808 www.epsii.com Brian K. Borst
(407) 578-6424 Fax: 407-578-6408 Electrical Reliability Services
www.epsii.com Electric Power Systems, Inc. Electrical Reliability Services 10606 Bloomfield Ave.
319 US Hwy. 70 E, Unit E 1057 Doniphan Park Circle, Ste. A Santa Fe Springs, CA 90670
Electric Power Systems, Inc. Garner, NC 27529 El Paso, TX 79922 (562) 236-9555 Fax: (562) 777-8914
7000 E. 47th Avenue Drive, Suite 100 (919) 322-2670 (915) 587-9440 Fax: (915) 587-9010 www.electricalreliability.com
Denver, CO 80216 www.epsii.com www.electricalreliability.com
(720) 857-7273 Fax: 303-928-8020 Electrical Reliability Services
www.epsii.com Electric Power Systems, Inc. Electrical Reliability Services 3535 Emerson Parkway, Ste. A
1090 Montour West Industrial Blvd. 1775 W. University Dr., Ste. 128 Gonzales, LA 70737
Electric Power Systems, Inc. Coraopolis, PA 15108 Tempe, AZ 85281 (225) 755-0530 Fax: (225) 751-5055
23823 Andrew Rd. (412) 276-4559 (480) 966-4568 Fax: (480) 966-4569 www.electricalreliability.com
Plainfield, IL 60585 www.epsii.com www.electricalreliability.com
(815) 577-9515 Fax: (815) 577-9516
www.epsii.com

NETA ACCREDITED COMPANIES


NETAWORLD 125
NETA ACCREDITED COMPANIES Setting the Standard

Electrical Reliability Services Elemco Services, Inc. Hampton Tedder Technical Services High Voltage Maintenance Corp.
245 Hood Rd. 228 Merrick Rd. , 3747 West Roanoke Ave. 9305 Gerwig Ln., Ste. B
Sulphur, LA 70665 Lynbrook, NY 11563 Phoenix, AZ 85009 Columbia, MD 21046
(337) 583-2411 Fax: (337) 583-2410 (631) 589-6343 Fax: (631) 589-6670 (480) 967-7765 Fax: (480) 967-7762 (410) 309-5970 Fax: (410) 309-0220
www.electricalreliability.com courtney@elemco.com www.hamptontedder.com www.hvmcorp.com
www.elemco.com
Electrical Reliability Services Courtney Gallo Harford Electrical Testing Co., Inc. High Voltage Maintenance Corp.
11000 Metro Pkwy., Ste. 30 1108 Clayton Rd. 24371 Catherine Industrial Dr,
Ft. Myers, FL 33966 EnerG Test Joppa, MD 21085 Ste. 207
(239) 693-7100 Fax: (239) 693-7772 204 Gale Lane (410) 679-4477 Fax: (410) 679-0800 Novi, MI 48375
www.electricalreliability.com Bldg. 2 - 2nd Floor testing@harfordtesting.com (248) 305-5596 Fax: (248) 305-5579
Kennett Square, PA 19348 www.harfordtesting.com www.hvmcorp.com
Electrical Reliability Services (484) 731-0200 Fax: (484) 713-0209 Vincent Biondino
2222 West Valley Hwy. N., Ste 160 kbleiler@energtest.com High Energy Electrical Testing, Inc. High Voltage Maintenance Corp.
Auburn, WA 98001 www.energtest.com 515 S. Ocean Ave. 5100 Energy Dr.
(253) 736-6010 Fax: (253) 736-6015 Katie Bleiler Seaside Park, NJ 08752 Dayton, OH 45414
www.electricalreliability.com (732) 938-2275 Fax: (732) 938-2277 (937) 278-0811 Fax: (937) 278-7791
Energis High Voltage Resources, Inc. hinrg@comcast.net www.hvmcorp.com
Electrical Reliability Services 1361 Glory Rd. www.highenergyelectric.com
3412 South 1400 West, Unit A Green Bay, WI 54304 Charles Blanchard High Voltage Service, LLC
West Valley City, UT 84119 (920) 632-7929 Fax: (920) 632-7928 3890 Pheasant Ridge Dr. NE, Ste. 170
(801) 975-6461 info@energisinc.com High Voltage Maintenance Corp. Blaine, MN 55449
www.electricalreliability.com www.energisinc.com 24 Walpole Park South Dr. (763) 784-4040 Fax: (763) 784-5397
Mick Petzold Walpole, MA 02081 www.hvserviceinc.com
Electrical Reliability Services (508) 668-9205 Mike Mavetz
6351 Hinson St., Ste. B EPS Technology www.hvmcorp.com
Las Vegas, NV 89118 29 N. Plains Hwy., Ste. 12 HMT, Inc.
(702) 597-0020 Fax: (702) 597-0095 Wallingford, CT 06492 High Voltage Maintenance Corp. 6268 Route 31
www.electricalreliability.com (203) 679-0145 941 Busse Rd. Cicero, NY 13039
www.eps-technology.com Elk Grove Village, Il 60007 (315) 699-5563 Fax: (315) 699-5911
Electrical Reliability Services (847) 640-0005 jpertgen@hmt-electric.com
9636 St. Vincent, Unit A Grounded Technologies, Inc. www.hvmcorp.com www.hmt-electric.com
