WBS Dictionary (Task Description): Procurement

Project name: ETB build Task #1.3 Date Issued: 15/06/2017 Person Assigned 10_
Assembly Line
Task Description (what work is authorized) Procurement of items for the equipments and building materials.

Quantified Objectives (See the description in the Project Charter) 40 hours a week with a budget of 1,000,000 and a resource persons of
#10
Product Description (what is the end result of the work package?)

The purchase order for the building and equipment meterials will be finalized.
Acceptance Criteria (how will the team member be able to check their work?)

A senior member is closely monitoring the activities of the team members.


Deliverables (See the description in the project charter)

The purchase order is mailed to the vendors for the procurement of the meterial
Assumptions : The of the supplying vendors is considered to be experienced in dealing with auto industry.

Resources assigned No of labour force allocated # 10 and a budget of 1,000,000.

Duration: 92 hours

Cost : $1,000,000
Due Date : 22/06/2017
Interdependencies: The design activities has to be completed before the procurement.

Approved by: Project Manager Anish T 15/06/2017

WBS Dictionary (Task Description): Procurement ( Building )

Project name: ETB build Task #1.3.1 Date Issued: 15/06/2017 Person Assigned 2_
Assembly Line
Task Description (what work is authorized) Procurement of items building materials.

Quantified Objectives (See the description in the Project Charter) : The procurement for the building material to be completed well before
the due date
Product Description (what is the end result of the work package?)

The purchase order for the building can be finalized


Acceptance Criteria (how will the team member be able to check their work?): The level of response to the tender notice and the number
of received quotations in an indication of the performance and efficacy at this stage.
Deliverables (See the description in the project charter) :The purchase order is mailed to the vendors for the procurement of the material

Assumptions: The supplying vendors is considered to be experienced in dealing with auto industry.

Resources assigned: No of labour force allocated # 10 and a budget of 1,000,000.

Duration: 27 hours

Cost : $300,000
Due Date : 17/06/2017
Interdependencies: The design activities has to be completed before fixing the quotation

Approved by: Project Manager Anish T 15/06/2017


WBS Dictionary (Task Description): Collating the received quotations

Project name: ETB build Task #1.3.2 Date Issued: 17/06/2017 Person Assigned 2_
Assembly Line
Task Description (what work is authorized) Procurement of items for the equipments and building materials.

Quantified Objectives (See the description in the Project Charter ) . Collating the quotations and juxtaposing considering the practical and
economic factors
Product Description (what is the end result of the work package?)

The quotation can be placed to the most suitable vendor


Acceptance Criteria (how will the team member be able to check their work?)

The response of the tender notice is an indication of the efficacy at this stage
Deliverables (See the description in the project charter)

The selected vendor is giving an intimation about the procedures for material procurement
Assumptions : The vendor has enough stock in his warehouse for immediate supply

Resources assigned No of labour force allocated # 2 and a budget of 30,000

Duration: 8hours

Cost : $30,000
Due Date : 21/06/2017
Interdependencies: The collating of orders has to be completed before placing the order

Approved by: Project Manager Anish T 17/06/2017

WBS Dictionary (Task Description): Placing the Order

Project name: ETB build Task #1.3.3 Date Issued: 21/06/2017 Person Assigned 2_
Assembly Line
Task Description (what work is authorized) Procurement of items building materials.

Quantified Objectives (See the description in the Project Charter) : The procurement for the building material to be completed well before
the due date
Product Description (what is the end result of the work package?)

The purchase order for the building can be finalized


Acceptance Criteria (how will the team member be able to check their work?): The level of response to the tender notice and the number
of received quotations in an indication of the performance and efficacy at this stage.
Deliverables (See the description in the project charter) :The purchase order is mailed to the vendors for the procurement of the material

Assumptions: The supplying vendors is considered to be experienced in dealing with auto industry.

Resources assigned: No of labour force allocated # 10 and a budget of 1,000,000.

Duration: 19 hours

Cost : $210,000
Due Date : 25/06/2017
Interdependencies: The design activities has to be completed before fixing the quotation

Approved by: Project Manager Anish T 21/06/2017


WBS Dictionary (Task Description): Procurement ( Equipment)

Project name: ETB build Task #1.3.2 Date Issued: 15/06/2017 Person Assigned 4
Assembly Line
Task Description (what work is authorized) Procurement of items for the equipment.

Quantified Objectives (See the description in the Project Charter): The procurement of the equipment has to be carried out well in
advance before the fabrication of the assembly starts
Product Description (what is the end result of the work package?)

The purchase order equipment will be finalized.


Acceptance Criteria (how will the team member be able to check their work?)

The time delay for the procurement is a negative measure of the efficacy in this stage
Deliverables (See the description in the project charter)

The purchase order is mailed to the vendors for the procurement of the equipment
Assumptions : The of the supplying vendors is considered to be experienced in dealing with auto industry.

Resources assigned No of labour force allocated # 10 and a budget of 1,000,000.

Duration: 65hours

Cost : $700,000
Due Date : 17/06/2017
Interdependencies: The design activities has to be completed before the procurement.

Approved by: Project Manager Anish T 15/06/2017

WBS Dictionary (Task Description): Tender Notice Equipment

Project name: ETB build Task #1.3.2.1 Date Issued: 15/06/2017 Person Assigned 4
Assembly Line
Task Description (what work is authorized): Tender Notice for the equipment

Quantified Objectives (See the description in the Project Charter): A highty circulated tender advertisement with all the necessary factors
and constraints to be presented in a transparent manner to attract the vendors /manufacturers.
Product Description (what is the end result of the work package?)

The quotations will be receiving from the vendors/manufactures


Acceptance Criteria (how will the team member be able to check their work?)

The number of received quotatons is an indication about the performance at this stage
Deliverables (See the description in the project charter)

The tender notice will provide the response from the vendors/manufacturs regarding the availability
Assumptions : The vendors/manufactures have enough logistics to supply the equipment at the earliest

Resources assigned No of labour force allocated # 4 and a budget of 70,000.

Duration: 10hours

Cost : $70,000
Due Date : 17/06/2017
Interdependencies: The design has to be completed before the procurement.

Approved by: Project Manager Anish T 15/06/2017


WBS Dictionary (Task Description): Collating the Quotations

Project name: ETB build Task #1.3.2.2 Date Issued: 17/06/2017 Person Assigned 3
Assembly Line
Task Description (what work is authorized): This stage aims at collecting the received quotations and sorting out the possible
vendors/manufactures
Quantified Objectives (See the description in the Project Charter): The objective at this stage is to collate the quotations so as to finalize
the purchasing order
Product Description (what is the end result of the work package?)

The placing of purchasing order


Acceptance Criteria (how will the team member be able to check their work?)

The dynamics of the selection of the received quotations in an indication of efficancy


Deliverables (See the description in the project charter)

The purchase order can be placed depending on the sorting of the received quotations
Assumptions : The vendors/manufactures have enough logistics to supply the equipment at the earliest

Resources assigned No of labour force allocated # 3 and a budget of 70,000.

Duration: 15hours

Cost : $500,000
Due Date : 21/06/2017
Interdependencies: The design has to be completed before the procurement.

Approved by: Project Manager Anish T 17/06/2017

WBS Dictionary (Task Description): Placing the Order

Project name: ETB build Task #1.3.2.3 Date Issued: 21/06/2017 Person Assigned 3
Assembly Line
Task Description (what work is authorized): This stage aims at placing the most practical vendor/manufacturer depending upon factors
such as time, cost etc.
Quantified Objectives (See the description in the Project Charter): The objective at this stage is to place the order for the procurement of
the equipment
Product Description (what is the end result of the work package?)

The assembly fabrication can start with the procurement of the equipment
Acceptance Criteria (how will the team member be able to check their work?)

The speed of response of selecting the right quotation is an indication of efficency


Deliverables (See the description in the project charter)

The procurement can help in starting the fabrication


Assumptions : The vendors/manufactures have enough logistics to supply the equipment at the earliest

Resources assigned No of labour force allocated # 3 and a budget of 500,000.

Duration: 15hours

Cost : $500,000
Due Date : 28/06/2017
Interdependencies: The design has to be completed before the procurement.

Approved by: Project Manager Anish T 21/06/2017


WBS Dictionary (Task Description): Managing the Installation

Project name: ETB build Task #1.3.2.4 Date Issued: 27/06/2017 Person Assigned 3
Assembly Line
Task Description (what work is authorized): This stage aims at managing the installation

Quantified Objectives (See the description in the Project Charter): The objective at this stage is to manage the installations in a timely
effective manner
Product Description (what is the end result of the work package?)

The assembly fabrication can start with the procurement of the equipment
Acceptance Criteria (how will the team member be able to check their work?)

The speed of response of selecting the right quotation is an indication of efficency


Deliverables (See the description in the project charter)

The procurement can help in starting the fabrication


Assumptions : The vendors/manufactures have enough logistics to supply the equipment at the earliest

Resources assigned No of labour force allocated # 3 and a budget of 13,000.

Duration: 14hours

Cost : $13,000
Due Date : 01/07/2017
Interdependencies: The placing of order has to be completed before managing the installation

Approved by: Project Manager Anish T 27/06/2017

WBS Dictionary (Task Description): Sign Maintenance

Project name: ETB build Task #1.3.2.5 Date Issued: 01/07/2017 Person Assigned 4
Assembly Line
Task Description (what work is authorized): This stage aims at the maintenance

Quantified Objectives (See the description in the Project Charter): The objective at this stage is to sign the maintenance

Product Description (what is the end result of the work package?)

The assembly fabrication can start with the procurement of the equipment
Acceptance Criteria (how will the team member be able to check their work?)

The time for the managing the final activiy of this stage can be considered as an indication of the working pattern of the involved people.
Deliverables (See the description in the project charter)

The procurement can help in starting the fabrication


Assumptions : The vendors/manufactures have enough logistics to supply the equipment at the earliest

Resources assigned No of labour force allocated # 4 and a budget of 13,000.

Duration: 15hours

Cost : $13,000
Due Date : 05/07/2017
Interdependencies: The placing of order has to be completed before managing the installation

Approved by: Project Manager Anish T 01/07/2017


WBS Dictionary (Task Description): Sign Maintenance

Project name: ETB build Task #1.3.2.5 Date Issued: 01/07/2017 Person Assigned 4
Assembly Line
Task Description (what work is authorized): This stage aims at the maintenance

Quantified Objectives (See the description in the Project Charter): The objective at this stage is to sign the maintenance

Product Description (what is the end result of the work package?)

The assembly fabrication can start with the procurement of the equipment
Acceptance Criteria (how will the team member be able to check their work?)

The time for the managing the final activiy of this stage can be considered as an indication of the working pattern of the involved people.
Deliverables (See the description in the project charter)

The procurement can help in starting the fabrication


Assumptions : The vendors/manufactures have enough logistics to supply the equipment at the earliest

Resources assigned No of labour force allocated # 4 and a budget of 13,000.

Duration: 15hours

Cost : $13,000
Due Date : 05/07/2017
Interdependencies: The placing of order has to be completed before managing the installation

Approved by: Project Manager Anish T 01/07/2017

WBS Dictionary (Task Description): PCBA Fabrication of the Assembly Line

Project name: ETB build Task #1.4 Date Issued: 05/07/2017 Person Assigned 4
Assembly Line
Task Description (what work is authorized): This stage aims at building the printed circuit board for the assembly line.

Quantified Objectives (See the description in the Project Charter): The objective at this stage to have a fabricated printed circuit board for
the assembly line
Product Description (what is the end result of the work package?)

The mechanical work can be started on finished the electrical work


Acceptance Criteria (how will the team member be able to check their work?)

