Sei sulla pagina 1di 1

STRAIGHT LINE DIAGRAM

CP 5B.1 - SICMIL BRIDGE AND APPROACHES, GIGMOTO, CATANDUANES

Sta. 66+040

Sta. 66+080

Sta. 66+120

Sta. 66+160

Sta. 66+200

Sta. 66+240

Sta. 66+280

Sta. 66+320

Sta. 66+360

Sta. 66+400

Sta. 66+440

Sta. 66+480
Back of Backwall
Sta 66+296.396

Back of Backwall
Sta 66+343.265

End of Proj.
Beg. of Proj.
Sta 66+080

Sta 66+470
Slope Protection
ORIGINAL

PCCP Bridge Approach


Bridge
Bridge
PCCP Bridge Approach
Slope Protection
Detour Bridge

Slope Protection
PCCP Bridge Approach
F.V.O.

Bridge
Bridge
PCCP Bridge Approach
Slope Protection
Detour Bridge

LEGEND

ITEM 302 (2), ITEM 310 (1)

ORIGINAL SCOPE OF WORKS

DELETION OF ITEM 302 (2) and ITEM 310 (1)


AND INCREASE IN ITEM 400(1) b-2 and ITEM 405(1) c

CONTRACTOR CONSULTANT DPWH


Prepared and Submitted by: Checked and Reviewed by: Concurred by:

Project Manager Deputy Project Manager Project Manager