RESUMEN DE EQUIPOS Y PERSONAL PARA EJECUCIN DE CAMPAMENTO

PROYECTO HIDROELECTRICO MANTA FASE 1


(VALORES EXPRESADOS EN USD$ SIN IGV)

ITEM DESCRIPCIN UNIDAD CANT P.UNIT. P. TOTAL


1 DA VIERNES 22/09/17 DIA 1 1017.36 1017.36
2 DIA SABADO 23/09/17 DIA 1 3231.36 3231.36
3 DIA LUNES 25/09/17 DIA 1 212.22 212.22
4 DIA MARTES 26/09/17 DIA 1 1280.8 1280.80
5 DIA MIERCOLES 27/09/17 DIA 1 1311.93 1311.93
6 DIA VIERNES 29/09/17 DIA 1 1301.24 1301.24
7 DIA SABADO 30/09/17 DIA 1 2146.14 2146.14
8 DIA LUNES 09/10/17 DIA 1 1972.92 1972.92
9 DIA MIERCOLES 11/10/17 DIA 1 1520.793 1520.79
=======
TOTAL (USD$) SIN IGV $13,994.76

DETALLE VALORIZACIN DE EQUIPOS Y PERSONAL PARA EJECUCIN DE CAMPAMENTO


ITEM DESCRIPCIN CARGO UNID CANT P. UNIT P. TOTAL
1 DA VIERNES 22/09/17 1017.36
1.01 MANO DE OBRA/ (ENCARGADO: ELADIO VASQUEZ SUAREZ-HORA: 15.00pm-18.00 pm) 46.17
1.01.01 CAPATAZ H 3 8.64 25.92
1.01.02 OPERARIO H 3 6.75 20.25
1.02 EQUIPO 971.19
1.02.01 CAMA BAJA + TRACTOR H 3 200.00 600.00
1.02.02 EXCAVADORA CAT. 336 H 3 98.73 296.19
1.02.03 MARTILLO HIDRAULICO H 3 25.00 75.00
2 DIA SABADO 23/09/17 3231.36
2.01 MANO DE OBRA/ (ENCARGADO: ELADIO VASQUEZ SUAREZ-HORA: 07.00am-16.00 pm) 317.79
2.01.01 CAPATAZ H 9 8.64 77.76
2.01.02 OPERARIO H 9 6.75 60.75
2.01.03 PEN H 9 4.98 44.82
2.01.04 PEN H 9 4.98 44.82
2.01.05 PEN H 9 4.98 44.82
2.01.06 PEN H 9 4.98 44.82
2.02 EQUIPO 2913.57
2.02.01 CAMA BAJA + TRACTOR H 9 200.00 1800.00
2.02.02 EXCAVADORA CAT. 336 H 9 98.73 888.57
2.02.03 MARTILLO HIDRAULICO H 9 25.00 225.00
3 DIA LUNES 25/09/17 212.22
3.01 MANO DE OBRA/ (ENCARGADO: ELADIO VASQUEZ SUAREZ-HORA: 07.00am-16.00 pm) 212.22
3.01.01 CAPATAZ H 9 8.64 77.76
3.01.02 PEN H 9 4.98 44.82
3.01.03 PEN H 9 4.98 44.82
3.01.04 PEN H 9 4.98 44.82
3.02 EQUIPO
3.02.01 -------------
4 DIA MARTES 26/09/17 1280.8
4.01 MANO DE OBRA/ (ENCARGADO: ELADIO VASQUEZ SUAREZ-HORA: 08.00am-16.00 pm) 256.8
4.01.01 CAPATAZ H 8 8.64 69.12
