9/14/2017 The most important phase of a project is the planning phase, not the execution.

" Do you agree with this statement? Why or why not? | Eng


Top Q&A Contributors

1 Mahmoud El Refaie (/users/view/2) 12


2 Mahmoud Omara (/users/view/107) 11
3 Engr. Mohammad Mallick - MBA. (/users/view/46) 10
4 Ahmad Jan - PMP (/users/view/196) 6
5 Hany Ismael (/-hanycv) 4
6 Muhammad Mamdouh Amer Elsayed Muhammad (/users/view/108) 2
7 Mohamed Amer (/users/view/293) 2
8 Soham Banerjee (/users/view/419) 1
9 GULAM MUJTABA KHAN (/users/view/157) 1
10 Muhammad Zahid (/users/view/50) 1

Highest Viewed Questions

(/questions/view/18/the-most-important-phase-of-a-project-is-the-planning-phase-not-the-ex)The most important phase of a project is the planning phase, not the execution." Do you agree with
this statement? Why or why not? (/questions/view/18/the-most-important-phase-of-a-project-is-the-
planning-phase-not-the-ex)

(/questions/view/24/how-do-u-measure-amp-compare-the-progress-using-primavera)How do u measure & compare the progress using primavera? (/questions/view/24/how-do-u-measure-amp-


compare-the-progress-using-primavera)

(/questions/view/4/what-is-an-s-curve-and-how-to-create-s-curve-in-primavera)What is an S Curve and how to create S Curve in primavera? (/questions/view/4/what-is-an-s-curve-and-how-to-


create-s-curve-in-primavera)

(/questions/view/19/cost-control-engineer)Cost Control Engineer (/questions/view/19/cost-control-engineer)

(/questions/view/2/open-end-activities)Open End Activities (/questions/view/2/open-end-activities)

(/questions/view/6/what-are-the-reasons-of-negative-float)What are the reasons of negative float? (/questions/view/6/what-are-the-reasons-of-negative-float)

(/questions/view/11/how-to-create-2-week-look-ahead-schedule-in-p6)How to create 2 Week look ahead schedule in P6 ? (/questions/view/11/how-to-create-2-week-look-ahead-schedule-in-p6)

(/questions/view/12/how-can-i-update-5000-activity-time-schedule-in-primavera-p6)How can i update 5000 Activity time schedule in primavera p6 ? (/questions/view/12/how-can-i-update-5000-


activity-time-schedule-in-primavera-p6)

(/questions/view/13/start-and-finish-milestones-are-not-showing-in-my-activity-table)START AND FINISH MILESTONES ARE NOT SHOWING IN MY ACTIVITY TABLE ?


(/questions/view/13/start-and-finish-milestones-are-not-showing-in-my-activity-table)

(/questions/view/5/how-to-avoid-negative-float)How to avoid negative float? (/questions/view/5/how-to-avoid-negative-float)

The most important phase of a project is the planning phase, not the execution." Do you agree with this
statement? Why or why not?

The most important phase of a project is the planning phase, not the execution." Do you agree with this statement? Why or why not?

Engr. Mohammad Mallick - MBA. (/users/view/46) 2 days, 21 hours ago in Project Management (/questions/index/all/category/44)
0

Mosa
Pangandama
n, Jr
(/users/view/
360)

I totally disagree with you Sir! Execution is the most important part to turn your plan into reality. No matter how good your plan is, if your
execution stage is worst. This will affect your perfect plan and cause delay in the project milestone and additional cost in your target budget. If
you have good execution, then that means your project is going according to your plan.
2 days, 1 hour ago . Edited (/questions/content_history/Comment/4)

Add comment

5 Answer(s)
Active (/questions/view/18/the-most-important-phase-of-a-project-is-the-planning-phase-not-the-ex?tab=active)
Votes (/questions/view/18/the-most-important-phase-of-a-project-is-the-planning-phase-not-the-ex?tab=vote)
Oldest (/questions/view/18/the-most-important-phase-of-a-project-is-the-planning-phase-not-the-ex?tab=old)

Best answer

I am agree with you. No matter what the project size is planning is important. If you are not planning then you are asking for trouble. And if you
0
are not planning for your project then you are planning to fail. I know a company who was thinking that Execution is more important than
Chat (1)

http://engineerbook.net/questions/view/18/the-most-important-phase-of-a-project-is-the-planning-phase-not-the-ex 1/2
9/14/2017 The most important phase of a project is the planning phase, not the execution." Do you agree with this statement? Why or why not? | Eng

planning. They never did any planning. There was no Baseline Schedule. There was no Cost Baseline. They were just executing the project on
instructions of their client. The project duration was 546 days but the project is still in progress after 6.5 yrs. Due to Scope Creep the project is
not in control and there are so many issues in formally accepting the project deliverable because no body knows who incorporated the change.
The company has spent almost double of what was their Project Price. The company is going to be blacklisted for ever.
Conclusion:
Plan well before going into execution otherwise be ready for a nightmare.

Ahmad Jan - PMP (/users/view/196) 2 days, 3 hours ago . Edited (/questions/content_history/Answer/11)

Romeo
Cornista (/-
Romeo)

Agree on this, in order to be successful in execution the contractor who will do the task should be involved in the planning stage to agree on
every milestone that was planned and they should be accountable for the outcome not only at the completion of each task.
1 day, 17 hours ago

Add comment

Nice Question Engineer Mohammad, I would say that the planning phase in any construction project is very important. However, the most
important is the execution phase. The reason i say so, you can start and finish the project without planning, yes you will pay more money, more
1 time, and maybe less quality, but at the end of the day, you will have your project finished. In the other hand, no project can be finished without
execution regardless of how accurate your planning is.

Conclusion: Execution stage is more important that planning stage.

Who agrees with me?

Hany Ismael (/-hanycv) 2 days, 21 hours ago

Sankar
Ramasamy
(/users/view/
295)

Yes ur correct.
2 days, 16 hours ago

GULAM
MUJTABA
KHAN
(/users/view/
157)

I agree
2 days, 6 hours ago

mumtajakram
(/users/view/
481)

i agree ...execution stage importan


6 hours, 57 minutes ago

Add comment

I will disagree with you. Most important phase is construction phase as explained by Engr. Hany.

Muhammad Zahid (/users/view/50) 1 day ago

Add comment

Mr. Ahmad Jan (/users/view/196) & Mr. Hany Ismael (/-hanycv) with both i am a gree