STATEMENT OF QUALIFICATIONS
Submission Date: 9/29/2017
We are pleased to submit our proposal to the City of Carmel-By-The-Sea in response to the Request for Statement of
Qualifications. For the past 28 years, locally owned SSA Landscape Architects, Inc. has been a leader in the design of
award-winning park facilities in communities throughout California. We are a small firm that values the quality of projects
we design over the quantity of projects.
From our headquarters in Santa Cruz, we have collaborated with many local municipalities in Monterey County, San
Benito County, Santa Cruz County and San Luis Obispo County. Past projects include Pajaro Neighborhood Park and
Soccer Complex, the historic Monterey County Government Center, the San Lorenzo Park Master Plan, Salinas High
School Sports Fields, Salinas Valley Memorial Hospital Master Plan, San Benito Parks Master Plan, Paso Robles
Downtown City Park, and CSUMB Roundabouts. We are familiar with the culture of small towns and larger communities
as well as the opportunities and constraints of the valley and coastal environments.
We are committed to providing a high level of responsiveness to all our clients. This is demonstrated through our open
door policy and availability to all our clients from returning a phone call promptly; to attending a spur of the moment
meeting; to taking the time and effort to develop innovative solutions to project challenges. Feedback from our clients
have identified these as two of our greatest client relationship strengths and were key components to our success.
We take pride in our ability to provide a consistent approach and quality of service. We provide continuity by assigning
professional staff on a project, maintaining teams throughout the life of the project, and creating a knowledge base for
each project that cannot be surpassed.
In addition to our project experience, we believe that SSA Landscape Architects, Inc. would be a valuable partner for the
City of Carmel-By-The-Sea CIP projects and other municipal programs because of the following distinguishing features:
6 licensed Landscape Architects and 1 licensed Landscape Contractor
2 certified LEED Accredited Professionals
1 certified QSD, 1 Certified Arborist
A successful track record of innovative Landscape Architectural Design
Hands-on background in construction, landscape maintenance, and sustainability
A subconsultant pool of professionals that are collaborative partners project after project
All our experience has been under my direction as Principal-in-Charge, and your project will receive the same high level
of my involvement. I will be the primary contact for the team, from initial contact, agreements and contracts, all the way
through the construction phase. We appreciate the opportunity to present our qualifications and look forward to providing
landscape architectural and arborist services to the City of Carmel-By-The-Sea community, implementing the vision for
2017-2019.
Sincerely,
2. Firms Local Address: 303 Potrero Street, Sute 40-C, Santa Cruz, CA 95060
3. Is your local office the Head Office? X Yes No Branch Office? Yes X No
Only Office? Yes X No
7. List of locations of no more than three (3) other offices where work may be performed (if applicable):
Please identify your tentative, key Project Team members, their titles/roles and primary duties:
Name Title/Role Primary Duties
Principal / Oversight of design, cost estimating,
Steve Sutherland
Landscape Architect agency presentations, QA/QC
Associate Principal / Project management, client liason,
Scott Reeves
Landscape Architect QA/QC, subconsultant coodination
Senior Project Manager / Project management, client liason,
Karen Folsom
Landscape Architect QA/QC, subconsultant coordination
Senior Project Manager / Project management, client liason,
Alison Hobbs
Landscape Architect QA/QC, subconsultant coordination
Project Manager / Production oversight,
Christian Harris
Landscape Architect small project management
Project Manager / Production oversight,
Briana Cox
Landscape Architect small project management
B. Subconsultant and Support Services
Please identify up to four (4) key subconsultants or vendors, contact persons, and services they would
provide in order to support your Project Team.
C. Organizational Chart
Principal-In-Charge:
SSA LANDSCAPE ARCHITECTS
Steve Sutherland
Subconsultants:
(Dependent on specific project scope these
consultants may be included)
Project Manager:
SSA LANDSCAPE ARCHITECTS 1. Civil Engineer Rodney Cahill
Mesiti-Miller Engineering, Inc.
Scott Reeves Alison Hobbs Karen Folsom
2. Structural Engineer Dale Hendsbee
Mesiti-Miller Engineering, Inc.
7. Relevant Project Title & Location (City & State): Salinas Valley Memorial Hospital Master Plan
Salinas, CA
- Year Completed Professional Services: 2012
- Year Completed Construction (if applicable): 2023 (forecasted)
- Brief Description (Scope, size, cost, etc.) and Specific Role: Campus master planning, conceptual
design, 3D modeling and cost estimating for this 11 acre facility modernization, including
courtyards, healing gardens, meditation garden, rooftop garden, arrival court, emergency drop-
off, power plant facility, and streetscape improvements. Total project budget is $12 million.
- Performed Relevant Project with Current Firm: Yes OX No O
8. Relevant Project Title & Location (City & State): Pajaro Neighborhood Park & Soccer Complex
Pajaro, CA
- Year Completed Professional Services: 2014
- Year Completed Construction (if applicable): 2014
- Brief Description (Scope, size, cost, etc.) and Specific Role: Master planning, community workshops,
conceptual design, construction documents and construction administration for this 5 acre park
including synthetic turf soccer/baseball field, basketball court, play structures, community art
walls, bioswales, restrooms and parking lot. Total construction cost was $6.3 million.
- Performed Relevant Project with Current Firm: Yes OX No O
9. Relevant Project Title & Location (City & State):Japanese Historic Schoolhouse & Park Renovation
Castroville, CA
- Year Completed Professional Services: 2012
- Year Completed Construction (if applicable): 2012
- Brief Description (Scope, size, cost, etc.) and Specific Role: Master Planning, community workshops,
design, construction documentation, bidding and construction support for this 5 acre park,
including restoring the historic Japanese schoolhouse, interpretive signage, teaching spaces, and
sports field. The total construction cost was $2 million.
- Performed Relevant Project with Current Firm: Yes OX No O
Page 04 | SSA Landscape Architects, Inc.
FORM C
RESUMES OF KEY PERSONNEL
7. Relevant Project Title & Location (City & State): Red Morton Park Westside Renovation
Redwood City, CA
- Year Completed Professional Services: Ongoing
- Year Completed Construction (if applicable): 2018 (forecasted)
- Brief Description (Scope, size, cost, etc.) and Specific Role: Master Planning, community workshops,
design, construction documentation, bidding and construction support for 4 acres of park
improvements including all-inclusive Magical Bridge playground, group picnic sites, parking
lot and roadway improvements, restroom, bleachers, and pedestrian circulation. Estimated
construction cost is currently $6.5 million.
- Performed Relevant Project with Current Firm: Yes OX No O
8. Relevant Project Title & Location (City & State): Stevens Creek Corridor Park & Restoration
Phase II Cupertino, CA
- Year Completed Professional Services: 2014
- Year Completed Construction (if applicable): 2014
- Brief Description (Scope, size, cost, etc.) and Specific Role: Master Planning, community workshops,
design, construction documentation, bidding and construction support. This 9 acre park project
included a mile Class II Bikeway trail, creek re-alignment, parking lot improvements, ADA
upgrades, teaching spaces, stormwater treatment and habitat restoration. Total project cost was
- $3.8 million.
- Performed Relevant Project with Current Firm: Yes O X No O
9. Relevant Project Title & Location (City & State): Salinas High School Salinas, CA
- Year Completed Professional Services: Ongoing
- Year Completed Construction (if applicable): 2018 (forecasted)
- Brief Description (Scope, size, cost, etc.) and Specific Role: Construction documentation, bidding and
construction support for this new 5 acre campus, including outdoor dining, plaza spaces,
performing arts stage, sports fields, parking lots and pedestrian circulation. The construction
cost for our site improvements is $16 million.
- Performed Relevant Project with Current Firm: Yes OX No O
7. Relevant Project Title & Location (City & State): Jose Higuera Adobe Park Milpitas, CA
- Year Completed Professional Services: 2016
- Year Completed Construction (if applicable): 2017
- Brief Description (Scope, size, cost, etc.) and Specific Role: Conceptual design services, construction
documentation, technical specifications, consultant coordination, cost estimating, bidding and
estimating, bidding and construction support for the renovation of this 4.4 acre historic park.
Enhancements included improving ADA accessibility, upgrading a group and individual picnic areas,
preservation of existing heritage trees, playground upgrades parking lot renovation and creating a looped
trail within the park. Total construction costs were $2 million.
- Performed Relevant Project with Current Firm: Yes X No
8. Relevant Project Title & Location (City & State): CSUMB Roundabouts - Seaside, CA
- Year Completed Professional Services: 2017
- Year Completed Construction (if applicable): 2017
- Brief Description (Scope, size, cost, etc.) and Specific Role: Senior project manager provided project
management, design services, construction documentation and construction administration
for the planting and irrigation improvements at 2 new roundabouts, including erosion control for
the surrounding hillsides. Total project cost was $3.46 million.
- Performed Relevant Project with Current Firm: Yes X No
9. Relevant Project Title & Location (City & State): Brentwood City Park & Civic Center
Brentwood, CA
- Year Completed Professional Services: 2012
- Year Completed Construction (if applicable): 2012
- Brief Description (Scope, size, cost, etc.) and Specific Role: Design, construction documentation,
specification, community presentations, construction administration and LEED documentation
services for this 3 acre park project which received LEED Silver certification. The project
included community rose gardens, a water splashpad, playground renovation, picnic areas, a
historic walk with educational signage, and a stage for community events. Stormwater
management practices included green roofs, Bioswales and infiltration planters. Total project cost
was $3 million.
- Performed Relevant Project with Current Firm: Yes No X
7. Relevant Project Title & Location (City & State): Paso Robles Historic City Park - Paso Robles, CA
- Year Completed Professional Services: 2016
- Year Completed Construction (if applicable): 2016
- Brief Description (Scope, size, cost, etc.) and Specific Role: Renovation of 1.25 acres of an existing
historic park and playground. Park programming and design, presentations, community
workshops, construction documentation, specifications, cost estimating and construction
administration. Total construction budget was $1.12 million.
- Performed Relevant Project with Current Firm: Yes OX No O
8. Relevant Project Title & Location (City & State): Seven Seas Park Sunnyvale, CA
- Year Completed Professional Services: 2013
- Year Completed Construction (if applicable): 2014
Brief Description (Scope, size, cost, etc.) and Specific Role: Park programming and design,
presentations, community workshops, construction documentation, specifications, cost
estimating and construction administration. This 5.3 acre park had a total construction cost
was $4.9 million.
- Performed Relevant Project with Current Firm: Yes OX No O
9. Relevant Project Title & Location (City & State): Sunnyvale Playground Renovations Sunnyvale,
CA
- Year Completed Professional Services: 2016
- Year Completed Construction (if applicable): Ongoing
- Brief Description (Scope, size, cost, etc.) and Specific Role: Park planning and design services,
including Agency coordination, construction documentation, cost estimating, technical
specifications for playgrounds at three city parks of varying scale. Total project budget is $1.5
million.
- Performed Relevant Project with Current Firm: Yes OX No O
5. Current Registration/Certification (State & Discipline) Civil Engineer, State of California #67728;
LEED Accredited Professional, Green Building Certification Institute; Qualified SWPPP
Developer and Practitioner #20301; Cal OES Safety Assessment Program #78583
7. Relevant Project Title & Location (City & State): Stevens Creek Corridor Park & Restoration
Phase II Cupertino CA
- Year Completed Professional Services: 2014
- Year Completed Construction (if applicable): 2014
- Brief Description (Scope, size, cost, etc.) and Specific Role: Master Planning, community workshops,
design, construction documentation, bidding and construction support. This 9 acre park project
included a mile Class II Bikeway trail, creek re-alignment, parking lot improvements, ADA
upgrades, teaching spaces, stormwater treatment and habitat restoration. Total project cost was
$3.8 million.
- Performed Relevant Project with Current Firm: Yes OX No O
8. Relevant Project Title & Location (City & State): 7th Avenue Roundabout & 8th Avenue
Realignment, California State University Monterey Bay Seaside, CA
- Year Completed Professional Services: 2017
- Year Completed Construction (if applicable): 2017
- Brief Description (Scope, size, cost, etc.) and Specific Role: Lead Consultant and Project Manager
for two new roadway intersection designs that improved safety for pedestrians and bicyclists
and reduced delays and congestion for drivers. Total project cost was $3.4 million.
- Performed Relevant Project with Current Firm: Yes OX No O
9. Relevant Project Title & Location (City & State): Shugart Park Bridges Scotts Valley, CA
- Year Completed Professional Services: 2015
- Year Completed Construction (if applicable): 2015
- Brief Description (Scope, size, cost, etc.) and Specific Role: Lead Consultant and Civil Engineer
responsible for design of a new 1,000-foot long bike trail and two 50-foot long bridges. This Safe
routes to School project connected an Elementary School and a High School. Total project cost
was $0.5 million.
- Performed Relevant Project with Current Firm: Yes OX No
Page 08 | SSA Landscape Architects, Inc.
FORM C
RESUMES OF KEY PERSONNEL
4. Education (Degree and Specialization) Lincoln College, Canterbury, New Zealand, Diploma of
Horticulture
7. Relevant Project Title & Location (City & State): Heart of Soquel Plaza Park Soquel, CA
- Year Completed Professional Services: Ongoing
- Year Completed Construction (if applicable): 2018 (forecasted)
- Brief Description (Scope, size, cost, etc.) and Specific Role: Consulting Arborist provided Evaluation of
existing Trees Report and Review of Development Plans Report for this $850,000 project on 1 acre of
land.
8. Relevant Project Title & Location (City & State): Jose Higuera Adobe Park Milpitas, CA
- Year Completed Professional Services: 2016
- Year Completed Construction (if applicable): 2017
- Brief Description (Scope, size, cost, etc.) and Specific Role: Consulting arborist provided Evaluation and
Recommendations Report for 51 trees at 4.4 acre historic park site. Overall construction budget was $2
million.
9. Relevant Project Title & Location (City & State): Chanticleer Park Live Oak, CA
- Year Completed Professional Services: Ongoing
- Year Completed Construction (if applicable): 2018 (forecasted)
- Brief Description (Scope, size, cost, etc.) and Specific Role: Consulting Arborist provided Evaluation
of Existing Trees Report for this park site located on 2.6 acres. Overall construction budget
is $4.6 million.