Shreveport, LA 71106 10505 S. Progress Way, Ste. 105 John Pertgen
(318) 869-4244 Parker, CO 80134 High Voltage Maintenance Corp.
www.electricalreliability.com P-(303) 781-2560 7200 Industrial Park Blvd. Industrial Electric Testing, Inc.
F- (303) 781-5240 Mentor, OH 44060 11321 West Distribution Ave.
Electrical Reliability Services jodymedina@groundedtech.com (440) 951-2706 Fax: (440) 951-6798 Jacksonville, FL 32256
610 Executive Campus Dr. www.groundedtech.com www.hvmcorp.com (904) 260-8378 Fax: (904) 260-0737
Westerville, OH 43082 Jody Medina gbenzenberg@bellsouth.net
(877) 468-6384 Fax: (614) 410-8420 High Voltage Maintenance Corp. www.industrialelectrictesting.com
info@electricalreliability.com Grubb Engineering, Inc. 3000 S. Calhoun Rd. Gary Benzenberg
www.electricalreliability.com 3128 Sidney Brooks New Berlin, WI 53151
San Antonio, Tx 78235 (262) 784-3660 Fax: (262) 784-5124 Industrial Electric Testing, Inc.
Electrical Testing and Maintenance Corp. (210) 658-7250 Fax: (210) 658-9805 www.hvmcorp.com 201 NW 1st Ave.
3673 Cherry Rd., Ste. 101 joy@grubbengineering.com Hallandale, FL 33009-4029
Memphis, TN 38118 www.grubbengineering.com High Voltage Maintenance Corp. (954) 456-7020
(901) 566-5557 Robert D. Grubb Jr. 8320 Brookville Rd. #E www.industrialelectrictesting.com
r.gregory@etmcorp.com Indianapolis, IN 46239
www.etmcorp.net Hampton Tedder Technical Services (317) 322-2055 Fax: (317) 322-2056 Industrial Electronics Group
Ron Gregory 4571 State St. www.hvmcorp.com 850369 Highway 17 South
Montclair, CA 91763 P.O. Box 1870
Electrical Testing, Inc. (909) 628-1256 x214 High Voltage Maintenance Corp. Yulee, FL 32041
2671 Cedartown Hwy. Fax: (909) 628-6375 1250 Broadway, Ste. 2300 (904) 225-9529 Fax: (904) 225-0834
Rome, GA 30161-6791 matt.tedder@hamptontedder.com New York, NY 10001 butch@industrialgroups.com
(706) 234-7623 Fax: (706) 236-9028 www.hamptontedder.com (718) 239-0359 www.industrialgroups.com
steve@electricaltestinginc.com Matt Tedder www.hvmcorp.com Butch E. Teal
www.electricaltestinginc.com
Hampton Tedder Technical Services High Voltage Maintenance Corp. Industrial Tests, Inc.
Electrical Testing Solutions 4920 Alto Ave. 355 Vista Park Dr. 4021 Alvis Ct., Ste. 1
2909 Green Hill Ct. Las Vegas, NV 89115 Pittsburgh, PA 15205-1206 Rocklin, CA 95677
Oshkosh, WI 54904 (702) 452-9200 Fax: (702) 453-5412 (412) 747-0550 Fax: (412) 747-0554 (916) 296-1200 Fax: (916) 632-0300
(920) 420-2986 Fax: (920) 235-7136 www.hamptontedder.com www.hvmcorp.com greg@indtest.com
tmachado@electricaltestingsolutions.com Roger Cates www.industrialtests.com
www.electricaltestingsolutions.com High Voltage Maintenance Corp. Greg Poole
Tito Machado 150 North Plains Industrial Rd.
Wallingford, CT 06492
(203) 949-2650 Fax: (203) 949-2646
www.hvmcorp.com

