Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
AJ ENGINEERING DEPATMENT
Lakhs
IMPORTANT INPUT DATA FOR AUTO LINKS
Memo No. AEE / DEE- I /MEDAK / NABARD RIDF XXI /Chinnakodur /Kasturipally/ 2015,
dt: -04-2016
Sub : Medak Dist - NABARD RIDF XXI - C/o Low Level Causeway on Road from
Kasturipally to Obulapur of Chinnakodur (M) in Medak District, Estt.Cost.Rs.90.00
LakhsOAS and Administrative clearance of Rs.160.00 Lakhs - Accorded
Technical Approval for Rs.160.00 Lakhs - Copy communicated Regarding.
*****
The work '' C/o Low Level Causeway on Road from Kasturipally to Obulapur of
Chinnakodur (M) in Medak District, Estt.Cost.Rs.90.00 LakhsOAS and Administrative
clearance of Rs.160.00 Lakhs - Accorded Technical Approval for Rs.160.00 Lakhs
The approval is accorded subject to the following conditions and on the responsibility
of the Superintending Engineer, P.R, Medak.
1) The SE,PR,Medak is instructed to inspect the site before laying foundation concrete
and check the alignment of bridge i.e., Piers & abutments and Check dam
simultaneously
2) Ensure that the crossing is Right angle crossing (without Skew) as the bridge is
designed without skew.
3) SBC of t/m2 is considered for bridge design as per the soil test report submitted by
SE. If any change is observed in SBC of soil at foundation level, then bring to the
notice to the Chief Engineer, before proceeding the further execution.
4) Get the design mixes approved well in advaqnce in any standard QC Lab or
Reputed/Recognised Engineering college before concreting.
5) Get all the materials used for construction may be checked for quality control test.
6) It is requested to finalise the land acquisition, forest clearance and shifting of electric
poles by duly addressing District collector, DFO & TSCPDCLauthority.
7) The work shall be executed with the provisions stipulated in the bridge codes of IRC
5,6,21,78 & 89 and SP -13- 2004 & SP20.
8) Record the SBC of the soil at locations of Piers & abutments in M Book before
execution of the foundation concrete.
9) If any deviations are observed over the sanctioned estimate, the working estimate
shall be submitted to this office within 1 month from the date of agreement/
grounding. The deviations should be taken up only after prior approval of the
undersigned.
Technical sanction is given for Tender Purpose only. Get the designs proof checked
and approved before grounding the work.
Encl: As above
Chief Engineer,
To, PR, Hyderabad.
The Superintending Engineer, PR Circle, Medak.
//t.c.f.b.o//
Submitted Sir,
Please peruse the reference cited wherein the SE (PR), has submitted estimate for the
work "C/o Low Level Causeway on Road from Kasturipally to Obulapur of Chinnakodur (M) in Medak
District , Estt. Cost. Rs.160.00 Lakhs" for according technical approval. The details are as
follows.The OAS of this work was sanctioned for Rs.90.00Lakhs
Bridge Details
10 Administartive sanction Ref. No. & date GO RT No:718 of PR & RD (Progs-I) Dept. dt. 04.12.2015.
A) Bridge Details
1) Hydraulic Particulars
Discharge in Cumecs
MFL +99.360 M
R.C.L +101.300 M
2) Bridge Provisions
i) Foundations Open foundation in VRCC M25 grade concrete are proposed.
Bed Blocks over Piers Bed Blocks are proposed in VRCC M25 grade as per drawing.
Bed Blocks & Backing walls Bed Blocks & Backing walls are proposed in VRCC M20 grade concrete as per
drawing.
Filling behind Abutment Good Gravel as per as per Clause 710.1.4 of IRC : 78 and as per MoRT&H
Specification No. 2200 (4th Revision)
Bridge Length The total bridge length from back to back of backing walls is M
3) Protection works :-
Stone Revetment No Protection work as the foundation with Isolated Footings
B) Approach Road Details
Check dam proposed along with the above CD work in sub-estimate which is
C) Check dam Details costing Rs.5637790.00
For the work Revised Administrative Clearance is accorded for Rs.90.00 lakhs+addl.
Amount of Rs.70.00 lakhs(Rs.160.00 lakhs), Vide GO RT No: 285 of PR & RD (Progs
II) Dept. dt. 12.04.2016 under NABARD - RIDF Tranche XXI.
Since only Revised Administrative clearance received and still Revised Administrative
Sanction has to be accorded by the Government the matter was discussed with the
Chief Engineer PR(NABARD) regarding, whether to putup the scrutinised Estimate to
the extent of OAS of RS.90.00 Lakhs only.The Chief Engineer PR(NABARD) has
instructed that since Revised Administrative clearance is issued by the Govt. the
estimate to be put up to the extent of Rs.160.00 Lakhs for Technical approval as well
as to call for tenders for the Revised Administrative clearance amount of Rs.160.00
Lakhs.
If agreed, the estimate will be scrutinized as per the above provisions submitted by
the SE, PR, Medak and will be put up for according Technical Approval along with
Schedule-A & Schedule-B. for Rs.160.00 Lakhs.
Amount
Sl.No Description (Rs.)
Part - A
13638963.00
TOTAL
Part - B
The Estimate is put up for Technical Approval for Rs. 160.00 lakhs.
The datas for Bridge, Checkdam & Approaches are scrutinised and
put up for approval and the Schedule-A along with Estimate is put
up for approval.
1 2 3 4
1 Earth work in excavation of foundation of structures as per drawing and
technical specification, including settingout, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing of sides
and bottom and back filling with approved material as per MORT&H
specification no.304 in ordinary soils upto SDR soils using Machinery.
2 PCC (1:3:6) mix using 40mm size HBG Machine crushed stone aggregate
and fine aggregate conforming to table 1000-2 of MoRT&H including cost
and conveyance of all materials to site and labour charges for centering,
machine mixing, laying, Vibrating, curing etc., including all other incidental
and operational charges of all T&P (excluding Seignorage charges) etc.,
complete for finished item of work as per MoRT&H specification 1500,1700,
2100 (4th Revision) and as directed by the Engineer-in-Charge for
foundations for levelling course.
Abutment 11.937
Pier 9.672
Return wall 0.000
21.609 cum 5030.04 /Cum
Sl. Rate
No DESCRIPTION Quantity
1 2 3 4
4 Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and
10mm size HBG crushed stone aggregate (Coarse aggregate conforming to
table 1000-1 and fine aggregate conforming to table 1000-2) including
cost,and conveyance of all materials to site and all labour charges for
machine mixing,laying in position, Compacting , Vibrating and curing
including all other incidental and all other operational charges of T&P
required etc., complete as per MoRT&H Specification 1500,1700, 2100 (4th
Revision) for footings.
Abutment 0.000
Pier 0.000
Return wall 0.000
0.000 cum 5589.17 /Cum
5 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including other incidental hire and operational charges
of all T&P as per approved drawings and as directed during execution but
excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as
directed by the Engineer-in-Charge for Footings/Guide Stone
Abutment 0.000
Pier 0.000
Return wall 0.000
0.000 cum 5757.43
6 Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including other incidental hire and operational charges
of all T&P as per approved drawings and as directed during execution but
excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as
directed by the Engineer-in-Charge for footings.
Abutment 73.726
Pier 66.520
Return wall 0.000
140.246 cum 6154.45
Sl. Rate
No DESCRIPTION Quantity
1 2 3 4
7 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and
10mm size HBG crushed stone aggregate (Coarse aggregate conforming to
table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
and conveyance of all materials to site and all labour charges for machine
mixing, laying in position,Compacting, Vibrating and curing including all other
incidental and all other operational charges of T&P required etc., complete as
per MoRT&H Specification 1500,1700, 2200 (4th Revision) for Sub structure.
