Sei sulla pagina 1di 10

CASUAL CONDITION

(1) Cruz v. Gasilian (Impossible Conditions)


(1) (Song Fo & Co. v. Hawaiian Phil. Co., G.R. No. 23769, September 16, 1925)
(4) (Filoil Refinery Corp. v. Mendoza, G.R. No. L-55526, June 15, 1987)
(5) (Hermanos v. Saldaa, G.R. No. L-26578, January 28, 1974)
(7) (Solar Harvest, Inc. v. Davao Corrugated Carton Corp., G.R. No. 176868, July 26, 2010)

judgment was asked for P70,369.50, with legal


interest, and costs. In an amended answer and
Cruz v. Gasilian (Impossible Conditions) cross-complaint, the defendant set up the special
defense that since the plaintiff had defaulted in the
-------not found------------ payment for the molasses delivered to it by the
defendant under the contract between the parties,
(Song Fo & Co. v. Hawaiian Phil. Co., G.R. No. 23769, the latter was compelled to cancel and rescind the
September 16, 1925) said contract. The case was submitted for decision
on a stipulation of facts and the exhibits therein
FIRST DIVISION mentioned. The judgment of the trial court
condemned the defendant to pay for the plaintiff a
[G.R. No. 23769. September 16, 1925.] total of P35,317.93, with legal interest from the date
of the presentation of the complaint, and with
SONG FO & COMPANY, plaintiff-appellee, vs. costs.
HAWAIIAN PHILIPPINE CO., defendant-appellant. From the judgment of the Court of First Instance the
defendant only has appealed. In this court it has
Hilado & Hilado, Ross, Lawrence & Selph and made the following assignment of errors: "I. The
Antonio T. Carrascoso, Jr., for appellant. lower court erred in finding that the appellant had
agreed to sell to the appellee 400,000, and not only
Arroyo, Gurrea & Muller for appellee. 300,000, gallons of molasses. II. The lower court
erred in finding that the appellant rescinded
SYLLABUS without sufficient cause the contract for the sale of
molasses executed by it and the appellee. III. The
1. CONTRACTS; SALES; INSTANT CASE. The written lower court erred in rendering judgment in favor of
contract examined and found to provide for the the appellee and not in favor of the appellant in
delivery by the Hawaiian-Philippine Co. to Song Fo accordance with the prayer of its answer and
& Company of 300,000 gallons of molasses. cross-complaint. IV. The lower court erred in
2. ID.; ID,.; ID.; PAYMENT. The terms of payment denying appellant's motion for a new trial." The
fixed by the parties are controlling. The time of specified errors raise three questions which we will
payment stipulated for in the contract should be consider in the order suggested by the appellant.
treated as of the essence of the contract. 1. Did the defendant agree to sell to the plaintiff
3. ID.; ID.; ID.; ID.; RESCISSION. The general rule is 400,000 gallons of molasses or 300,000 gallons of
that rescission will not be permitted for a slight or molasses? The trial court found the former amount
casual breach of the contract, but only for such to be correct. The appellant contends that the
breaches as are so substantial and fundamental as smaller amount was the basis of the agreement.
to defeat the object of the parties in making the The contract of the parties is in writing. It is found
agreement. principally in the documents, Exhibits F and G. The
4. ID.; ID.; ID.; ID.; ID. A delay in payment for a first mentioned exhibit is a letter addressed by the
small quantity of molasses for some twenty days is administrator of the Hawaiian-Philippine Co. to
not such a violation of an essential condition of the Song Fo & Company on December 13, 1922. It
contract as warrants rescission for non- reads:
performance. "SILAY, OCC. NEGROS, P. I.
5. ID.; ID.; ID.; MEASURE OF DAMAGES FOR BREACH "December 13, 1922.
OF CONTRACT. The facts examined and Song Fo "MESSRS. SONG FO AND CO.
& Company allowed P3,000 on account of the "Iloilo, Iloilo.
greater expense to which it was put in being "DEAR SIRS: Confirming our conversation we had
compelled to secure molasses in the open market. today with your Mr. Song Fo, who visited this
6. ID.; ID.; ID. The facts examined and Song Fo & Central, we wish to state as follows:
Company allowed nothing for lost profits on "He agreed to the delivery of 300,000 gallons of
account of the breach of the contract, because of molasses at the same price as last year under the
failure of proof. same condition, and the same to start after the
DECISION completion of our grinding season. He requested if
possible to let you have molasses during January,
MALCOLM, J p: February and March or in other words, while we are
grinding, and we agreed with him that we would to
In the Court of First Instance of Iloilo, Song Fo & the best of our ability, altho we are somewhat
Company, plaintiff, presented a complaint with two handicapped. But we believe we can let you have
causes of action for breach of contract against the 25,000 gallons during each of the milling months,
Hawaiian-Philippine Co., defendant, in which altho it interfere with the shipping of our own and
1|OBLICON_Chapter 3_CASUAL CONDITION
planters sugars to Iloilo. Mr. Song Fo also asked if we Company on October 17, 1922, expressly mentions
could supply him with another 100,000 gallons of an understanding between the parties of a
molasses, and we stated we believe that this is contract for 300,000 gallons of molasses.
possible and will do our best to let you have these We sustain appellant's point of view on the first
extra 100,000 gallons during the next year the same question and rule that the contract between the
to be taken by you before November 1st, 1923, parties provided for the delivery by the Hawaiian-
along with the 300,000, making 400,000 gallons in Philippine Co. to Song Fo & Company of 300,000
all. gallons of molasses.
"Regarding the payment for our molasses, Mr. Song 2. Had the Hawaiian-Philippine Co. the right to
Fo gave us to understand that you would pay us at rescind the contract of sale made with Song Fo &
the end of each month for molasses delivered to Company? The trial judge answers No, the
you. appellant Yes.
"Hoping that this is satisfactorily and awaiting your Turning to Exhibit F, we note this sentence:
answer regarding this matter, we remain. "Regarding the payment for our molasses, Mr. Song
"Yours very truly, Fo (Mr. Song Heng) gave us to understand that you
"HAWAIIAN-PHILIPPINE COMPANY would pay us at the end of each month for
"By: R.C. PITCAIRN molasses delivered to you." In Exhibit G, we find
"Administrator." Song Fo & Company stating that they understand
Exhibit G is the answer of the manager of Song Fo & the contents of Exhibit F, and that they "confirm all
Company to the Hawaiian-Philippine Co. on the arrangements you have stated, and in order to
December 16, 1922. This letter reads: make the contract clear, we hereby quote below
"December 16th, 1922. our old contract as amended, as per our new
"MESSRS. HAWAIIAN-PHILIPPINE CO., arrangements. (a) Price, at 2 cents per gallon
"Silay, Neg. Occ., P. I. delivered at the central." In connection with the
"DEAR SIRS: We are in receipt of your favors dated portion of the contract having reference to the
the 9th and the 13th inst. and understood all their payment for the molasses, the parties have agreed
contents. on a table showing the date of delivery of the
"In connection to yours of the 13th inst, we regret to molasses, the account and date thereof, the date
hear that you mentioned Mr. Song Fo the one who of receipt of account by plaintiff, and date of
visited your Central, but it was not for he was Mr. payment. The table mentioned is as follows:
Song Heng, the representative and the manager of Date of receipt
Messrs. Song Fo & Co.
"With reference to the contents of your letter dated Date of delivery Account and date of account by
the 13th inst. we confirm all the arrangements you Date of payment
have stated and in order to make the contract
clear, we hereby quote below our old contract as thereof plaintiff
amended, as per our new arrangements.
"(a) Price, at 2 cents per gallon delivered at the 1922 1923 1923
central. Dec. 18 P206.16 Dec. 26/22 Jan. 5 Feb. 20
"(b) All handling charges and expenses at the Dec. 29 206.16 Jan. 3/23 do Do.
central and at the dock at Mambaguid for our 1923
account. Jan. 5 206.16 Jan. 9/23 Mar. 7 or 8 Mar. 31
"(c) For services of one locomotive and flat cars Feb. 12 206.16 Mar. 12/23 do Do.
necessary for our six tanks at the rate of P48 for the Feb. 27 206.16 do do Do.
round trip dock to central and central to dock. This Mar. 5 206.16 do do Do.
service to be restricted to one trip for the six tanks. Mar. 16 206.16 Mar. 20/23 Apr. 2/23 Apr. 19
"Yours very truly, Mar. 24 206.16 Mar. 31/23 do Do.
"SONG FO & COMPANY Mar. 29 206.16 do do Do.
"By__________________ Some doubt has risen as to when Song Fo &
"Manager." Company was expected to make payments for the
We agree with appellant that the above quoted molasses delivered. Exhibit F speaks of payments "at
correspondence is susceptible of but one the end of each month." Exhibit G is silent on the
interpretation. The Hawaiian-Philippine Co. agreed point. Exhibit M, a letter of March 28, 1923, from
to deliver to Song Fo & Company 300,000 gallons of Warner, Barnes & Co., Ltd., the agent of the
molasses. The Hawaiian-Philippine Co. also believed Hawaiian-Philippine Co. to Song Fo & Company,
it possible to accommodate Song Fo & Company mentions "payment on presentation of bills for each
by supplying the latter company with an extra delivery." Exhibit O, another letter from Warner,
100,000 gallons. But the language used with Barnes & Co., Ltd. to Song Fo & Company dated
reference to the additional 100,000 gallons was not April 2, 1923, is of a similar tenor. Exhibit P, a
a definite promise. Still less did it constitute an communication sent direct by the Hawaiian-
obligation. Philippine Co. to Song Fo & Company on April 2,
If Exhibit T relied upon by the trial court shows 1923, by which the Hawaiian-Philippine Co. gave
anything, it is simply that the defendant did not notice of the termination of the contract, gave as
consider itself obliged to deliver to the plaintiff the reason for the rescission, the breach of Song Fo
molasses in any amount. On the other hand, Exhibit & Company of this condition: "You will recall that
A, a letter written by the manager of Song Fo & under the arrangements made for taking our
2|OBLICON_Chapter 3_CASUAL CONDITION
molasses, you were to meet our accounts upon had to purchase in the open market. As expressly
presentation and at each delivery." Not far conceded by the plaintiff at page 25 of its brief
removed from this statement, is the allegation of 100,000 gallons of molasses were secured from the
plaintiff in its complaint that "plaintiff agreed to pay Central North Negros Sugar Co., Inc., at two
defendant, at the end of each month upon centavos a gallon. As this is the same price
presentation of accounts." specified in the contract between the plaintiff and
the defendant, the plaintiff accordingly suffered no
Resolving such ambiguity as exists and having in material loss in having to make this purchase. So
mind ordinary business practice, a reasonable 244,994 gallons minus the 100,000 gallons just
deduction is that Song Fo & Company was to pay mentioned leaves as a result 144,994 gallons. As to
the Hawaiian-Philippine Co. upon presentation of this amount, the plaintiff admits that it could have
accounts at the end of each month. Under this secured it and more than the Central Victorias
hypothesis, Song Fo & Company should have paid Milling Company one and one-half centavos per
for the molasses delivered in December, 1922, and gallon. In other words, the plaintiff had to pay the
for which accounts were received by it on January Central Victorias Milling Company one and one-
5, 1923, not later than January 31 of that year. half centavos a gallon more for the molasses than it
Instead, payment was not made until February 20, would have had to pay the Hawaiian-Philippine Co.
1923. All the rest of the molasses was paid for either Translated into pesos and centavos, this meant a
on time or ahead of time. loss to the plaintiff of approximately P2,174.91. As
The terms of payment fixed by the parties are the conditions existing at the central of the
controlling. The time of payment stipulated for in Hawaiian-Philippine Co. may have been different
