Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
DESIGN GUIDE
Compiled by
TABLE OF CONTENTS
1 INTRODUCTION ................................................................................................................................ 1
1.1 SCOPE OF MANUAL ............................................................................................................................... 1
1.2 DESIGN STANDARDS ....................................................................................................................... 1
1.3 REFERENCE DOCUMENTS ....................................................................................................................... 1
1.4 MINISTRY OF TRANSPORT MANUALS .............................................................................................. 1
1.5 CONVERSION UNITS .............................................................................................................................. 2
1.6 SCHEDULE FOR QUANTITY MEASUREMENTS ............................................................................................... 2
2 ROADS .............................................................................................................................................. 3
2.1 DESIGN STANDARDS AND ROAD CLASSIFICATIONS ........................................................................ 3
2.1.1 DESIGN STANDARDS ............................................................................................................... 3
2.1.2 ROAD CLASSIFICATION ............................................................................................................ 3
2.2 PAVEMENT DESIGN ............................................................................................................................... 3
2.2.1 FLEXIBLE PAVEMENT DESIGN TO MOT STANDARDS............................................................... 3
2.2.2 PAVEMENT MATERIAL SPECIFICATION ................................................................................... 4
2.2.3 FLEXIBLE PAVEMENT DESIGN TO COH STANDARDS ............................................................... 5
2.2.4 TYPICAL ROAD CROSS-SECTIONS ............................................................................................ 6
2.2.5 SURFACING ............................................................................................................................. 7
2.3 GEOMETRICAL DESIGN OF ROADS .................................................................................................. 9
2.3.1 DESIGN SPEED ......................................................................................................................... 9
2.3.2 VERTICAL ALIGNMENT ............................................................................................................ 9
2.3.3 HORIZONTAL ALIGNMENT .................................................................................................... 10
2.3.4 GENERAL SURVEY ................................................................................................................. 13
2.4 TRAFFIC ENGINEERING......................................................................................................................... 14
2.4.1 ROUNDABOUT DESIGN ......................................................................................................... 14
2.4.2 JUNCTION DESIGN ................................................................................................................ 14
2.4.3 DESIGN OF TOLL PLAZAS ....................................................................................................... 15
2.4.4 TRAFFIC COUNTS .................................................................................................................. 16
2.4.5 PARKING ............................................................................................................................... 17
2.4.6 TRAFFIC SIGNS ...................................................................................................................... 18
2.4.7 AERODROME DESIGN ........................................................................................................... 19
2.5 CONCRETE WORKS ........................................................................................................................ 20
2.5.1 CONCRETE MIX DESIGN ........................................................................................................ 20
2.5.2 CONCRETE INDUSTRIAL FLOORS ........................................................................................... 21
2.5.3 STATISTICS AND MARGINS .................................................................................................... 22
2.5.4 CONCRETE ROAD FURNITURE ............................................................................................... 23
3 STORMWATER DRAINAGE .............................................................................................................. 24
3.1 SCOPE ........................................................................................................................................... 24
3.2 GUIDELINES................................................................................................................................... 24
3.3 HYDRAULICS OF PIPES ......................................................................................................................... 24
3.4 ESTIMATION OF DESIGN FLOOD ................................................................................................... 24
3.4.1 RATIONAL FORMULA ............................................................................................................ 24
3.4.2 QUICK METHOD .................................................................................................................... 25
3.5 PIPE CULVERT SELECTION ..................................................................................................................... 25
3.6 PIPE FLOW EQUATIONS ........................................................................................................................ 26
3.6.1 MANNINGS EQUATION ........................................................................................................ 26
3.6.2 VARIATION OF FLOW WITH DEPTH....................................................................................... 26
3.7 SHELVERT DESIGN ......................................................................................................................... 28
4 WATER SUPPLY SYSTEMS ............................................................................................................... 29
4.1 INTRODUCTION.................................................................................................................................. 29
4.2 WATER SUPPLY SCHEME DESIGN PARAMETERS ........................................................................... 29
4.2.1 WATER DEMAND .................................................................................................................. 29
4.2.2 FIRE FIGHTING REQUIREMENTS ........................................................................................... 30
4.2.3 PEAK FACTORS ...................................................................................................................... 30
4.2.4 POPULATION GROWTH RATE R ............................................................................................ 31
4.2.5 DESIGN PERIOD ..................................................................................................................... 31
4.2.6 PRESSURE .............................................................................................................................. 31