Abutment 0.000
Pier 0.000
Return wall 0.000
0.000 cum 5320.24
Abutment 0.000
Pier 0.000
Return wall/Wing walls 0.000
0.000 cum 6507.12
9 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including other incidental hire and operational charges
of all T&P as per approved drawings and as directed during execution but
excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as
directed by the Engineer-in-Charge Sub structure
Abutment 0.000
Pier 0.000
Return wall/Wing walls 0.000
0.000 cum 6702.89
Sl. Rate
No DESCRIPTION Quantity
1 2 3 4
10 Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including other incidental hire and operational charges
of all T&P as per approved drawings and as directed during execution but
excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as
directed by the Engineer-in-Charge Sub structure.
Abutment 36.616
Pier 4.765
Return wall/Wing walls 29.607
For Hammer Head, Bed blocks & Backing walls 0.000
70.988 cum 7164.80
11 Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including other incidental hire and operational charges
of all T&P as per approved drawings and as directed during execution but
excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as
directed by the Engineer-in-Charge.For Pier cap & Bearing pedestals(or
Substructure)
12 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including other incidental hire and operational charges
of all T&P as per approved drawings and as directed during execution but
excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as
directed by the Engineer-in-Charge. For Super structure - for Deck Slab
1 2 3 4
13 Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including other incidental hire and operational charges
of all T&P as per approved drawings and as directed during execution but
excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as
directed by the Engineer-in-Charge. For Super structure - for Deck Slab
14 VRCC M 30 grade using 20mm & 10mm HBG machine crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost and conveyance of all materials to
site and labour charges for centering, machine mixing, laying, vibrating,
curing etc., including other incidental hire and operational charges of all T&P
(excluding seignorage charges) as per approved drawings and as directed
during execution but excluding cost of steel and its fabrication charges for
finished item as per MoRT&H specification 1500,1600,1700 & 2200 (4th
revision ) and as directed by the Engineer-in-Charge for Bearing Pedestal.
15 Suplying ,fitting and fixing in position true to line and level elastomeric
neoprene bearing confirming to IRC: 83 (Part -II ) ,section IX and Clause
2005 of MoRTH Specifications complete including all accessories as per
drawing and Technical Specifications and MORTH Spn.2000 & 2200 Bearing
size 500x360x99mm
1 2 3 4
17 Vibrated reinforced cement concrete M.30 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including all other incidental and operational charges of
all T&P etc., complete for finished item of work as per Approved drawing,
excluding cost of steel and its fabrication charges as per MoRT&H
specification 1500, 1600,1700, & 2704 (4th Revision) and as directed by
the Engineer-in-Charge for Approach slab.
18 Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including all other incidental and operational charges of
all T&P etc., complete for finished item of work as per drawing but excluding
cost of steel and its fabrication charges as per MoRT&H specification 1500,
1600,1700, & 2702 (4th Revision) and as directed by the Engineer-in-
Charge for wearing coat over Deck slab.
1 2 3 4
20 Providing HYSD bars (Fe-500 from Primary Producers like
TATA,SAIL,VSP,Jindal etc.) of different diameters, wrought and put up bars of
all diameters including cost and conveyance of steel to site and all labour
charges for fabrication of reinforcement including cutting, bending, binding
rods, tying grills, placing them in position etc., complete including cost and
conveyance of binding wire and all handling charges and operational charges
etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H specification 1600
&2200 (4th revision) and as per I.S.1786 of 1985 for Super structure of
R.C.C items.
26.000 MT 54284.11 /MT
23 Providing Grouted Revetment with rough stone (HBG) of not less than 300
mm size grouted with 0.20 cum of CC (1:4:8) including cost of conveyance of
materials to site and including labour charges for packing the stones for
revetment etc., complete for finished item of work as per MoRT&H
specification 2504 (4th revision) and as directed by the Engineer-in-Charge
for quadrential revetment.
1 2 3 4
24 Rough stone revetment using rough stone of not less than 300 mm size and
quarry spall including cost and conveyance of all materials to site and labour
charges for packing the stones for revetment (Excluding seignorage charges)
etc., complete for finished item of work as per MoRT&H specification 2504
( 4th revision ) and as directed by the Engineer-in-Charge .
25 Providing and laying filter material with carted Gravel underneath pitching in
slopes including cost and conveyance of all materials to site including labour
charges (Excluding seignorage charges) etc., complete for finished item of
work as per MoRT&H Specification 2504 (4th Revision) and as per MOST
specification Nos. 305,309 & 2504 and as directed by the Engineer-in-
Charge.
26 Back filling behind Abutments with carted gravel including cost and
conveyance and of all materials to site (Excluding seignorage charges) etc.,
complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H
Specification No. 2200 (4th Revision) and as per Drawing and technical
specifications for finished item of work
1 2 3 4
29 Supply and fixing of Drainage Spouts complete as per drawing and Technical
specification No. 2705. (As per Data communicated vide Circular Memo No.
D&P/Bridge work estimates/Non SSR Items/rates/2009-1 Dt 13-08-09 of the
Chief Engineer (R&B), Designs & Planning wing,) Hyderabad.
Total
ram to Manchyathanda via Suryanaikthanda in
uryapet District
Amount
36629
0
108694
Amount
863137
Amount
0
Amount
508615
230464
0
Amount
925754
5242
101761
48552
Amount
103385
133350
43466
Amount
1411387
320883
261693
159221
Amount
22962
63361
52990
5006
Amount
20439
236737
48726
50000
500
5762955
ABSTRACT ESTIMATE FOR ROAD FURNITURE
Providing BT on R/F Bandaramaram to Manchyathanda via Suryanaikthanda in
Suryapet District
Ordinery KM Stone
4 1962.13 / No. 7849.00
Providing and fixing of semi reflective cautionary, mandatory and informatory sign board
as per IRC:67 made of 1.5 mm thick MS Sheet duly stove white colour in front and gray
colour on back with red reflective border of 65 mm width and required letters and figures
with reflective tape engineering grade as per Clause 1701.3.9 of MORD for Rural Roads
of required shade and colour supported and welded on 47 mm x 47 mm 12 SWG sheet
tube firmly fixed to the ground by means of properly designed foundation with M15
2 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as
per drawings and Technical Specification Clause 1701 MORD ,including overhead
charges & Contractors profit ,But Exculding VAT & Seignarage charges.
Providing and fixing of typical SDF informatory and Name Board with necessary Logo
as per specifications and drawing. Three MS Plates of 1.6 mm thick, top and middle
plate duly welded with MS flat iron 25mm x 5m size on back on edges. The lower plate
will be we welded with MS angle irone frame of 25 mm x 25 mm x 5 mm. The angle iron
frame of the lower most plate and flat iron frame of middle plate will be welded to 2 nos.
75 mm x 75 mm of 12 SWG sheet tubes posts duly embedded in cement concrete M-15
grade blocks of 450 mm x 450 mm x 600 mm, 600 mm below ground level. The top
most diamond plate will be welded to middle plate by 47 mm x 47mm of 12 SWG sheet
3 tube. All M.s. will be stove enameled on both sides. Lettering and printing arrows,
border etc., will be pointed with ready mixed synthetic enamel paint of superior quality in
required shade and colour. All sections of framed posts and steel tube will be painted
with primer and two coats of epoxy paint as per drawing clause 1701 MORD ,including
overhead charges & Contractors profit ,But Exculding VAT & Seignarage charges.
