REPLACEMENT OF CRUDE DISTILLATION COLUMN (11-C-01) - 13RREDR11118 23-Jan-16 03:07 PM

Activity ID Activity Name Original Start Finish Total Float 2016


Duration February March April
31 07 14 21 28 06 13 20 27 03 10 17
REPLACEMENT OF CRUDE DISTILLATION CO
REPLACE 991h 01-Feb-16 29-Mar-16 0h
07:00 AM 07:00 PM
PRE-SHUTDOWN ACTIVITIES
PRE-SH 314h 01-Feb-16 29-Feb-16 0 677h

PRELIMINARIES
PRELIM 290h 01-Feb-16 27-Feb-16 0 701h
A1000 HSE INDUCTION OF MANPOWER 148h 01-Feb-16 15-Feb-16 0h
07:00 AM 06:00 PM

A1010 FIRE WATCHER,HOLE WATCHER AND PTW 20h 04-Feb-16 07-Feb-16 0h


TRAININGS 07:00 AM 04:00 PM

A1020 DRIVER DEFENSIVE TRAININGS 60h 07-Feb-16 11-Feb-16 148h


06:00 AM 06:00 PM

A1030 EQUIPMENT CERTIFICATION BY TAKREER 36h 09-Feb-16 11-Feb-16 148h


06:00 AM 06:00 PM

A1040 SHUTDOWN VILLAGE PREPARATION 108h 12-Feb-16 20-Feb-16 148h


06:00 AM 06:00 PM

A1050 ESTABLISHMENT & MOBILIZATION OF SITE 36h 15-Feb-16 17-Feb-16 148h


FACILITIES 06:00 AM 06:00 PM

A1060 MOBILIZATION OF MANPOWER AT SITE 240h 07-Feb-16 27-Feb-16 0h


04:00 PM 04:00 PM

A1070 IDENTIFICATION AND APPROVAL OF BLINDING 60h 18-Feb-16 22-Feb-16 759h


LOCATION AS PER BLINDING LIST 06:00 AM 06:00 PM

ERECTION OF SCAFFOLDING
ERECT 314h 01-Feb-16 29-Feb-16 0 0h
A1090 SHIFTING OF SCAFFOLDING MATERIAL AT SITE 40h 01-Feb-16 04-Feb-16 30h
07:00 AM 05:00 PM

A1100 MOBILIZATION OF SCAFFOLDERS AT SITE 20h 03-Feb-16 04-Feb-16 30h


07:00 AM 05:00 PM

A1110 ERECTION OF SCAFFOLDING AT SITE 264h 07-Feb-16 29-Feb-16 0h


04:00 PM 04:00 PM

PREPARATION OF ELECTRICAL NETWORK


PREPAR 42h 18-Feb-16 21-Feb-16 148h
A1160 ELECTRICAL GENERATOR DB'S CONNECTION 30h 18-Feb-16 20-Feb-16 148h
06:00 AM 12:00 PM

A1170 ELECTRICAL CABLE LAYING & SUPPLY 30h 19-Feb-16 21-Feb-16 148h
CONNECTION 06:00 AM 12:00 PM

SHUTDOWN ACTIVITIES
SHUTD 451h 06-Mar-16 24-Mar-16 0 104h
A1120 COMMENCEMENT OF COLUMN SHUTDOWN BY 6h 06-Mar-16 06-Mar-16 0h
TAKREER OPERATION DEPARTMENT 12:00 AM 06:00 AM

A1125 MOBILE VEHICLE & MACHINE ENTRY PERMIT 6h 06-Mar-16 06-Mar-16 0h


02:00 AM 08:00 AM

A1130 ISOLATION/REMOVAL OF ELECTRICAL LIGHT 12h 06-Mar-16 06-Mar-16 0h


POLES ,CABLES& CABLE TRAYS 08:00 AM 08:00 PM

A1140 ISOLATION/REMOVAL OF INSTRUMENT ITEMS 8h 06-Mar-16 06-Mar-16 0h


12:00 PM 08:00 PM

A1150 ISOLATION/REMOVAL OF VALVES 6h 06-Mar-16 06-Mar-16 0h


12:00 PM 06:00 PM

Primary Baseline Remaining Work Milestone Page 1 of 5 Level IV Plan

Actual Work Critical Remaining Work Summary Primavera Systems, Inc.


