Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
6. TOLERANCES
6.1 GENERAL. The degree of accuracy of the finished work and the permissible deviations (PD) (see Clause 6
of SABS 1200 A , SABS 1200 AA, or SABS 1200 AD, as applicable) shall be within the appropriate of the
limits given in 6.2.
SABS 1200 DE-1984 10
Small earth dams
Item
tII I1 I
*
4) Random fill material ...............................
5) Dispersive soil ....................................
7. TESTING
7.1 EXPLORATORY HOLES. The Engineer may require the Contractor to drill, auger, or excavate holes in advance
of the start of construction to determine founding conditiona or for other purposes. when so requested
by the Engineer, the Contractor shall provide labour, tools, machinery, and equipment for sinking such
exploratory holes and for refilling them. The operations specified in this subclause will be paid for as
daywork.
7.2 TAKING AND TESTING OF SAMPLES. The Contractor shall carry out sufficient tests to satisfy himself as to
the consistency of materials placed in embankments, around and over pipes, and as backfill to structures.
In addition he shall carry out routine compaction control tests to ensure that the specified densities
are being attained. Records of the test results and the Working sheets shall be kept in a systematic
manner and shall be submitted to the Engineer on a regular basis.
Routine in-situ control tests will be carried out by the Engineer at such frequency as he considers
necessary for the proper evaluation of the quality of the embankment, etc. (See also 5.2.3.2(e) and
8.1.3.)
7.3 MATERIAL OR COMPACTION STANDARD NOT TO SPECIFICATION. Where the Engineer's tests reveal that the
material used does not comply with the applicable requirements of the specification, or that the
compaction specified has not been attained, the Contractor rihall so rectify the work that the material
complies with the said requirements and the compaction specified is attained.
7.4 TRIAL EMBANKMENT. The Engineer may order the construction of a trial embankment to test the properties
and compaction characteristics of the earthfill material. In such an event the Contractor shall
construct the trial embankment in the manner specified for the main embankment. Payment for such work
will be made in terms of 8.3.7.
7.5 DENSITY. The density of the earthfill shall be measured in accordance with the standard Proctor test
(see ASTM D 698).
Should the average Proctor density determined from 10 consecutive routine compaction control tests at
random locations in the earthfill fall below the specified density, the Engineer may order that, before
further material is placed, the Contractor submit a revised compaction procedure for approval by the
Engineer.
11 SABS 1200 DE-1'784
Small earth dams
Should the Engineer consider that any area in the earthfill is not receiving adequate compaction he may
require specific tests to be carried out.
should the Proctor density determined in any specific test be more than 5 percentage points belor that
required for the layer, the material in the area of work represented by that specific test shall be
reworked until it complies with the said requirement or it shall be removed from the emhankment, as
directed, at the Contractor's expense.