Installation & Commissioning Sheet

_______________________________________________________________________________________

Installation Details

Customer Name:

Installation Address: City:

Postcode:

Solar Module Brand & No of


Model Number: Modules:

PV Inverter Brand & No of


Model Number: Inverters:

Panel Layout

String 1 String 2 String 3

Tilt Orientation Tilt Orientation Tilt Orientation

Inverter 1

Inverter 2

Inverter 3

String 4 String 5 String 6

Tilt Orientation Tilt Orientation Tilt Orientation

Inverter 1

Inverter 2

Inverter 3
Installation Checklist.

Inverter Tests

Inverter 1

Inverter ceases supplying power within 2 seconds of a loss of AC mains

Inverter does not resume supplying power until mains have been present for more than 120
seconds.

Item Polarity Operating Voltage Operating Current


Check

String 1 - On Roof

String 2 - On Roof

String 3 - On Roof

String 4 - On Roof

String 5 - On Roof

String 6 - On Roof

Array A - At Inverter

Array B - At Inverter
Inverter 2

Inverter ceases supplying power within 2 seconds of a loss of AC mains

Inverter does not resume supplying power until mains have been present for more than 120
seconds.

Item Polarity Operating Voltage Operating Current


Check

String 1 - On Roof

String 2 - On Roof

String 3 - On Roof

String 4 - On Roof

String 5 - On Roof

String 6 - On Roof

Array A - At Inverter

Array B - At Inverter

Inverter 3

Inverter ceases supplying power within 2 seconds of a loss of AC mains

Inverter does not resume supplying power until mains have been present for more than 120
seconds.

Item Polarity Operating Voltage Operating Current


Check

String 1 - On Roof

String 2 - On Roof

String 3 - On Roof

String 4 - On Roof

String 5 - On Roof

String 6 - On Roof

Array A - At Inverter

Array B - At Inverter
Label Confirmation

Is permanently fixed at the main switch

Is permanently fixed at the solar main switch

Is Installed on the switchboard which the system is directly


connected

Installed on all other sub boards.

Is installed on all AC Isolators

Is installed on all DC Isolators

Is installed on inverter or adjacent to solar supply main


switch. Voltage & current labelled as per SLD.

Is installed in main switchboard.

Voltage & current labelled as per SLD.

Installed on meter box.

Is installed on MSB and/ or meter box if not together.

Is permanently fixed on array junction boxes black on


Yellow.

All cables labelled SOLAR every 3m or change in direction


Panel Serial Numbers:

1 31

2 32

3 33

4 34

5 35

6 36

7 37

8 38

9 39

10 40

11 41

12 42

13 43

14 44

15 45

16 46

17 47

18 48

19 49

20 50

21 51

22 52

23 53

24 54

25 55

26 56

27 57

28 58

29 59

30 60
Inverter Serial Numbers:

Inverter 1

Inverter 2

Inverter 3

Datalogging Details:

Serial Number

Registry Key

Datalogger is connected to the customers network and is accessing the


internet?

Photos taken of all inverters & Datalogger labels clearly showing serial
numbers & registry keys?

Installer Signo.

I verify that the above system has been installed to relevant standards.

Signed: Date:

Licensed Electricians
Name:

License Number:

Signed: Date: