Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1. Regulating Reserve
2. Contingency Reserve
3. Dispatchable Reserve
Schedules for the Ancillary Services Procurement Agreement
Between NGCP and xxxxxx Corporation
for its xxxxMWxxxx Plant
Page 2 of 19
Non-firm
Firm
Non-Firm
5. The System Operator may opt to require the AS provider to synchronize the
generating unit for validation of the units availability prior to or upon approval
of the request for re-nomination.
Firm
5. The System Operator may opt to require the AS provider to synchronize the
generating unit for validation of the units availability prior to or upon approval
of the request for re-declaration of available capacity.
Non-Firm
5. In cases where the nomination is more than the required level, the operating
mode such as Free-Governor, AGC and Manual Control, and nominated
price (in the order of priority) shall be considered.
7. Only when the Firm Contracted Capacity is not sufficient will the nominations
from Non-Firm Contracted Capacity be considered. The scheduling shall be
based on the technical considerations and least cost.
Schedules for the Ancillary Services Procurement Agreement
Between NGCP and xxxxxx Corporation
for its xxxxMWxxxx Plant
Page 6 of 19
Firm
1. The Firm Contracted Capacity shall be scheduled first by NGCP before the
Non-Firm Contracted Capacity.The Firm Contracted Capacity shall be
scheduled at all times when declared by the Service Provider.
NGCP shall inform the Service Provider of the automatic cancellation of the
approved AS Schedule promptly when the cancellation occurred.
6. Any request for the change of unit assignment for Regulating Reserve shall
be subjected to the assessment by the System Operator prior to approval.
Non submission of request for re-nomination shall mean non-confirmation of
the request for change in unit assignment.
1. The System Operator shall make sure that Contingency Reserve provider is
synchronized to the grid as generator (w/ at least 5MW load for market
based) and the AS provider shall respond automatically and/or immediately
follow instruction when called upon without delay.
3. Whenever called upon, the Contingency Reserve provider must sustain the
dispatched capacity as long as it is required by the System Operator and in
accordance to the Philippine Grid Code, unless ordered otherwise.
9. The System Operator shall require the AS provider to synchronize the unit
upon submission of request for re-nomination to ensure the units availability.
Failure to comply shall mean cancellation of request for re-nomination.
System Operator shall ensure that the scheduled AS providers generator
breaker must be closed on or before the start and until the end of the
scheduled interval.
INSTRUCTIONS
2.0 Upon arrival at the plant control room, inform the following personnel that
the test is about to be started:
3.0 Set-up the PQ Analyzer and other related equipment (if needed) in
coordination with the plant technicians (electrical and instrumentation &
control) and let the latter connect said test equipment to the unit control
switchboards.
4.0 Make sure that the following test forms are already at hand for manual
recording of test data (generator MW and Frequency):
5.0 Check that the communication protocol is functioning by calling all the
concerned personnel at their respective stations.
6.0 After getting clearance from RCC, instruct the Plant Control Engineer to
adjust the unit output to 50% of regulating range (minimum to maximum
capacity). This shall be the prescribed loading to be considered for the test.
Take note of the units frequency deadband (up to 0.15 Hz).
7.2 Observe the response of the unit and record the incremental rate
and data as indicated on the test instrument. This step shall be
done until the unit returns to its initial state, and download the data
to analyze its response.
7.4 Observe the response of the unit and record the decremental rate
and data as indicated on the test instrument. This step shall be
done until the unit returns to its initial state, and download the data
to analyze its response.
8.0 If the test process has been successfully completed, the PNPD-ASS head
or his representative shall declare end of the test. Otherwise, let the Plant
Control Engineer/Shift Superintendent-on-duty repeat the process
accordingly but only up to maximum allotted time for the particular test.
9.0 Let all the authorized report forms signatories affix their signature on the
duly-filled test reports.
10.0 Conduct post-test briefing or conference with all the concerned parties
present during the test.
INSTRUCTIONS
2.0 Upon arrival at the plant control room, inform the following personnel that
the test is about to be started:
3.0 Set-up the PQ Analyzer and other related equipment (if needed) in
coordination with the plant technicians (electrical and instrumentation &
control) and let the latter connect said test equipment to the unit control
switchboards.
4.0 Check that the communication protocol is functioning by calling all the
concerned personnel at their respective stations.
5.0 Record the status and operating parameters, e.g., load and system
frequency before the start of the test.
6.0 After getting clearance from RCC, instruct the Plant Control Engineer to
adjust the units output to approximately the midpoint of the regulation
range. This shall be the initial state to be considered for the test.
Schedules for the Ancillary Services Procurement Agreement
Between NGCP and xxxxxx Corporation
for its xxxxMWxxxx Plant
Page 11 of 19
7.0 Instruct the Plant Control Engineer to switch the unit controller to Automatic
Generation Control operation mode (remote); taking into consideration the
required operating level for AGC operation is met.
