Sei sulla pagina 1di 33

Government of Nepal Page 1

Ministry of Physical Infrastructure and Transport


Department of Roads
Division Road Office Baglung
DETAILED ESTIMATE
Name of Road : Rakse Jimi Sakneyare Tundanda Sishakhani Pandvkhani Sadak F/Y: 2072/73

Name of Work : Roadway Construction


Budget Head No. 337123-4
Length
S.N. Description of Works Unit No Breadth (m) Height (m) Quantity
(m)
A #N/A

A.1 LS 1 1.00
#N/A
B Roadway Construction along

Excavation and disposal of landslides to


B.1 environmentally safe side using
excavator tipping trucks etc as per
Specification and Engineer's Instruction. m3
1 40.00 X- sectional Area 5.10 204.00
Total 204.00

Road way excavation in all types of


soil (Soft Soil/BMS/Soft Rock)
excluding Hard Rock for New
cutting / Back Cutting/ Grade Cutting
including disposal of excavated
B.2
material at approved environmentally
safe tipping sites in line & level
(using tipping truck if necessary) all
complete as per Specification &
Engineer's instruction. [900] m3
1.00 1650.00 X- sectional Area 5.50 9075.00
1.00 757.00 X- sectional Area 5.20 3936.40
Total 13011.40

Road way excavation in Hard Rock


for New Cutting / Grade Cutting /
Backcutting including disposal of
excavated material at approved
B.3 environmentally safe tipping sites in
line & level ( using tipping truck if
necessary) all complete as per
Specification & Engineer's
instruction. [900] m3
1.00 20.00 X- sectional Area 6.00 120.00
Total 120.00

C Roadway Construction along..

Excavation and disposal of landslides to


C.1 environmentally safe side using
excavator tipping trucks etc as per
Specification and Engineer's Instruction. m3
1 40.00 X- sectional Area 5.10 204.00
Total 204.00
Government of Nepal Page 2
Ministry of Physical Infrastructure and Transport
Department of Roads
Division Road Office Baglung
DETAILED ESTIMATE
Name of Road : Rakse Jimi Sakneyare Tundanda Sishakhani Pandvkhani Sadak F/Y: 2072/73

Name of Work : Roadway Construction


Budget Head No. 337123-4
Length
S.N. Description of Works Unit No Breadth (m) Height (m) Quantity
(m)

Road way excavation in all types of


soil (Soft Soil/BMS/Soft Rock)
excluding Hard Rock for New
cutting / Back Cutting/ Grade Cutting
including disposal of excavated
C.2
material at approved environmentally
safe tipping sites in line & level
(using tipping truck if necessary) all
complete as per Specification &
Engineer's instruction. [900] m3
1.00 1650.00 X- sectional Area 5.50 9075.00
1.00 757.00 X- sectional Area 5.20 3936.40
Total 13011.40

Road way excavation in Hard Rock


for New Cutting / Grade Cutting /
Backcutting including disposal of
excavated material at approved
C.3 environmentally safe tipping sites in
line & level ( using tipping truck if
necessary) all complete as per
Specification & Engineer's
instruction. [900] m3
1.00 20.00 X- sectional Area 6.00 120.00
Total 120.00
Government of Nepal Page 3
Ministry of Physical Infrastructure and Transport
Department of Roads
Division Road Office Baglung
ABSTRACT OF COST
Name of Road : Rakse Jimi Sakneyare Tundanda Sishakhani Pandvkhani Sadak F/Y: 2072/73
Name of Work : Roadway Construction Budget Head No. 337123-4

S.N. Description of Works Unit Quantity Rate Amount Remarks

A General Items
Insurance for the loss of damage to
A.1 works,plant, material, equipment,property and LS 1.00 9,000.00
personnel injury or death.
B Roadway Construction
Excavation and disposal of landslides to
B.1 environmentally safe side using excavator m3 204.00 45.68 9,318.72
tipping trucks etc as per Specification and
Engineer's Instruction.
Road way excavation in all types of soil (Soft
Soil/BMS/Soft Rock) excluding Hard Rock for
New cutting / Back Cutting/ Grade Cutting
B.2 m3 13011.40 121.21 1,577,111.79
including disposal of excavated material at
approved environmentally safe tipping sites in
line & level (using tipping tru

Road way excavation in Hard Rock for New


Cutting / Grade Cutting / Backcutting
including disposal of excavated material at
B.3 m3 120.00 828.28 99,393.60
approved environmentally safe tipping sites in
line & level ( using tipping truck if necessary)
all complete as per Specification &

Total A+B 1,694,824.11


13% VAT 220,327.13
Contengencies @ 5 % 84,741.20
Grand Total 1,999,892.44
Government of Nepal Page 4
Ministry of Physical Infrastructure and Transport
Department of Roads
Division Road Office Baglung
Quantity Compilation

Name of Road : Rakse Jimi Sakneyare Tundanda Sishakhani Pandvkhani Sadak F/Y: 2072/73

Name of Work : Roadway Construction


Budget Head No. 337123-4

S.N. Description of Works Unit Quantity Rate Amount Remarks

A General Items
Insurance for the loss of damage to works,plant,
1 material, equipment,property and personnel injury or LS 1.00 9000 9000
death.
Excavation and disposal of landslides to
environmentally safe side using excavator tipping
2 trucks etc as per Specification and Engineer's m3 204.00 45.68 9318.72
Instruction.
Road way excavation in all types of soil (Soft
Soil/BMS/Soft Rock) excluding Hard Rock for New
cutting / Back Cutting/ Grade Cutting including
3 disposal of excavated material at approved m3 13011.40 121.21 1577111.79
environmentally safe tipping sites in line & level (using
tipping tru