Information Sign
2 8951.03 / No. 17902.00
board
S.No Description L B D Quantity Rate Amount
Providing and erecting direction and place identifications of semi reflective sign boards
as per IRC:67 made of 2 mm thick M.S. Sheet duly stove enameled paint in white colour
in front and grey colour on back with red reflective border of 70 mm width and required
message, letters, figures with reflective engineering grade tape as per MORD
specifications of required shade and colour. supported and welded on 47 mm x 47 mm
of 12 SWG Square tube of 3050 mm height duly strengthened by 25 mm x 5 mm M/s
flat iron on edges on back firmly fixed to the ground by means of properly designed
4 foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm
below ground level as per drawings and Technical Specification Clause 1701
MORD.,including overhead charges & Contractors profit ,But Exculding VAT &
Seignarage charges.
Place identification
board(1000 x 900) 4 2063.56 / No. 8254.00
ROAD ITEMS
Total 60358.00
Total 890651.00
ABSTRACT ESTIMATE
PART - A
Index-code Amount
S. No Description Unit Quantity Rate Rs. Rs.
1 2 3 4 5 6
Allowances Made
Over heads & Contractor's Profit 13.615%
Add 20% MAA / AA 0.00%
Sub Analysis
RBR- 24 Supplying, fitting and placing HYSD bar reinforcement in foundation complete as
FNDN-7 per drawings and technical specifications Clauses 1000 and 1202 MORD & 1100,
1600 MORTH for Bars below 36 mm dia including over laps and wastage, where
they are not welded.
Unit = t
(a) Material
HYSD bars including 5 per cent for overlaps t 1.05 39000.00 40950.00
and wastage
Binding wire kg 6.00 0.00
(b) Labour for cutting, bending, shifting to site,
tying and placing in position
Mate day -
Blacksmith day 2.00 445.00 890.00
Mazdoor (Unskilled) day 6.40 350.00 2240.00
Add 20% MAA / AA 0.00% 0.00
c&d) Overheads & Contractors Profit 0.00% 0.00
Rate per t = a+b+c+d 44080.00
RBR- 25 Earthwork in excavation for structures as per drawing and technical specifications
FNDN-1 Clause 305.1 including setting out, construction of shoring and bracing, removal of
stumps and other deleterious material and disposal upto a lead of 50 m, dressing of
sides and bottom and backfilling in trenches with excavated suitable material as per
Technical Specification 305 MORD / 304 MORTH ,including overhead charges &
Contractors profit ,But Exculding VAT & Seignarage charges.
P.C.C grade M 10
Nominal mix 1:3:6
Unit = cum
(a) Material
Cement t 0.22 6000.00 1320.00
Coarse sand cum 0.45 855.74 385.08
40 mm aggregate cum 0.90 1132.39 1019.16
Water kl 1.20 0.00 0.00
(b) Labour
RBR-TSRA
Index-code Amount
S. No Description Unit Quantity Rate Rs. Rs.
1 2 3 4 5 6
Mate day -
Mason (1st Class) day 0.10 445.00 44.50
Mazdoor (Unskilled) day 1.39 350.00 486.5
Add 20% MAA / AA 0.00% 0.00
(c) Machinery
Mechanical concrete mixer 0.4/0.28 cum hour 0.40 472.60 189.04
capacity fitted with water measuring device and
preferably also with load cell.
Water tanker 6 kl capacity hour 0.13 624.00 81.12
3525.40
e&f) Overheads & Contractors Profit 0.00% 0.00
Rate per cum = a+b+c+d+e+f 3525.40
Unit = Each
Taking output = one traffic sign
(i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.126 127.40 16.05
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.126 3970.62 500.30
Unit = each
Take Output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.126 127.40 16.05
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.126 3970.62 500.30
Rate per (for sign having area upto 0.9 sqm) 2063.56
= (i+ii+iii+a+b+c+d+e)/ 1no
Unit = each
Taking output = 14 Nos.
RBR-TSRA
Index-code Amount
S. No Description Unit Quantity Rate Rs. Rs.
1 2 3 4 5 6
a) M-15 grade of concrete
As per item No. 5 (i) or (ii) of Chapter 12 cum 3.77 3970.62 14969.22
b) Steel reinforcement @ 5 kg per sqm
As per item No. 6 of Chapter 12 kg 26.32 44.08 1160.19
c) Excavation in soil for foundation
As per item No. 1 of Chapter 11 cum 2.77 127.40 352.90
d) Painting two coats on concrete surface
As per item No.5 of Chapter 10 sqm 11.41 101.75 1160.97
e) lettering on km post (average 12 letters of 10
cm height each)
per cm high per
As per item No. 1 of Chapter 10 letter
1680.00 0.59 995.66
Transportation and fixing
f) Labour
Mate day -
Mason (1st Class) day 1.00 445.00 445.00
Mazdoor (Unskilled) day 7.32 350.00 2562.00
Add 20% MAA / AA 0.00% 0.00
g) Machinery
50 HP Tractor with trolley hour 6.00 422.00 2532.00
h&i) Overheads & Contractors Profit 13.615% 3291.83
j) Cost for 14 Nos. ordinary km stone = 27469.77
(a+b+c+d+e+f+g+h+i)
Rate for each ordinary km stone = j/ 14 1962.13
(iii 200 m / Hectometer stone (precast)
) Unit = each
Taking output = 33 Nos.
a) M-15 grade of concrete
As per item No. 5 (i) or (ii) of Chapter 12 cum 1.58 3970.62 6273.57
b) Steel reinforcement @ 5 kg per sqm
As per item No. 6 of Chapter 12 kg 66.00 44.08 2909.28
c) Excavation in soil for foundation
As per item No. 1 of Chapter 11 cum 1.39 127.40 177.09
d) Painting two coats on concrete surface
As per item No.5 of Chapter 10 sqm 6.27 101.75 637.97
e) lettering on km post (average 1 letter of 10
cm height each)
per cm high per
As per item No. 1 of Chapter 10 letter
330.00 0.59 195.58
Transportation and fixing
f) Labour
Mate day -
Mason (1st Class) day 1.50 445.00 667.50
Mazdoor (Unskilled) day 7.34 350.00 2569.00
Add 20% MAA / AA 0.00% 0.00
g) Machinery
50 HP Tractor with trolley hour 6.00 422.00 2532.00
h&i) Overheads & Contractors Profit 13.615% 2173.22
j) Cost for 33 Nos. 200 m stone = 18135.21
(a+b+c+d+e+f+g+h+i)
Rate for each 200 m stone = j / 33 549.55
RBR- 32 Providing and Fixing ' SDF Project information & Name Board
TSRA-20
RBR-TSRA
Index-code Amount
S. No Description Unit Quantity Rate Rs. Rs.
RBR-
1 2 3 4 5 6
TSRA-20 Providing and fixing of typical SDF informatory and Name Board with necessary Logo as per
specifications and drawing. Three MS Plates of 1.6 mm thick, top and middle plate duly welded with
MS flat iron 25mm x 5m size on back on edges. The lower plate will be we welded with MS angle
irone frame of 25 mm x 25 mm x 5 mm. The angle iron frame of the lower most plate and flat iron
frame of middle plate will be welded to 2 nos. 75 mm x 75 mm of 12 SWG sheet tubes posts duly
embedded in cement concrete M-15 grade blocks of 450 mm x 450 mm x 600 mm, 600 mm below
ground level. The top most diamond plate will be welded to middle plate by 47 mm x 47mm of 12 SWG
sheet tube. All M.s. will be stove enameled on both sides. Lettering and printing arrows, border etc.,
will be pointed with ready mixed synthetic enamel paint of superior quality in required shade and
colour. All sections of framed posts and steel tube will be painted with primer and two coats of epoxy
paint as per drawing clause 1701 MORD ,including overhead charges & Contractors profit ,But
Exculding VAT & Seignarage charges.
