Develop the alternatives


1 Problem
1. Expand alternative road from KESAS to Federal
road.
2. Traffic congestion during peak hours.
Propose all decision alternative
1. To up grade from 1 lane to 2 lane.
2. Sampling & lab testing for others action approval
from authorities.
3. New improvement method design
Choose expected decision alternative
(1) & (2)
2 Focus on the differences
1. To up grade from 1 lane to 2 lane.
2. Sampling & lab testing for others action approval
from authorities
1. To upgrade from 1 lane to 2 lane.
a. To find utilities maps to relocated after the new lane.
b. take time to design and prepare report and must submit &
approve by the local authorities.
3 Use a consistent viewpoint
2. Sampling & lab testing for others action approval
from authorities
a. take time to design and prepare report and must
submit & approve by the local authorities.
b. Recognize type of soil which is suitable
2. Sampling & lab testing for others action approval
from authorities
a. take time to design and prepare report and must
submit & approve by the local authorities.
b. Recognize type of soil which is suitable for the
4 Use a common unit of measure
construction method used.

3. New improvement method design


a. Change design used for support slope at river from sheet
pile to gabion wall.

5 Consider all relevant criteria Review again all criteria


Advantages
a. Cost saving than using sheet pile
b. Vibrating machine cost
6 Make uncertainty explicit risk
Disadvantages
a. Take a long time to construct gabion wall
b. Hire more general worker
77 7 Revisit your decisions Choose the best decision