REPLACEMENT OF CRUDE DISTILLATION COLUMN (11-C-01) - 13RREDR11118 23-Jan-16 03:07 PM
Activity ID Activity Name Original Start Finish Total Float 2016
Duration February March April
31 07 14 21 28 06 13 20 27 03 10 17
A1180 OPENING AND VENTILATION BY EJECTORS & 20h 06-Mar-16 07-Mar-16 0h
BLOWERS 06:00 PM 02:00 PM

A1190 DISMANTLING OF TOP SECTION EXTERNAL 18h 07-Mar-16 08-Mar-16 0h


ATTACHMENTS (Monkey Ladder,Platform,Manways) 02:00 PM 08:00 AM

A1200 REMOVAL OF INSULATION FROM CUTTING LINE 8h 07-Mar-16 08-Mar-16 0h


10:00 PM 06:00 AM

A1210 TO PERFORM GAS TEST 4h 08-Mar-16 08-Mar-16 0h


06:00 AM 10:00 AM

A1220 CONFINED SPACE ENTRY PERMIT 4h 08-Mar-16 08-Mar-16 0h


06:00 AM 10:00 AM

A1230 ENTRY & ELECTRICAL LIGHT (24V) INSTALLATION 8h 08-Mar-16 08-Mar-16 0h


10:00 AM 06:00 PM

A1233 DE-SLUDGING & CLEANING FROM ALL TRAYS FOR 252h 08-Mar-16 19-Mar-16 31h
PORTION-1 06:00 PM 06:00 AM

A1234 DE-SLUDGING & CLEANING FROM ALL TRAYS FOR 252h 08-Mar-16 19-Mar-16 31h
PORTION-2 06:00 PM 06:00 AM

A1235 DE-SLUDGING & CLEANING FROM ALL TRAYS FOR 252h 08-Mar-16 19-Mar-16 31h
PORTION-3 06:00 PM 06:00 AM

A1236 DE-SLUDGING & CLEANING OF ENTIRE SHELL 252h 08-Mar-16 19-Mar-16 31h
SURFACES OF PORTION-1 06:00 PM 06:00 AM

A1237 DE-SLUDGING & CLEANING OF ENTIRE SHELL 252h 08-Mar-16 19-Mar-16 31h
SURFACES OF PORTION-2 06:00 PM 06:00 AM

A1238 DE-SLUDGING & CLEANING OF ENTIRE SHELL 252h 08-Mar-16 19-Mar-16 31h
SURFACES OF PORTION-3 06:00 PM 06:00 AM

A1239 DE-SLUDGING & CLEANING AT BOTTOM OF 252h 08-Mar-16 19-Mar-16 0h


COLUMN 06:00 PM 06:00 AM

A1240 CLEANING OF INSIDE CUTTING LINE ZONE 12h 08-Mar-16 09-Mar-16 5h


01:00 PM 01:00 AM

A1250 TOP DISHEND CLEANING FROM INSIDE 12h 09-Mar-16 09-Mar-16 5h


01:00 AM 01:00 PM

A1260 MARKING OF CUTTING LINE AS PER NEW 10h 09-Mar-16 09-Mar-16 5h


FABRICATED TOP SECTION OF CDC 01:00 PM 11:00 PM

A1270 MARKING OF REFERENCE POINTS ON EXISTING 12h 09-Mar-16 10-Mar-16 5h


COLUMN 11:00 PM 11:00 AM

A1280 INSTALLATION OF TEMPORARAY RING FROM 10h 10-Mar-16 10-Mar-16 5h


MARKED CUTTING LINE 11:00 AM 09:00 PM

A1290 HOLDING OF NOZZLES BEFORE CUTTING 12h 10-Mar-16 11-Mar-16 5h


09:00 PM 09:00 AM

A1300 INSTALLATION OF 4 NO.OF LIFTING LUGS ON TOP 12h 11-Mar-16 11-Mar-16 5h


DISHEND OF EXISTING PORTION 09:00 AM 09:00 PM

Primary Baseline Remaining Work Milestone Page 2 of 5 Level IV Plan

Actual Work Critical Remaining Work Summary Primavera Systems, Inc.


REPLACEMENT OF CRUDE DISTILLATION COLUMN (11-C-01) - 13RREDR11118 23-Jan-16 03:07 PM
Activity ID Activity Name Original Start Finish Total Float 2016
Duration February March April
31 07 14 21 28 06 13 20 27 03 10 17
A1310 REMOVAL OF INSIDE TRAYS 10h 11-Mar-16 12-Mar-16 5h
09:00 PM 07:00 AM