4.2.7 VELOCITY ............................................................................................................................... 31
4.2.8 LOSSES .................................................................................................................................. 31
4.3 RAW WATER SOURCES ................................................................................................................... 31
4.4 WATER TREATMENT WORKS ........................................................................................................ 32
4.5 DESIGN FOR PRESSURE MAINS AND RETICULATION NETWORKS.................................................. 32
4.5.1 SELECTION OF PIPE MATERIALS ............................................................................................ 32
4.5.2 SPECIFICATION OF PIPES ....................................................................................................... 32
4.5.3 TESTING OF PIPES ................................................................................................................. 33
4.5.4 NETWORK ANALYSIS ............................................................................................................. 34
4.5.5 DESIGN OF PUMPING MAINS................................................................................................ 35
4.5.6 EQUIVALENT PIPE ................................................................................................................. 36
4.5.7 ACCESSORIES FOR SUPPLY networks .................................................................................... 36
4.5.8 PUMPING MAINS VERSUS GRAVITY MAINS .......................................................................... 37
5 WASTE WATER DISPOSAL SYSTEMS ................................................................................................ 39
5.1 INTRODUCTION.................................................................................................................................. 39
5.1.1 SYSTEM COMPONENTS ......................................................................................................... 39
5.1.2 GENERAL NOTES ................................................................................................................... 39
5.2 DESIGN FACTORS ............................................................................................................................... 39
5.3 SEWER HYDRAULICS ........................................................................................................................... 40
5.3.1 DIAMETERS AND GRADIENTS ............................................................................................... 40
5.3.2 APPROXIMATE PIPE CAPACITIES ........................................................................................... 40
5.3.3 PIPE & PUMP SUPPLIERS....................................................................................................... 41
5.3.4 AVAILABLE SEWER PIPES ...................................................................................................... 41
5.4 PUMP STATIONS ........................................................................................................................... 41
5.4.1 GENERAL NOTES ................................................................................................................... 41
5.4.2 SIZING A PUMP SUMP .......................................................................................................... 41
5.5 WASTEWATER TREATMENT WORKS ............................................................................................. 42
5.5.1 INTRODUCTION ..................................................................................................................... 42
5.5.2 DESIGN OF SEPTIC TANKS & SOAKAWAYS ............................................................................ 42
5.5.3 DESIGN OF WASTEWATER STABILISATION PONDS ............................................................... 42
INTRODUCTION (BASED ON WASTE STABILISATION PONDS IN TROPICS BY DUNCAN MARA) ......................................... 42
DESIGN PHILOSOPHY ...................................................................................................................................... 42
ANAEROBIC PONDS ........................................................................................................................................ 43
FACULTATIVE POND ....................................................................................................................................... 43
MATURATION POND ...................................................................................................................................... 43
6 HYDRAULIC STRUCTURES ............................................................................................................... 44
6.1 CATCHMENT AND YIELD CHARACTERISTICS ............................................................................................... 44
6.2 YIELD CALCULATIONS .......................................................................................................................... 44
6.3 DESIGN FLOOD .................................................................................................................................. 44
6.3.1 DESIGN FLOOD ...................................................................................................................... 44
6.3.2 DISTRIBUTIONS ..................................................................................................................... 44
6.4 FACTORS TO CONSIDER DURING DAM DESIGN........................................................................................... 44
6.5 RIVER/ DAM ABSTRACTION POINTS .................................................................................................... 45
1 INTRODUCTION
This manual is mainly concerned with the design of civil engineering infrastructure;
roads and stormwater drainage
water supply and reticulation
sewerage reticulation and treatment
As a rule of thumb guide to roads & stormwater cost 55%, sewerage 25% and water reticulation 20% of
total cost of servicing a housing development. The average cost of servicing a housing infrastructure
development is USD30 000.00/ha
1.2 DESIGN STANDARDS
Roads: - City of Bulawayo, City of Harare Road Design Manual and Ministry of Transport Manuals
Water Reticulation : Department of Water Development: Design & Training Manual (Water)
Sewerage Disposal : SALA Manual 5: Sanitation Design Procedures
1.3 REFERENCE DOCUMENTS
The design guidelines in this manual are based on the following documents;
City of Harare (COH) Road Design Manual, City of Bulawayo
Ministry of Transport Manual listed in the section below
Department of Water Development: Design & Training Manual (Water)
Swedish Association of Local Authorities (SALA) Manual 5: Sanitation Design Procedures
Ministry of Local Government & Housing: Water & Sewerage Design; 1982 (Yellow Manual)
Ministry of Local Government & Housing: Principles of Planning &Design; 1981 (Green Manual)
Pump and Pipe Supplier Catalogues
Arup Civil Engineering Design Guide (1993)
Hydraulics: Charwick & Moffert & Fluid Mechanics: J F Douglas
Water Treatment Handbook: 6th Edition Volume 1, Degremont, France
Model Building By Laws
BS 6297: 1983 Design and Installation of Small Treatment Works and Cesspools
Irrigation Manual by FAO
SABS 090
1.4 MINISTRY OF TRANSPORT MANUALS
Taking off of quantities can be done based on the following schedules of quantities;
Table 1-A : Building Materials Quantity Schedule
2 ROADS
This document covers the design of roads to Ministry of Transport Parts F, C and K Manual, City of
Harare Guidelines and City of Bulawayo Design Guidelines.