Road way excavation in Hard Rock for New Cutting /


Grade Cutting / Backcutting including disposal of
4 excavated material at approved environmentally safe m3 120.00 828.28 99393.6
tipping sites in line & level ( using tipping truck if
necessary) all complete as per Specification &
Total 1694824.11

1,694,824.11

-
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
Division Road Office Baglung
Bill of Quantity
Contract identification no: DROBLG/337123/2072/73-
Name of Road : Rakse Jimi Sakneyare Tundanda Sishakhani Pandvkhani Sadak F/Y: 2072/73
Name of Work : Roadway Construction Budget Head No. 337123-4
Rate
S.N. Description of Works Unit Quantity Remarks
In Figure In words
Insurance for the loss of damage to
works,plant, material,
1 LS 1.00
equipment,property and personnel
injury or death.
Excavation and disposal of landslides
to environmentally safe side using
2 excavator tipping trucks etc as per m3 204.00
Specification and Engineer's
Instruction.
Road way excavation in all types of
soil (Soft Soil/BMS/Soft Rock)
excluding Hard Rock for New cutting /
Back Cutting/ Grade Cutting including
3 m3 13011.40
disposal of excavated material at
approved environmentally safe
tipping sites in line & level (using
tipping tru
Road way excavation in Hard Rock
for New Cutting / Grade Cutting /
Backcutting including disposal of
excavated material at approved
4 m3 120.00
environmentally safe tipping sites in
line & level ( using tipping truck if
necessary) all complete as per
Specification &
Total(NRs)
Vat @ 13%(NRs)
Grand Total(NRs)
Grand Total In words(NRs)
* The numbers enclosed in the bracket in the particulars represents the DOR Standard Specifications Section Number.
* Rate quoted are considered exclusive of VAT. Contractor's Signature:
* Cost for laboratory tests as per specification shall be bome by the contractor and included in rates.
* All works shall be completed complying Specification, Special provision and contract documentsSeal:
Name:
Address:
Summary of rates

Specification Rate
S.N. Norms No Description Unit
Clause No. ( NRs.)
Proving and laying RCC pipes of diameter 900 mm (internal) with or without collars jointed with stiff
1 7.02.iii 701
mixture of cement mortar in the proportion of 1 : 2 ( 1 cement : 2 fine sand ). [701 ]
m 15,434.59

2 9.01.a 905 Road way excavation in soft soil including disposal all complete. [905 ] m3 577.44
Road way excavation in soft soil including disposal upto 10 m and lift upto 1.5 m etc. all complete as per
3 9.01.a 905
specification. [Manual(10%), Machine(90%)] [905 ]
m3 96.89
Road way excavation in Hard soil / Gravel / Boulder mixed soil including disposal upto 10 m and lift upto
4 9.01.b 905
1.5 m etc. all complete as per specification.[Manual(10%), Machine(90%)] [905 ]
m3 112.69
Road way excavation in Soft rock including disposal upto 10 m and lift upto 1.5 m etc. all complete as per
5 9.01.c 905
specification.[Manual(10%), Machine(90%)] [905 ]
m3 245.97
Road way excavation in Hard rock including disposal upto 10 m and lift upto 1.5 m etc. all complete as per
6 9.01.c 905
specification.[Manual(5%), Machine(95%)] [905 ]
m3 507.50
Formation of embankment including compaction in layers not exceeding 150 mm compacted depth,
7 9.07.01.a 907
watering and haulage 10 m etc. all complete as per specification (ii)using equipments. [907 ]
m3 445.68
Providing , Preparing and Installing form work including necessary supports and removing after
8 18.01 1804, 1805
completion for foundation and footings . [1804, 1805 ]
m2 475.53
Providing and placing machine mixed M15/40 cement concrete for the foundation and footing etc.
9 20.01.a.02 2000
including compaction, curing, testing etc. all complete as per specification and drawing. [2000 ]
m3 12,521.71
Providing and placing machine mixed M20/20 cement concrete for the foundation and footing etc.
10 20.01.a.04 2000
including compaction, curing, testing etc. all complete as per specification and drawing. [2000 ]
m3 13,879.65
Providing and laying Reinforcement ( diameter above 8 mm and upto 16 mm) including cutting, bending,
11 20.07.02 2000
binding, fixing in position etc. all complete as per specification and drawing. [2000 ]
mt 126,603.50
Providing and placing concrete with 60% M 15/40 concrete and 40% boulders/stones as per specification
12 24.14.01.a 2406; 2, 4
Lead 30m, lift 1.5m , using concrete mixer and vibrator. [2406; 2, 4 ]
m3 9,278.82
26.01, 6.05
13 old
2602, 2603 Providing, laying and levelling of dry stone soling works in the foundation all complete. [2602, 2603 ] m3 3,045.32
2602, 2603, Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(4)] including
14 26.03.b
2607 scaffolding, curing, preparation of mortar etc. all complete. [2602, 2603, 2607 ]
m3 10,400.81
Materials Rate : Jhapa District

1) District rate : Materials (Baglung)