The complexity and the level of accuracy of the fabricated board with respect to the design can be used to evaluate the work.
Deliverables (See the description in the project charter)

The mechanical work can be started on finishing the printed circutis board
Assumptions : The PCBA fabrication facility is located near to the design lab

Resources assigned No of labour force allocated # 4 and a budget of 500,000.

Duration: 46hours

Cost : $500,000
Due Date : 12/07/2017
Interdependencies: The material and equipment procurement has to carried out before the process of PCB

Approved by: Project Manager Anish T 05/07/2017


WBS Dictionary (Task Description): Etching

Project name: ETB build Task #1.4.1 Date Issued: 05/07/2017 Person Assigned 4
Assembly Line
Task Description (what work is authorized): This stage aims at Etching for the Printed Circuit Board

Quantified Objectives (See the description in the Project Charter): The objective at this stage to have a fabricated printed circuit board for
the assembly line
Product Description (what is the end result of the work package?) The etching of the printed circuit board is to be carried out.

Acceptance Criteria (how will the team member be able to check their work?)

The speed of operation can effectively measure the work volume by the involved labour resources
Deliverables (See the description in the project charter)

The HASL can be carried out on completing the process of etching


Assumptions : The PCBA fabrication facility is located near to the design lab

Resources assigned No of labour force allocated # 4 and a budget of 120,000.

Duration: 9hours

Cost : $120,000
Due Date : 07/07/2017
Interdependencies: The process of etching can start only after the procurement of the meterials.

Approved by: Project Manager Anish T 05/07/2017

WBS Dictionary (Task Description): HASL Coating

Project name: ETB build Task #1.4.2 Date Issued: 07/07/2017 Person Assigned 1
Assembly Line
Task Description (what work is authorized): Hot air solder levelling is performed for the finishing of the printed circuit board

Quantified Objectives (See the description in the Project Charter): The objective at this stage to have a well polished finished printed
circuit board.
Product Description (what is the end result of the work package?) The finishing of the printed circuit board is carried out in this process.

Acceptance Criteria (how will the team member be able to check their work?)

The thermal stress on the fabricated board gives an indication about the quality of the work perfomed at this stage
Deliverables (See the description in the project charter)

The HASL finishing is necessary for the solder paste application


Assumptions : The thermal stress during this process wont affect the functional performance of the Printed Circuit Board

Resources assigned No of labour force allocated # 4 and a budget of 90,000.

Duration: 8hours

Cost : $90,000
Due Date : 09/07/2017
Interdependencies: The finishing process requires a fabricated PCB

Approved by: Project Manager Anish T 07/07/2017


WBS Dictionary (Task Description): Application of Solder Paste

Project name: ETB build Task #1.4.3 Date Issued: 09/07/2017 Person Assigned 1
Assembly Line
Task Description (what work is authorized): Application of Solder paste to the printed circuit board

Quantified Objectives (See the description in the Project Charter): The objective at this stage to apply the solder paste to the printed
circuit board
Product Description (what is the end result of the work package?) The use of solder paste is carried out in this session

Acceptance Criteria (how will the team member be able to check their work?)

The quality of operation with respect to the design of the PCB determines the quality of work
Deliverables (See the description in the project charter)

The pcb with solder paste is provide to the pick and place
Assumptions : A smooth of application of solder without much chemical degradation is assumed

Resources assigned No of labour force allocated # 4 and a budget of 80,000.

Duration: 8hours

Cost : $80,000
Due Date : 10/07/2017
Interdependencies: The application of solder paste requires finished PCB

Approved by: Project Manager Anish T 09/07/2017

WBS Dictionary (Task Description): Pick and Place

Project name: ETB build Task #1.4.4 Date Issued: 10/07/2017 Person Assigned 1
Assembly Line
Task Description (what work is authorized): The implementation of pick and place is carried out in this stage

Quantified Objectives (See the description in the Project Charter): The soldering of components into the PCB is carried out in this stage

Product Description (what is the end result of the work package?) The soldering of components into the PCB in a automatic fashion is
carried out in this step.
Acceptance Criteria (how will the team member be able to check their work?)