4.01.02 OPERARIO H 8 6.75 54.00
4.01.03 OPERARIO H 8 6.75 54.00
4.01.04 PEN H 8 4.98 39.84
4.01.05 PEN H 8 4.98 39.84
4.02 EQUIPO 1024
4.02.01 MOTONIVELADORA KOMATSU H 8 77.00 616.00
4.02.02 RODILLO H 8 51.00 408.00
5 DIA MIERCOLES 27/09/17 1311.93
5.01 MANO DE OBRA/ (ENCARGADO: TOMAS VALDERRAMA-HORA: 07.00am-16.00 pm) 423.36
5.01.01 CAPATAZ H 9 8.64 77.76
5.01.02 OPERARIO H 9 6.75 60.75
5.01.03 OPERARIO H 9 6.75 60.75
5.01.04 PEN H 9 4.98 44.82
5.01.05 PEN H 9 4.98 44.82
5.01.06 PEN H 9 4.98 44.82
5.01.07 PEN H 9 4.98 44.82
5.01.08 PEN H 9 4.98 44.82
5.02 EQUIPO 888.57
5.02.01 EXCAVADORA CAT 336 H 9 98.73 888.57
6 DIA VIERNES 29/09/17 1301.24
6.01 MANO DE OBRA/ (ENCARGADO: JUAN C. HUALLA-HORA: 07.00am-16.00 pm) 138.51
6.01.01 CAPATAZ H 9 8.64 77.76
6.01.02 OPERARIO H 9 6.75 60.75
6.02 EQUIPO 1162.73
6.02.01 EXCAVADORA CAT. 336 DL H 9 98.73 888.57
6.02.02 EXCAVADORA CAT 320 DL H 4 68.54 274.16
7 DIA SABADO 30/09/17 2146.14
7.01 MANO DE OBRA/ (ENCARGADO: -HORA: 07.00am-16.00 pm) 105.57
7.01.01 OPERARIO H 9 6.75 60.75
7.01.02 PEN H 9 4.98 44.82
7.02 EQUIPO 2040.57
7.02.01 EXCAVADORA 336 D H 9 98.73 888.57
7.02.02 MOTONIVELADORA KOMATSU H 9 77.00 693.00
7.02.03 RODILLO H 9 51.00 459.00
8 DIA LUNES 09/10/17 1972.92
8.01 MANO DE OBRA/ (ENCARGADO: ELADIO VASQUEZ SUAREZ-HORA: 06.00am-18.00 pm) 81.00
8.01.01 OPERARIO H 12 6.75 81.00
8.02 EQUIPO 1891.92
8.02.01 MOTONIVELADORA KOMATSU H 12 77.00 924.00
8.02.02 RODILLO H 12 51.00 612.00
8.02.03 CISTERNA DE AGUA H 12 29.66 355.92
9 DIA MIERCOLES 11/10/17 1520.79
9.01 MANO DE OBRA/ (ENCARGADO: ELADIO VASQUEZ SUAREZ-HORA: 08.45am-18.00 pm) 62.44
9.01.01 OPERARIO H 9.25 6.75 62.44
9.02 EQUIPO 1458.36
9.02.01 MOTONIVELADORA KOMATSU H 9.25 77.00 712.25
9.02.02 RIDOLLO H 9.25 51.00 471.75
9.02.03 CISTERNA DE AGUA H 9.25 29.66 274.36
DETALLE VALORIZACIN DE EQUIPOS Y PERSONAL PARA EJECUCIN DE CAMPAMENTO
PROYECTO HIDROELECTRICO MANTA FASE 1
(VALORES EXPRESADOS EN USD$ SIN IGV)