District Rate Collection Royalty ( Transportation Total Rate
S.N. Description Unit Remarks
(D) Rate (C) R ) Rate ( Tp ) ( C + R + Tp)
1 Gravel
1.a ( 5 - 70 mm ) m3 1900.00 650.00 447.00 1097.00
1.b ( 5 - 40 mm) m3 1900.00 2080.00 447.00 2347.00
1.c ( 5 - 20 mm) m3 1900.00 3055.00 447.00 2347.00
1.d ( 5 - 10 mm) m3 1900.00 5200.00 447.00 2347.00
2 Broken Aggregates
2.a ( 70 - 100 mm) m3 2750.00 3900.00 447.00 3197.00
2.b ( 40 - 70 mm) m3 2750.00 5200.00 447.00 3197.00
2.c Road Base( 20 - 40 mm) m3 2750.00 7800.00 447.00 3197.00
2.d ( 10 - 20 mm) m3 2750.00 11700.00 447.00 3197.00
2.e ( 5 - 10 mm) m3 2750.00 16250.00 447.00 3197.00
3 Sand m3 1850.00 1950.00 0.00 1850.00
4 Brick nos. 12.50 12.50
5 Wood
5.a wood ( Sisau) m3 36000.00 36000.00
5.b Sal wood m3 98800.00 98800.00
5.c Local Wood (Kukath) m3 19000.00
6 Stone dust m3 1300.00 1300.00
7 Rubble m3 1300.00 910.00 484.25 1394.25
8 a) Cement (OPC) mt. 16800.00 16800.00
b) Cement (PPC) mt. 15000.00 15000.00
9 Water lt. 0.54 0.31 0.31
10 Bitumen kg 76.00 76.00
Emulsion (MC) kg 73.00 73.00
11 Reinforcement (Tor Steel)
11.a 8 mm dia mt. 79000.00 79000.00
11.b 10 - 25 mm dia mt. 79000.00 79000.00
11.c 25 - 32 mm dia mt. 81000.00 81000.00
11.d 4.75 - 7 mm dia mt. 79000.00 79000.00
12 Binding Wire kg 100.00 100.00
13 G.I Wire heavy coated
13.a 8 gauge kg 101.00 101.00
13.b 10 gauge kg 101.00 101.00
13.c 12 gauge kg 101.00 101.00
14 RCC Hume Pipes
14.a 450mm diameter m 4672.00 0.00 4672.00
14.b 500 mm diameter m 5185.20 0.00 5185.20
14.c 600 mm diameter m 6371.20 0.00 6371.20
14.d 750 mm diameter m 8654.00 0.00 8654.00
14.e 900 mm diameter m 11509.60 0.00 11509.60
15 Jute kg 80.00 80.00
16 Nails kg 105.00 105.00
17 Ply wood
17.a plywood 3 mm m2 290.52 290.52
17.b plywood 4 mm m2 322.80 322.80
17.c plywood 6 mm m2 441.16 441.16
17.d plywood 8 mm m2 484.20 484.20
17.e plywood 10 mm m2 645.60 645.60
17.f plywood 12 mm m2 505.72 505.72
17.g plywood 20 mm m2 667.12 667.12
18 Road Paint lit. 520.00 520.00
19 Enamel Paint lit. 420.00 420.00
20 Lime kg 32.00 32.00
21 Gum/Fevicol kg 300.00 300.00
22 Snow cem kg 77.00 77.00
23 Primer Cement kg 26.00 26.00
24 Steel Plate(3 mm ) Sq. m 0.00
25 Steel tube(50 mm dia) Rm 0.00
26 GI Pipe Medium Class 0.00
26.a 38 mm m 560.00 560.00
26.b 50 mm m 770.00 770.00
26.c 75 mm m 984.00 984.00
26.d 100 mm m 1837.00 1837.00
27 HDPE 110mm m 0.00
28 Bearing pad nos. 0.00
29 Geotextile(MC 30) m2 122.00 122.00
30 Expansion joint r.m. 0.00
Round Aggregates
31
(Used in Analysis)
70 to 100 mm m3 1900.00 447.00 2347.00
40 to 70mm m3 1900.00 447.00 2347.00
20 to 40 mm m3 1900.00 447.00 2347.00
10 to 20 mm m3 1900.00 447.00 2347.00

Prepared By Checked By Approved By


Materials Rate : Jhapa District

10 mm and down m3 1900.00 447.00 2347.00

Prepared By Checked By Approved By


Materials Rate : Jhapa District

2) District Rate : Labour


S.N. Description Unit District Rate Remarks
1 Skilled md 870.00
2 Unskilled (Labour) md 650.00
3 Driller/Blaster md
4 Road Supervisor md
5 Road Length Worker md

3) District Rate : Fuel and Lubricant


S.N. Description Unit District Rate Lead Total With VAT
1 Diesel lit. 75.00 0.00 75.00 75.00 *
2 Kerosene lit. 75.00 0.00 75.00 75.00
3 Petrol lit. 99.00 0.00 99.00 99.00