the contract should be treated as of the essence of than those found at the Central North Negros Sugar
the contract. Theoretically, agreeable to certain Co., Inc., and the Central Victorias Milling
conditions which could easily be imagined, the Company, and as not alone through the delay but
Hawaiian-Philippine Co. would have had the right through expenses of transportation and incidental
to rescind the contract because of the breach of expenses, the plaintiff may have been put to
Song Fo & Company. But actually, there is her greater cost in making the purchase of the
present no outstanding fact which would legally molasses in the open market, we would concede
sanction the rescission of the contract by the under the first cause of action in round figures
Hawaiian-Philippine Co. P3,000.
The general rule is that rescission will not be The second cause of action relates to lost profits on
permitted for a slight or casual breach of the account of the breach of the contract. The only
contract, but only for such breaches as are so evidence in the record on this question is the
substantial and fundamental as to defeat the stipulation of counsel to the effect that had Mr.
object of the parties in making the agreement. A Song Heng, the manager of Song Fo & Company,
delay in payment for a small quantity of molasses been called as a witness, he would have testified
for some twenty days is not such a violation of an that the plaintiff would have realized a profit of
essential condition of the contract as warrants P14,948.43, if the contract of December 13, 1922,
rescission for non-performance. Not only this, but had been fulfilled by the defendant. Indisputably,
the Hawaiian-Philippine Co. waived this condition this statement falls far short of presenting proof on
when it arose by accepting payment of the which to make a finding as to damages.
overdue accounts and continuing with the In the first place, the testimony which Mr. Song
contract. Thereafter, Song Fo & Company was not Heng would have given undoubtedly would follow
in default in payment so that the Hawaiian- the same line of thought as found in the decision of
Philippine Co. had in reality no excuse for writing its the trial court, which we have found to be
letter of April 2, 1923, cancelling the contract. unsustainable. In the second place, had Mr. Song
(Warner, Barnes & Co. vs. Inza [1922], 43 Phil., 505.) Heng taken the witness-stand and made the
We rule that the appellant had no legal right to statement attributed to him, it would have been
rescind the contract of sale because of the failure insufficient proof of the allegations of the
of Song Fo & Company to pay for the molasses complaint, and the fact that it is a part of the
within the time agreed upon by the parties. We stipulation by counsel does not change this result.
sustain the finding of the trial judge in this respect. And lastly, the testimony of the witness Song Heng,
3. On the basis first, of a contract for 300,000 gallons if we may dignify it as such, is a mere conclusion,
of molasses, and second, of a contract imprudently not a proven fact. As to what items make up the
breached by the Hawaiian-Philippine Co., what is more than P14,000 of alleged lost profits, whether
the measure of damages? We again turn to the loss of sales or loss of customers, or what not, we
facts as agreed upon by the parties. have no means of knowing.
The first cause of action of the plaintiff is based on We rule that the plaintiff is entitled to recover
the greater expense to which it was put in being damages from the defendant for breach of
compelled to secure molasses from other sources. contract on the first cause of action in the amount
Three hundred thousand gallons of molasses was of P3,000 and on the second cause of action in no
the total of the agreement, as we have seen. As amount. Appellant's assignments of error are
conceded by the plaintiff 55,006 gallons of accordingly found to be well in taken in part and
molasses were delivered by the defendant to the not well taken in part.
plaintiff before the breach. This leaves 244,994 Agreeable to the foregoing, the judgment
gallons of molasses undelivered which the plaintiff appealed from shall be modified and the plaintiff
3|OBLICON_Chapter 3_CASUAL CONDITION
shall have and recover from the defendant the sum On November 10, 1976, the private respondents
of P3,000, with legal interest from October 2, 1923, filed a Motion for Execution pending appeal which
until payment. Without special finding as to costs in was opposed by petitioners in their Motion for
either instance, it is ordered. Reconsideration. Said Motion for Reconsideration
Avancea, C.J., Johnson, Street, Villamor, Ostrand, was denied by the lower court prompting
Johns, Romualdez, and Villa-Real, JJ., concur. petitioners to file a Petition for Certiorari and Review
with the Court of Appeals docketed as CA-G.R. No.
(Filoil Refinery Corp. v. Mendoza, G.R. No. L-55526, 06145-SP. On September 29, 1980, the Court of
June 15, 1987) Appeals rendered its decision denying the petition
for certiorari and review to annul and set aside the
SECOND DIVISION order of the lower court granting the Motion for
Execution pending appeal. prcd
[G.R. No. L-55526. June 15, 1987.]
Meanwhile herein private respondents filed a
FILOIL REFINERY CORPORATION, PETROPHIL motion to dismiss the appeal of petitioners in the
CORPORATION and FILOIL MARKETING original complaint on the ground of alleged
CORPORATION, petitioner, vs. HON. RAFAEL T. abandonment thereof by reason of the failure of
MENDOZA and HON. MARIANO A. ZOSA, in the the petitioners to amend their record on appeal so
capacity as Judge, Branch V, Court of First Instance as to include in their Record on Appeal two
of Cebu, JESUS P. GARCIA and SEVERINA B. important orders of the lower court dated July 30,
GARCIA, respondents. 1975 and February 4, 1376, the "Motion for
Execution Pending Appeal," and the "Order" of the
Jesus P. Garcia for respondents. lower court granting said "Motion for Execution
Pending Appeal."
DECISION
The lower court issued an order dismissing the
PARAS, J p: appeal on September 24, 1979 stating as follows:

This is a petition for the issuance of the writs of 1) "Let it be remembered that the Order of this Court
CERTIORARI to annul and set aside: (a) the order of July 30, 1975, authorized the plaintiffs to implead
issued on September 24, 1979, by the Court of First the Filoil Marketing Corporation as one of the
Instance of Cebu in Civil Case No. R-14164, entitled defendants in this case; the Order dated February
"Jesus P. Garcia, et al. vs. Filoil Refinery Corporation, 4, 1976, contained the agreement of the parties to
et al.", dismissing petitioners' appeal from the submit this case for summary judgment and listed
decision rendered in the same case on May 14, the exhibits presented by both parties which were
1976; and (b) the order issued on October 20, 1980, admitted in evidence. There is no gainsaying that
in the same case denying petitioners' motion for the inclusion of these orders in defendants' record
reconsideration of the dismissal of their appeal and on appeal is necessary for a proper understanding
2) MANDAMUS to compel respondent Honorable of the issues involved in the appeal. Without them, it
Rafael T. Mendoza, as Presiding Judge of Branch V, is believed the Court of Appeals will not be in a
Court of First Instance of Cebu, to give due course position to know why the case was decided on
to petitioners' appeal. summary judgment, what exhibits have been
admitted in evidence and why Filoil Marketing
In a complaint filed by herein private respondents, Corporation had been ordered impleaded." (Rollo,
the lower court rendered on May 14, 1976, a pp. 69-70)
decision rescinding the contract of lease over a 750
square meters lot situated in Cebu City covered by Petitioners filed their Motion for Reconsideration of
TCT No. 30712 entered into between Filoil Refinery the said Order which was denied by the lower court
Corporation and private respondents Jesus P. in its Order dated October 20, 1980. Hence, the
Garcia and Severina B. Garcia and ordering the present petition for certiorari and mandamus.
petitioner herein to vacate the leased premises. It
appears that the herein petitioners violated the Petitioners' contentions merit Our consideration.
terms and conditions of the lease agreement in the
sense that the signatory Filoil Refinery Corporation The records reveal that the lower court dismissed
subleased it to Filoil Marketing and subsequently to petitioners' appeal because of their failure to
petitioner Petrophil Corporation and that herein amend or to complete their record on appeal.
petitioners were delayed several times in the Such alleged failure was brought to the attention of
payment of the monthly rentals. the lower court by private respondents in their
opposition to the approval of the Record on
On June 11, 1976, private respondents filed their Appeal on the ground that petitioners failed to
Motion for execution of the aforementioned include in the Record of Appeal the Motion for
decision pending appeal. Petitioners opposed said Execution pending appeal dated July 30, 1975 and
motion and on July 15, 1976 petitioners filed their the Order granting the motion for execution
notice of appeal. On July 30, 1976 they filed their pending appeal dated February 4, 1976. However it
Record on Appeal. is a fact that petitioners filed their record on appeal
well within the reglementary period and that the
4|OBLICON_Chapter 3_CASUAL CONDITION
lower court never issued an order declaring the All these arguments however have become moot
Record on Appeal incomplete or defective nor an and academic considering that the contract of
order ordering petitioners to complete or correct lease sought to be rescinded expired or terminated
the same. The lower court did not act on the record last September 16, 1987 or almost 5 years ago by its
on appeal filed by petitioners despite the own terms as provided for in the Lease Contract.
opposition of the private respondents to the Petitioners have won the case without the necessity
approval of the same. Obviously as there was no of an order by this Court to reverse the judgment of
order by a competent court requiring them to the respondent court and/or to grant the petition
complete their record on appeal, the petitioners as prayed for.
were under no obligation to amend the same,
petitioners having the impression that their record WHEREFORE premises considered the petition is
on appeal was then adequate and regular. hereby DISMISSED, with the petitioners ordered to
Petitioners were also under the belief that the failure VACATE the premises.
of the lower court in not acting immediately on their
record on appeal was because at the time the SO ORDERED.
record on appeal was awaiting approval by the
lower court, the petition for certiorari filed with the Fernan (Chairman), Gutierrez, Jr., Padilla, Bidin and
Court of Appeals to question the execution of the Cortes, JJ., concur.
decision pending appeal was still unresolved by the
Court of Appeals; and that had the lower court (Hermanos v. Saldaa, G.R. No. L-26578, January
approved outright the record on appeal, or had it 28, 1974)
required petitioners to amend the same and
petitioners complied, constraining it to give its FIRST DIVISION
approval thereto, it would have lost its jurisdiction to
order execution of the decision pending appeal. [G.R. No. L-26578. January 28, 1974.]
Petitioners cited the ruling handed by Us in the case
of De Leon vs. De Los Santos 1 to invoke the rule LEGARDA HERMANOS and JOSE LEGARDA,
that once an appeal has been perfected, the trial petitioners, vs. FELIPE SALDAA and COURT OF
court loses jurisdiction over the case and cannot APPEALS (FIFTH DIVISION), ** respondents.
generally act anymore on any matter raised
therein. It was more for these reasons that Manuel Y . Macias for petitioners.
petitioners felt there was no need to follow up or to
inquire about the approval of their record on Mario E. Ongkiko for private respondent.
appeal rather than an act of abandonment of their
appeal as theorized by private respondents. prcd DECISION

