Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
METHOD OF STATEMENT
(SYABAS)
... ...
MOHD SHAFIQ BIN MUSTAPA ABDUL RASHID BIN ABAS
(TEGUH AMANI SDN BHD) (TEGUH AMANI SDN BHD)
... ...
HAJI ANUAR BIN ABD RAHMAN IR MOHD SHAHROM BIN AHMAD
(ABAD CONSULTANT) SAMAN
(JURUTERA DAERAH)
TEGUH AMANI SDN BHD Page 1 of 3
METHOD STATEMENT
PIPE SYABAS 400mm DIA.
CONTENTS
1. OBJECTIVE
2. MATERIAL
3. LOCATION OF WORK
4. DRAWING
5. CONSTRUCTION METHOD
6. MACHINERY, EQUIPMENT, AND WORKFORCE
7. TRAFFIC MANAGEMENT AND SAFETY ASPECT
8. QUALITY CONTRIL PROCEDURE
1) OBJECTIVE
a) This method statement describes the method and procedure for pipe crossing under road of
Jalan Batu Tiga Lama.
b) The scope of works shall include:
i) Mobilization and installation of 400mm dia. SYABAS pipe, equipment and accessories.
2) MATERIALS
3) LOCATION OF WORK
a) The location will be at CH355.00b which is 400mm dia. SYABAS new pipe will be connected
with 300mm dia. SYABAS pipe located at the side of Sungai Rasah.
4) DRAWING
5) CONSTRUCTION METHOD
a) PRE CONSTRUCTION
i) Request For Inspection (RFI) should be send to let know work will commence to C.O.W or
Resident Engineer (RE).
b) SETTING OUT
i) Setting out the trench way that need to excavate on site
c) MOBILIZATION
i) New 20m 400mm dia. located at the road shoulder will be used as crossing pipe in road
of Jalan Batu Tiga Lama. The pipe will be moved to the site by excavator.
d) EXCAVATION
i) The excavation work will be done on 15 April 2016, Friday night (7.00pm) until 16 April
excavation work (before traffic light from Shah Alam). Two flag man standby at each road
way.
iv) Road diversion during the excavation work will be provided in Traffic Management Plan
(refer to TMP).
e) PIPE LAYING PROCEDURE
i) Any existing utilities that cross with the proposed pipe alignment will be protected and
avoided.
ii) After excavation work is finished, 20m length of 400mm dia. SYABAS pipe will be lay
maintained in their position until pipe laying work finish. Delineator post should be placed
along the barrier at the excavation area.
c) Traffic management shall be complying to Arahan Teknik (Jalan) 2c/85
d) All site personal shall wear PPE gear.