Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Copyright 2008, IADC/SPE Asia Pacific Drilling Technology Conference and Exhibition
This paper was prepared for presentation at the IADC/SPE Asia Pacific Drilling Technology Conference and Exhibition held in Jakarta, Indonesia, 2527 August 2008.
This paper was selected for presentation by an IADC/SPE program committee following review of information contained in an abstract submitted by the author(s). Contents of the paper have not
been reviewed by the International Association of Drilling Contractors or the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily
reflect any position of the International Association of Drilling Contractors or the Society of Petroleum Engineers, its officers, or members. Electronic reproduction, distribution, or storage of any
part of this paper without the written consent of the International Association of Drilling Contractors or the Society of Petroleum Engineers is prohibited. Permission to reproduce in print is
restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of IADC/SPE copyright.
Abstract
Characteristic difference between Extended Reach Drilling (ERD) well and conventional directional well often cause
problem in drilling an ERD well. Drag, torque, and hook load force that occur in an ERD well is higher than conventional
o
well, because of long Horizontal Displacement and near 90 lateral inclination angle which are characteristics of an ERD
well. Three critical parameters are affected by that characters, those parameters are: drill string design, casing design, and
hydraulic design.
Drill string design optimization in ERD well is analyzed based on four basic parameters, those are: neutral point, torque
force, hook load force, and axial force. Casing design optimization is analyzed from hook load force that occurs when
picking up and slacking off. For casing design, there are three alternative methods: conventional method, casing floatation or
negative weight method, and partial floatation method. Hydraulic design optimization is analyzed base on cutting
concentration, mud weight, and drill string rotary speed.
Rig specification in drilling an ERD well is based on minimum requirement for rig hookload, rig drawwork, and pump
power. Software with 3D trajectory visualization feature has been developed to calculate tubular and hydraulic design
sensitivity regarding to friction force and pipe composition. In a study case, ERD method will be applied for deep water
drilling process to extent the cluster system range. By using the developed software, calculation result gives information
about ERD design optimization for similar case.
Keywords: ERD, drillstring design, casing design, hydraulic design, deep water drilling.
2 IADC/SPE 115286
o
where the casing installed at whole trajectory section. higher than 45 . A critical point of which cutting bed is
o o
Illustration for conventional casing installation can be formed occurs in 60 70 , however for higher inclination
seen in Figure 3. Tie back method is a casing installation angle the tendency of cutting bed occurrence is decrease.
method where the casing does not place at whole
trajectory section but only be placed at certain depth High mud density always used for ERD well. It is done to
below the surface. See Figure 4 for illustration. keep wellbore stability while drilling and casing
installation is in process. High mud density also gives
Casing floatation method is a casing installation method higher buoyancy effect that can help to reduce tubular
of which mud is removed from casing inside, therefore string weight. Because of the high mud density
make the inside part of the casing only filled with air characteristic, mud pump rate is needed to increase. This
(Figure 5). The purpose of this method is to reduce casing effect is not predicted in early calculation method.
weight by increasing the buoyancy force. The formula
bellow is being used to calculate casing density reduction From field and laboratory experience, wellbore cleaning
because of casing floatation method. process will be better if drill string is still at rotating
condition while drilling and tripping in/out. Sliding
OD 2 ID 2 drilling by using mud motor is proved have affecting
Wair = Wmud cutting bed forming that could cause pipe sticking. It is
OD 2 need to consider RPM correction while drilling with
regard to rotary pipe effect importance.
Partial floatation method is a modified from casing
floatation method. In this method, some part of casing By considering the factors that are explained above,
string is filled with air while the other part is filled with Moore method is corrected by using Rudi method. Rudi
mud (Figure 6). Division of the casing string into these method corrects Moore method for
two different parts is done by using a tool which is called
as shear out plug.
inclination angle, mud density, and RPM calculations,
Method that is chosen for casing installation is depend on therefore the calculation results could reached near actual
field condition and forces that work in casing string. Two condition on field. Rudi Method Formula is shown in
forces that work in casing string are drag force and casing Table 1.
weight force. Calculation formulas that are used are the
same with drillstring calculation formula. Sensitivity Table 1 Rudi Method Formula
analysis is needed to be done for friction factor and
chosen method in casing design.
0.2) occurs when oil base mud or synthetic base mud force requirement. From the calculation is known that
being used and the hole is in cased hole condition. If position of neutral point (Figure 8) is in 1250 ft measured
wellbore condition is unknown, it is preferred to use 0.3 depth from the surface. Therefore, maximum limit for DP
for friction factor number. installation in vertical section is 1250 ft.
