HANDOVER NOTES

Site / Place of Handover : Handil


Department / Service : CST/OPB/HDL
From :I Gede Andi Dipayadnya
Date / Time :13 June 2012
To : Agus D.L
CC : Mr. Sentot H./ Mr. Sri Widadi

I. HSE Matters

ALWAYS REMINDER ALL OF THE CREW ABOUT ZERO TOLERANCE CAMPIGN

II. Work In progress and Today Activities


Item. 11867C
Install new 3 and 1 diesel fuel line to replace existing line due to leaking
and corrosion at CEB.
Status:
- Install scaffolding
- Stringing material
- Double joint activity, NDT (penetrant and radiography)
- Tie ins activity, completed 8 joints, 1 line to all DEGs and TEGs
Remaining:
- Tie ins activity to 3 header line, cold joint by flange connection. Ensure 2 temporary line
by using 2 flexible hose must be connected to 2 #150 flange at new 3 pipe before
dismantle existing line, so there will be no interruption at diesel fuel distribution to all
DEGs and TEGs.
- Leak test all joints at new 3 pipe (threaded joint and flange connection)
- Install pipe support for 3 new pipe.
- Touch up painting
- Dismantle existing 3 line and 1 line (all pipe up stream of 1 valve will be
dismantled and plugged, please refer to TOP. 1754.
- Dismantle scaffolding.

Item. 12215C
Replacement of 3 condensate drain line at CEB
Status:
Sheet 1 of 2
- Install scaffolding
- Stringing material
- Double joint, 1 ea
Remaining:
Sheet 1 of 2
- Tie ins activity, waiting for TOP, follow up with CPA/PRD/PRO
- Leak test and touch up painting, after NDT completion.
- Dismantle scaffolding
Sheet 2 of 2
- The job started today.
- Replace condensate drain of fuel gas line V-6010, CEB area

III. Main Events on the Period.

Item. 12507C
Replacement of diesel fuel distribution line due to seepage from T-6020,
CEB
Status:
- sheet 1 of 3, completed.
Remaining:
- Sheet 2 of 3
- sheet 3 of 3
Note: waiting for material readiness and TOP, follow up with CPA/PRD/PRO for window
time for this item.

Item. 12398H
Piping modification and bar tee installation 6 HP line from HP cluster to
HDA cluster
Status:
Sheet 1 of 2, Location: HDA cluster
- Install scaffolding
- Hot bolting activity
- Person in charge: Mr. MANJA Lifa
Sheet 2 of 2, Location: HP cluster
- Install scaffolding
- Hot bolting activity
Remaining:
Sheet 2 of 2, Location: HP cluster
- Due to revision drawing, need for additional scaffolding installation at HP cluster, please
refer to drawing no.HDF-00-3090 REV.04.
- Additional for hot bolting point at 6 #900 ball valve.
- Stringing material
- Installation of temporary lifting, as necessary, with scaffolding.
IV. High Priority Job to be done in forthcoming days
Item. 11632C
Replacement of 3 diesel fuel line, CEB to fuel jetty MP1
Other item, please refers to shut down schedule.
V. Pending Job and to be solved

NIL

VI. Miscellaneous Items

- Contractors team under PT. Meindo, Foreman: Sukasmono


- MOP LCT. Logindo Pelican will be valid until 18 June 2012

VII. Signature of Leaving Personnel Signature of Incoming Personnel

( I Gede Andi Dipayadnya ) ( Agus DL )