A1330 PREPARATION OF HOT WORK ON TOP SECTION 12h 12-Mar-16 12-Mar-16 5h


OF COLUMN 07:00 AM 07:00 PM

A1350 CUTTING & REMOVAL OF RELATED PIPE LINE AND 12h 13-Mar-16 13-Mar-16 0h
SUPPORTING IT. 12:00 AM 12:00 PM

A1355 ASSEMBLY OF 400 TON CRANE 8h 13-Mar-16 13-Mar-16 0h


12:00 PM 08:00 PM

A1358 HOLDING OF TOP SECTION OF COLUMN WITH 400 8h 13-Mar-16 14-Mar-16 0h


TON CRANE 08:00 PM 04:00 AM

A1360 CUTTING OF TOP SECTION OF CDC 14h 14-Mar-16 14-Mar-16 0h


04:00 AM 06:00 PM

A1370 REMOVAL OF TOP SECTION CDU AFTER CUTTING 8h 14-Mar-16 15-Mar-16 0h


06:00 PM 02:00 AM

A1380 ERECTION OF INTERNAL SCAFFOLDING 6h 12-Mar-16 13-Mar-16 0h


PLATFORM AT TRAY # 37 FOR IN -SITU WORK 06:00 PM 12:00 AM

A1390 EDGE PREPARATION OF AND PRE-HEAT OF TOP 12h 15-Mar-16 15-Mar-16 0h


SECTION OF CDU 02:00 AM 02:00 PM

A1400 DPT&INSPECTION OF BEVELLED EDGES 8h 15-Mar-16 15-Mar-16 0h


02:00 PM 10:00 PM

A1410 REMOVAL OF INSULATION OF EXISTING TOP 8h 15-Mar-16 16-Mar-16 293h


SECTION OF COLUMN 10:00 PM 06:00 AM

A1420 INSTALLATION OF INSULATION ON NEW TOP 8h 16-Mar-16 16-Mar-16 293h


SECTION 06:00 AM 02:00 PM

A1430 INSTALLATION OF EXTERNAL ATTACHMENTS ON 8h 16-Mar-16 16-Mar-16 293h


NEW TOP SECTION AT FLOOR 02:00 PM 10:00 PM

A1440 INSTALLATION OF TAPERED CLEATS ON 8h 15-Mar-16 16-Mar-16 0h


BEVELLED EDGES 10:00 PM 06:00 AM

A1450 LIFTING& INSTALLATION OF PRE-FABRICATED 10h 16-Mar-16 16-Mar-16 0h


NEW TOP SECTION OF COLUMN 06:00 AM 04:00 PM

A1460 FIT-UP OF NEW TOP SECTION WITH EXISTING 8h 16-Mar-16 17-Mar-16 0h


SHELL OF COLUMN 04:00 PM 12:00 AM

A1465 VISUAL EXAMINATION OF FIT-UP OF CS-1A (NEW 8h 17-Mar-16 17-Mar-16 0h


TOP SECTION WITH EXISTING SHELL OF COLUMN) 12:00 AM 08:00 AM

A1468 ROOT , ROOT HOT AND DPT OF IN SITU CS-1A 12h 17-Mar-16 17-Mar-16 0h
(GOLDEN JOINT) AS PER PROCEDURE & WPS 08:00 AM 08:00 PM

A1470 FILLING AND CAPPING OF IN SITU CS-1A 13h 17-Mar-16 18-Mar-16 0h


(GOLDEN) JOINT AS PER PROCEDURE & WPS 08:00 PM 09:00 AM

A1472 VISUAL EXAMINATION OF WELDING AFTER 8h 18-Mar-16 18-Mar-16 0h


CAPPING OF IN-SITU CS-1A JOINT 09:00 AM 05:00 PM

Primary Baseline Remaining Work Milestone Page 3 of 5 Level IV Plan

Actual Work Critical Remaining Work Summary Primavera Systems, Inc.


REPLACEMENT OF CRUDE DISTILLATION COLUMN (11-C-01) - 13RREDR11118 23-Jan-16 03:07 PM
Activity ID Activity Name Original Start Finish Total Float 2016
Duration February March April
31 07 14 21 28 06 13 20 27 03 10 17
A1474 DPT AND BACK-PASS FROM INSIDE OF IN-SITU 8h 18-Mar-16 19-Mar-16 0h
CS-1A JOINT 05:00 PM 01:00 AM

A1476 RADIOGRAPHY OF IN-SITU CIRCUMFERENTIAL 12h 19-Mar-16 19-Mar-16 0h


SEAM CS-1A JOINTS 01:00 AM 01:00 PM

A1478 WELD OVERLAY OF IN-SITU CIRCUMFERENTIAL 12h 19-Mar-16 20-Mar-16 0h


SEAM AND CONNECTED NOZZLES JOINTS 01:00 PM 01:00 AM

A1479 RADIOGRAPHY OF IN-SITU CONNECTED NOZZLES 12h 20-Mar-16 20-Mar-16 0h


JOINTS 10N,2NA & 2NB 01:00 AM 01:00 PM

A1480 VISUAL EXAMINATION OF WELDED OVERLAY OF 10h 20-Mar-16 20-Mar-16 0h


IN-SITU CS-1A AND NOZZLES JOINT 10N,2NA & 01:00 PM 11:00 PM
2NB

A1485 RADIGRAPHY OF IN-SITU NOZZLES JOINTS 12h 20-Mar-16 21-Mar-16 0h


11NA,11NB,8"( Header line @ Top) & OPTIONAL 11:00 PM 11:00 AM
SCOPE FOR SOCKET WELD JOINTS

