Designed for project planning and scheduling that uses probabilistic activity times.
Stochastic PERT
Project scheduling technique in which the activity times are of probabilistic nature
Deterministic PERT
Project scheduling technique in which the activity time are assumed to be known with certainty
1. Optimistic Time is a PERT activity time estimate based on the assumption that it would take the
shortest possible time to complete an activity if everything went right.
2. Most Probable Time is a PERT activity time estimate based on the assumption that the time
would occur most frequent if the activity is repeated many times.
3. Pessimistic Time is a PERT activity time estimate based on the assumption that it would take the
longest possible time to complete an activity if everything went wrong.
The Sigma Bravo Company is planning to develop a new chemical process. They have the following
activities:
A. Test method 1 for the process
B. Test method 2 for the process
C. Select the best method and refine the process
D. Complete initial preparation of production facilities.
E. Train personnel
F. Develop final procedures manual
G. Run tests on the refined process
H. Adjust the production method
I. Set up complete production system
J. Run final tests
Activity Immediate Optimistic (a) Most Pessimistic
Predecessor Probable (m) (b)
A - 10 15 26
B - 8 10 18
C A,B 4 5 6
D - 10 12 14
E D 1 2 3
F D 1 3 11
G C,E 1 2 3
H F,G 2 2 2
I F 3 4 5
J H,I 1 2 3
a. Develop a project network and determine the expected project completion time.
b. What is the probability that the project completion will meet the 30-week deadline?
Steps.