The accuracy of the pick and place can evaluate the working at this session
Deliverables (See the description in the project charter)

The reflow soldering is carried out after component fixing


Assumptions : A smooth of application of solder without much chemical degradation is assumed

Resources assigned No of labour force allocated # 1 and a budget of 80,000.

Duration: 8hours

Cost : $80,000
Due Date : 11/07/2017
Interdependencies: The application of solder paste requires finished PCB

Approved by: Project Manager Anish T 10/07/2017


WBS Dictionary (Task Description): Reflow Soldering

Project name: ETB build Task #1.4.5 Date Issued: 10/07/2017 Person Assigned 1
Assembly Line
Task Description (what work is authorized): The reflow soldering is carried out to temporarily attach contact pads.

Quantified Objectives (See the description in the Project Charter): The temporal attachment of the contact pads to the fabrication board

Product Description (what is the end result of the work package?) The printed circuit board contact pads are being connected to the
components through the application of heat
Acceptance Criteria (how will the team member be able to check their work?)

The thermal stress on the printed circuit board is an indication of the work quality
Deliverables (See the description in the project charter)

The testing can be carried out after the process of reflow soldering
Assumptions : A smooth of application of reflow without much chemical degradation is assumed

Resources assigned No of labour force allocated # 1 and a budget of 70,000.

Duration: 8hours

Cost : $70,000
Due Date : 11/07/2017
Interdependencies: The application of solder paste requires finished PCB

Approved by: Project Manager Anish T 10/07/2017

WBS Dictionary (Task Description): Testing

Project name: ETB build Task #1.4.6 Date Issued: 11/07/2017 Person Assigned 3
Assembly Line
Task Description (what work is authorized): The entire testing of the printed circuit board is carried out

Quantified Objectives (See the description in the Project Charter): The conformant of the fabricated PCB with the theoretical design is
tested in this stage.
Product Description (what is the end result of the work package?) The testing of the PCB for various testing points of voltage and current is
performed.
Acceptance Criteria (how will the team member be able to check their work?)

The application of the suitable voltage and current at the right spot is an indication of work at this stage.
Deliverables (See the description in the project charter)

The mechanical work can be initiated on getting a green signal from the testing facility
Assumptions : A rigrous testing pattern considering the practical cases is assumed

Resources assigned No of labour force allocated # 1 and a budget of 70,000.

Duration: 8hours

Cost : $70,000
Due Date : 12/07/2017
Interdependencies: A fully completed PCB is needed for this stage.

Approved by: Project Manager Anish T 10/07/2017


WBS Dictionary (Task Description): Testing

Project name: ETB build Task #1.4.6 Date Issued: 11/07/2017 Person Assigned 3
Assembly Line
Task Description (what work is authorized): The entire testing of the printed circuit board is carried out

Quantified Objectives (See the description in the Project Charter): The conformant of the fabricated PCB with the theoretical design is
tested in this stage.
Product Description (what is the end result of the work package?) The testing of the PCB for various testing points of voltage and current is
performed.
Acceptance Criteria (how will the team member be able to check their work?)

The application of the suitable voltage and current at the right spot is an indication of work at this stage.
Deliverables (See the description in the project charter)

The mechanical work can be initiated on getting a green signal from the testing facility
Assumptions : A rigrous testing pattern considering the practical cases is assumed

Resources assigned No of labour force allocated # 1 and a budget of 70,000.

Duration: 8hours

Cost : $70,000
Due Date : 12/07/2017
Interdependencies: A fully completed PCB is needed for this stage.

Approved by: Project Manager Anish T 10/07/2017

WBS Dictionary (Task Description): Injection molding of the Assembly section

Project name: ETB build Task #1.5. Date Issued: 22/07/2017 Person Assigned 12
Assembly Line
Task Description (what work is authorized): The injection molding of the section of the assembly line is carried out in this session

Quantified Objectives (See the description in the Project Charter): The molding of the assembly stage is performed during this stage of
operation
Product Description (what is the end result of the work package?) The molded parts of the assembly line

Acceptance Criteria (how will the team member be able to check their work?)