Anent petitioners' grounds for appealing, petitioners TEEHANKEE, J p:


aver that they have good and valid grounds. In
rescinding the contract of lease between petitioner The Court, in affirming the decision under review of
Filoil Refinery Corporation and private respondents, the Court of Appeals, which holds that the
the lower court found that petitioners illegally respondent buyer of two small residential lots on
subleased the lot to petitioner Filoil Marketing installment contracts on a ten-year basis who has
Corporation and that the latter, in turn, assigned its faithfully paid for eight continuous years on the
sublease to petitioner Petrophil Corporation. principal alone already more than the value of one
However an examination of the lease contract lot, besides the larger stipulated interests on both
reveals that there is no express prohibition against lots, is entitled to the conveyance of one fully paid
the assignment of the leasehold right. Under the lot of his choice, rules that the judgment is fair and
law, when there is no express prohibition, the lessee just and in accordance with law and equity.
may sublet the thing leased 2 and all rights
acquired by virtue of an obligation are The action originated as a complaint for delivery of
transmissible, if there has been no stipulation to the two parcels of land in Sampaloc, Manila and for
contrary 3 execution of the corresponding deed of
conveyance after payment of the balance still due
Petitioners admit that on a few occasions, they on their purchase price. Private respondent as
were late in paying the rentals which were due plaintiff had entered into two written contracts with
within the first 15 days of each month but their petitioner Legarda Hermanos as defendant
delay was only for a few days. The delayed rentals subdivision owner, whereby the latter agreed to sell
for the months of May, July, August and September, to him Lots Nos. 7 and 8 of block No. 5N of the
1974 were remitted to private respondents on May subdivision with an area of 150 square meters each,
21, July 19, August 19 and September 16, 1974, for the sum of P1,500.00 per lot, payable over the
respectively. Such breaches were not so substantial span of ten years divided into 120 equal monthly
and fundamental as to defeat the object of the installments of P19.83 with 10% interest per annum,
parties in making the agreement because the law is to commence on May 26, 1948, date of execution
not concerned with such trifles. of the contracts. Subsequently, Legarda Hermanos
partitioned the subdivision among the brothers and
sisters, and the two lots were among those allotted
5|OBLICON_Chapter 3_CASUAL CONDITION
to co-petitioner Jose Legarda who was then of the contracts, plaintiff averred that no demand
included as co-defendant in the action. has been made upon him regarding the unpaid
installments, and for this reason he could not be
It is undisputed that respondent faithfully paid for declared in default so as to entitle the defendants
eight continuous years about 95 (of the stipulated to cancel the said contracts.
120) monthly installments totalling P3,582.06 up to
the month of February, 1956, which as per "The issue, therefore, is: Under the above facts, may
petitioners' own statement of account, Exhibit "1", defendants be compelled, or not, to allow plaintiff
was applied to respondent's account (without to complete payment of the purchase price of the
distinguishing the two lots), as follows: two lots in dispute and thereafter to execute the
final deeds of conveyance thereof in his favor?
"To interests P1,889.78
"To principal P1,682.28 "xxx xxx xxx