2.1.2 ROAD CLASSIFICATION
Step 1: Axle load survey (mass vs number of vehicles for the given road counted or estimated)
Step 2: Equivalent factor e = (X / WS)X
where X = measured axial load
WS = standard axial load (8160 kg) x = 4
Calculate the equivalent axles per day as E = (equivalent axial) x number of vehicles
Find the sum of equivalent axles per day
Choose design life (10 to 20 years) for flexible pavement or up to 40 years for rigid pavement
Decide on traffic growth rate 5 to 10% per annum
Calculate cumulative equivalent standard axle Esa as
Esa = daily Esa x f x 100 or Esa = daily Esa x 365
f is taken from tables and f = 3.65R
R = [(1+r)n 1]/ r r = traffic growth rate and n = design life
Note: Normal cars (2 ton axle load), have an equivalent factor of less than 0.004, therefore cars have
negligible effect on the road as compared to large trucks and can be ignored. In normal cases heavy
vehicles constitute 10% to 30% of the total traffic volume and in the absence of given information an
equivalent total axle of 0.256 can be assumed for each heavy vehicle.
2.2.2 PAVEMENT MATERIAL SPECIFICATION
Cumulative Esa < 0.1 x 106 0.1 0.3 x 106 0.3 1.0 x 106 > 1.0 x 106
Pavement group 0.1M 0.3M 1.0M 3.0M
Step 5: Specify pavement based on the Part F : Figures 206 to 2010 attached. Compaction
specifications are as indicated below, based on Part F, Section 13 Table 2.
Table 2-D : Compaction Specification.
Step 1: Classifying the road according to its use (See Attached Classification Sheet)
Step 2 : Deciding on the layerworks corresponding to the soil type (See Attached Layerworks Sheet)
Note: The attached Schedule for Pavement Material is used for pavement material classification
2.2.5 SURFACING
5.2.2.1 Introduction
Surfacing usually costs about 20 30% of the overall costs of road pavements. Thus an economical design
of surfacing will lead to a significant saving on the overall cost of the road.
Use premix for construction of speed humps (according to City of Harare). MOT recommends single seal
for shoulders and double seal for carriageway.
The speed at which 85% of the vehicles are travelling below is termed the design speed. The usual design
speeds adopted by MOT are 60km/hr, 80km/hr and 120km/hr.
2.3.2 VERTICAL ALIGNMENT
Design Speed Sight Stopping Distance (m) Sight Passing Distance (m)
(km/hr)
AASHTO MOT AASHTO MOT
120 215
100 160 210 580 700
80 120 140 490 550
60 70 80 345 350
2.3.3 HORIZONTAL ALIGNMENT
3.2.3.1 General
There should be a distance of at least 40m between two adjacent curves. Transition curves must be used
where the curve radius is less than that specified below. Long straight sections (longer than 3km) should
be avoided to prevent driver boredom and light glare at night.
3.2.3.2 Horizontal Curves
These are circles of given radii. These are the minimum radii to avoid vehicles skidding off the road when
travelling at the design speed. It is obtained by balancing the centrifugal force F 1 = mv2/r to the side
friction force F2 = mg to give r = v2/ug, where = 0.18 (0.16 to 0.22 for Zimbabwe) and g = 9.81m/s 2.