The tolerance level withrespect to the dimensions of the die determines the work quality
Deliverables (See the description in the project charter)

The casting process is carried out on completing the molding stage


Assumptions : A well established tool and dye setup is assumed near to the assembly line

Resources assigned No of labour force allocated # 12 and a budget of 150,000.

Duration: 138hours

Cost : $150,000
Due Date : 15/10/2017
Interdependencies: A fully completed PCB is needed for this stage.

Approved by: Project Manager Anish T 22/07/2017


WBS Dictionary (Task Description): Injection molding of the Assembly section

Project name: ETB build Task #1.5. Date Issued: 22/07/2017 Person Assigned 12
Assembly Line
Task Description (what work is authorized): The injection molding of the section of the assembly line is carried out in this session

Quantified Objectives (See the description in the Project Charter): The molding of the assembly stage is performed during this stage of
operation
Product Description (what is the end result of the work package?) The molded parts of the assembly line

Acceptance Criteria (how will the team member be able to check their work?)

The tolerance level withrespect to the dimensions of the die determines the work quality
Deliverables (See the description in the project charter)

The casting process is carried out on completing the molding stage


Assumptions : A well established tool and dye setup is assumed near to the assembly line

Resources assigned No of labour force allocated # 12 and a budget of 150,000.

Duration: 138hours

Cost : $150,000
Due Date : 15/10/2017
Interdependencies: A fully completed PCB is needed for this stage.

Approved by: Project Manager Anish T 22/07/2017

WBS Dictionary (Task Description): Tooling

Project name: ETB build Task #1.5.1 Date Issued: 22/07/2017 Person Assigned 12
Assembly Line
Task Description (what work is authorized): The fixing of tools for the tool and dye operation

Quantified Objectives (See the description in the Project Charter): The molding of the assembly stage is performed during this stage of
operation
Product Description (what is the end result of the work package?) Tooling

Acceptance Criteria (how will the team member be able to check their work?)

The nature and the strength of the tool is an indication of the work quality
Deliverables (See the description in the project charter)

The tooling carried out for the pelleting operation


Assumptions : A well established tool and dye setup is assumed near to the assembly line

Resources assigned No of labour force allocated # 12 and a budget of 150,000.

Duration: 45hours

Cost : $150,000
Due Date : 30/07/2017
Interdependencies: The electrical activities has to be completed before the mechanical processes

Approved by: Project Manager Anish T 22/07/2017


WBS Dictionary (Task Description): Pellet Inspection

Project name: ETB build Task #1.5.2 Date Issued: 01/08/2017 Person Assigned 6
Assembly Line
Task Description (what work is authorized): The material is converted into pellets in this session

Quantified Objectives (See the description in the Project Charter): Pellets are created for the effective operation of molding

Product Description (what is the end result of the work package?) Pellets are obtained after this stage

Acceptance Criteria (how will the team member be able to check their work?)

The nature of pellets can assess the quality of work


Deliverables (See the description in the project charter)

The injection molding is carried out after pelleting


Assumptions : A well established tool and dye setup is assumed near to the assembly line

Resources assigned No of labour force allocated # 6 and a budget of 350,000.

Duration: 40hours

Cost : $350,000
Due Date : 15/08/2017
Interdependencies: The pellet inspection can be considered only after tooling

Approved by: Project Manager Anish T 01/08/2017

WBS Dictionary (Task Description): Injection molding

Project name: ETB build Task #1.5.3 Date Issued: 15/08/2017 Person Assigned 7
Assembly Line
Task Description (what work is authorized): The molding operation is carried out in this stage

Quantified Objectives (See the description in the Project Charter): The injection molding of the assembly section is performed in this
activity.
Product Description (what is the end result of the work package?) Molded parts of the assembly line are obtained

Acceptance Criteria (how will the team member be able to check their work?)