8.0 Upon completion of all the Real Time preparation on the plant site,
SED/AEMS personnel-on-duty take over the test for AGC and setting of
the control mode to Economic and participation to Full through SCADA.
9.0 SED/AEMS to conduct the tests and revalidate AGC setting of the
generating unit by sending pulse thru AGC control signals.
10.0 If the test process has been successfully completed by the SED/AEMS, the
PNPD-ASS head or his representative shall declare end of the test.
Otherwise, let the Plant Control Engineer/Shift Superintendent-on-duty
repeat the process accordingly but only up to maximum allotted time for
the particular test.
11.0 Conduct post-test briefing or conference with all the concerned parties
present during the test.
INSTRUCTIONS
2.0 Upon arrival at the plant control room, inform the following personnel that
the test is about to be started:
3.0 Set-up the PQ Analyzer and other related equipment (if needed) in
coordination with the plant technicians (electrical and instrumentation &
control) and let the latter connect said test equipment to the unit control
switchboards.
4.0 Make sure that the following test forms are already at hand for manual
recording of test data (generator MW and Frequency):
5.0 Check that the communication protocol is functioning by calling all the
concerned personnel at their respective stations.
Schedules for the Ancillary Services Procurement Agreement
Between NGCP and xxxxxx Corporation
for its xxxxMWxxxx Plant
Page 12 of 19
6.0 To verify the primary response of the unit, instruct the Plant Control
Engineer to operate it in Free-Governor Mode and adjust the output to its
minimum operating capacity. Take note of the units frequency deadband
(up to -0.3 Hz).
7.0 Request RCC to adjust the system frequency above the deadband setting
of the generating unit.
8.0 Observe the response of the unit under test and record the data indicated
by the test instrument. Download the data to the PC and analyze its
results.
9.0 To verify the secondary response of the unit using the Manual Adjustment,
instruct the Plant Control Engineer to increase the generation output of the
unit based on its declared ramp rate until it reaches its maximum rated
capacity and sustain it for at least thirty (30) minutes. Observe/record the
result of the test (i.e., MW output, ramp rate, and system frequency).
10.0 If the test process has been successfully completed, the PNPD-ASS head
or his representative shall declare end of the test. Otherwise, let the Plant
Control Engineer/Shift Superintendent-on-duty repeat the process
accordingly but only up to maximum allotted time for the particular test.
11.0 Let all the authorized report forms signatories affix their signature on the
duly-filled test reports.
12.0 Conduct post-test briefing or conference with all the concerned parties
present during the test.
INSTRUCTIONS
2.0 Upon arrival at the plant control room, inform the following personnel that
the test is about to be started:
3.0 Set-up the PQ Analyzer and other related equipment (if needed) in
coordination with the plant technicians (electrical and instrumentation &
control) and let the latter connect said test equipment to the unit control
switchboards.
Schedules for the Ancillary Services Procurement Agreement
Between NGCP and xxxxxx Corporation
for its xxxxMWxxxx Plant
Page 13 of 19
4.0 Make sure that the following test forms are already at hand for manual
recording of test data:
5.0 Check that the communication protocol is functioning by calling all the
concerned personnel at their respective stations.
6.0 After getting clearance from RCC, instruct the Plant Control Engineer to
implement the start-up procedure for the unit.
6.2 For plants consisting of large generating units, instruct the Plant
Control Engineer to start each unit, one at a time upon instruction of
RCC.
7.0 Record the data of the start up and synchronization time of the unit under
test. Once synchronized, instruct the Plant Control Engineer to increase
the generation output until it reaches its maximum capacity and sustain it
for at least two (2) hours.
8.0 If the test process has been successfully completed, the PNPD-ASS head
or his representative shall declare end of the test. Otherwise, let the Plant
Control Engineer/Shift Superintendent-on-duty repeat the process
accordingly but only up to maximum allotted time for the particular test.
9.0 Let all the authorized report forms signatories affix their signature on the
duly-filled test reports.
10.0 Conduct post-test briefing or conference with all the concerned parties
present during the test.
Schedules for the Ancillary Services Procurement Agreement
Between NGCP and xxxxxx Corporation
for its xxxxMWxxxx Plant
Page 14 of 19
Incidental Energy
Cost of Incidental Energy (IE) shall be computed using the formula below:
= ( + + )
Wherein:
Actual Fuel and Lube Cost = Monthly Fuel and Lube Oil
Consumption rate in P/kWh due to dispatched energy (G).
The monthly fuel and lube oil consumption rate shall be the
actual consumption rate if less than the approved
consumption rate of ERC otherwise it shall be the approved
consumption rate by ERC.
Where;
G = Summation of net energy generated or dispatched in a particular interval hour
due to Firm and Non-Firm Contracted Capacity, in kWh
REVWESM = Summation of WESM revenue in a particular interval hour based on
Final Ex-post market clearing price of the AS Providers trading Nodearising from G
above.