Transition curves are required where a straight meets a sharp curve, which according to the MOT is
R<700m (100km/hr) and R<300m (80km/hr). The curves can be cubic, lemniscate or Euler spirals whose
length is give by L = v3/ar
Where L = length of transition curve in m
v = design speed in m/s
a = 0.3m/s3
r = horizontal curve radius in m
S = 1.6(e v)/l
x2 = v + (e - v)/ (1 +2S)
M = e[(D-60)/10]
tp = 1 +[0.5/(1 + M)]
fc = 0.21 tp (1+0.2 x2)
F = 303 x2
k = 0.00347( 30) 0.978[(1/r - 0.05)]
Qe = k(F - fc Qc)
According to the Kenyan Road Design Manual Part 1 of 1979, the design of junctions should consider
traffic volumes, geometric layout, design speed, road classification and turning paths of vehicles.
The design process involves, data collection (site survey, traffic counts and road alignment), layout
selection and design modification. The design can be check against chart capacities and aim to obtain at
least an equivalency of 85% of minor road traffic passing through the junction at any given time.
COB requires that the angle at a T junction be 70 900 with minimum curve radius of 10m for belmouths.
Refer to the attachment from the South African National Road Agency.
2.4.5 PARKING
Traffic signs are required to control, guide and inform drivers. Road side signs should be between 0.5 and
1.5m from the road edge and up to 3m height. Centre line markings are 4m long by 100mm wide and
spaced at 9m in towns and 22m in rural areas.
Aerodromes should be designed in liaison with the Civil Aviation Authority of Zimbabwe (CAAZ).
According to the book; Pavements and Surfacing for Highways and Airports by M Sagious;
The landing impact of planes is ignored. The weight of the plane, wheel alignment and runway repetitions
are considered as loading. After determining the axle load in kN, and soil subgrade reaction K, the
pavement thickness is determined from the Charts. The Chart is reproduced in the table below;
Table 2-V : Pavement Thickness for Aerodromes
Design Basis
Concrete industrial floors are designed according to recommendations in the Concrete Industrial Floors
on the Ground by L Marais & B Perrie. Three different types of loading namely uniformly distributed,
vehicular and point loads are considered.
The slab resists compressive, shear and flexural stresses. Reinforcement is placed merely to control
cracking, as it will not increase the load carrying properties of the slab in any way.
Design Procedure (based on Marais & Perrie)
Selection of Slab Properties
Select Subgrade CBR and determine Modulus of Subgrade Reaction k from Fig 1.3
Select concrete grade and determine flexural strength from the chart below. (However Marais &
Perrie suggest 3.8Mpa for 30Mpa concrete).
Figure 2-B: Flexural Strength of Concrete
Given a specified value of fcu, we need to determine our target average value such that not more than 5%
of the sample is less than fcu,
Thus ft = fcu + z
ft = fcu + 1.64s
Conditions
Good 45
Fair 57
Poor >7
3 STORMWATER DRAINAGE
3.1 SCOPE
This manual covers the design of open drains (lined and unlined), pipe culverts and shelverts. The design
of box culverts and bridges is addressed in the Structural Design Manual.
3.2 GUIDELINES
Drains should be placed along the higher side of the road to avoid a lot of water crossing and
flooding the road along the natural gradient along the roadside.
Catchment areas for drainage structures should be obtained using a plannimeter or by scaling
off. Allow a 150mm drop at the outlet for a self-cleansing culvert.
Take 600mm culvert as minimum (easy maintenance) and use 750mm for main outlets and
450mm for stand access
Culvert velocity should be 1 3.5 m/s to avoid both silting and scouring
Open drains with velocity > 0.75m/s or which are > 1.5m deep should be lined to avoid erosion
and collapse respectively
Relief culverts along highways should be placed at 500m intervals
Material below culvert to be stabilised if expansive
Mitre drain spacing to be 200 250m
For box culvert the preferred width to height ratio is 1.
A hydraulic analysis helps to select the required pipe. For short pipes the flow conditions are dependent
on the inlet and outlet conditions. These are the flow controls.