4) DOR's Equipment Hire Rate


Operator's DOR Hire Total
S.N. Description Unit Allowance rate rate
1 Excavator (upto 150 HP) hr. 75.00 1800.00 1875.00
2 Loader( upto 2.2 m3) hr. 75.00 1200.00 1275.00
3 Tractor hr. 45.00 300.00 300.00
4 Truck ( 3 tonnes) hr. 75.00 300.00 375.00
5 Truck ( 6 tonnes) hr. 75.00 450.00 525.00
6 Truck ( 8 tonnes) hr. 75.00 800.00 875.00
7 Pump 10cm dia hr. 45.00 150.00 195.00
8 Grader ( 90 HP) hr. 75.00 1200.00 1275.00
9 Water bowser hr. 45.00 550.00 595.00
10 Vibrator Roller Self Propelled hr. 75.00 800.00 875.00
11 3 Wheel Roller ( 8 - 10 ton) hr. 75.00 500.00 575.00
12 Pneumatic Tyred Roller hr. 75.00 1200.00 1275.00
13 Air compressor hr. 45.00 250.00 295.00
14 Boiler (Bitumen Heater) hr. 45.00 180.00 225.00
15 Sprayer hr. 75.00 260.00 335.00
16 Hand Sprayer hr. 45.00 300.00 345.00
17 Bitumen Distributor hr. 75.00 1300.00 1375.00
18 Chip Spreader (Self propelled) hr. 75.00 1500.00 1575.00
19 Chips Spreader (Tail mounted) hr. 75.00 300.00 375.00
20 Asphalt plant hr. 75.00 400.00 300.00
21 Asphalt mixer hr. 75.00 1000.00 300.00
22 Asphalt paver hr. 75.00 1400.00 300.00
23 Blasting machine hr. 45.00 1400.00 1445.00
24 Generator hr. 45.00 150.00 195.00
25 Screw Jack hr. 45.00
26 Electric Heating Plate hr. 45.00
27 mixer hr. 45.00 470.00 515.00
28 Needle Vibrator hr. 45.00 100.00 145.00

Prepared By Checked By Approved By


Transportation Analysis of Construction Materials : (Baglung District)
Labour Rate Fuel per ltr. 75.00
Unskilled 650 Truck Rate 875.00
Skilled 870 Truck capactiy 8 mt
Labour Total
Earthen Gravel Blacktop Total Truck Load /
Transport
Material Type Unit Km Km Km Travel Fuel Coefficient Fuel, Ltr. Coefficien Unload Truck, Hr.
Unskilled Skilled ation Cost
(10 kmph) (20 Kmph) (40 kmph) Time (T) t Time
per unit
1)Excavated earth work
a)Soil Material m3 0.00 0.40 0.00 2.00 0.00 0.15 0.75 0.11 0.00
b)Rock Material m3 0.00 0.50 0.00 2.30 0.00 0.18 0.75 0.14 0.00
2) Sand m3 0.00 0.30 0.00 1.70 0.00 0.13 0.75 0.10 0.00
3) Gravel, river shingle, broken stone
aggregates, and bats.
a) Gravel m3 1.00 0.05 0.50 0.00 2.10 0.11 0.16 0.75 0.13 447.00
b) River shingle m3 1.00 0.05 0.50 0.00 2.10 0.11 0.16 0.75 0.13 447.00
c) Broken stone aggregates m3 1.00 0.05 0.50 0.00 2.10 0.11 0.16 0.75 0.13 447.00
d) Brick bats m3 0.00 0.50 0.00 2.10 0.00 0.16 0.75 0.12 0.00
4) Boulder, Cobbles, quarry stone m3 1.00 0.05 0.50 0.00 2.70 0.14 0.21 0.75 0.17 484.25
5)Dressed Stone m3 1.00 0.05 0.60 0.00 2.60 0.13 0.20 0.75 0.16 539.75
6)Bricks 1000 nos 0.00 0.60 0.00 4.00 0.00 0.31 0.75 0.23 0.00
7)Cement t 0.00 0.40 0.00 1.50 0.00 0.12 0.75 0.09 0.00
8)Reinforcement Steel and gabion wire t 0.00 0.60 0.00 1.50 0.00 0.12 0.75 0.09 0.00
9) Bitumen 1000 lit 0.00 1.00 0.00 2.60 0.00 0.20 0.75 0.15 0.00
10) GI, CI, Pipe and fittings t 0.00 1.00 0.00 1.50 0.00 0.12 0.75 0.09 0.00
11)Timber for temporary works m3 0.00 0.30 0.00 1.40 0.00 0.11 0.75 0.08 0.00
12) Fabricated Structural Timber m3 0.00 0.50 0.00 2.00 0.00 0.15 1.25 0.19 0.00
13) Fabricated Structural Steel t 0.00 4.00 0.40 1.50 0.00 0.12 1.25 0.15 0.00
14)RCC Precast Element t 0.00 1.00 0.00 1.50 0.00 0.12 0.75 0.09 0.00
15)Equiptment & accessoriesetc.
truck 0.00 20.00 4.00 13.00 0.00 1.00 1.75 1.75 0.00
requiring careful handling
16) RCC hume pipe
a) 900mm dia m 0.00 0.40 0.04 0.78 0.00 0.06 1.75 0.11 0.00
b) 750 mm dia m 0.00 0.33 0.03 0.69 0.00 0.06 1.75 0.11 0.00
c) 600mm dia m 0.00 0.25 0.02 0.60 0.00 0.05 1.75 0.09 0.00
17) Water 1000 lit 0.00 0.10 0.01 1.50 0.00 0.12 0.50 0.06 0.00
18) Petrol / Diesel / Kerosene 1000 lit 0.00 0.10 0.01 1.50 0.00 0.12 0.50 0.06 0.00
Fuel =Total Travel Time (T)*Fuel Coefficient
Truck, Hr.=Truck Coefficient *(Total Travel Time (T)+Load / Unload Time)
Total Transportation Cost per unit = Labour, md. * Labour Rate + Fuel, Ltr.* Fuel Rate + Truck, Hr.* Truck Rate