Schedules for the Ancillary Services Procurement Agreement
Between NGCP and xxxxxx Corporation
for its xxxxMWxxxx Plant
Page 16 of 19
5.1 The Generation Facility shall be tested, to ensure its continuing capability to
provide the Ancillary Services specified in Schedule 1 of this Agreement, in
accordance with the requirements and procedures set out in Section 6.10 of
the Grid Code and Schedule 3 of this Agreement.
5.2 The Service Provider shall submit to NGCP, within one (1) month from the
effectivity of this Agreement as provided under Section 2.1 herein, its
preferred schedule for the testing of the Generation Facility, which shall not
be more than twice within a calendar year. NGCP shall then evaluate the
submitted schedule based on its availability and in consideration to the
system condition. The submitted schedule shall be mutually accepted by
both NGCP and the service provider. Preferred schedule of testing shall be
during weekdays.
5.3 Pursuant to Section 6.10.1.4 of the Grid Code, NGCP may at anytime issue
instructions requiring tests to be carried out on the Generation Facility. All
such tests shall be of sufficient duration and shall be conducted not more
than twice within a calendar year except when there are reasonable grounds
to justify the necessity for further tests.
5.4 All relevant and incidental costs incurred in relation to the testing and
certification activities in relation to Section 5.3 above shall be approved and
agreed upon by the Parties in writing within a reasonable time prior to the
actual conduct of said activities, andshall be for the Service Providers own
account.
5.5 NGCP is not obligated to pay for the capacity of a specific unit of the
Generation Facility during the period of testing pursuant to Section 5.3
above. Any incidental energy that may be injected to the Grid during
suchtesting and certification activities in respect of such unitsshall be
recovered from the WESM.
5.6 Subject to the procedures set out in the ASPP, NGCP shall regularly monitor
the Generation Facilitys performance to determine its capability of providing
the Ancillary Services set out in Schedule 1 hereof.
5.7 NGCP may, at any time, and in accordance with the ASPP, verify whether
the provision of an Ancillary Service is in accordance with this Agreement.
At NGCPs request, the Service Provider shall provide and not unreasonably
withhold, the results of any testing conducted which may have a Material
Effect on the capability of the Generation Facility to meet its required
performance level/s.
Schedules for the Ancillary Services Procurement Agreement
Between NGCP and xxxxxx Corporation
for its xxxxMWxxxx Plant
Page 17 of 19
6.1 The total number of Hours Complied by an AS Provider shall be at least 98%
of the total number of Scheduled Hours in a year.
Formula:
(Total no. of Hours Complied in a year/total no. of hours scheduled in a year)
x 100 98%
6.2 Once the Reserve Market becomes operational, the Reserve Effectiveness
Factor (REF) may be used by NGCP to gauge the performance of an AS
Provider for its provision of the contracted Ancillary Services
The Service Provider may be exempted from providing the Firm Contracted
Capacity during Hydrological Constraint periods.
a. The actual water elevation of the _____Reservoir (in masl) is below the rule
curve set by NIA, as outlined in the Water Rule Curve below;
b. The Service Provider notifies NGCP in writing before 2 pm at least one business
day before of their intent to cancel the Firm Contracted Capacity and submits to
NGCP actual water elevation data.
Schedule 8 Outage Allowance (as applicable for Firm AS for Thermal plants)
The Service Provider shall be allowed a number of Outage Hours per year, the
aggregate of the Outage Hours shall be called the Outage Allowance. During the
Outage Hours, the Service Provider shall be deemed unavailable; NGCP shall not
schedule the Service Provider for the Firm Contracted Capacity, resulting in non-
payment during such Outage Allowance.
For the purposes of this agreement, an Outage Hour will be defined as a period
where the Service Provider, on a day-ahead basis, informs NGCP that it is unable to
provide the Firm Contracted Capacity, due to outage or maintenance.
The Service Provider shall be allowed an Outage Allowance per year under the
following Schedule:
Unit 1
Type Outage
Period
Allowance
(hours/year)
Normal Outage December 26, 2012 to December 25, 2013
Normal Outage December 26, 2013 to December 25, 2014
Normal Outage December 26, 2014 to December 25, 2015
Normal Outage December 26, 2015 to December 25, 2016
Major December 26, 2016 to December 25, 2017
Outage
Unit 2
Type Outage
Period
Allowance
(hours/year)
Normal Outage December 26, 2012 to December 25,
2013
Normal Outage December 26, 2013 to December 25,
2014
Normal Outage December 26, 2014 to December 25,
2015
Major December 26, 2015 to December 25,
Outage 2016
Normal Outage December 26, 2016 to December 25,
2017
Should the timing of the Service Providers scheduled Major Outage be delayed, the
Service Provider may elect to switch the allowed Outage Days for the designated
Major Outage year with the allowed Outage Days of a Normal Outage year.
Outage Allowance for may be consumed only for the specified period, and shall not
be transferrable to another year.