ITEM DESCRIPCIN UNID CANT


1 DA VIERNES 22/09/17
1.01 MANO DE OBRA/ (ENCARGADO: ELADIO VASQUEZ SUAREZ-HORA: 15.00pm-18.00 pm)
1.01.01 CAPATAZ H 3
1.01.02 OPERARIO H 3
1.02 EQUIPO
1.02.01 CAMA BAJA + TRACTOR H 3
1.02.02 EXCAVADORA CAT. 336 H 3
1.02.03 MARTILLO HIDRAULICO H 3
2 DIA SABADO 23/09/17
2.01 MANO DE OBRA/ (ENCARGADO: ELADIO VASQUEZ SUAREZ-HORA: 07.00am-16.00 pm)
2.01.01 CAPATAZ H 8
2.01.02 OPERARIO H 8
2.01.03 PEN H 8
2.01.04 PEN H 8
2.01.05 PEN H 8
2.01.06 PEN H 8
2.02 EQUIPO
2.02.01 CAMA BAJA + TRACTOR H 8
2.02.02 EXCAVADORA CAT. 336 H 8
2.02.03 MARTILLO HIDRAULICO H 8
3 DIA LUNES 25/09/17
3.01 MANO DE OBRA/ (ENCARGADO: ELADIO VASQUEZ SUAREZ-HORA: 07.00am-16.00 pm)
3.01.01 CAPATAZ H 8
3.01.02 PEN H 8
3.01.03 PEN H 8
3.01.04 PEN H 8
3.02 EQUIPO
3.02.01 -------------
4 DIA MARTES 26/09/17
4.01 MANO DE OBRA/ (ENCARGADO: ELADIO VASQUEZ SUAREZ-HORA: 08.00am-16.00 pm)
4.01.01 CAPATAZ H 7
4.01.02 OPERARIO H 7
4.01.03 OPERARIO H 7
4.01.04 PEN H 7
4.01.05 PEN H 7
4.02 EQUIPO
4.02.01 MOTONIVELADORA KOMATSU H 7
4.02.02 RODILLO H 7
5 DIA MIERCOLES 27/09/17
5.01 MANO DE OBRA/ (ENCARGADO: TOMAS VALDERRAMA-HORA: 07.00am-16.00 pm)
5.01.01 CAPATAZ H 8
5.01.02 OPERARIO H 8
5.01.03 OPERARIO H 8
5.01.04 PEN H 8
5.01.05 PEN H 8
5.01.06 PEN H 8
5.01.07 PEN H 8
5.01.08 PEN H 8
5.02 EQUIPO
5.02.01 EXCAVADORA CAT 336 H 8
6 DIA VIERNES 29/09/17
6.01 MANO DE OBRA/ (ENCARGADO: JUAN C. HUALLA-HORA: 07.00am-16.00 pm)
6.01.01 CAPATAZ H 8
6.01.02 OPERARIO H 8
6.02 EQUIPO
6.02.01 EXCAVADORA CAT. 336 DL H 8
6.02.02 EXCAVADORA CAT 320 DL H 8
7 DIA SABADO 30/09/17
7.01 MANO DE OBRA/ (ENCARGADO: -HORA: 07.00am-16.00 pm)
7.01.01 OPERARIO H 8
7.01.02 PEN H 8
7.02 EQUIPO
7.02.01 EXCAVADORA 336 D H 8
7.02.02 MOTONIVELADORA KOMATSU H 8
7.02.03 RODILLO H 8
8 DIA LUNES 09/10/17
8.01 MANO DE OBRA/ (ENCARGADO: ELADIO VASQUEZ SUAREZ-HORA: 06.00am-18.00 pm)
8.01.01 OPERARIO H 11
8.02 EQUIPO
8.02.01 MOTONIVELADORA KOMATSU H 11
8.02.02 RODILLO H 11
8.02.03 CISTERNA DE AGUA H 11
9 DIA MIERCOLES 11/10/17
9.01 MANO DE OBRA/ (ENCARGADO: ELADIO VASQUEZ SUAREZ-HORA: 08.45am-18.00 pm)
9.01.01 OPERARIO H 8.25
9.02 EQUIPO
9.02.01 MOTONIVELADORA KOMATSU H 8.25
9.02.02 RIDOLLO H 8.25
9.02.03 CISTERNA DE AGUA H 8.25
N DE CAMPAMENTO

P. UNIT P. TOTAL
492.36
46.17
8.64 25.92
6.75 20.25
446.19
25.00 75.00
98.73 296.19
25.00 75.00
1472.32
282.48
8.64 69.12
6.75 54
4.98 39.84
4.98 39.84
4.98 39.84
4.98 39.84
1189.84
25.00 200.00
98.73 789.84
25.00 200.00
188.64
188.64
8.64 69.12
4.98 39.84
4.98 39.84
4.98 39.84

1120.7
224.7
8.64 60.48
6.75 47.25
6.75 47.25
4.98 34.86
4.98 34.86
896
77.00 539.00
51.00 357.00
1166.16
376.32
8.64 69.12
6.75 54
6.75 54
4.98 39.84
4.98 39.84
4.98 39.84
4.98 39.84
4.98 39.84
789.84
98.73 789.84
1461.28
123.12
8.64 69.12
6.75 54
1338.16
98.73 789.84
68.54 548.32
1907.68
93.84
6.75 54
4.98 39.84
1813.84
98.73 789.84
77.00 616.00
51.00 408.00
1808.51
74.25
6.75 74.25
1734.26
77.00 847.00
51.00 561.00
29.66 326.26
1356.38
55.69
6.75 55.69
1300.70
77.00 635.25
51.00 420.75
29.66 244.70