For an inlet control system (usually steep gradient) the inlet controls the amount of water entering and
hence the amount of flow. For an outlet control system (shallow gradient/ blocked end) friction or
downstream water level controls the amount of flow. Energy losses at the outlet and inlet points far
exceeds all other losses.
For long pipelines the flow conditions are dictated by steady flow conditions. Stormwater pipes are
designed to flow full. Sewer pipes are designed to flow partially full (3/4 or 2/3). Pipelines flowing under
gravity use difference in levels to bring about flow. We therefore check parameters like Q, v, etc for
their suitability
The relevant drainage structure is obtained from the attached Part F: Fig. 9 for culverts. The table below
can be used as a guideline.
Table 3-A : Culvert Size and Required Catchment Areas
1 x 750mm 3 ha
2 x 600mm 8ha
3 x 600mm 15ha
3 x 750mm 30ha
3 x 900mm 50ha
RATIOS
A/Af = r2 ( sin )/ r2 =1/(2 ) ( sin )
R/Rf = r (1 sin / )/ r = (1 sin / )
v/vf = (1/n) s1/2 ( r) 2/3 (1 sin / )2/3/(1/n) s1/2 ( r) 2/3 = (1 sin / )2/3
Q/Qf = r (1 sin / ) (1/n) s1/2 ( r) 2/3 (1 sin / ]2/3 / (1/n) s1/2 r8/3 2/3
Q/Qf = 1/(2 ) [( sin ) (1 sin / ) 2/3]
d/D = d = r ( 1 cos )/2r = ( 1 cos )
4.1 INTRODUCTION
A water supply system encompasses the raw water supply, treatment works and the distribution network.
4.2 WATER SUPPLY SCHEME DESIGN PARAMETERS
Type Size
City of Harare Ministry of Local Govt
High density <500m2 <400m2
Medium density 500 1000m2 400 1000m2
Low density >1000m2 >1000m2
The general layout and design factors are as shown on the attached Water Supply Scheme.
Peak Month Factor (PMF)
The ratio of the water demand during the month with the highest demand in a year over the daily
demand and is commonly taken as 1.25.
PMF = (MMWD/AADWD) = 1.25
Usually 3 to 6 %. This can only be fixed after a study of the design area.
4.2.5 DESIGN PERIOD
Usually 10 to 25 years. This depends on the expected life span of design materials and expected
development scenario.
4.2.6 PRESSURE
Minimum 10m and maximum 60m for gravity main in residential areas. This ensures that water gets to
the required destination without bursting water main.
4.2.7 VELOCITY
If steel is required use GI for sizes < 125 (and mild steel for sizes > 125). Steel pipes need some form of
corrosion protection; (bitumen coating, epoxy coating, coupon painting and aluminium painting). Steel
pipes are very expensive but robust and easier to fabricate into funny shapes. Thus steel pipes are usually
used only in pump stations and stream crossing, where robustness is required, pipes sometimes are
exposed and a lot of complicated shapes encountered.
The thickness of a steel pipe is given by;
t = PD Fs/2y
where t = pipe thickness in mm
P = working pressure in Mpa
D = outside pipe diameter in mm
y = yield stress in Mpa (assume 250Mpa)
Fs = safety factor (usually 2 when water hammer is unlikely)
4.4.5.2 Input
Input the following into the analysing programme
Nodes & Pipes
Demands ( ve)
Reservoir level (fixed)
Design peak factor (= 3)
Hazen Williams coefficient C
Table 4-F: Pipe Material Constants
Pipe Material C
PVC 140
AC 130
Steel/ GI 110
GRP 146 150
Note: Bigger C means smoother pipe and lower head loss. A 20% increase in C may result in a 40%
decrease in head loss.