126 SUMMER 2016 NETA ACCREDITED COMPANIES


NETA ACCREDITED COMPANIES Setting the Standard

Infra-Red Building and Power Service Magna IV Engineering Orbis Engineering Field Services Ltd. Power Products & Solutions, LLC
152 Centre St. 96 Inverness Dr. East, Unit R #300, 9404 - 41st Ave. 12465 Grey Commercial Rd.
Holbrook, MA 02343-1011 Englewood, CO 80112 Edmonton, AB T6E 6G8 Midland, NC 28107
(781) 767-0888 Fax: (781) 767-3462 (303) 799-1273 Fax: (303) 790-4816 Canada (704) 573-0420 x12
tom.mcdonald@infraredbps.com info.denver@magnaiv.com (780) 988-1455 Fax: (780) 988-0191 Fax: (704) 573-3693
www.infraredbps.com Aric Proskurniak lorne@orbisengineering.net ralph.patterson@powerproducts.biz
Thomas McDonald Sr. www.orbisengineering.net www.powerproducts.biz
Magna IV Engineering Lorne Gara Ralph Patterson
Longo Electrical-Mechanical, Inc. Avenida del Condor #590
One Harry Shupe Blvd., Box 511 Oficina 601 Pacic Power Testing, Inc. Power Products & Solutions, LLC
Wharton, NJ 07885 Huechuraba, Santiago 8580676 14280 Doolittle Dr. 13 Jenkins Ct.
(973) 537-0400 Fax: (937) 537-0404 Chile San Leandro, CA 94577 Mauldin, SC 29662
jmlongo@elongo.com +(56) 9-9-517-4642 (510) 351-8811 Fax: (510) 351-6655 (800) 328-7382
www.elongo.com info.chile@magnaiv.com steve@pacificpowertesting.com ralph.patterson@powerproducts.biz
Joe Longo Harvey Mendoza www.pacificpowertesting.com www.powerproducts.biz
Steve Emmert Raymond Pesaturo
Longo Electrical-Mechanical, Inc. Magna IV Engineering
1625 Pennsylvania Ave. 1040 Winnipeg St. Pacic Powertech, Inc. Power Services, LLC
Linden, NJ 07036 Regina , SK S4R 8P8 #110, 2071 Kingsway Ave. 998 Dimco Way, P.O. Box 750066
(908) 925-2900 Fax: (908) 925-9427 Canada Port Coquitlam, BC V3C 6N2 Centerville, OH 45475
jmlongo@elongo.com (306) 585-2100 Fax: (306) 585-2191 Canada (937) 439-9660 Fax: (937) 439-9611
www.elongo.com info.regina@magnaiv.com (604) 944-6697 Fax: (604) 944-1271 mkbeucler@aol.com
Joe Longo Andrew Westerman jkonkin@pacificpowertech.ca Mark Beucler
www.pacificpowertech.ca
Longo Electrical-Mechanical, Inc. Magna IV Engineering Josh Konkin Power Solutions Group, Ltd.
1400 F Adams Rd. 106, 4268 Lozells Ave. 425 W. Kerr Rd.
Bensalem, PA 19020 Burnaby, BC VSA 0C6 Canada Phasor Engineering Tipp City, OH 45371
(215) 638-1333 Fax: (215) 638-1366 (604) 421-8020 Sabaneta Industrial Park #216 (937) 506-8444 Fax: (937) 506-8434
jmlongo@elongo.com Scott Nixon Mercedita, PR 00715 bwilloughby@powersolutionsgroup.com
www.elongo.com Puerto Rico www.powersolutionsgroup.com
Joe Longo Magna IV Engineering (787) 844-9366 Fax: (787) 841-6385 Barry Willoughby
