The following is a collection of questions remembered by various students who took API 570
exam in the past.
31. When evaluating a radiograph of 2 1/4 thick carbon steel piping, what is the maximum geometric unsharpness?
A. 0.020
B. 0.030
C. 0.040
D. 0.070
A. 1G
B. 2G
C. 5G
D. 6G
33. The location markers which are to appear as radiographic images on the film shall be placed on the
_______________
A. part
B. film holder/cassette
C. film side only
D. IQI
34. What is the outside diameter of a gasket for a Class 400 NPS 12 slip-on raised face flange, the edges of the gasket
do not extend to the bolt.
A. 12.75
B. 15.00
35. If the soil resistivity is 6,500 ohm-cm, what is the inspection interval for buried piping without cathodic protection?
A. 10 years
B. 15 years
C. 5 years
D. Whenever a leak is suspected
36. The ammeter on each piece of magnetizing equipment shall not deviate by more than _____________
A. 30%
B. 10%
C. 20%
D. 15%
37. A welder is tested on inch thick pipe in the 5G position. How many face bends are required for this test?
A. 1
B. 2
C. 3
D. 4
38. What is the minimum operating temperature that normalized A 516 Grade 70 plate can be used without impact
testing?
A. -29F
B. -20F
C. -50F
D. 0F
A. misalignment
B. thickness
C. weight
D. coating thickness
40. A welder is tested on 1/2 inch thick plate, how many face bends are required for this test?
A. 1
B. 2
C. 3
D. 4
41. During the final four hours of buried piping test, which was repressured to 125 PSI, the gauge fell 5 PSI
42. A WPS is written qualified welding procedure prepared to provide direction for ___________
43. A steel that hardens during cooling in air from a temperature above its transformation range is ________________
44. A pipe welder successfully passes a 6G pipe test. The welder can weld in which of the following positions?
A. 1G
B. 2G
C. 5G
D. All positions
A. A client approves it
B. The inspector approves it
C. The density and penetrameter meet Article-2 requirements
D. The weld quality is satisfactory
46. The work necessary to restore a piping system to a condition suitable for safe operation at the design condition is
_________________
A. rework
B. repair
C. renewal
D. Total replacement
47. Material in the form of ring used to support molten weld metal is called ______________
A. Backing gas
B. Cold wire slug
C. Consumable insert
D. Backing ring
A. Piping engineer
B. Repair organization
C. inspector
D. Owner/user
50. During a procedure qualification test on pipe that is 3/8 inches thick, how many side bends are required if the face
and root bends are acceptable?
A. 1
B. 2
C. 4
D. None
51. As a standard technique, the temperature of the penetrant and the surface of the part to be processed shall not be
below _____________
A. 125F
B. 50F
C. 32F
D. 81C
A. NPS 2
B. NPS 3
C. Or equal to NPS 2
D. NPS 6
53. Excess water washable penetrant shall be removed with a water spray. The water pressure shall not exceed
__________________
A. 110 PSI
B. 90 PSI
C. 50 PSI
D. 20 PSI
54. The intent of B 31.3 is to set forth engineering requirement deemed necessary for safe design and
______________
55. Flushing the surface with solvent, following the application of the penetrant and prior to developing is
_________________
56. Welding terms not specifically referenced in ASME B31.3 can be found in what document?
A. ASME Section IX
B. ASME Section V
C. AWS A 2.4
D. AWS A 3.0
57. How many tensile test are required to qualify a plate groove weld?
A. 2
B. 3
C. 4
D. 6
58. What is the maximum allowable prod spacing using an AC prod technique?
A. t/2
B. 8 inches
C. 10 inches
D. No spacing required
59. _________ may not be performed on the root pass or final pass of a weld.
A. Peening
B. Cleaning
C. Stress Relieving
D. Painting