Unit = Each
Taking out put = one typical board
i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.252 127.40 32.10
(ii) Cement Concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.252 3970.62 1000.60
(iii) Painting on MS Steel tubes with primer and two
coats of epoxy paint
2x2.05x.30 = 1.23
1x1.10x188 = 0.21
As per item no. 9 of Chapter 10 sqm 1.80 92.56 166.60
(iv) Printing new letters and figures of any shade with
synthetic enamel paint black or any other approved colour
to give an even shade.
Logo Border 60x4x5 = 1200 per cm height per
letter
Figure 60x10 = 600 per cm height per letter
Middle plate words 28x5 = 140 per cm height per letter
Bottom plate border 150x2x5 = 1500 per cm height per
letter
Bottom plate border 60x2x5 = 600 per cm
height
Words per letter = 252.5
101x2.5
Words 80x3 = 240.00
Total (4532.5 per cm height per letter)
As per item No. 1 of Chapter 10 per cm height /
4532.50 0.59 2686.21
letter
Total
RT ABSTRACT ESTIMATE
Amount
24028
2380040
445581
162900
Amount
3428678
227194
70939
2695940
59184
Amount
301205
1788372
839357
12423416
Providing BT on R/F Bandaramaram to Manchyathanda via Suryanaikthanda in
Suryapet District
1 2 3 4
1 Earth work in excavation of foundation of structures as per drawing and
technical specification, including settingout, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing of sides
and bottom and back filling with approved material as per MORT&H
specification no.304 in ordinary soils upto SDR soils using Machinery.
3 Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including other incidental hire and operational charges
of all T&P as per approved drawings and as directed during execution but
excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as
directed by the Engineer-in-Charge for footings.
1 2 3 4
4 Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including other incidental hire and operational charges
of all T&P as per approved drawings and as directed during execution but
excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as
directed by the Engineer-in-Charge. For Super structure - for check dam
body wall
5 VRCC M 30 grade using 20mm & 10mm HBG machine crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost and conveyance of all materials to
site and labour charges for centering, machine mixing, laying, vibrating,
curing etc., including other incidental hire and operational charges of all T&P
(excluding seignorage charges) as per approved drawings and as directed
during execution but excluding cost of steel and its fabrication charges for
finished item as per MoRT&H specification 1500,1600,1700 & 2200 (4th
revision ) and as directed by the Engineer-in-Charge for Bearing Pedestal.
6 Vibrated reinforced cement concrete M.30 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including all other incidental and operational charges of
all T&P etc., complete for finished item of work as per Approved drawing,
excluding cost of steel and its fabrication charges as per MoRT&H
specification 1500, 1600,1700, & 2704 (4th Revision) and as directed by
the Engineer-in-Charge for Approach slab.
7 Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and
fine aggregate conforming to table 1000-2) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including all other incidental and operational charges of
all T&P etc., complete for finished item of work as per drawing but excluding
cost of steel and its fabrication charges as per MoRT&H specification 1500,
1600,1700, & 2702 (4th Revision) and as directed by the Engineer-in-
Charge for wearing coat over Deck slab.
1 2 3 4
6 Providing HYSD bars (Fe-500 from Primary Producers like
TATA,SAIL,VSP,Jindal etc.) of different diameters, wrought and put up bars of
all diameters including cost and conveyance of steel to site and all labour
charges for fabrication of reinforcement including cutting, bending, binding
rods, tying grills, placing them in position etc., complete including cost and
conveyance of binding wire and all handling charges and operational charges
etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H specification 1600
&2200 (4th revision) and as per I.S.1786 of 1985 for Super structure of
R.C.C items.
18.000 MT 54284.11 /MT
9 Rough stone revetment using rough stone of not less than 300 mm size and
quarry spall including cost and conveyance of all materials to site and labour
charges for packing the stones for revetment (Excluding seignorage charges)
etc., complete for finished item of work as per MoRT&H specification 2504
( 4th revision ) and as directed by the Engineer-in-Charge .
Total
aram to Manchyathanda via Suryanaikthanda in
Suryapet District
Amount
360462
469680
574672
Amount
579843
671366
564539
266701
Amount
977114
1163081
123554
5751012
DETAILED AND ABSTRACT ESTIMATE
Construction of 1 vent 1000 mm dia Pipe Culvert (4 Nos) at 0/2, 0/7 , 1/4 to 1/6, 1/7 Kms
Amount
3400.00
32857.00
95973.00
109971.00
2778.00
244979.00
DETAILED AND ABSTRACT ESTIMATE
Amount
6893.00
49630.00
109957.00
219942.00
3265.00
389687.00
DETAILED AND ABSTRACT ESTIMATE
Amount
8991.00
69198.00
130228.00
329912.00
3996.00
542325.00
SUB ESTIMATE
Providing BT on R/F Bandaramaram to Manchyathanda via Suryanaikthanda in Suryapet District
1 2 3 4 5 6 7 8 9
I Earth work in excavation of foundation of structures as per drawing
and technical specification, including settingout, construction of
shoring and bracing, removal of stumps and other deleterious
matter, dressing of sides and bottom and back filling with approved
material as per MORT&H specification no.304 in ordinary soils upto
SDR soils using Machinery.
1 2 3 4 5 6 7 8 9 10
1 Earth work in excavation of foundation of structures as per drawing and
technical specification, including settingout, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and back filling with approved material as per
MORT&H specification no.304 in ordinary soils upto SDR soils using
Machinery.
Baswapur Village 450 1 x 1 450.00 1.50 0.60 405.00
Kokkonda Village250 1 x 1 250.00 1.50 0.60 225.00
Near Factory 300mts 1 x 1 300.00 1.50 0.60 270.00
900.00 93.93 1Cum 84537.00
Cum
2 PCC (1:3:6) mix using 40mm size HBG Machine crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H
including cost and conveyance of all materials to site and labour
charges for centering, machine mixing, laying, Vibrating, curing etc.,
including all other incidental and operational charges of all T&P
(excluding Seignorage charges) etc., complete for finished item of work
as per MoRT&H specification 1500,1700, 2100 (4th Revision) and as
directed by the Engineer-in-Charge for foundations for levelling course.
1 2 3 4 5 6 7 8 9
I Earth work in excavation of foundation of structures as per drawing
and technical specification, including settingout, construction of
shoring and bracing, removal of stumps and other deleterious
matter, dressing of sides and bottom and back filling with approved
material as per MORT&H specification no.304 in ordinary soils upto
SDR soils using Machinery.
Conveyan
ce Blastin Machine
Sl. Source of Lead in Conveya Toal Cost per
Description of Material excluding Initial cost g crushing
No Supply Kms nce Cum
OH of charges charges
13.615%
1 150 mm IRC Soling Stone (HBG) Thimmapuram 35.00 451.50 397.39 95.00 0.00 492.39
2 40 mm IRC HBG Metal Thimmapuram 35.00 451.50 397.39 500.00 70.00 0.00 967.39
Quarry spall (Field picked metal) Av. of rate
3 Thimmapuram 35.00 451.50 397.39 45.00 0.00 0.00 442.39
25mm & 40mm
4 Rough stone 300 mm Thick Thimmapuram 35.00 451.50 397.39 164.00 0.00 0.00 561.39
5 Jeddy stone 450 to 600mm Thimmapuram 35.00 451.50 397.39 188.00 0.00 0.00 585.39
6 40 mm SS-5 HBG M/C metal Thimmapuram 35.00 451.50 397.39 532.00 70.00 133.00 1132.39
7 25 mm SS-5 HBGT M/C metal Thimmapuram 35.00 451.50 397.39 874.00 70.00 218.50 1559.89
8 20 mm SS-5 HBG M/C metal Thimmapuram 35.00 451.50 397.39 916.00 70.00 229.00 1612.39
9 12 mm SS-5 HBG M/C metal Thimmapuram 35.00 451.50 397.39 822.00 70.00 205.50 1494.89
10 10 mm SS-5 HBG M/C metal Thimmapuram 35.00 451.50 397.39 692.00 70.00 173.00 1332.39
11 6 mm SS-5 HBG M/C metal Thimmapuram 35.00 451.50 397.39 532.00 70.00 133.00 1132.39
12 Sand for concrete Jajireddygudem 25.00 336.00 295.74 560.00 0.00 0.00 855.74
13 Sand for Filling Jajireddygudem 25.00 336.00 295.74 560.00 0.00 0.00 855.74
14 Gravel Local 5.00 84.00 73.93 103.00 0.00 0.00 176.93
BT Emulsion SS 1 (Chennai) - 16th June ST @
15 Chennai 600.00 1800.00 37342.11 1867.11 41009.22
2017 5%=
BT Emulsion RS 1 (Chennai) - 16th June ST @
16 Chennai 600.00 1800.00 24092.28 1204.61 27096.89
2017 5%=
BT (60/70 grade) (Chennai) - 16th June ST @
17 Chennai 600.00 1800.00 29126.76 1456.34 32383.10
2017 5%=
18 6mm MS Rods 39000.00 0.00 0.00 39000.00
19 HYSD Fe 500 TATA,SAIL 41000.00 0.00 0.00 41000.00
May-17
Conveyan
ce Blastin Machine
Sl. Source of Lead in Conveya Toal Cost per
Description of Material excluding Initial cost g crushing
No Supply Kms nce Cum
OH of charges charges
13.615%
20 Cement (OPC) May-17 6000.00 0.00 0.00 6000.00
21 Mild steel 40000.00 0.00 0.00 40000.00
22 Structural Steel 40000.00 40000.00
Conveyan
ce Blastin Machine
Sl. Source of Lead in Conveya Toal Cost per
Description of Material excluding Initial cost g crushing
No Supply Kms nce Cum
OH of charges charges
13.615%
ROAD METAL RATES
Providing BT on R/F Bandaramaram to Manchyathanda via Suryanaikthanda in Suryapet District
23 40 to 45 mm IRC and MoRTH HBG metal Thimmapuram 35.00 451.50 397.39 500.00 70.00 0.00 967.39
40 to 45 mm IRC and MoRTH HBG M/C
24 Thimmapuram 35.00 451.50 397.39 500.00 70.00 125.00 1092.39
metal
25 to 27 mm IRC and MoRTH HBG M/C
25 Thimmapuram 35.00 451.50 397.39 824.00 70.00 206.00 1497.39
metal
19 to 22 mm IRC and MoRTH HBG M/C
26 Thimmapuram 35.00 451.50 397.39 864.00 70.00 216.00 1547.39
metal
12 to 14 mm IRC and MoRTH HBG M/C
27 Thimmapuram 35.00 451.50 397.39 717.00 70.00 179.25 1363.64
metal
9.5 to 11.20 mm IRC and MoRTH HBG M/C
28 Thimmapuram 35.00 451.50 397.39 656.00 70.00 164.00 1287.39
metal
29 5 to 7 mm IRC and MoRTH HBG M/C metal Thimmapuram 35.00 451.50 397.39 504.00 70.00 126.00 1097.39
2.36 to 5 mm IRC and MoRTH HBG M/C
30 Thimmapuram 35.00 451.50 397.39 320.00 70.00 80.00 867.39
metal
31 HBG Stone chips 2.36mm and below Thimmapuram 35.00 451.50 397.39 360.00 0.00 0.00 757.39
32 RCC pipes 1000mm Dia., NP4 Medak 100.00 1153.00 1014.83 8501.90 9516.74
33 RCC Collars 1000mm Dia., NP4 Medak 100.00 1091.33 1091.33
34 Selected earth Local 5.00 84.00 73.93 40.00 0.00 0.00 113.93
(B) Machinery
6.00 Hrs Hydralic excavator 2821.50 cum 16929.00
(C) Seigniorage charges
240.00 Cum Seigniorage charges 0.00 cum 0.00
Unit = cum
Taking output = 15 cum
(A) Labour
0.64 nos Mate 350.00 day 224.00
1.00 nos Mason 405.00 day 405.00
15.00 nos Mazdoor 350.00 day 5250.00
Page 73
S. No Quantity Description of Item Rate per Amount
Add Municipal/ Agency Allowance 0% 5879.00 0.00
Total 5879.00
(B) Material
13.50 cum Cost of 40mm SS-5 HBG M/C metal 1132.39 cum 15287.33
6.75 cum Coarse Sand 855.74 cum 5776.22
3.45 MT Cement at site 6000.00 MT 20700.00
Total 41763.55
(c) Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 472.60 hr 2835.60
6.00 hr Generator set 35 KVA 842.20 hr 5053.20
2.00 hr Water Tanker 6 KL Capacity 624.00 hr 1248.00
9136.80
(D)
13.615 %
Over head charges and Contractors Profit @ 13.615% on
(A)+(B)+( C) 7730.51
(E) Total of (A) + (B)+( C)+(D) 64509.86
Cost per 15 cum (F)+(G) 64509.86
64509.86
Rate for 1 cum 4300.66
4300.66
Rate to be adopted 4300.66
CUM
15 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to
table 1000-2) including cost,and conveyance of all materials to site and all labour charges for
machine mixing,laying in position, Compacting , Vibrating and curing including all other incidental and
all other operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700,
2100 (4th Revision) for footings
Page 74
S. No Quantity Description of Item Rate per Amount
(D) Form work
4.00 % Form work @ 4% on (A)+(B)+( C) 63854.85 Cum 2554.19
13.615 % Over head charges and Contractors Profit @ 13.615% on(A)+(B)+( C) 9041.59
(F) Total of (A) + (B)+( C)+(D) 75450.63
Cost per 15 cum (F)+(G) 75450.63
75450.63
Rate for 1 cum 5030.04
5030.04
Rate to be adopted 5030.04
1 Cum
16 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, conveyance of all materials to site and labour charges, centering, machine
mixing, laying, vibrating, curing etc., including other incidental hire and operational charges of all T&P
as per approved drawings and as directed during execution but excluding cost of steel and its
fabrication charges for finished item as per MoRT&H specification 1500,1600,1700 & 2200 (4th
revision ) and as directed by the Engineer-in-Charge for Footings/Guide Stone
Page 75
S. No Quantity Description of Item Rate per Amount
5757.43
Rate to be adopted 5757.43
1 Cum
17 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to
table 1000-2) including cost, and conveyance of all materials to site and all labour charges for
machine mixing, laying in position,Compacting, Vibrating and curing including all other incidental and
all other operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700,
2200 (4th Revision) for Sub structure.