11811 North Freeway, Ste. 500 rcastro@phasorinc.com
M&L Power Systems, Inc. Houston, TX 77060 Rafael Castro Power Solutions Group, Ltd.
109 White Oak Ln., Ste. 82 (281) 436-7329 135 Old School House Rd.
Old Bridge, NJ 08857 www.magnaiv.com Potomac Testing, Inc. Piedmont, SC 29673
(732) 679-1800 Fax: (732) 679-9326 1610 Professional Blvd., Ste. A (864) 845-1084 Fax:: (864) 845-1085
milind@mlpower.com National Field Services Crofton, MD 21114 fcrawford@powersolutionsgroup.com
www.mlpower.com 649 Franklin St. (301) 352-1930 Fax: (301) 352-1936 www.powersolutionsgroup.com
Milind Bagle Lewisville, TX 75057 kbassett@potomactesting.com Anthony Crawford
(972) 420-0157 www.potomactesting.com
Magna IV Engineering www.natlfield.com Ken Bassett Power Solutions Group, Ltd.
1103 Parsons Rd. SW Eric Beckman 670 Lakeview Plaza Blvd.
Edmonton, AB T6X 0X2 Power & Generation Testing, Inc., Columbus, OH 43085
Canada Nationwide Electrical Testing, Inc. a CE Power Company (614) 310-8018
(780) 462-3111 Fax: (780) 450-2994 6050 Southard Trace 480 Cave Rd. sspohn@powersolutionsgroup.com
info@magnaiv.com Cumming, GA 30040 Nashville, TN 37210 www.powersolutionsgroup.com
www.magnaiv.com (770) 667-1875 Fax: (770) 667-6578 (615) 882-9455 Fax: (615) 882-9591 Stuart Spohn
Virgina Balitski Shashi@N-E-T-Inc.com mose@pgti.net
www.n-e-t-inc.com www.pgti.net Power Systems Testing Co.
Magna IV Engineering Shashikant B. Bagle Mose Ramieh 4688 W. Jennifer Ave., Ste. 108
200, 688 Heritage Dr. Fresno, CA 93722
Calgary, AB T2H 1M6 North Central Electric, Inc. Power Engineering Services, Inc. (559) 275-2171 ext 15
Canada 69 Midway Ave. 9179 Shadow Creek Lane Fax: (559) 275-6556
(403) 723-0575 Fax: (403) 723-0580 Hulmeville, PA 19047-5827 Converse, TX 78109 dave@pstcpower.com
info.calgary@magnaiv.com (215) 945-7632 Fax: (215) 945-6362 (210) 590-4936 Fax: (210) 590-6214 www.powersystemstesting.com
Dave Emerson ncetest@aol.com engelke@pe-svcs.com David Huffman
www.ncetest.com www.pe-svcs.com
Magna IV Engineering Robert Messina Miles R. Engelke Power Systems Testing Co.
8219D Fraser Ave. 600 S. Grand Ave., Ste. 113
Fort McMurray, AB T9H 0A2 Northern Electrical Testing, Inc. POWER PLUS Engineering, Inc. Santa Ana, CA 92705-4152
Canada 1991 Woodslee Dr. 46575 Magellan (714) 542-6089 Fax: (714) 542-0737
(780) 791-3122 Fax: (780) 791-3159 Troy, MI 48083-2236 Novi, MI 48377 www.powersystemstesting.com
info.fmcmurray@magnaiv.com (248) 689-8980 Fax: (248) 689-3418 (248) 344-0200 Fax: (248) 305-9105
Ryan Morgan ldetterman@northerntesting.com smancuso@epowerplus.com
www.northerntesting.com www.epowerplus.com
Lyle Detterman Salvatore Mancuso