4.4.5.3 Analysis Basis
The software analysis is based on the Hardy Cross Method, which assumes the following basic principles;
Flow entering a junction is equal to flow leaving a junction
The head loss leading to any particular node is the same despite the route taken to go to that
node
The head loss is calculated from the Hazen Williams Formula;
v = 0.82 C m0.6 i0.54
where v = velocity in m/s
C = Hazen Williams coefficient (see above)
m = hydraulic radius = Area/Perimeter = r2/2r = r = D (diameter)
i = hydraulic gradient, head loss per unit length (m/100m)
= 1000kg/m3
Suppose the flow Q in one pipe is distributed into two pipes with flows Q 1 and Q2. Then;
v = 0.85 C R0.63 h0.54 general formula
Q = Av = 0.85 C A R0.63 h0.54 i.e. h0.54 = Q/ 0.85 C A R0.63
Q1 = Q Q 2
h10.54 = Q1/ 0.85 C1 A1 R10.63 = Q2/ 0.85 C2 A2 R20.63 head loss in the same in each pipe
Q1/ 0.85 C1 A1 R10.63 = (Q Q1)/ 0.85 C2 A2 R20.63
Q1/ 0.85 C1 A1 R10.63 = Q / 0.85 C1 A1 R10.63 Q1/ 0.85 C2 A2 R20.63
Let 0.85 C A R0.63 = K
Q1/ K1 = Q /K2 Q1/K2
Q1/ K1 + Q1/K2 = Q /K2
Q1(1/ K1 + 1/K2 ) = Q /K2
Q1(K1 + K2 ) / (K1 K2 ) = Q /K2
Q1 = Q(K1 K2 ) / K2 (K1 + K2 ) Flow Distribution.
Let h0.54 = Q/K = x i.e. Q = Kx is the same
From Q = Q1 + Q 2
Kx = K1 x + K2 x
K = K1 + K 2
5.1 INTRODUCTION
Sewerage disposal systems consist of collection (reticulation) works, treatment works and disposal works.
5.1.2 GENERAL NOTES
For low residential areas where there is space on each stand it is cheaper to use septic tanks. Sewer lines
therefore are usually confined to medium and high-density areas. Sewer lines usually run in between the
stands for residential houses. Loops, very deep manholes and sharp bends should be avoided
Site clearance is usually 2m and the minimum self-cleansing velocity = 0.75m/s (collectors and
reticulation) and 0.6 m/s (outfall). The maximum velocity to avoid scour is 3m/s. Excavations can be
minimised by crossing contours. Deep excavations cannot be avoided where contours have to be followed
(very flat area). Where gravity flow is unattainable, pumps can be used as an alternative.
Drop inlets should be used where the drop is >600mm, and should have a manhole or roding way. Pipes
should always be laid soffit to soffit. Assume invert level to be at least 0.6m at the head.
5.2 DESIGN FACTORS
AWDF The average dry weather flow is expressed as a percentage of the daily water demand
MDWF The maximum dry weather flow MDWF = AWDF x PF (peak factor)
The peak factor caters for fluctuations in flow and mainly the inflow from ground water. Smaller
flows have higher peak factors (more affected by groundwater inflow)
The MDWF is the design flow
The average dry weather flows are;
Table 5-A: Average Sewerage Return Factors
Sewer lines are designed as open channels and usually flowing 2/3 or full (d/D). The critical design
parameters are pipe size (capacity to carry flow), gradients and velocity.
Table 5-D: Minimum and Maximum Pipe Gradients
Product Suppliers
PVC Proplastics (Prodorite, Promat)
AC Turnall Fibre Cement
Steel Morewear, Warrap Engineering, De Souza, AMA
Concrete Fort Concrete, Hume Pipes
Earthenware Clay Products
Pumps (Relmo, Flyght) HE Jackson, J W Searcy, Cochrane, Africa Sales
Submersibles can pump up to about 45m. Centrifugal pumps can take much more head. The type of pump
to be used will determine the configuration of the pump station (flooded suction, dry well etc)
Assume a number (10 15 say) of starts per hour, n = 10 say or as specified by manufacturer.
Calculate cycle time T = 60minutes/n starts
Pumping time tp is cycle time ( T min)
Let Qin = inflow and Qp = pumping rate
Qp = 2Qin ( pumping resting)
5.5.1 INTRODUCTION
There are basically two methods of treatment of wastewater, which are mechanical aided and natural
pond system. The choice for the proper treatment methods depends on the following factors;
Mechanical methods need higher capital and maintenance costs
Natural methods are very dependent/ affected by natural phenomena such as temperature, rain
etc
Ponds require a lot of land due to high retention periods
Fly and odour problems can result from malfunctioning ponds
The design is based on BS 6297: 1983 Design and Installation of Small Sewerage Works and Cesspools.