A1490 NDE & INSPECTION OF IN-SITU 10N,2NA & 8h 21-Mar-16 21-Mar-16 0h


2NB,11NA,11NB,8"( Header line @ Top) AND OPT 11:00 AM 07:00 PM
SCOPE OF SW JOINTS

A1495 PRELIMINARY INSPECTION OF AND ALL TRAYS 12h 19-Mar-16 19-Mar-16 31h
AND ENTIRE SHELL SURFACES AFTER CLEANING 06:00 AM 06:00 PM

A1510 REMOVAL OF TEMPORARY RING 4h 21-Mar-16 21-Mar-16 0h


07:00 PM 11:00 PM

A1520 FINAL VISUAL DIMENSIONAL INSPECTION OF ALL 6h 21-Mar-16 22-Mar-16 0h


IN-SITU JOINTS 09:00 PM 03:00 AM

A1530 PAINTING TOUCH-UP ON IN-SITU JOINTS 24h 22-Mar-16 23-Mar-16 0h


03:00 AM 03:00 AM

A1600 BUFFING OF TSR;LS AND CS JOINTS AS PER 12h 22-Mar-16 22-Mar-16 0h


COMPANY INSPECTION REQUIREMENT 05:00 AM 05:00 PM

A1610 INSPECTION OF TSR,LONGITUDINAL SEAM AND 8h 22-Mar-16 23-Mar-16 0h


CIRCUMFERENTIAL SEAM JOINTS AFTER 05:00 PM 01:00 AM
CLEANING

A1620 PNEUMATIC TESTING OF 15 NO.OF NOZZLES 8h 22-Mar-16 22-Mar-16 140h


05:00 AM 01:00 PM

A1630 INNER LINING REPAIR ARRESTING 10h 22-Mar-16 22-Mar-16 140h


01:00 PM 11:00 PM

A1640 PNEUMATIC TESTING & INSPECTION AFTER 8h 22-Mar-16 23-Mar-16 140h


REPAIRING 11:00 PM 07:00 AM

A1650 REPAIRIRNG OF 30'' IN SITU FLANGE FOR 1N 36h 21-Mar-16 23-Mar-16 140h
NOZZLE 07:00 PM 07:00 AM

A1655 FINAL INSPECTION OF ALL TRAYS, ENTIRE ALL 10h 23-Mar-16 23-Mar-16 0h
SHELL SURFACES AND BOTTOM OF COLUMN 01:00 AM 11:00 AM
AFTER CLEANING

A1660 REMOVE INTERNAL SCAFFOLDING 6h 23-Mar-16 23-Mar-16 0h


11:00 AM 05:00 PM

A1665 INSTALLATION OF INSULATION OF 8h 23-Mar-16 23-Mar-16 0h


COLUMN(11-C-01) WHEREVER REQUIRED 11:00 AM 07:00 PM

Primary Baseline Remaining Work Milestone Page 4 of 5 Level IV Plan

Actual Work Critical Remaining Work Summary Primavera Systems, Inc.


REPLACEMENT OF CRUDE DISTILLATION COLUMN (11-C-01) - 13RREDR11118 23-Jan-16 03:07 PM
Activity ID Activity Name Original Start Finish Total Float 2016
Duration February March April
31 07 14 21 28 06 13 20 27 03 10 17
A1668 INSTALLATION OF REMAINING EXTERNAL 8h 23-Mar-16 23-Mar-16 0h
ATTACHMENTS ON COLUMN 11:00 AM 07:00 PM

A1670 OFFER CRUDE COLUMN INSPECTION BEFORE 6h 23-Mar-16 24-Mar-16 0h


BOX-UP 07:00 PM 01:00 AM

A1680 TO OBTAIN BOX-UP PERMIT & BOX-UP THE MAN 10h 24-Mar-16 24-Mar-16 0h
WAYS AND FLANGES 01:00 AM 11:00 AM

A1690 DE-BLINDING 8h 24-Mar-16 24-Mar-16 0h


11:00 AM 07:00 PM

POST-SHUTDOWN ACTIVITIES
POST-S 104h 24-Mar-16 29-Mar-16 0 0h
A1700 COMMISSIONING 48h 24-Mar-16 27-Mar-16 0h
07:00 PM 11:00 AM

A1710 REMOVAL OF EXTERNAL SCAFFOLDING 72h 25-Mar-16 29-Mar-16 0h


07:00 PM 11:00 AM

A1720 HOUSE KEEPING 8h 29-Mar-16 29-Mar-16 0h


11:00 AM 07:00 PM