Total 48057.55
(c) Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 472.60 hr 2835.60
6.00 hr Generator set 35 KVA 842.20 hr 5053.20
7888.80
(D) Form work
10.00 % Form work @ 10% on (A)+(B)+( C) 63854.85 Cum 6385.49
(E) 0
E 13.615 % Over head charges and Contractors Profit @ 13.615% on 9563.22
(F) Total of (A) + (B)+( C)+(D)+(E) 79803.56
Cost per 15 cum (F)+(G) 79803.56
Rate for 1 cum 5320.24
5320.24
Rate to be adopted 5320.24
1 Cum
18 Providing HYSD bars (Fe-500 from Primary Producers like TATA,SAIL,VSP,Jindal etc.) of different
diameters, wrought and put up bars of all diameters including cost and conveyance of steel to site and
all labour charges for fabrication of reinforcement including cutting, bending, binding rods, tying grills,
placing them in position etc., complete including cost and conveyance of binding wire and all handling
charges and operational charges etc., and including over lapping welding if required etc., complete for
all R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th revision) and as per
I.S.1786 of 1985 for Super structure of R.C.C items.
Page 76
S. No Quantity Description of Item Rate per Amount
Unit = MT Page 489,490 of MoRT&H SDB
Taking output = 1 MT
(A) Labour
0.44 nos Mate 350.00 day 154.00
3.00 nos Black smith 445.00 day 1335.00
8.00 nos Mazdoor 350.00 day 2800.00
Add Municipal/ Agency Allowance 0% 4289.00 0.00
Total 4289.00
(B) Material
1.05 MT HYSD bars including overlaps 41000.00 MT 43050.00
8.00 Kg Binding wire 55.00 Kg 440.00
Total 43490.00
Rate per 1 MT (A)+(B) 47779.00
Deck Slab
Unit = cum Page 474,475 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate 350.00 day 301.00
1.50 nos Mason 405.00 day 607.50
20.00 nos Mazdoor 350.00 day 7000.00
Add Municipal/ Agency Allowance 0% 7908.50 0.00
Total 7908.50
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1612.39 cum 13060.40
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1332.39 cum 7194.93
6.75 cum Coarse Sand 855.74 cum 5776.22
5.99 MT Cement at site 6000.00 MT 35940.00
Total 61971.55
(c) Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 472.60 hr 2835.60
6.00 hr Generator set 35 KVA 842.20 hr 5053.20
Total 7888.80
(D) Form wor25% for Height 5-10M
25.00 % Form work @ 25% on (A)+(B)+( C) 77768.85 Cum 19442.21
Page 77
S. No Quantity Description of Item Rate per Amount
Page 78
S. No Quantity Description of Item Rate per Amount
21 Back filling behind Abutments with carted gravel including cost and conveyance and of all
materials to site (Excluding seignorage charges) etc., complete as per Clause 710.1.4 of IRC :
78and as per MoRT&H Specification No. 2200 (4th Revision) and as per Drawing and technical
specifications for finished item of work
Providing and Laying Reinforced Cement Concrete Pipe NP4 as per design.
22 Providing and laying reinforced cement concrete pipe NP4 for culverts on first class bedding of
granular material including fixing collar with cement mortar 1:2 but excluding excavation, protection
works, backfilling, concrete and masonry works in head wall and parapets. Tech Specification Clause
2900 MoRTH ,including overhead charges & Contractors profit ,But excluding VAT & Seignarage
charges.
Page 79
S. No Quantity Description of Item Rate per Amount
Cost per 12.50 Rmt 137463.47
Rate for 1 Rmt 10997.08
Rate to be adopted 10997.08
1 Rmt
23 1700 Painting Two Coats on New Concrete Surfaces
Painting two coats including primer coat after filling the surface with Cement paint in all shades on
new, plastered / concrete surfaces as per drawing and Technical Specification Clause 1701
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.20 350.00 70.00
Painter (1st Class) day 3.00 515.00 1,545.00
Mazdoor (Unskilled) day 2.00 350.00 700.00
Add Municipal/ Agency Allowance 0% 2315.00 0.00
Total 2,315.00
b) Material
Add for scaffolding @ 1 per cent of labour cost where required 23.15
Total 1,973.15
13.615 %
c) Overheads & Contractors profit @ 13.6150% on (a+b) 583.83
Page 80
39 VRCC M 30 grade using 20mm & 10mm HBG machine crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost and conveyance of all materials to site
and labour charges for centering, machine mixing, laying, vibrating, curing etc.,
including other incidental hire and operational charges of all T&P (excluding
seignorage charges) as per approved drawings and as directed during execution
but excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as directed
by the Engineer-in-Charge for Bearing Pedestal.
Output = 15 cum
Material
6.100 Cement 6,000.00 MT 36,600.00
6.750 Coarse Sand 855.74 m3 5,776.22
8.100 20mm aggregate 1,612.39 m3 13,060.40
5.400 10mm aggregate 1,332.39 m3 7,194.93
62,631.54
Labour
0.860 Mate 405.00 1 348.30
1.500 Mason 405.00 1 607.50
20.000 Mazdoor 350.00 1 7,000.00
0% Add Municipal/ Agency Allowance 7,955.80 0.00
7,955.80
Machinery
6.000 Cncrete mixer 040 / 0.28 cum 472.60 hour 2,835.60
6.000 33 KVA Generater set 842.20 hour 5,053.20
7,888.80
78,476.14
Form work
Height upto 5m
Basic rate for 15 cum of concrete 78,476.14
0.000 % add for extra lift on cost of concrete 78,476.14 0.00
10.000 % add for form work on cost of concrete 78,476.14 7,847.61
Total Rs. 86,323.76
Unit = 1 RM
HAND RAILS WITHOUT FOOT PATHS
Taking output = 2 x 24 = 48.00 mtrs
a) Material
No. of Vertical Posts (2 spans both sides) = (12+2)*2 =28 Nos
Qty of vertical end posts= 28*0.25*0.275*0.77 1.4823 cum
unit = 1Rm
Taking output = 12m
Labour
0.050 Mate 405.00 1 20.25
1.000 Mazdoor 350.00 1 350.00
0.250 Mazdoor (skilled) 405.00 1 101.25
0% Add Municipal/ Agency Allowance 471.50 0.00
471.50
Material
12.000 Rm. Supply of complete assembly of strip seal expansion 5,300.00 1 63,600.00
joint comprsing of egde beams, anchorage, strip seal
element and complete accessories as per approved
specifications and drawings
5.000 % add on cost materials for anchorage reinforcement, 63,600.00 1 3,180.00
welding and other incidents.
66,780.00
Total Rate 67,251.50
13.615 % add Over Head charges 67,251.50 9,156.29
76,407.79
10.000 % add Contractor's profit 76,407.79 7,640.78
84,048.57
0.000 % add for price escalation 84,048.57 0.00
Rate per 12 Rm 84,048.57
Rate per 1 Rm 7,004.05
or say 7,004.05
ROAD DATA - SSR 2016-17
Add Municipal/ Agency Allowance 0%
Over heads & Contractors Profit @ 13.615%
Contractor's profit 10.00%
Unit = 1 sqm
Taking output = 1 hectare
Page 21-22 of MoRT&H SDB
0 (A) Labour
0 0.16 day Mate 350.00 1.00 56.00
0 4.00 day Mazdoor unskilled 350.00 1.00 1400.00
0 1456.00
0 0% Add Municipal/ Agency Allowance 1456.00 0.00
0 TOTAL A= 1456.00
0
0 (B) Machinery
10.00 hour 2561.80 1.00 25618.00
Dozer 80 HP with attachment for removal of trees
&stumps
4.00 hour Tractor - Trolley 415.00 1.00 1660.00
TOTAL B= 27278.00
(C ) Seigniorage charges
100.00 cum Seigniorage charges 0.00 1.00 0.00
C= 0.00
(A + B +C) 28734.00
13.615 % (D) Over Head Charges & Contractors profit @ 28734.00 3912.13
13.615% on (A+B+C)
1 hectare TOTAL Cost for 1 hectare = (A+B+C+D) 32646.13
Construction of embankment with approved materials deposited at site from roadway cutting and
excavation from drain (not exceeding 0.6 m depth) and foundation of other structures graded ,
depositing the soil on the embankment, spreading soil, breaking clods, sectioning, grading and
consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement of table 300-2 of
MoRT&H, including all hire and operational charges of T&P, complete for finished item of work as per
MoRT&H specification 305 (4th revision) (Payment will be made based on levels for finished item of
work).
