Purpose
This specification outlines the requirements for design, procurement, location and installation of gas and liquid
sampling equipment used at Receipt Points on Spectra Energy Transmission (SET) West Raw Gas Transmission
(RGT) systems.
Responsibility
Responsibility for ensuring this specification is followed resides with the designer, owner and operator of Receipt
Point measurement facilities on SET West RGT systems.
A Bureau of Mines type chilled mirror dew point tester meeting ASTM D1142 and/or GPA 2140 standards
with a supply of chill gas must be permanently installed at the Receipt Point. The specific model supplied
must be manufacturer approved for sour gas application and have a pressure rating equal to or greater than
the maximum allowable operating pressure of the receipt point.
Exceptions
The specifications stated in this document are minimum requirements; additional specifications may be necessary
when circumstances warrant. Exemptions from these specifications are not permitted without the written permission
from SET Measurement Technical Services.
Revision History
Rev-0: March 30, 2007 KC Original Issue Approved by K. Checkwitch & G. Parmar
Rev-1: April 15, 2014 ATL Updated sample probe requirement to Genie A+ GPHV. Approved
by K. Checkwitch & G. Parmar