Septic Tank
Tanks Capacity C = 180 P + 2000 >= 2720 litres where P = population
Note: 180 is made up as follows; 12 hrs storage (1/2 day at 120l/day) 60 l
Infiltration 30 l
Sludge storage 90 l
Total 180 l
The tank geometry is obtained by assuming width W = 0.9m, height H = 1.2m for P =<10 and 1.5 for P> 10
Design Philosophy
It is required to find the volume of each pond and subsequently the geometry (area) based on an
assumed depth. Anaerobic and maturation ponds are designed based on the hydraulic loading being
retained over a given retention period. Facultative ponds are designed based on the biological (BOD)
loading.
Anaerobic ponds have to be deep to avoid oxidation conditions and depth of 3 6m can be assumed.
Facultative and maturation ponds depend on oxidation and are thus shallower with depth of 1.2 1.5m.
In general the length to width ratio for all ponds is between 2 and 3.
Anaerobic Ponds
Assumed retention time 18hrs
Design flow AADWF Q m3/d
Peak factor P 3
Pond depth D 3m
Facultative Pond
Retention Period in days T = P 1/(C Pmax)
Where P assume a specific BOD reduction P = 0.5L mg/l for 50%reduction
C is a constant C = 0.17
Pmax = 600/(2x1.2+8) = 57.69 P = 57.69
Maturation Pond
Assume two set of pond with retention times of 5 and 10 days respectively.
Pond Volume V m3 = Q m3/d x T days
Pond area A m2 = V m3/ Dm
6 HYDRAULIC STRUCTURES
An x year flood or a 1: x flood has a probability of 1/x of being equated or exceeded in any one year. The
return period is the average interval expected between occurrences of a flood of a certain magnitude.
6.3.2 DISTRIBUTIONS
Common distributions used for flood calculation include the Normal, Log Normal, Pearson, Log Pearson III,
Log Gumbel and Weibull. The Wiebull is shown below.
6.4 FACTORS TO CONSIDER DURING DAM DESIGN
Foundation properties
Valley shape
Construction material availability
The design of canals is based on the Agritex Irrigation Manual Second Edition 1994. The design is based
on the Mannings Formular. Slopes of 1:300 to 1:2000 have been used with velocities of 0.2 1m/s. A
slope of 60o is usually assumed on the sides.
Table 6-B: Canal Friction Coefficients (K = 1/n)
Surface K Value
Clean 25 40
Light Vegetation 15 25
Heavy Vegetation < 15
Sand Cement 65 90
Concrete Lined 55 80
The freeboard is the safety distance allowed for between the expected flow level and the top of the canal.
The freeboard F is calculated as
F = C h0.5 where h = depth of flow and
Table 6-D: Freeboard Values for Different Discharges
Discharge (m3/s) C
Earth Canals 0.5 0.8
80 1.35
Lined Canals 5 0.4
50 1.2
7 CONTRACT ADMINISTRATION
Projects can be building or civil. Project Members include Clients, Architects, Town Planners, Engineers,
Quantity Surveyors, Contractors, Engineering Surveyors, Testing Laboratories and Local Authorities. The
execution of our part of the works involves interacting with most of all these people.
7.2 TENDER DOCUMENT
Names of the Client, Project and Consultants, contact detail and dates
7.2.2 BIDDING INSTRUCTIONS
Invitation to tender, list of bidding documents including drawings, bidders eligibility, site visits,
submission time and place, returnable documents, tender evaluation and contract award criteria.
7.2.3 CONTRACT CONDITIONS
Parties to the contract, duties and responsibilities, payment and contract termination, particular
conditions of contract.
7.2.4 SPECIFIC CATIONS
Preliminary and generals, extent of works, site conditions, material and workmanship specifications,
applicable legislation and environmental management plan. Covers site clearance, excavations,
earthworks, pipe work, concrete works, steel work etc.
7.2.5 ATTACHMENTS
Bid authority, available plant and staff, subcontractors, cash flow projections, basic price lists, programme
of works, qualifications by tenderer, site visit records, tax clearances.
7.2.6 AGREEMENT
Plant costs account for probably the highest costs for the civil engineering contractor, especially when we
consider earthworks, which require more of plant than material or labour input. Invariably the largest
component of total project increase costs are expected here therefore it is crucial for the Contract and
Client to agree on the evaluation of these costs since this may lead to loss by either party.
Several methods have been used for evaluating plant increase costs and these include;