A senior is member is given a check list to carry out the evaluation within the group
Deliverables (See the description in the project charter)

The process of finishing can be carried out to the molded assembly line.
Assumptions : A well established tool and dye setup is assumed near to the assembly line

Resources assigned No of labour force allocated # 7and a budget of 400,000.

Duration: 30hours

Cost : $400,000
Due Date : 23/08/2017
Interdependencies: The inspection of pelleting is a key requirement for this stage

Approved by: Project Manager Anish T 15/08/2017


WBS Dictionary (Task Description): Finishing

Project name: ETB build Task #1.5.4 Date Issued: 23/08/2017 Person Assigned 5
Assembly Line
Task Description (what work is authorized): The finishing of the molded parts

Quantified Objectives (See the description in the Project Charter): A well finished and polished assembly line part is expected at the end
of this stage.
Product Description (what is the end result of the work package?) Finished assembly line

Acceptance Criteria (how will the team member be able to check their work?)

The acutal dimension with respect to the design is a matter of quality check in this stage
Deliverables (See the description in the project charter)

The finished mold is put under quality analysis and checking


Assumptions : A well established tool and dye facility is present near to the facility

Resources assigned No of labour force allocated # 5and a budget of 175,000.

Duration: 15hours

Cost : $175,000
Due Date : 29/08/2017
Interdependencies: A completed mold is required at this stage

Approved by: Project Manager Anish T 23/08/2017

WBS Dictionary (Task Description): Quality Check

Project name: ETB build Task #1.5.5 Date Issued: 29/08/2017 Person Assigned 5
Assembly Line
Task Description (what work is authorized): The finishing of the molded parts

Quantified Objectives (See the description in the Project Charter): A well finished and polished assembly line part is expected at the end
of this stage.
Product Description (what is the end result of the work package?) Finished assembly line

Acceptance Criteria (how will the team member be able to check their work?)

The acutal dimension with respect to the design is a matter of quality check in this stage
Deliverables (See the description in the project charter)

The finished mold is put under quality analysis and checking


Assumptions : A well established quality analysis department is present.

Resources assigned No of labour force allocated # 5and a budget of 175,000.

Duration: 8 hours

Cost : $175,000
Due Date : 04/09/2017
Interdependencies: A completed mold is required at this stage

Approved by: Project Manager Anish T 29/08/2017


WBS Dictionary (Task Description): Die casting of the Assembly Line

Project name: ETB build Task #1.6 Date Issued: 04/09/2017 Person Assigned 11
Assembly Line
Task Description (what work is authorized): The die casting of the assembly line

Quantified Objectives (See the description in the Project Charter): A well finished and polished assembly line part is expected at the end
of this stage.
Product Description (what is the end result of the work package?) Finished assembly line

Acceptance Criteria (how will the team member be able to check their work?)

The acutal dimension with respect to the design is a matter of quality check in this stage
Deliverables (See the description in the project charter)

The molded section is fed to the cooling section


Assumptions : A well established molding facility is in the facility

Resources assigned No of labour force allocated # 5and a budget of 200,000.

Duration: 20 hours

Cost : $200,000
Due Date : 15/10/2017
Interdependencies: A completed mold is required at this stage

Approved by: Project Manager Anish T 29/08/2017

WBS Dictionary (Task Description): Molding

Project name: ETB build Task #1.6.1 Date Issued: 04/09/2017 Person Assigned 3
Assembly Line
Task Description (what work is authorized): The molding of the assembly line

Quantified Objectives (See the description in the Project Charter): A molded section of the assembly line is expected at the end of this
stage
Product Description (what is the end result of the work package?) A molded assembly line is fed to cooling operation

Acceptance Criteria (how will the team member be able to check their work?)

The dimensional juxtapose compared to the design provides the quality of work during this stage
Deliverables (See the description in the project charter)

The finished mold is put under quality analysis and checking


Assumptions : A well established quality analysis department is present.