13.615 % (D) Over Head Charges & Contractors profit @ 8285.80 1128.11
13.615% on (A+B+C)
100.00 cum TOTAL Cost for 100 cum = (A+B+C+D) 9413.91
13.615 % (D) Over Head Charges & Contractors profit @ 14059.71 1914.23
13.615% on (A+B+C)
100.00 cum TOTAL Cost for 100 cum = (A+B+C+D) 15973.94
(C) Material
Coarse graded Granular sub-base material as per
Table 400-2 of MORT&H
9.5-4.75mm IRC & MORT&H HBG Chips @ 66%
255.00 cum Average rate of (9.5-11.2),( 5-7)&(2.36-5) 1084.06 1.00 276435.65
2.36mm and below @34%
129.00 cum Rate of 2.36mm & below HBG metal 757.39 1.00 97703.92
TOTAL C= 374139.57
(A + B +C) 405744.97
13.615 % (D) Over Head Charges & Contractors profit @ 405744.97 55242.18
13.615% on (A+B+C)
300.00 cum TOTAL Cost for 300 cum = (A+B+C+D) 460987.15
Rate per 1 cum 1536.62
Rate per 1 cum 1536.62
SNo Quantity Unit Description of Item Rate per Amount
1 2 3 4 5 6 7
3 Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix
macadam specification including cost, seigniorage of all materials and including premixing the
material with water at OMC in Mechanical mix plant carriage of mixed material by tipper to site , laying
in uniform layers with paver in base courses on well prepared surface and compacting with Vibratory
roller to achieve the desired density etc., as directed by the Engineer-in-Charge and as per MoRT&H
specification.406 (4th revision) for finished item of work.
13.615 % (D) Over Head Charges & Contractors profit @ 399542.14 54397.66
13.615% on (A+B+C)
225.00 cum TOTAL Cost for 225 cum = (A+B+C+D) 453939.80
Rate per 1 cum 2017.51
Rate per 1 cum 2017.51
4 Providing and applying Prime Coat with bitumen emulsion (Slow Setting) bulk using emulsion
pressure distributor on prepared surface of Granular base including cleaning of road surface and
spraying emulsion at the rate of 0.60 Kg/sqm using emulsion pressure distributor for finished item of
work etc., complete for finished item of work as per MoRT&H Specification 502 (4th Revision) and as
directed by the Engineer-in-charge.
13.615 % (D) Over Head Charges & Contractors profit @ 91650.32 12478.19
13.615% on (A+B+C)
3500.00 sqm TOTAL Cost for 3500 sqm = (A+B+C+D) 104128.51
Rate per 1 sqm 29.75
Rate per 1 sqm 29.75
5 Providing and applying Tack coat with bitumen Emulsion (Rapid setting -1 ) (Bulk) using Emulsion
pressure distributor at the rate of 0.20 Kgs per sqm on the prepared bituminous/granular surface
cleaned with mechanical broom for finished item of work as per MoRT&H Specification 503 (4 th
revision) and as directed by the Engineer-in-Charge.
5.00 nos. Skilled Mazdoor for checking line and levels. 405.00 1.00 2025.00
7919.00
0% Municipal Area Allowance 7919.00 0.00
TOTAL A= 7919.00
TOTAL
(B) Machinery
6.00 hour Hot mix plant 75/60TPH 21668.00 1.00 130008.00
6.00 hour Generator 250 KVA 1850.00 1.00 11100.00
6.00 hour Front end loader 1 cum capacity 1646.00 1.00 9876.00
6.00 hour Mechanical Paver finisher @ 100 TPH 2249.00 1.00 13494.00
6.00 hour Smooth wheeled roller 8-10 Tonnes 1131.00 1.00 6786.00
TOTAL B= 171264.00
(C) Material
14.97 M.T (i) Bitumen 60/70 Grade @14.60 kg per 10 sqm 32383.10 1.00 484774.94
SNo Quantity Unit Description of Item Rate per Amount
1 2 3 4 5 6 7
276.75 cum Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum 1305.42 1.00 361274.99
per 10 sqm
TOTAL C= 846049.93
(A + B +C) 1025232.93
13.615 % (D) Over Head Charges & Contractors profit @ 1025232.93 139585.46
13.615% on (A+B+C)
10250.00 sqm TOTAL Cost for 10250 sqm = (A+B+C+D+E) 1164818.39
Rate per 1 sqm 113.64
Rate per 1 sqm 113.64
7 Providing and laying bituminous liquid seal coat (Type A) comprising of a layer of bitumuneous binder
followed by a cover of stone chipping of grading as defined in table 500.16 of MOST at of Crushed
stone chipping of 6.7 mm size 100% passing through 11.2mm seive and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm chips to be laid simultaneously along with the bitumunous course
using 9.80 kgs of bitumen 60/70 grade for 10 sqm and rolling with power roller including of required
line, level, grade to serve as wearing course on previously prepared surface and finishing to rquired
level and grades including cost and conveyance of all materials from approved sources and stacking
at site to departmental gauge for premeasurements, labour charges and hire and operational charges
of power road roller 8 to 10 tonnes capacity and all other machinery, tools and plants, providing
barricading for diversion of traffic, erecting red flags other incidental and operational charges etc.,
complete for finished item of work as per technical specification clause 513 of MORTH. excluding VAT
and Seignorage and including Over head charges & contractors profit etc., complete. Using Hot mix
plant
13.615 % (D) Over Head Charges & Contractors profit @ 474235.25 64567.13
13.615% on (A+B+C)
10250.00 sqm TOTAL Cost for 10250 sqm = (A+B+C+D) 538802.38
Rate per 1 sqm 52.57
Rate per 1 sqm 52.57
SNo Quantity Unit Description of Item Rate per Amount
1 2 3 4 5 6 7
8 Providing and laying bituminous premixed Seal coat (Type B) comprising of a thin application of fine
aggregate premixed with bituminous binder of grading as defined in table 500.16 of MOST at of
Crushed sand defined as passing through 2.36 mm sieve and retained on 180 micron seive applied @
0.06 cum per 10 sqm. chips to be laid simultaneously along with the bitumunous course using 6.80
kgs of bitumen 60/70 grade for 10 sqm and rolling with power roller including of required line, level,
grade to serve as wearing course on previously prepared surface and finishing to rquired level and
grades including cost and conveyance of all materials from approved sources and stacking at site to
departmental gauge for premeasurements, seigniorage, labour charges and hire and operational
charges of power road roller 8 to 10 tonnes capacity and all other machinery, tools and plants,
providing barricading for diversion of traffic, erecting red flags other incidental and operational charges
etc., complete for finished item of work as per technical specification clause 513 of MORTH Using Hot
mix plant excluding VAT and Seignorage and including Over head charges & contractors profit etc.,
complete
13.615 % (D) Over Head Charges & Contractors profit @ 267708.46 36448.51
13.615% on (A+B+C)
7858.00 sqm TOTAL Cost for 7858 sqm = (A+B+C+D+E) 304156.97
Rate per 1 sqm 38.71
Rate per 1 sqm 38.71
5 Providing, laying and rolling of built-up spray grout layer over prepared base consisting of a two
layer composite construction of crushed coarse aggregates using motor grader for aggregates. Key
stone chips spreader may be used with application of bituminous binder after each layer, and with key
aggregates placed on top of the second layer to serve as a base, conforming to the line, grades and
cross-section specified, the compacted layer thickness being 75 mm as per Technical Specification
Clause 506 MORTH. (using Three wheel 80-100 KN static Roller/ Vibratory Roller 80-100 kN).
including overhead charges & Contractors profit but excluding VAT and seionarage Charges.