Project Key Number (1to 4): 10X 2 0 30 4O (Match the bottom of Form E)
6. Description of Project and Relevance to this Service Area (include scope, size, cost, etc.):
SSA was selected by the Monterey County Redevelopment Agency to facilitate community
workshops and prepare a park master plan, design, and construction documents for the
development of this 5 acre, $6.3 million park (mostly funded by the Proposition 84 grant) along the
Pajaro River in North Monterey County. Most park users are living below poverty levels and this is
the towns first community park.
After several workshops with the community to facilitate visioning for the first park in the community
of Pajaro, the program was developed. The program was established to include a synthetic turf
soccer field/baseball field, jogging path around the perimeter, community art walls and interpretive
signs, shade and picnic pavilions and barbecues for group rentals, a stage pavilion for community
events, play structures, a full size basketball court, restroom buildings, bioswales to collect and
clean water run-off, a storage building for maintenance equipment, a meeting and storage building
for the local Boy Scout troops, and a small parking lot.
The park was successfully completed in 2014 and was immediately embraced by the community.
1. Title of Example Project: Stevens Creek Corridor Park & Restoration Phase II
6. Description of Project and Relevance to this Service Area (include scope, size, cost, etc.):
Stevens Creek Corridor Park & Restoration Project includes a multi-use trail along the restored
Stevens Creek. The trail passes through a historic site. The project improves native habitat,
environmental sustainability, and pedestrian safety. It represents a successful partnership between
visionary planning, creative design solutions, regulatory collaboration, and conscientious
construction practices to overcome environmental challenges and site constraints to create a
serene and natural recreation area.
This project completes the multi-use trail between McClellan Ranch and the transportation hub of
Stevens Creek Boulevard, linking several important spaces: the historic Stocklmeir Ranch,
Blackberry Farm Golf Course & Picnic Grounds, and the McClellan Ranch Preserve. It provides an
accessible trail head on Stevens Creek Boulevard with bus drop-off capacity for school groups and
a new cross-walk with solar powered warning beacons for enhanced pedestrian safety.
The community outreach process overcame the organizational challenge of garnering consensus
among diverse groups with contrasting desires. There were several groups with differing priorities.
The final trail design took into consideration the wishes of all these groups while providing design
latitude to improve the historic Stocklmeir Ranch site, consistent with the goal to create a legacy
farm. The project included 9 acres of land improved at a cost of $3.8 million.
6. Description of Project and Relevance to this Service Area (include scope, size, cost, etc.):
This Brownfield site, once home to five industrial buildings built on an old contaminated agricultural
site, was transformed into a 5.3 acre neighborhood park for the community of Tasman Crossing at
a cost of $4.9 million. SSA led their consultant team in the preparation of an EIR document,
coordinated with the Citys environmental consultant, and assisted during the multiple phased
projects to remediate the land and provide a clean site for the construction of Seven Seas Park.
SSA hosted multiple community workshops, collaborated with the locally organized neighborhood
advisory committee and prepared three conceptual plans for the design of the park. The final plan
includes an ADA and inclusive playground designed as a shipping port with large custom faux-rock
outcroppings and docks, a splash pad with a subsurface reservoir designed to irrigate site trees,
maple tree grove and picnic areas, tennis and basketball courts, seven shade structures, musical
play elements, large grassy meadow/field, a restroom facility and parking lot. Project
responsibilities included community outreach workshops, scheduling, cost estimating, 3D modeling,
site and landscape design, PS&E and construction administration.
1. Title of Example Project: California State University Monterey Bay Traffic Roundabouts
6. Description of Project and Relevance to this Service Area (include scope, size, cost, etc.):
California State University at Monterey Bay is located on an old military fort site. Since opening its
doors, the university has been challenged with updating the military site and reconfiguring elements
to fit the needs of a university campus. Most recently, several roadway intersections were identified
for potential upgrades and installation of traffic roundabouts to improve safety and adequately
serve the growing campus. The project goals were to upgrade the vehicular circulation patterns
while being mindful of adjacent property owners, mature oak trees, and stormwater runoff.
Vegetative Bioswales were incorporated to filter pavement run-off. Post-construction hillside
erosion control was achieved through the incorporation of California native species and wildflower
hydroseed that complement the native California Oak Woodland community.
Aurum Consulting
9. Electrical Engineering X
Engineers, Inc.
Biotic Resources
10. Environmental Reports
Group
AutoCAD, LandFX, SketchUp, Adobe Creative Cloud Suite, Microsoft Office Suite, Bluebeam,
Does your firms fully burdened hourly rates include the following?
Please initial here to acknowledge that markups for subconsultants and other direct costs shall