Prepared By Checked By Recommended By Approved By


Remarks

From Pokhara

Prepared By Checked By Recommended By Approved By


Government of Nepal
Department of Roads
Western Division Road Office No 4, Butwal
Chart for collection of materials
Activity Labour
S.N. Description Unit Amount Remarks
no Type Unit Qty. Rate
1 Collection and seiving gravel including stacking within
8.01.02
10m. Hauling distance.
a ( 5 - 70 mm size) Norms 9.01
m3 Unskilled md 1 650 650.00
(b)Soft Soil
b ( 5 - 40 mm size) m3 Unskilled md 3.2 650 2080.00
c ( 5 - 20 mm size) m3 Unskilled md 4.7 650 3055.00
d ( 5 - 08 mm size) m3 Unskilled md 8 650 5200.00
2 Collection of rubble of required size, hauling
m3 8.01.03 Unskilled md 1.4 650 910.00
distance10m. and stacking.
3 Collection and seiving sand within 10m. hauling
8.01.04
distance.
a ( Quarry output less than 33%) m3 Unskilled md 4 650 2600.00
b ( Quarry output 33 - 66 %) m3 Unskilled md 3 650 1950.00
c ( Quarry output more than 66%) m3 Unskilled md 1.43 650 929.50
4 Collection, quarring and seiving sand in hilly areas
m3 8.01.05 Unskilled md 1.5 650 975.00
within 10m. hauling distance.
5 Washing broken stone, gravel and sand. m3 8.01.07 Unskilled md 1.5 650 975.00
6 Washing rubble m3 8.01.08 Unskilled md 0.4 650 260.00
7 Breaking stones including Collection, seiving and
8.02.01
stacking within 10m.
a ( 70 - 100 mm size) m3 Unskilled md 6 650 3900.00
b ( 40 - 70 mm size) m3 Unskilled md 8 650 5200.00
c ( 20 - 40 mm size) m3 Unskilled md 12 650 7800.00
d ( 10 - 20 mm size) m3 Unskilled md 18 650 11700.00
e ( 5 - 10 mm size) m3 Unskilled md 25 650 16250.00
8 Making rubbles of required size including breaking with m3 8.02.03 Unskilled md 5.5 650 3575.00
distance 10m. and stacking.
9 Transportation of water by manpower including loading, 1000
8.03.17 Unskilled md 0.47 650 305.50
hauling, unloading and stacking. lit

Prepared by: Checked by: Approved by:


Rate analysis Page 1

Description of works: Proving and laying RCC pipes of diameter 900 mm (internal) with or without collars jointed with stiff mixture of cement mortar in the proportion of 1 : 2 ( 1
cement : 2 fine sand ) , lead upto 100m. Unit : 1 rm
Spec. cl. No: 701
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
7.02.03 Skilled md 0.344 870.000 299.28 RCC Pipe m 1.0 11509.60 11509.60 Ballies, crow, bars, chain , pulleys ,
3.00% of total cost 390.91
Unskilled md 1.562 650.00 1015.30 Cement kg 9.062 16.80 152.24 block and ropes etc.
Sand m3 0.013 1850.00 24.05
Jute kg 0.375 80.00 30.00
Sub total of A = 1314.58 Sub total of B = 11715.89 Sub total of C = 390.91
Sub total of A +B + C = 13421.38 Contractor's overhead expenses 15% = 2013.21 Unit Rate = 15434.59

Description of works: Road way excavation in soft soil including disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification.
Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.01.a Unskilled md 0.750 650.00 487.50 Tools and plant 3.00% of L.C. 14.62
Sub total of A = 487.50 Sub total of B = 0.00 Sub total of C = 14.62
Sub total of A +B + C = 502.12 Contractor's overhead expenses 15% = 75.32 Unit Rate = 577.44

Description of works: Road way excavation in soft soil including disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification. [Manual 10% and Machine 90%]
Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual 10
9.01.a Unskilled md 0.075 650.00 48.75 Tools and plant 3.00% of L.C. 1.46
Machine 90
907.01 Unskilled md 0.00422 650.00 2.74 Diesel lit 0.135 75 10.12 Excavator hr 0.0113 1875.00 21.18
Sub total of A = 51.49 Sub total of B = 10.12 Sub total of C = 22.64
Sub total of A +B + C = 84.25 Contractor's overhead expenses 15% = 12.64 Unit Rate = 96.89
Roadway excavation using machine (100%) 43.49

Description of works: Road way excavation in Hard soil / Gravel / Boulder mixed soil including disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification.
[Manual 90% and Machine 10%] Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual 10
9.01.a Unskilled md 0.100 650.00 65.00 Tools and plant 3.00% of L.C. 1.95
Machine 90
907.01 Unskilled md 0.00047 650.00 0.30 Diesel lit 0.135 75 10.12 Excavator hr 0.011 1875.00 20.62
Sub total of A = 65.30 Sub total of B = 10.12 Sub total of C = 22.57
Sub total of A +B + C = 97.99 Contractor's overhead expenses 15% = 14.70 Unit Rate = 112.69
Roadway excavation using machine (100%) 39.66

Description of works: Earthwork excavation by bull dozer in soft rock .


Unit : 1 m3

Prepared By Checked By Approved By


Rate analysis Page 2

Earthwork excavation by bull dozer in soft rock .


Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Unskilled md 0.010 650.00 6.50 Diesel lit 0.195 75 14.62 Bull Dozer 200 hp hr 0.0065 1842.85 11.97
Sub total of A = 6.50 Sub total of B = 14.62 Sub total of C = 11.97
Sub total of A +B + C = 33.09 Contractor's overhead expenses 15% = 4.96 Unit Rate = 38.05

Description of works: Road way excavation in soft rock including disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification. [Manual 10% and Machine 90%]
Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual 10
9.01.a Unskilled md 2.750 650.00 1787.50 Tools and plant 3.00% of L.C. 53.62
Sub total of A = 1787.50 Sub total of B = 0.00 Sub total of C = 53.62
Manual Sub Total (I=A+B+C) : 1841.12 Manual Sub Total (I=A+B+C) :(10% ) 184.11
Machine 90
907.01 Unskilled md 0.010 650.00 6.50 Diesel lit 0.195 75 14.62 Bull Dozer 200 hp hr 0.0065 1842.85 11.97
Sub total of A = 6.50 Sub total of B = 14.62 Sub total of C = 11.97
Machine Sub Total (I=A+B+C) : 33.09 Machine Sub Total (I=A+B+C) :(90% ) 29.78
Sub-Total 213.89 Overhead (15%) 32.08 Total Rate : 245.97
Description of works: Earthwork excavation by bull dozer in hard rock .
Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Unskilled md 0.010 650.00 6.50 Diesel lit 0.258 75 19.35 Bull Dozer 200 hp hr 0.0086 1842.85 15.84
Sub total of A = 6.50 Sub total of B = 19.35 Sub total of C = 15.84
Sub total of A +B + C = 41.69 Contractor's overhead expenses 15% = 6.25 Unit Rate = 47.94

Description of works: Road way excavation in Hard rock including disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification. [Manual 5% and Machine 95%]
Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual 5
9.01.a Unskilled md 12.000 650.00 7800.00 Tools and plant 3.00% of L.C. 234.00
Sub total of A = 7800.00 Sub total of B = 0.00 Sub total of C = 234.00
Manual Sub Total (I=A+B+C) : 8034.00 Manual Sub Total (I=A+B+C) :(5% ) 401.70
Machine 95
907.01 Unskilled md 0.010 650.00 6.50 Diesel lit 0.258 75 19.35 Bull Dozer 200 hp hr 0.0086 1842.85 15.84
Sub total of A = 6.50 Sub total of B = 19.35 Sub total of C = 15.84
Machine Sub Total (I=A+B+C) : 41.69 Machine Sub Total (I=A+B+C) :(95% ) 39.61
Sub-Total 441.31 Overhead (15%) 66.19 Total Rate : 507.50

Description of works: Formation of embankment including compaction in layers not exceeding 150 mm compacted depth, watering and haulage 10 m etc. all complete as per
specification (ii)using equipments. Unit : 1 m3
Spec. cl. No: 909
Labour (A) Material (B) Equipment (C)
Norms No.

Prepared By Checked By Approved By


Rate analysis Page 3

Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.05.02 Skilled md 0.002 870.00 1.74 suitable material cu.m 1.1 294.98 324.47 Grader hr 0.005 1275 6.37
Unskilled md 0.008 650.00 5.20 deisel lit. 0.12 75.00 9.00 Roller ( 8 ~ 10 tonnes) hr 0.017 575 9.77
water lit. 100 0.31 31.00 Testing and quality control 10.00% 38.75
Sub total of A = 6.94 Sub total of B = 364.47 Sub total of C = 16.14
Sub total of A +B + C = 387.55 Contractor's overhead expenses 15% = 58.13 Unit Rate = 445.68

Description of works: Transportation by dump truck for haulage distance of 2 km.


Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Unskilled md 0.100 650.00 65.00 Diesel lit 0.7692 75 57.69 Dump Truck hr 0.1538 875.00 134.57
Sub total of A = 65.00 Sub total of B = 57.69 Sub total of C = 134.57
Sub total of A +B + C = 257.26 Contractor's overhead expenses 15% = 38.59 Unit Rate = 295.85

Description of works: Road way excavation in soft soil by machines


Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.01.a Unskilled md 0.00469 650.00 3.04 diesel lit 0.15 75 11.25 Excavator hr 0.0125 1875 23.43
Sub total of A = 3.04 Sub total of B = 11.25 Sub total of C = 23.43
Sub total of A +B + C = 37.72 Contractor's overhead expenses 15% = 5.66 Unit Rate = 43.38

Description of works: Providing , Preparing and Installing form work including necessary supports and removing after completion for foundation and footings
(a) using timber ( soft wood) - Class F1 finish. Unit : 10 m2
Spec. cl. No: 1804,1805
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
18.01 Skilled md 1.50 870.00 1305.00 Planks 38mm thick. m3 0.42 2375.00 997.50
Unskilled md 2.00 650.00 1300.00 struts, ballies, etc. m3 0.18 2375.00 427.50
Nails,spikes,etc. kg 1.00 105.00 105.00
Sub total of A = 2605.00 Sub total of B = 1530.00 Sub total of C = 0.00
Sub total of A +B + C = 4135.00 Contractor's overhead expenses 15% = 620.25 Rate (10 m2) = 4755.25
Unit Rate (1 m2) = 475.53

Description of works: Providing and placing machine mixed M15/40 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per
specification and drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.a.2 Skilled md 0.50 870.00 435.00 cement mt 0.260 16800.00 4368.00 mixer (0.28/ 0.20 m3 ) hr 0.60 515 309.00
Unskilled md 3.50 650.00 2275.00 aggregate 20-40mm m3 0.530 2347.00 1243.91 vibrator hr 0.25 145 36.25
aggregate 10-20mm m3 0.240 2347.00 563.28 of Cost of
Mix Design and Quality Control 2.50% 265.57
aggregate 10mm & down m3 0.110 2347.00 258.17 concrete
coarse sand m3 0.460 1850.00 851.00

Prepared By Checked By Approved By


Rate analysis Page 4

petrol lit 0.100 99.00 9.90


diesel lit 3.000 75.00 225.00
water lit 156.000 0.31 48.36
Sub total of A = 2710.00 Sub total of B = 7567.62 Sub total of C = 610.82
Sub total of A +B + C = 10888.44 Contractor's overhead expenses 15% = 1633.27 Unit Rate = 12521.71

Description of works: Providing and placing machine mixed M20/20 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per
specification and drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.a.4 Skilled md 0.50 870.00 435.00 cement mt 0.330 16800.00 5544.00 mixer (0.28/ 0.20 m3 ) hr 0.60 515 309.00
Unskilled md 3.50 650.00 2275.00 aggregate 10-20mm m3 0.580 2347.00 1361.26 vibrator hr 0.25 145 36.25
aggregate 10mm & down m3 0.300 2347.00 704.10 of Cost of
Mix Design and Quality Control 2.50% 294.37
coarse sand m3 0.440 1850.00 814.00 concrete
petrol lit 0.100 99.00 9.90
diesel lit 3.000 75.00 225.00
water lit 198.000 0.31 61.38
Sub total of A = 2710.00 Sub total of B = 8719.64 Sub total of C = 639.62
Sub total of A +B + C = 12069.26 Contractor's overhead expenses 15% = 1810.39 Unit Rate = 13879.65

Description of works: Providing and laying Reinforcement ( diameter above 8 mm and upto 16 mm) including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per
specification and drawing. Unit : 1 mt.
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.07.2 Skilled md 12.00 870.00 10440.00 Reinforcement t 1.150 79000.00 90850.00
Unskilled md 12.00 650.00 7800.00 Binding wire kg 10.000 100.00 1000.00
Sub total of A = 18240.00 Sub total of B = 91850.00 Sub total of C = 0.00
Sub total of A +B + C = 110090.00 Contractor's overhead expenses 15% = 16513.50 Unit Rate = 126603.50

Description of works: Providing and placing concrete with 60% M 15/40 concrete and 40% boulders/stones as per specification Lead 30m, lift 1.5m , using concrete mixer and
vibrator. Unit : 1 m3
Spec.cl.No: 2406: 2, 4
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.14.01.a Skilled md 0.30 870.00 261.00 cement t 0.169 16800.00 2839.20 Concrete mixer ( 0.28 / 0.20 m3 ) hr. 0.50 515 257.50
Unskilled md 3.00 650.00 1950.00 Aggregates 20-40(mm) m3 0.345 2347.00 809.71 Concrete vibrator hr. 0.10 145 14.50
Aggregates 10-20 (mm) m3 0.156 2347.00 366.13
Aggregates 5-10(mm) m3 0.072 2347.00 168.98
sand m3 0.299 1850.00 553.15
petrol lit 0.100 99.00 9.90
diesel lit 3.000 75.00 225.00
Boulder/Stone m3 0.440 1394.25 613.47
Sub total of A = 2211.00 Sub total of B = 5585.54 Sub total of C = 272.00
Sub total of A +B + C = 8068.54 Contractor's overhead expenses 15% = 1210.28 Unit Rate = 9278.82

Prepared By Checked By Approved By


Rate analysis Page 5

Description of works: Providing, laying and levelling of dry stone soling works in the foundation all complete.
Spec. cl. No: Norms 2041(1st Unit : 1 m3
ammendment 2050)
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.01, 6.05 old Unskilled md 1.50 650.00 975.00 Blockstone m3 1.00 1394.25 1394.25
Bond stone m3 0.20 1394.25 278.85
Sub total of A = 975.00 Sub total of B = 1673.10 Sub total of C = 0.00
Sub total of A +B + C = 2648.10 Contractor's overhead expenses 15% = 397.22 Unit Rate : 3045.32

Description of works: Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(4)] including scaffolding, curing, preparation of mortar etc.
complete, masoned height 0-5m, lead 30m (machine mixing), mortar 35% Unit : 1 m3
Spec. cl. No: 2602,2603,2607

Labour (A) Material (B) Equipment (C)


Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.03.b Skilled md 1.50 870.00 1305.00 Cement t 0.155 16800.00 2604.00 Concrete mixer (0.28/0.2 m3) hr. 0.15 515 77.25
Unskilled md 3.50 650.00 2275.00 Sand m3 0.450 1850.00 832.50 Tools & Plant 3% of L.C. 107.4
Stone m3 1.150 1394.25 1603.38 Quality Control 1.50% of T.C. 133.65
Diesel lit 1.000 75 75.00
water lit 100.00 0.31 31.00
Sub total of A = 3580.00 Sub total of B = 5145.88 Sub total of C = 318.30
Sub total of A +B + C = 9044.18 Contractor's overhead expenses 15% = 1356.63 Unit Rate = 10400.81