NETA ACCREDITED COMPANIES NETAWORLD 127


NETA ACCREDITED COMPANIES Setting the Standard

Power Systems Testing Co. Premier Power Maintenance Corporation REV Engineering, LTD Shermco Industries
6736 Preston Ave, Ste. E 3066 Finley Island Cir NW 3236 - 50 Ave. SE 33002 FM 2004
Livermore, CA 94551 Decatur, AL 35601 Calgary, AB T2B 3A3 Angleton, TX 77515
(510) 783-5096 Fax: (510) 732-9287 (256) 355-1444 Canada (979)848-1406 Fax: (979) 848-0012
www.powersystemstesting.com johnnie.mcclung@premierpower.us (403) 287-0156 Fax: (403) 287-0198 cking@shermco.com
www.premierpowermaintenance.com rdavidson@reveng.ca www.shermco.com
Power Test, Inc. Johnnie McClung www.reveng.ca Chris King
2200 Highway 49 Roland Nicholas Davidson, IV
Harrisburg, NC 28075 Premier Power Maintenance Corporation Shermco Industries
(704) 200-8311 Fax: (704) 455-7909 4301 Iverson Blvd., Ste. H Saber Power Services 1357 N. 108th E. Ave.
rich@powertestinc.com Trinity, AL 35673 9841 Saber Power Lane Tulsa, OK 74116
www.powertestinc.com (256) 355-3006 Rosharon, TX 77583-5188 (918) 234-2300
Richard Walker kevin.templeman@premierpower.us (713) 222-9102 jharrison@shermco.com
www.premierpowermaintenance.com info@saberpower.com www.shermco.com
POWER Testing and Energization, Inc. Kevin Templeman www.saberpower.com Jim Harrison
14006 NW 3rd Ct., Ste. 101 Mark Reid
Vancouver, WA 98685 Premier Power Maintenance Corporation Shermco Industries
(360) 597-2800 Fax: (360) 576-7182 7301 E County Road 142 Scott Testing Inc. 796 11th St.
chris.zavadlov@powerte.com Blytheville, AR 72315 1698 5th St. Marion, IA 52302
www.powerte.com (870) 762-2100 Ewing, NJ 08638 (319) 377-3377 Fax: (319) 377-3399
Chris Zavadlov kevin.templeman@premierpower.us (609) 882-2400 Fax: (609) 882-5660 jedwards@shermco.com
www.premierpowermaintenance.com rsorbello@scotttesting.com www.shermco.com
POWER Testing and Energization, Inc. Kevin Templeman www.scotttesting.com Jason Edwards
731 E. Ball Rd., Ste. 100 Russ Sorbello
Anaheim, CA 92805 Premier Power Maintenance Corporation Shermco Industries
(714) 507-2702 7262 Kensington Rd. Sentinel Power Services, Inc. 2100 Dixon St., Ste. C
www.powerte.com Brighton, MI 48116 7517 E. Pine St. Des Moines, IA 50316
(517) 230-6620 Tulsa, OK 74115 (515) 263-8482
POWER Testing and Energization, Inc. brian.ellegiers@premierpower.us (918) 359-0350 jedwards@shermco.com
22035 70th Ave. South www.premierpowermaintenance.com gellis@spstulsa.com www.shermco.com
Kent, WA 98032 Brian Ellegiers www.sentinelpowerservices.com Jason Edwards
(253) 437-3100 Greg Ellis
www.powerte.com Premier Power Maintenance Corporation Shermco Industries
4537 S. Nucor Rd. Sentinel Power Services, Inc. 4383 Professional Parkway
Powertech Services, Inc. Crawfordsville, IN 47933 1110 West B St., Ste. H Groveport, OH 43125
4095 South Dye Rd. (317) 879-0660 Russellville, AR 72801 (614) 836-8556 Fax: (614) 836-8557
Swartz Creek, MI 48473-1570 kevin.templeman@premierpower.us (918) 359-0350 jharrison@shermco.com
(810) 720-2280 Fax: (810) 720-2283 www.premierpowermaintenance.com gellis@spstulsa.com www.shermco.com
kirkd@powertechservices.com Kevin Templeman www.sentinelpowerservices.com Jim Harrison
www.powertechservices.com Greg Ellis
Kirk Dyszlewski Reuter & Hanney, Inc. Shermco Industries
149 Railroad Dr. Shermco Industries 998 East Berwood Ave.
Precision Testing Group Northampton Industrial Park 2425 E. Pioneer Dr. Saint Paul, MN 55110
5475 Highway 86, Unit 1 Ivyland, PA 18974 Irving, TX 75061 (651) 484-5533 Fax: (651) 484-7686
Elizabeth, CO 80107 (215) 364-5333 Fax: (215) 364-5365 (972) 793-5523 Fax: (972) 793-5542 jedwards@shermco.com
(303) 621-2776 Fax: (303) 621-2573 mikereuter@reuterhanney.com rwidup@shermco.com www.shermco.com
glenn@precisiontestinggroup.com www.reuterhanney.com www.shermco.com Jason Edwards
Glenn Stuckey Michael Reuter Ron Widup
Shermco Industries
Premier Power Maintenance Corporation Reuter & Hanney, Inc. Shermco Industries 12000 Network Blvd., Bldg D,, Ste. 410
6525 Guion Rd. 4270-I Henninger Ct. 112 Industrial Dr., PO Box 606 San Antonio, TX 78249
Indianapolis, IN 46268 Chantilly, VA 20151 Minooka, IL 60447 (512) 267-4800 Fax: (512) 267-4808
(317) 879-0660 (703) 263-7163 Fax: 703-263-1478 (815) 467-5577 Fax: (815) 467-5883 cking@shermco.com
kevin.templeman@premierpower.us www.reuterhanney.com rwidup@shermco.com www.shermco.com
www.premierpowermaintenance.com www.shermco.com Chris King
Kevin Templeman Reuter & Hanney, Inc. Ron Widup
11620 Crossroads Circle, Suites D-E Shermco Industries Canada Inc.
Premier Power Maintenance Corporation Middle River, MD 21220 Shermco Industries 1033 Kearns Crescent, Box 995
2725 Jason Rd. (410) 344-0300 Fax: (410) 335-4389 1705 Hur Industrial Blvd. Regina, SK S4P 3B2
Ashland, KY 41102 www.reuterhanney.com Cedar Park, TX 78613 Canada
(606) 929-5969 Michael Jester (512) 267-4800 Fax: (512) 258-5571 (306) 949-8131 Fax: (306) 522-9181
jay.milstead@premierpower.us cking@shermco.com kheid@magnaelectric.com
www.premierpowermaintenance.com www.shermco.com www.shermco.com
Jay Milstead Chris King Kerry Heid

128 SUMMER 2016 NETA ACCREDITED COMPANIES


NETA ACCREDITED COMPANIES Setting the Standard

Shermco Industries Canada Inc. Taurus Power & Controls, Inc. Trace Electrical Services & Testing, LLC
851-58th St. East 9999 SW Avery St. 293 Whitehead Rd.
Saskatoon, SK S7K 6X5 Tualatin, OR 97062-9517 Hamilton, NJ 08619
Canada (503) 692-9004 Fax: (503) 692-9273 (609) 588-8666 Fax: (609) 588-8667
(306) 955-8131 robtaurus@tauruspower.com jvasta@tracetesting.com
Fax: (306) 955-9181 www.tauruspower.com www.tracetesting.com
ajaques@magnaelectric.com Rob Bulfinch Joseph Vasta
www.shermco.com Taurus Power & Controls, Inc.
Adam Jaques 19226 66th Ave. S, Ste. L102 Utilities Instrumentation Service, Inc.
Kent, WA 98032 2290 Bishop Circle East
Shermco Industries Canada Inc. (425) 656-4170 Fax: (425) 656-4172 Dexter, MI 48130
3731-98 St. servicereq@tauruspower.com (734) 424-1200 Fax: (734) 424-0031
Edmonton, AB T6E 5N2 www.tauruspower.com GEWalls@UISCorp.com
Canada David Koons www.uiscorp.com
(780) 436-8831 Fax: (780) 468-9646 Gary E. Walls
cgrant@magnaelectric.com 3C Electrical Co., Inc.
www.shermco.com 40 Washington St. Utility Service Corporation
Cal Grant Westborough, MA 01581 4614 Commercial Dr. NW
(508) 881-3911 Fax: (508) 881-4814 Huntsville, AL 35816-2201
Shermco Industries Canada Inc. jim@three-c.com (256) 837-8400 Fax: (256) 837-8403
3430 25th St. NE www.three-c.com apeterson@utilserv.com
Calgary, AB T1Y 6C1 Jim Cialdea www.utilserv.com
Canada Alan D. Peterson
(403) 769-9300 Fax: (403)769-9369 3C Electrical Co., Inc.
cgrant@magnaelectric.com 72 Sanford Dr. Western Electrical Services, Inc.
www.shermco.com Gorham, ME 04038 14311 29th St. East
Cal Grant (800) 649-6314 Fax: (207) 782-0162 Sumner , WA 98390
jim@three-c.com (253) 891-1995 Fax: (253) 891-1511
Shermco Industries Canada Inc. www.three-c.com dhook@westernelectricalservices.com
1375 Church Ave. Jim Cialdea www.westernelectricalservices.com
Winnipeg, MB R2X 2T7 Dan Hook
Canada Tidal Power Services, LLC
(204) 925-4022 Fax: (204) 925-4021 4202 Chance Lane Western Electrical Services, Inc.
cbrandt@magnaelectric.com Rosharon, TX 77583 3676 W. California Ave., #C, 106
www.shermco.com (281) 710-9150 Fax: (713) 583-1216 Salt Lake City, UT 84104
Curtis Brandt monty.janak@tidalpowerservices.com (888) 395-2021 Fax: (253) 891-1511
www.tidalpowerservices.com rcoomes@westernelectricalservices.com
Sigma Six Solutions, Inc. Monty C. Janak www.westernelectricalservices.com
2200 West Valley Hwy., Ste. 100 Rob Coomes
Auburn, WA 98001 Tidal Power Services, LLC
(253) 333-9730 Fax: (253) 859-5382 8184 Highway 44, Ste. 105 Western Electrical Services, Inc.
jwhite@sigmasix.com Gonzales, LA 70737 5680 South 32nd St.
www.sigmasix.com (225) 644-8170 Fax: (225) 644-8215 Phoenix, AZ 85040
John White www.tidalpowerservices.com (602) 426-1667 Fax: (253) 891-1511
Darryn Kimbrough carcher@westernelectricalservices.com
Southern New England Electrical Testing, LLC www.westernelectricalservices.com
3 Buel St., Ste. 4 Tidal Power Services, LLC Craig Archer
Wallingford, CT 06492 1056 Mosswood Dr.
(203) 269-8778 Fax: (203) 269-8775 Sulphur, LA 70663 Western Electrical Services, Inc.
dave.asplund@sneet.org (337) 558-5457 Fax: (337) 558-5305 4510 NE 68th Dr., Ste. 122
www.sneet.org www.tidalpowerservices.com Vancouver, WA 98661
David Asplund, Sr. Steve Drake (888) 395-2021 Fax: (253) 891-1511
Tasciutto@westernelectricalservices.com
Southwest Energy Systems, LLC Tony Demaria Electric, Inc. www.westernelectricalservices.com
2231 East Jones Ave., Ste. A 131 West F St. Tony Asciutto
Phoenix, AZ 85040 Wilmington, CA 90744
(602) 438-7500 Fax: (602) 438-7501 (310) 816-3130
bob.sheppard@southwestenergysystems.com (310) 549-9747
www.southwestenergysystems.com neno@tdeinc.com
Robert Sheppard www.tdeinc.com
Nenad Pasic