Total P3,582.06" 1 "Whether or not plaintiff's explanation for his failure
It is equally undisputed that after February, 1956 up to pay the remaining installments is true,
to the filing of respondent's complaint in the Manila considering the circumstances obtaining in this
court of first instance in 1961, respondent did not case, we elect to apply the broad principles of
make further payments. The account thus shows equity and justice. In the case at bar, we find that
that he owed petitioners the sum of P1,311.72 on the plaintiff has paid the total sum of P3,582.06
account of the balance of the purchase price including interests, which is even more than the
(principal) of the two lots (in the total sum of value of the two lots. And even if the sum applied
P3,000.00), although he had paid more than the to the principal alone were to be considered,
stipulated purchase price of P1,500.00 for one lot. which was of the total of P1,682.28, the same was
already more than the value of one lot, which is
Almost five years later, on February 2, 1961 just P1,500.00. The only balance due on both lots was
before the filing of the action, respondent wrote P1,317.72, which was even less than the value of
petitioners stating that his desire to build a house on one lot. We will consider as fully paid by the plaintiff
the lots was prevented by their failure to introduce at least one of the two lots, at the choice of the
improvements on the subdivision as "there is still no defendants. This is more in line with good
road to these lots," and requesting information of conscience than a total denial to the plaintiff of a
the amount owing to update his account as "I little token of what he has paid the defendant
intend to continue paying the balance due on said Legarda Hermanos." 4
lots."
Hence, the present petition for review, wherein
Petitioners replied in their letter of February 11, 1961 petitioners insist on their right of cancellation under
that as respondent had failed to complete total the "plainly valid written agreements which
payment of the 120 installments by May, 1958 as constitute the law between the parties" as against
stipulated in the contracts to sell, "pursuant to the "the broad principles of equity and justice" applied
provisions of both contracts all the amounts paid in by the appellate court. Respondent on the other
accordance with the agreement together with the hand while adhering to the validity of the doctrine
improvements on the premises have been of the Caridad Estates cases 5 which recognizes the
considered as rents paid and as payment for right of a vendor of land under a contract to sell to
damages suffered by your failure," 2 and "Said cancel the contract upon default, with forfeiture of
cancellation being in order, is hereby confirmed." the installments paid as rentals, disputes its
applicability herein contending that here
From the adverse decision of July 17, 1963 of the petitioners-sellers were equally in default as the lots
trial court sustaining petitioners' cancellation of the were "completely under water" and "there is neither
contracts and dismissing respondent's complaint, evidence nor a finding that the petitioners in fact
respondent appellate court on appeal rendered its cancelled the contracts previous to receipt of
judgment of July 27, 1966 reversing the lower court's respondent's letter." 6
judgment and ordering petitioners "to deliver to the
plaintiff possession of one of the two lots, at the The Court finds that the appellate court's judgment
choice of defendants, and to execute the finding that of the total sum of P3,582.06 (including
corresponding deed of conveyance to the plaintiff interests of P1,889.78) already paid by respondent
for the said lot," 3 ruling as follows: (which was more than the value of two lots), the
sum applied by petitioners to the principal alone in
"During the hearing, plaintiff testified that he the amount of P1,682.28 was already more than the
suspended payments because the lots were not value of one lot of P1,500.00 and hence one of the
actually delivered to him, or could not be, due to two lots as chosen by respondent would be
the fact that they were completely under water; considered as fully paid, is fair and just and in
and also because the defendants-owners failed to accordance with law and equity.
make improvements on the premises, such as
roads, filling of the submerged areas, etc., despite As already stated, the monthly payments for eight
repeated promises of their representative, the said years made by respondent were applied to his
Mr. Cenon. As regards the supposed cancellation account without specifying or distinguishing
6|OBLICON_Chapter 3_CASUAL CONDITION
between the two lots subject of the two [G.R. No. 176868. July 26, 2010.]
agreements under petitioners' own statement of SOLAR HARVEST, INC., petitioner, vs. DAVAO
account, Exhibit "1". 7 Even considering respondent CORRUGATED CARTON CORPORATION,
as having defaulted after February 1956, when he respondent.
suspended payments after the 95th installment, he
had as of the already paid by way of principal DECISION
(P1,682.28) more than the full value of one lot NACHURA, J p:
(P1,500.00). The judgment recognizing this fact and Petitioner seeks a review of the Court of Appeals
ordering the conveyance to him of one lot of his (CA) Decision 1 dated September 21, 2006 and
choice while also recognizing petitioners' right to Resolution 2 dated February 23, 2007, which denied
retain the interests of P1,889.78 paid by him for eight petitioner's motion for reconsideration. The assailed
years on both lots, besides the cancellation of the Decision denied petitioner's claim for
contract for one lot which thus reverts to petitioners, reimbursement for the amount it paid to
cannot be deemed to deny substantial justice to respondent for the manufacture of corrugated
petitioners nor to defeat their rights under the letter carton boxes.
and spirit of the contracts in question.
The case arose from the following antecedents:
The Court's doctrine in the analogous case of J.M.
Tuason & Co. Inc. vs. Javier 8 is fully applicable to In the first quarter of 1998, petitioner, Solar Harvest,
the present case, with the respondent at bar being Inc., entered into an agreement with respondent,
granted lesser benefits, since no rescission of Davao Corrugated Carton Corporation, for the
contract was therein permitted. There, where the purchase of corrugated carton boxes, specifically
therein buyer-appellee identically situated as herein designed for petitioner's business of exporting fresh
respondent buyer had likewise defaulted in bananas, at US$1.10 each. The agreement was not
completing the payments after having religiously reduced into writing. To get the production
paid the stipulated monthly installments for almost underway, petitioner deposited, on March 31, 1998,
eight years and notwithstanding that the seller- US$40,150.00 in respondent's US Dollar Savings
appellant had duly notified the buyer of the Account with Westmont Bank, as full payment for
rescission of the contract to sell, the Court upheld the ordered boxes.
the lower court's judgment denying judicial
confirmation of the rescission and instead granting
the buyer an additional grace period of sixty days Despite such payment, petitioner did not receive
from notice of judgment to pay all the installment any boxes from respondent. On January 3, 2001,
payments in arrears together with the stipulated petitioner wrote a demand letter for reimbursement
10% interest per annum from the date of default, of the amount paid. 3 On February 19, 2001,
apart from reasonable attorney's fees and costs, respondent replied that the boxes had been
which payments, the Court observed, would have completed as early as April 3, 1998 and that
the plaintiff-seller "recover everything due thereto, petitioner failed to pick them up from the former's
pursuant to its contract with the defendant, warehouse 30 days from completion, as agreed
including such damages as the former may have upon. Respondent mentioned that petitioner even
suffered in consequence of the latter's default." placed an additional order of 24,000 boxes, out of
which, 14,000 had been manufactured without any
In affirming, the Court held that "Regardless, advanced payment from petitioner. Respondent
however. of the propriety of applying said Art. 1592 then demanded petitioner to remove the boxes
thereto, We find that plaintiff herein has not been from the factory and to pay the balance of
denied substantial justice, for, according to Art. US$15,400.00 for the additional boxes and
1234 of said Code: 'If the obligation has been P132,000.00 as storage fee.
substantially performed in good faith, the obligor
may recover as though there had been a strict and On August 17, 2001, petitioner filed a Complaint for
complete fulfillment, less damages suffered by the sum of money and damages against respondent.
obligee,'" and "that in the interest of justice and The Complaint averred that the parties agreed that
equity, the decision appealed from may be upheld the boxes will be delivered within 30 days from
upon the authority of Article 1234 of the Civil Code." payment but respondent failed to manufacture
9 and deliver the boxes within such time. It further
alleged: AEScHa
ACCORDINGLY, the appealed judgment of the
appellate court is hereby affirmed. Without 6. That repeated follow-up was made by the
pronouncement as to costs. plaintiff for the immediate production of the
ordered boxes, but every time, defendant [would]
Makalintal, C .J ., Castro, Makasiar, Esguerra and only show samples of boxes and ma[k]e repeated
Muoz Palma, JJ ., concur. promises to deliver the said ordered boxes.

