Additional Reservoir
Padang Halaban 60 TPH Palm Oil Mill
1. GENERAL
1.1 Dimension, shape, construction detail, quality of material, and construction methods must
refer to Civil Drawings and General Specifications for Civil Works.
2.1 Existing ground must be cut until reached design level, as per drawings.
2.2 Soil fill must be compacted per 150 mm thick layer with whelled roller.
2.3 Surrounding area of kolam air to be applied clay liner to provide impermeable layer as
thick as 2.4 m, as per drawings.
2.4 General specification material for clay liner :
2.4.1 Soil material must be specified of SC, CL or CH based on Unified Soil
Classification system.
2.4.2 Soil permeability must be < 10-7cm/det .
2.4.3 Total amount of gravel, particle with 4.76 mm in size, must be < 30%.
2.4.4 Soil plasticity index must be 7 - 10%.
2.4.5 Maximum soil particle size must be 25 - 50 mm.