AC Labor =$19,998 (shown on the Chart) (labor only)

AC Total =$219,998 (not show on the Chart) (that include Labor, equipment, expense)->why??? Have to
choose Total in the activity usage profile option

PV Labor =$10,000 (not show on the Chart)

PV Total =$34,274 (show on the Chart) > THIS IS A PLAN VALUE that always include the Labor, Material,
Expend, No labor cost-> Earned Value cost is the same.

Insert the column Actual Labor cost, Actual Material cost, actual labor unit to fill in directly from the
screen.