(Solar Harvest, Inc. v. Davao Corrugated Carton 7. That because of the failure of the defendant to
Corp., G.R. No. 176868, July 26, 2010) deliver the ordered boxes, plaintiff ha[d] to cancel
the same and demand payment and/or refund
SECOND DIVISION from the defendant but the latter refused to pay
7|OBLICON_Chapter 3_CASUAL CONDITION
and/or refund the US$40,150.00 payment made by For respondent, Bienvenido Estanislao (Estanislao)
the former for the ordered boxes. 4 testified that he met Que in Davao in October 1998
to inspect the boxes and that the latter got samples
In its Answer with Counterclaim, 5 respondent of them. In February 2000, they inspected the boxes
insisted that, as early as April 3, 1998, it had already again and Que got more samples. Estanislao said
completed production of the 36,500 boxes, that petitioner did not pick up the boxes because
contrary to petitioner's allegation. According to the ship did not arrive. 11 Jaime Tan (Tan), president
respondent, petitioner, in fact, made an additional of respondent, also testified that his company
order of 24,000 boxes, out of which, 14,000 had finished production of the 36,500 boxes on April 3,
been completed without waiting for petitioner's 1998 and that petitioner made a second order of
payment. Respondent stated that petitioner was to 24,000 boxes. He said that the agreement was for
pick up the boxes at the factory as agreed upon, respondent to produce the boxes and for petitioner
but petitioner failed to do so. Respondent averred to pick them up from the warehouse. 12 He also
that, on October 8, 1998, petitioner's representative, said that the reason why petitioner did not pick up
Bobby Que (Que), went to the factory and saw the boxes was that the ship that was to carry the
that the boxes were ready for pick up. On February bananas did not arrive. 13 According to him, during
20, 1999, Que visited the factory again and the last visit of Que and Estanislao, he asked them
supposedly advised respondent to sell the boxes as to withdraw the boxes immediately because they
rejects to recoup the cost of the unpaid 14,000 were occupying a big space in his plant, but they,
boxes, because petitioner's transaction to ship instead, told him to sell the cartons as rejects. He
bananas to China did not materialize. Respondent was able to sell 5,000 boxes at P20.00 each for a
claimed that the boxes were occupying warehouse total of P100,000.00. They then told him to apply the
space and that petitioner should be made to pay said amount to the unpaid balance.
storage fee at P60.00 per square meter for every
month from April 1998. As counterclaim, respondent In its March 2, 2004 Decision, the Regional Trial
prayed that judgment be rendered ordering Court (RTC) ruled that respondent did not commit
petitioner to pay $15,400.00, plus interest, moral and any breach of faith that would justify rescission of
exemplary damages, attorney's fees, and costs of the contract and the consequent reimbursement of
the suit. the amount paid by petitioner. The RTC said that
respondent was able to produce the ordered
In reply, petitioner denied that it made a second boxes but petitioner failed to obtain possession
order of 24,000 boxes and that respondent already thereof because its ship did not arrive. It thus
completed the initial order of 36,500 boxes and dismissed the complaint and respondent's
14,000 boxes out of the second order. It maintained counterclaims, disposing as follows:
that respondent only manufactured a sample of
the ordered boxes and that respondent could not WHEREFORE, premises considered, judgment is
have produced 14,000 boxes without the required hereby rendered in favor of defendant and against
pre-payments. 6 the plaintiff and, accordingly, plaintiff's complaint is
hereby ordered DISMISSED without pronouncement
During trial, petitioner presented Que as its sole as to cost. Defendant's counterclaims are similarly
witness. Que testified that he ordered the boxes dismissed for lack of merit.
from respondent and deposited the money in
respondent's account. 7 He specifically stated that, SO ORDERED. 14
when he visited respondent's factory, he saw that
the boxes had no print of petitioner's logo. 8 A few Petitioner filed a notice of appeal with the CA.
months later, he followed-up the order and was
told that the company had full production, and On September 21, 2006, the CA denied the appeal
thus, was promised that production of the order for lack of merit. 15 The appellate court held that
would be rushed. He told respondent that it should petitioner failed to discharge its burden of proving
indeed rush production because the need for the what it claimed to be the parties' agreement with
boxes was urgent. Thereafter, he asked his partner, respect to the delivery of the boxes. According to
Alfred Ong, to cancel the order because it was the CA, it was unthinkable that, over a period of
already late for them to meet their commitment to more than two years, petitioner did not even
ship the bananas to China. 9 On cross-examination, demand for the delivery of the boxes. The CA
Que further testified that China Zero Food, the added that even assuming that the agreement
Chinese company that ordered the bananas, was was for respondent to deliver the boxes,
sending a ship to Davao to get the bananas, but respondent would not be liable for breach of
since there were no cartons, the ship could not contract as petitioner had not yet demanded from
proceed. He said that, at that time, bananas from it the delivery of the boxes. 16
Tagum Agricultural Development Corporation
(TADECO) were already there. He denied that Petitioner moved for reconsideration, 17 but the
petitioner made an additional order of 24,000 motion was denied by the CA in its Resolution of
boxes. He explained that it took three years to refer February 23, 2007. 18
the matter to counsel because respondent
promised to pay. 10 HIaAED In this petition, petitioner insists that respondent did
not completely manufacture the boxes and that it
8|OBLICON_Chapter 3_CASUAL CONDITION
was respondent which was obliged to deliver the Hence, no demand is generally necessary
boxes to TADECO. cCTESa because, once a party fulfills his obligation and the
other party does not fulfill his, the latter
We find no reversible error in the assailed Decision automatically incurs in delay. But when different
that would justify the grant of this petition. dates for performance of the obligations are fixed,
the default for each obligation must be determined
Petitioner's claim for reimbursement is actually one by the rules given in the first paragraph of the
for rescission (or resolution) of contract under Article present article, 19 that is, the other party would
1191 of the Civil Code, which reads: incur in delay only from the moment the other party
demands fulfillment of the former's obligation. Thus,
Art. 1191. The power to rescind obligations is implied even in reciprocal obligations, if the period for the
in reciprocal ones, in case one of the obligors fulfillment of the obligation is fixed, demand upon
should not comply with what is incumbent upon the obligee is still necessary before the obligor can
him. be considered in default and before a cause of
action for rescission will accrue. cEDaTS
The injured party may choose between the
fulfillment and the rescission of the obligation, with Evident from the records and even from the
the payment of damages in either case. He may allegations in the complaint was the lack of
also seek rescission, even after he has chosen demand by petitioner upon respondent to fulfill its
fulfillment, if the latter should become impossible. obligation to manufacture and deliver the boxes.
The Complaint only alleged that petitioner made a
The court shall decree the rescission claimed, unless "follow-up" upon respondent, which, however,
there be just cause authorizing the fixing of a would not qualify as a demand for the fulfillment of
period. the obligation. Petitioner's witness also testified that
they made a follow-up of the boxes, but not a
This is understood to be without prejudice to the demand. Note is taken of the fact that, with
rights of third persons who have acquired the thing, respect to their claim for reimbursement, the
in accordance with Articles 1385 and 1388 and the Complaint alleged and the witness testified that a
Mortgage Law. demand letter was sent to respondent. Without a
previous demand for the fulfillment of the
The right to rescind a contract arises once the other obligation, petitioner would not have a cause of
party defaults in the performance of his obligation. action for rescission against respondent as the latter
In determining when default occurs, Art. 1191 would not yet be considered in breach of its
should be taken in conjunction with Art. 1169 of the contractual obligation.
same law, which provides:
Even assuming that a demand had been previously
Art. 1169. Those obliged to deliver or to do made before filing the present case, petitioner's
something incur in delay from the time the obligee claim for reimbursement would still fail, as the
judicially or extrajudicially demands from them the circumstances would show that respondent was
fulfillment of their obligation. not guilty of breach of contract.