TOTAL C= 714650.13
(A + B +C) 773914.67
13.615 % (D) Over Head Charges & Contractors profit @ 773914.67 105368.48
13.615% on (A+B+C)
3000.00 sqm TOTAL Cost for 3000 sqm = (A+B+C+D+E) 879283.15
Rate per 1 sqm 293.09
Rate per 1 sqm 293.09
7 Providing and laying Dense graded bituminous Macadam with 40 - 60 TPH batch type HMP
producing an average output of 32.5 tonnes per hour using crushed aggregates of specified grading,
premixed with bituminous binder @ 4.0 to 4.5 per cent of mix and filler, transporting the hot mix to
work site, laying with a Mechanical paver finisher to the required grade, level and alignment, rolling
with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH
specification clause No. 507 complete in all respects, including overhead charges & Contractors profit
but excluding VAT and seinorage Charges. .
5.00 nos. Skilled Mazdoor for checking line and levels. 417.00 1.00 2085.00
7979.00
SNo Quantity Unit Description of Item Rate per Amount
1 2 3 4 5 6 7
0% Municipal Area Allowance 7979.00 0.00
TOTAL A= 7979.00
TOTAL
(B) Machinery
11.00 hour HMP 40-60 TPH 19120.00 1.00 210320.00
6.00 hour Mechanical Paver finisher @ 100 TPH 2249.00 1.00 13494.00
13.615 % (D) Over Head Charges & Contractors profit @ 1211822.79 164989.67
13.615% on (A+B+C)
195.00 Cum TOTAL Cost for 195 Cum = (A+B+C+D+E) 1376812.46
Rate per 1 Cum 7060.58
Rate per 1 Cum 7060.58
8 Providing and laying Semi dense bituminous concrete with 40- 60 TPH batch type HMP producing
an average output of 32.5 tonnes per hour using crushed aggregates of specified grading, premixed
with bituminous binder @ 4.5 to 5 per cent of mix and filler, transporting the hot mix to work site,
laying with a Mechanical paver finisher to the required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH
specification clause No. 508 complete in all respects, including overhead charges & Contractors profit
but excluding VAT and seinorage Charges. .
13.615 % (D) Over Head Charges & Contractors profit @ 1223313.03 166554.07
13.615% on (A+B+C)
195.00 Cum TOTAL Cost for 195 Cum = (A+B+C+D+E) 1389867.10
Rate per 1 Cum 7127.52
Rate per 1 Cum 7127.52
8 Construction of improved subgrade/ Shoulders by providing selected earth having minimum CBR of
10%, MDD not less than 1.85 g/cc with LL & PI not more than 40% and 20 respectively and spreading
in uniform layers with tractor grader on prepared surface, and compacted at OMC with vibratory roller
80-100 kN to meet requirement of Table 300.2 with as per Technical Specification Clause 408
MORTH, by using machinery excluding VAT and Seignorage and including Over head charges &
contractors profit etc., complete
(C) Material
300.00 cum Selected earth 113.93 1.00 34180.17
TOTAL C= 34180.17
(A + B +C) 65763.57
13.615 % (D) Over Head Charges & Contractors profit @ 65763.57 8953.71
13.615% on (A+B+C)
300.00 cum TOTAL Cost for 300 cum = (A+B+C+D+E) 74717.28
Rate per 1 cum 249.06
Rate per 1 cum 249.06
Unit = cum
Taking output = 75cum (172.50 t)
(100x3.75 x 0.200)
a) Labour
Mason (1st class) day 5 445 2,225.00
Mason (2nd class) day 5 405 2,025.00
Mazdoor (unskilled) day 150 350 52,500.00
Mazdoor(skilled) day 6 417 2,502.00
Surveyor day 2 650 1,300.00
Mazdoor (semi-skilled) day 6 400 2,400.00
Black smith for cutting of dowel bars including removal of bday 1 445 445.00
63397.00
0% Municipal Area Allowance 0.00
b) Machinery
Concrete mixer 0.28/0.40 cum capacity ( 6 17,013.60
mixers) with weight batcher and suitable
capacity calibrated water tank Hour 36 472.6
Needle vibrator Hour 9 184 1,656.00
Screed vibrator Hour 9 0 0.00
Plate vibrator Hour 9 48 432.00
Water tanker 6 Kl. Capacity Hour 5 624 3,120.00
Air compressor ( 1hour initial + 1 hour final) Hour 2 530.4 1,060.80
c) Material
Crushed stone coarse aggregates, grading will be as per clause
1501.2.4.1 (Table 1500.1) of specifications @ 0.90 Cum/cum of
(I) concrete
20mm Cum 44.55 1612.39 71,832.18
10mm Cum 22.95 1332.39 30,578.46
(ii) Sand as per IS:383 and conforming to clause 1500.2.4.2. cum 33.75 855.74 28,881.08
(iii) Cement @ 350 Kg/cum of concrete t 26.25 6000.00 157,500.00
(iv) Polythene sheet 125 micron sqm 412.5 18.00 7,425.00
Mild steel dowel bar 25mm dia of grade S 240.500 mm long 20 Nos. at culvert/bridge slab and at
construction joiont including 5 percent wastage
(v)
(4x20x0.500) + 5 per cent wastage = 42m @3.854 Kg perKg 161.91 40.00 6,476.40
Bitumen primer @ 200ml. Per joint for 23 joints t 0.005 41009.22 205.05
Bitumenous sealant 800 ml. Per joint for 23 joints Litre 19 85.00 1,615.00
Jute rope 12mm dia including 5 per cent wastage m 90 8.75 787.50
Debonding strips 3.75m. (length) x 10mm (width) x 5 mm (thi
m 90 11.00 990.00
Polythene sheathing, covering 2/3rd dowel bars (20x23) and
No 483 0.50 241.50
Plasticizer 0.5 per cent by weight of cement Litre 122 85.00 10,370.00
Water for curing kl 18 0.00 0.00
Joint filler board 20mm thick as per IS:1838 sqm 3 804.00 2,412.00
SNo Quantity Unit Description of Item Rate per Amount
1 2 3 4 5 6 7
(4x3.75x0.200 = 3 sqm)
Total (a+b+c) 405993.57
(d) Form work @ 3% on (a+b+c) 12179.81
Cost for 75 cum = a+b+c+d 418173.38
Rate per Cum = (a+b+c+d)/75 5575.65
(e) Over head charges & Contractors profit @13.615%- 759.12
6334.77
Rate per Cum 6334.77
12 Scarifying the existing granular road surface to a depth of 50 mm and disposal of scarified material
with all lifts and lead upto 1000 m as per Technical Specification Clause 305.4.3 MORTH including
contractors profit & Over head charges, VAT.
Amount
7