Besides doing sensitivity analysis for the friction factor, Torque sensitivity is one of the calculated parameter,
this software is also completed by pipe string sensitivity which is done to acquire maximum drill pipe installation
analysis for non homogenous drill string and casing capacity in lateral section. Optimization will be done by
string. Non homogenous drill string analysis is required to consider two properties. The properties are friction factor
acquire the best combination between DP and HWDP in and pipe grade that is installed in vertical section. From
drill string design. Non homogenous casing string those two sensitivities analysis, torque sensitivity graph
analysis is needed to identify the best casing installation will be acquired (see Figure 9). From torque sensitivity
method that can be used. graph, cross over points between friction factors and pipe
grades become drill pipe minimum requirement that need
The software has the ability to calculate forces interaction to be installed in lateral section. Calculation results for
that arise in pipe string between torque, drag and weight ERD X well is shown at the table below:
force when picking up and slacking off the pipe string.
Result of forces interaction could be determined in every Table 2 Minimum Drillpipe Requirement from Torque
point of well trajectory. At the end, various forces Sensitivity
interaction conditions figure that are caused by friction
factor and non homogenous pipe string sensitivity could
be obtained. Sensitivity analysis is shown in torque, drag,
hook load slack off, hook load pick up, casing running,
and casing hook load graph. To summarize, forces
interaction figure that occurs in many variation of drill
string and casing string design can be developed by using Hook load sensitivity analysis will be done to compare
this software. the acquired result with torque sensitivity result. Hook
load sensitivity calculation procedure is the same as
VI. CASE STUDY torque sensitivity procedure. The different is the pipe
property that is used as boundary parameter. Pipe torque
To see the advantages that could be obtained with the strength becomes boundary parameter in torque
ERD software, analysis for one ERD well hypothetical sensitivity, while pipe tensile strength becomes boundary
data (we called ERD X well) will be done. Hypothetical parameter in hook load sensitivity. For ERD X well, the
data consist of trajectory data (Table 6) such as depth, result of hook load sensitivity (Figure 10) is in the table
inclination and azimuth. Tubular specification (Table 7), below:
hydraulic (Table 8), and others assumption data are given.
Table 3 Minimum Drillpipe Requirement from Hookload
From trajectory calculation by using ERD software, it is Sensitivity
known that ERD X well use Single Build Curve Design,
of which the length of lateral section is 12000 ft, ERD
ratio 3.3 and total length (Measured Depth) is 17400 ft.
Trajectory calculation software result view is shown in
Figure 7.
eliminated. Minimum drill pipe requirement that need to software simulation result (Figure 13), casing could be
be installed in lateral section is given in the table below: run to target depth by using floatation method.
Table 4 Minimum Drill pipe Requirement in Lateral Wair = pipe weight in air, ppg
Section Wmud = pipe weight in mud, ppg
Vs = slip velocity, ft/s
m = mud density, ppg
RPM = Rotary Per Minute
Vsv = Vs vertical Moore, ft/s
Vmin = minimum velocity to lift cutting, ft/s
Vcut = cutting velocity, ft/s
6. Casing Design REFERENCES
Casing could be installed by using conventional 1. J.M Peden, J.T Ford and M.B Oyeneyin, Heriot
method. Watt U, SPE Paper Comprehensive
It is recommended to use casing floatation method or Experimental Investigation of Drilled
using partial floatation method with minimum casing Cuttings Transport in Incline Wells
section that required to be emptied is 4391 ft from the Including the Effect of Rotation and
target, if casing is installed tie back @ EOC. Eccentricity Drillpipe, October 1990. SPE
No 20925.
7. Hydraulic Design 2. M.L Payne, and A.J. Hatch, SPE Paper Critical
Cutting minimum velocity requirement for cutting Technologies for Success in Extended
concentration 5 2 % is vary between 3.4979 ft/s Reach Drilling, September 1994, SPE No
5.5049 ft/s. 28293.
8. Rig Recommendation 3. Moore, P.L Drilling Practice Manual, Pennwell
Table 5 Rig Recommendation Publishing Company, Tulsa, (1974).
4. R.Rudi R.S, Equation For Estimating Mud
minimum Rate for Cutting transport in an
Inclined-Until Horizontal Well, SPE
57541, Middle East Drilling Technology
LIST OF SYMBOLS Conference, Abu Dhabi, November 1999.
5. S. Frank, Horizontal Well Planning-Build Curve
D = drag, lb Design, Drilling Technology, Inc., SPE
Wm = pipe weight in mud, ppg 12050 Reprint Series, 1989.
L = pipe length, ft 6. T.I. Larsen, A.Apilehveari, and J.J.Azar, SPE Paper
= friction factor Development of A New Cutting Transport
= inclination, degree Model for High Angle Wellbores Including
T = torque, lb ft Horizontal Wells, June 1997, SPE No
OD = outside diameter, inch 25872
Figure 13. ERD X Tie Back Casing Installation with Floatation Software Result
Figure 14. ERD X Tie Back Casing Installation with Partial Floatation Software Result