NETA ACCREDITED COMPANIES NETAWORLD 129


ADVERTISERS MANUFACTURERS AND
OTHER SERVICE PROVIDERS
AEMC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
This issues advertisers are identified below. Aero Tec Laboratories . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
Please thank these advertisers by telling them you Ampteks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
ANSI/NETA ATS & ECS Bundle . . . . . . . . . . . . . . . . . . . . . . . . . . 25
saw their advertisement in YOUR magazine ANSI/NETA MTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
NETA World. Arbiter Systems, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102
AVO Training Institute, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
BCS Switchgear, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Belyea Company . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106
Burlington Safety Laboratory, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
Doble Engineering Company . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
Dranetz . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
Electro Rent . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38, 65
Elsco. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .45, 106
Group CBS, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
High Voltage, Inc.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
INDEPENDENT NETA High Voltage Electrical Services . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88
HV Diagnostics, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
ACCREDITED COMPANIES Instel Power Products . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
Intellirent . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Absolute Testing Services, Inc. . . . . . . . . . . . . . . . . . . . . . . 73
IRISS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110
American Electrical Testing Co., Inc. . . . . . . . . . . . . . . . . 37
L.W. Brittain . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
Apparatus Testing and Engineering . . . . . . . . . . . . . . . . . 123
Megger . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Inside Front Cover
Burlington Electrical Testing Co., Inc. . . . . . . . . . . . . . . . 57
Monster Fuses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
Eastern High Voltage. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
National Switchgear. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Electrical Energy Experts, Inc.. . . . . . . . . . . . . . . . . . . . . . . 81
NETA PowerTest Call for Sponsors . . . . . . . . . . . . . . . . . . . . . . . . . 32
Electrical Reliability Services. . . . . . . . . . . . . . . . . . . . . . . . 56
NETA PowerTest Save The Date . . . . . . . . . . . . . . . . . . . . . . . . . . . . 96
Elemco Services, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
NETA PowerTest Call for Exhibitors . . . . . . . . . . . . . . . . . . . . . . . 103
EnerG Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
NETA PowerTest Thank You Sponsors. . . . . . . . . . . . . . . . . . . . . . 117
Harford Electrical Testing Co., Inc. . . . . . . . . . . . . . . . . . . 64
NETA Why Hire NAC? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 122
High Voltage Maintenance Corp. . . . . . . . . . . . . . . . . . . . 20
OMICRON electronics Corp. USA. . . . . . . . . . . . . . . . . Back Cover
Industrial Electric Testing, Inc. . . . . . . . . . . . . . . . . . . . . . 17
Phenix Technologies, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119
Infra-Red Building and Power Service . . . . . . . . . . . . . . . 50
Protec Equipment Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Nationwide Electrical Testing, Inc . . . . . . . . . . . . . . . . . . 101
Quality Switchgear, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
North Central Electric, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . 27
Raytech . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Inside Back Cover
Orbis Engineering Field Services, Ltd. . . . . . . . . . . . . . . 115
Sertec Relay Services . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
Potomac Testing, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
SMC International . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 123
Power Products & Solutions, Inc. . . . . . . . . . . . . . . . . . . . . 20
Solid State Exchange & Repair Co.. . . . . . . . . . . . . . . . . . . . . . . . . . 21
Power Services, LLC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 123
Southland Electrical Supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107
Power Systems Testing Co. . . . . . . . . . . . . . . . . . . . . . . . . . . 23
SPTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
POWER Testing and Energization, Inc. . . . . . . . . . . . . . . . 6
Technitrol, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121
Scott Testing, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 115
Thyritronics, Inc.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121
Shermco Industries. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
Utility Relay Company . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 116
Sigma Six Solutions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Vacuum Interrupters, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
Taurus Power & Controls, Inc. . . . . . . . . . . . . . . . . . . . . . . 57
Vanguard Instrument Co., Inc. . . . . . . . . . . . . . . . . . . . . . . . . . 23, 102
3C Electrical Co. Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
Tony Demaria Electric, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . 65
Trace Electrical Services & Testing, LLC . . . . . . . . . . . . . 27
Utility Service Corporation . . . . . . . . . . . . . . . . . . . . . . . . 72

130 SUMMER 2016 ADVERTISERS


BATTERY-OPERATED
2.5kV VARIABLE FREQUENCY
POWER FACTOR TEST SET
Perfect for ALL of your power factor measuring needs

'HVLJQHGIRUIDVWHDV\HOGPHDVXUHPHQWV
ZLWK5D\WHFKSUHFLVLRQDQGDFFXUDF\
Battery-operated Unique to market
Built-in standard capacitor
Test frequency 10 Hz 400 Hz
External safety switch for safe operation
Easy export of results using USB interface
Built-in printer

TROUBLE-FREE AND BACKED BY OUR 5 YEAR WARRANTY!


Toll free 888 484 3779 | Phone 267 404 2676 | Fax 267 404 2685
118 South 2nd St., Perkasie, PA 18944

www.RaytechUSA.com
Benton Vandiver
Application Engineer

Tomorrows protection testing, today!


As a power systems engineer its essential that I keep up to date
with whats going on in the market and what our customers need.
Based on this, I am constantly looking for better ways of doing
things. Take our simulation-based protection testing solution; now
even complex networks can be tested automatically from a single
point of control. This allows a comprehensive assessment of the
entire protection scheme, taking into account the settings and
functionality of the individual relays.

www.omicronenergy.com | 1-800-OMICRON

Potrebbero piacerti anche