DETAIL 1080

Approved cover board (Note 3)


Approved insulation (Note 3)
Duro-Last membranes
Field weld (Note 2)

A.R.P. membrane

Insulation (if needed)

New roofing material


per asphalt manufacturer's
requirements

Existing asphalt-
based roofing

Termination Bar
or wood

Approved Duro-Last sealant

Deck
Approved Duro-Last fasteners
spaced 6 inches on center
Existing asphalt-
based roofing

Note 1: Tie-in detail for all flat surfaces. The use of Detail Drawing 1070 will be required
in conjunction with Detail Drawing 1080 when tie-in is across metal flutes.
Note 2: All field welds shall be a minimum of 1-1/2 inches wide.
Note 3: Refer to specifications for vapor barrier, insulation and cover board requirements.

REVISED: 01/31/2017 GENERAL DETAIL FOR MECHANICALLY FASTENED SYSTEMS


PREVIOUS: 01/01/2009 ASPHALT ROOF TIE-IN
SCALE: NONE RE-ROOF