NON-COMPLIANCE REPORT#25
SERVICES
JULY/AUGUST-2011
PROJECT: MIOT INTERNATIONAL
General Comments:
All the issues projected are examples. Actual number of
defects may be in multiples.
Issues mentioned in the NCR should not be repeated
during future erection process.
General working condition in the site and house keeping
has been poor.
Emphasis can be put to improve site level supervision to
ensure health & safety
Please send the compliance report within 15 days.
Issue Description Location Instruction Given
Date Status
Proper supports Service Remove temporary 18.08.11 Pending
(pedestal ) have not building support & provide
been provided for basement - proper pedestal
pipes pump support as per drawing
room
Issue Instruction Given
Description Location Date Status
Pictures are self Ground Written approval from 18.8.11 Pending.
explanatory Floor- design team is to be False
Zone-1 submitted, if the p- ceiling
traps are to be works
concealed in the wall. are in
Alternatively, traps are progress
recommended to be without
kept open and rectifying
accessible.
Issue Description Instruction
Location Given Date Status
CPVC Pipes covered Service The pipes should be 18.08.11 Pending
with cement slurry building cleaned & freed from
which may lead to basement - cement slurry &
cracks in pipe pump room Provided with proper
Moreover pedestal pedestal support
supports have not
been provided for
pipes
Issue Instruction Given
Description Location Date Status
Improper support Service Remove temporary 18.08.11 Pending
for pipes Building support & provide proper
Terrace pedestal support as per
drawing
Issue Instruction Given
Description Location Date Status
Crack found in the Service Replace with a new pipe 18.08.11 Pending
pipe installed to building
connect HVAC tank Terrace
& cooling tower
Issue Instruction Given
Description Location Date Status
Water seepage from Service Rectify by grouting / 18.08.11 Pending
HVAC make up building water proofing
water tank Terrace
Issue Instruction Given
Description Location Date Status
CHW main pipe line Pipe rack- Provide proper supports 18.08.11 Pending
on pipe rack with North side as per drawing . Maintain
no/improper of nallah standard Gap between
support consecutive supports.
1. Poor quality of welding in Service 1. The weld pool in all the 18.08.11 Pending
CHW pipe line Uneven & floor welding joints should be
improper thickness of Weld Zone-3 freed from slag, properly
pool & also not properly grinded & painted with
grinded & painted which red oxide prima.
will lead the joint to 2. Any patch work in MS
corrode. pipe is strictly avoidable.
2. Defect/ patch work in The affected pipe must
CHW pipe line The hole in be cut & replaced with
CHW pipe line has been new pipe.
arrested by welding with
plate
Issue Instruction Given
Description Location Date Status
Duct & CPVC 1st All the insulated duct 18.08.11 Pending
penetration through Basement- (fresh/supply/ return air)
the wall has been Zone-1 penetrations and CPVC
closed & plastered 1st water line penetration
without providing Basement- through the wall must
any packing around Zone-2 be closed & plastered
the duct & pipe Ground
providing proper
Floor- Zone-1 packing of neoprene or
polystyrene material
around the duct or pipe
Issue Instruction
Description Location Given Date Status
Poor workmanship Ground Floor- AHU filters must be 18.08.11 Pending
Installed AHU Zone-1 covered properly as
filters found Ground Floor intimated repeatedly
uncleaned, Zone-4-AHU-27 before.
unprotected and Differential pressure
damaged. gauge reading must
Cement slurry & be shown during
dirt found inside commissioning to
AHU filter prove that filters are
functioning properly.
Issue Instruction Given
Description Location Date Status
Positioning of the Service All the AHUs must be 18.08.11 Pending
AHU is wrong and Floor erected on the pedestal
still piping is Zone 3- with proper alignment.
completed. AHU-90 The alignment of
highlighted AHU must be
corrected immediately.
Issue Description Instruction
Location Given Date Status
Poor workmanship Wall 1st All the AHUs should 18.08.11 Pending
plastering in progress inside Basement be covered with
AHU room without providing Zone- 3 proper cover
proper cover over installed AHU room immediately since
AHU which has caused the finishing & plastering
accumulation of cement works are in progress
slurry & dirt all over the AHU up to 4th floor
which may lead to rusting of The affected AHU
the AHU pipe as well as must be cleaned
corrosion of AHU surface
Thank You
Please revert back with a compliance report
within 15 days.