However, the demand by the creditor shall not be The existence of a breach of contract is a factual
necessary in order that delay may exist: matter not usually reviewed in a petition for review
under Rule 45. 20 The Court, in petitions for review,
(1) When the obligation or the law expressly so limits its inquiry only to questions of law. After all, it is
declares; or not a trier of facts, and findings of fact made by the
trial court, especially when reiterated by the CA,
(2) When from the nature and the circumstances of must be given great respect if not considered as
the obligation it appears that the designation of the final. 21 In dealing with this petition, we will not veer
time when the thing is to be delivered or the service away from this doctrine and will thus sustain the
is to be rendered was a controlling motive for the factual findings of the CA, which we find to be
establishment of the contract; or adequately supported by the evidence on record.

(3) When demand would be useless, as when the As correctly observed by the CA, aside from the
obligor has rendered it beyond his power to pictures of the finished boxes and the production
perform. report thereof, there is ample showing that the
boxes had already been manufactured by
In reciprocal obligations, neither party incurs in respondent. There is the testimony of Estanislao who
delay if the other does not comply or is not ready to accompanied Que to the factory, attesting that,
comply in a proper manner with what is incumbent during their first visit to the company, they saw the
upon him. From the moment one of the parties pile of petitioner's boxes and Que took samples
fulfills his obligation, delay by the other begins. thereof. Que, petitioner's witness, himself confirmed
this incident. He testified that Tan pointed the boxes
In reciprocal obligations, as in a contract of sale, to him and that he got a sample and saw that it
the general rule is that the fulfillment of the parties' was blank. Que's absolute assertion that the boxes
respective obligations should be simultaneous.
9|OBLICON_Chapter 3_CASUAL CONDITION
were not manufactured is, therefore, implausible Moreover, assuming that respondent was obliged
and suspicious. to deliver the boxes, it could not have complied
with such obligation. Que, insisting that the boxes
In fact, we note that respondent's counsel had not been manufactured, admitted that he did
manifested in court, during trial, that his client was not give respondent the authority to deliver the
willing to shoulder expenses for a representative of boxes to TADECO:
the court to visit the plant and see the boxes. 22
Had it been true that the boxes were not yet Q. Did you give authority to Mr. Tan to deliver these
completed, respondent would not have been so boxes to TADECO?
bold as to challenge the court to conduct an
ocular inspection of their warehouse. Even in its A. No, sir. As I have said, before the delivery, we
Comment to this petition, respondent prays that must have to check the carton, the quantity and
petitioner be ordered to remove the boxes from its quality. But I have not seen a single carton.
factory site, 23 which could only mean that the
boxes are, up to the present, still in respondent's Q. Are you trying to impress upon the [c]ourt that it
premises. is only after the boxes are completed, will you give
authority to Mr. Tan to deliver the boxes to
We also believe that the agreement between the TADECO[?] DAEcIS
parties was for petitioner to pick up the boxes from
respondent's warehouse, contrary to petitioner's A. Sir, because when I checked the plant, I have
allegation. Thus, it was due to petitioner's fault that not seen any carton. I asked Mr. Tan to rush the
the boxes were not delivered to TADECO. HCacTI carton but not. . . 26

Petitioner had the burden to prove that the Q. Did you give any authority for Mr. Tan to deliver
agreement was, in fact, for respondent to deliver these boxes to TADECO?
the boxes within 30 days from payment, as alleged
in the Complaint. Its sole witness, Que, was not A. Because I have not seen any of my carton.
even competent to testify on the terms of the
agreement and, therefore, we cannot give much Q. You don't have any authority yet given to Mr.
credence to his testimony. It appeared from the Tan?
testimony of Que that he did not personally place
the order with Tan, thus: A. None, your Honor. 27

Q. No, my question is, you went to Davao City and Surely, without such authority, TADECO would not
placed your order there? have allowed respondent to deposit the boxes
within its premises.
A. I made a phone call. In sum, the Court finds that petitioner failed to
establish a cause of action for rescission, the
Q. You made a phone call to Mr. Tan? evidence having shown that respondent did not
commit any breach of its contractual obligation. As
A. The first time, the first call to Mr. Alf[re]d Ong. previously stated, the subject boxes are still within
Alfred Ong has a contact with Mr. Tan. respondent's premises. To put a rest to this dispute,
we therefore relieve respondent from the burden of
Q. So, your first statement that you were the one having to keep the boxes within its premises and,
who placed the order is not true? consequently, give it the right to dispose of them,
after petitioner is given a period of time within
A. That's true. The Solar Harvest made a contact which to remove them from the premises.
with Mr. Tan and I deposited the money in the
bank. WHEREFORE, premises considered, the petition is
DENIED. The Court of Appeals Decision dated
Q. You said a while ago [t]hat you were the one September 21, 2006 and Resolution dated February
who called Mr. Tan and placed the order for 36,500 23, 2007 are AFFIRMED. In addition, petitioner is
boxes, isn't it? given a period of 30 days from notice within which
to cause the removal of the 36,500 boxes from
A. First time it was Mr. Alfred Ong. respondent's warehouse. After the lapse of said
period and petitioner fails to effect such removal,
Q. It was Mr. Ong who placed the order[,] not you? respondent shall have the right to dispose of the
boxes in any manner it may deem fit.
A. Yes, sir. 24
SO ORDERED.
Q. Is it not a fact that the cartons were ordered Carpio, Peralta, Abad and Mendoza, JJ., concur.
through Mr. Bienvenido Estanislao?

A. Yes, sir. 25

10 | O B L I C O N _ C h a p t e r 3 _ C A S U A L C O N D I T I O N

Potrebbero piacerti anche