Resources assigned No of labour force allocated # 5and a budget of 200,000.

Duration: 20 hours

Cost : $200,000
Due Date : 14/09/2017
Interdependencies: A completed mold is required at this stage

Approved by: Project Manager Anish T 04/09/2017


WBS Dictionary (Task Description): Cooling

Project name: ETB build Task #1.6.2 Date Issued: 14/09/2017 Person Assigned 3
Assembly Line
Task Description (what work is authorized): Cooling of the molded section

Quantified Objectives (See the description in the Project Charter): The hot molded section is put under the cooling section

Product Description (what is the end result of the work package?) A water based or vapour based coolant system is employed for taking
out the temperture
Acceptance Criteria (how will the team member be able to check their work?)

The rate of heat removal will tell the efficacy at this stage
Deliverables (See the description in the project charter)

A sectionof the assembly line at the room temperature is required for the grinding operation
Assumptions : A backup power system is assumed.

Resources assigned No of labour force allocated # 5and a budget of 175,000.

Duration: 19 hours

Cost : $175,000
Due Date : 25/09/2017
Interdependencies: A completed mold is required at this stage

Approved by: Project Manager Anish T 17/09/2017

WBS Dictionary (Task Description): Grinding

Project name: ETB build Task #1.6.3 Date Issued: 25/09/2017 Person Assigned 4
Assembly Line
Task Description (what work is authorized): Grinding of the molded section

Quantified Objectives (See the description in the Project Charter): Grinding is performed to cut out the protruding non intended edgese

Product Description (what is the end result of the work package?) A well finished molded part is obtained at the end of this process

Acceptance Criteria (how will the team member be able to check their work?)

The supervisor is being assigned with a check list to carry out the evaluation
Deliverables (See the description in the project charter) A well grinded section is being fed to the marking process

Assumptions : A backup power system is assumed.

Resources assigned No of labour force allocated # 4and a budget of 200,000.

Duration: 15 hours

Cost : $200,000
Due Date : 29/09/2017
Interdependencies: A completed mold is required at this stage

Approved by: Project Manager Anish T 25/09/2017


WBS Dictionary (Task Description): Marking

Project name: ETB build Task #1.6.4 Date Issued: 29/09/2017 Person Assigned 4
Assembly Line
Task Description (what work is authorized): Marking of the molded section

Quantified Objectives (See the description in the Project Charter): The final marking is performed on the molded section

Product Description (what is the end result of the work package?) A well marked assembly part is expected at the end of this activiy

Acceptance Criteria (how will the team member be able to check their work?)

The dimensional analysis will indicate the efficacy of the activity


Deliverables (See the description in the project charter) A marked section is provided to the quality department for the quality check

Assumptions : A backup power system is assumed.

Resources assigned No of labour force allocated # 4and a budget of 100,000.

Duration: 10 hours

Cost : $100,000
Due Date : 06/10/2017
Interdependencies: A completed mold is required at this stage

Approved by: Project Manager Anish T 29/09/2017

WBS Dictionary (Task Description): Quality Control

Project name: ETB build Task #1.6.5 Date Issued: 06/10/2017 Person Assigned 3
Assembly Line
Task Description (what work is authorized): Quality Control of the molded section

Quantified Objectives (See the description in the Project Charter): A detailed quality check of the processed molded section

Product Description (what is the end result of the work package?) The product with a positive quality analysis is being fed for the
assembling unit
Acceptance Criteria (how will the team member be able to check their work?)

The check list based analysis will indicate the efficacy of the activity
Deliverables (See the description in the project charter) The assembling unit takes the products which passes the quality check

Assumptions : A detailed quality checking lab is assumed near to the facility

Resources assigned No of labour force allocated # 4and a budget of 75,000.

Duration: 8 hours

Cost : $75,000
Due Date : 13/10/2017
Interdependencies: A completed mold is required at this stage

Approved by: Project Manager Anish T 06/10/2017