Prepared By Checked By Approved By


Initial Group Final
S.N.
Condition
startindex endindex
Condition Condition
Description
Clearing and grubbing of forest including uprooting, carrying and disposing of
vegetation, grass, bush, spaling and trees of girth upto 300 mm (measured at
1 0 2 9 1 0
a height of 1m above the ground level), lead 10m for (a) Trees and spaling
less than 15 numbers per 100 sq. m.
Clearing and grubbing of forest including uprooting, carrying and disposing of
vegetation, grass, bush, spaling and trees of girth upto 300 mm (measured at
2 0 10 17 0
a height of 1m above the ground level), lead 10m for (a) Trees and spaling
more than 15 numbers per 100 sq. m.
Clearing of grass, removing roots breaking sods, levelling the surface and
3 0 18 25 0
disposal 10 m.
Feeling and uprooting of bamboo, clearing the area, stacking of bamboo, and
4 0 26 33 0 disposing of wastes to 10 m. (Voulme of the excavated area should be
measured)
Feeling trees (the girth measured at a height of 1m above the ground level)
including cutting of trunks and branches, removing the roots, stacking
5 0 34 41 0
serviceable materials to 10m distance and back filling the depression/pits. (a)
above 300 mm to 600 mm.
Feeling trees (the girth measured at a height of 1m above the ground level)
including cutting of trunks and branches, removing the roots, stacking
6 0 42 49 0
serviceable materials to 10m distance and back filling the depression/pits. (b)
above 600 mm to 900 mm.
Feeling trees (the girth measured at a height of 1m above the ground level)
including cutting of trunks and branches, removing the roots, stacking
7 0 50 57 0
serviceable materials to 10m distance and back filling the depression/pits. (c)
above 900 mm to 1800 mm.
Feeling trees (the girth measured at a height of 1m above the ground level)
including cutting of trunks and branches, removing the roots, stacking
8 0 58 65 0
serviceable materials to 10m distance and back filling the depression/pits. (d)
above 1800 mm to 2400 mm.
Feeling trees (the girth measured at a height of 1m above the ground level)
including cutting of trunks and branches, removing the roots, stacking
9 0 66 73 0
serviceable materials to 10m distance and back filling the depression/pits. (e)
above 2400 mm to 3000 mm.
Feeling trees (the girth measured at a height of 1m above the ground level)
including cutting of trunks and branches, removing the roots, stacking
10 0 74 81 0
serviceable materials to 10m distance and back filling the depression/pits. (e)
above 3000 mm.
Dressing and levelling of the construction surface including cutting and filling of
11 0 82 89 0
small undulation.
Excavation of top soil (sub grade) and carrying away from construction site,
12 0 90 97 0
lead 10m and thickness upto 100mm.
13 0 98 105 0 Spreading, shaping and light compacting of top soil on slopes.
Dismantling Bridge, culvert and other structures including stockpiling the
14 0 106 114 0 reusable materials and diposal of usable materials within 50 m lead for
(a) Plain cement concrete, 1:4:8 or leaner mix
Dismantling Bridge, culvert and other structures including stockpiling the
15 0 115 123 0 reusable materials and diposal of usable materials within 50 m lead for
(b) Plain cement concrete, 1:3:6 or richer mix
Dismantling Bridge, culvert and other structures including stockpiling the
16 0 124 132 0 reusable materials and diposal of usable materials within 50 m lead for
(c) Reinforced cement concrete work
Dismantling Bridge, culvert and other structures including stockpiling the
17 0 133 141 0 reusable materials and diposal of usable materials within 50 m lead for
(e) Random rubble masonry in cement mortar
Excavation of metalled road and removal of all materials including soling and
screening, sorting out reusable materials and disposing unusable materials
18 0 142 150 0
upto 20m lead
(a) Water bound macadam materials including soling / sub-base.
Excavation of metalled road and removal of all materials including soling and
screening, sorting out reusable materials and disposing unusable materials
19 0 151 159 0
upto 20m lead
(b)Bitumenous Materials
Dismantling of RCC pipes (excluding excavation and refilling).
20 0 160 168 0
i) upto 600 mm dia.
Dismantling of RCC pipes (excluding excavation and refilling).
21 0 169 177 0
ii) above 600 mm dia.
Dismantling gabion works including stockpiling the reusable materials and
22 0 178 186 0
disposal of reusable materials within 50m lead.
Providing, jointing and laying HDP pipes (110 mm/125mm outer diameter) with
23 0 187 197 1 0
or without collar etc. complete in place as per specification.
Proving and laying RCC pipes of diameter 600 mm (internal) with or without
24 0 198 209 0 collars jointed with stiff mixture of cement mortar in the proportion of
1 : 2 ( 1 cement : 2 fine sand ) , lead upto 100m.
Proving and laying RCC pipes of diameter 750 mm (internal) with or without
25 0 210 221 0 collars jointed with stiff mixture of cement mortar in the proportion of 1 : 2 ( 1
cement : 2 fine sand ) , lead upto 100m.
Proving and laying RCC pipes of diameter 900 mm (internal) with or without
26 1 222 233 1 collars jointed with stiff mixture of cement mortar in the proportion of 1 : 2 ( 1
cement : 2 fine sand ) , lead upto 100m.
Road way excavation in soft soil including disposal upto 10 m and lift upto 1.5
27 1 234 242 1 1
m etc. all complete as per specification [Manual]
Road way excavation in soft soil including disposal upto 10 m and lift upto 1.5
28 1 243 255 1
m etc. all complete as per specification. [Manual(10%), Machine(90%)]
Road way excavation in Hard soil / Gravel / Boulder mixed soil including
29 0 256 264 0 disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification.
[Manual]
Road way excavation in Hard soil / Gravel / Boulder mixed soil including
30 1 265 277 1 disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification.
[Manual(10%), Machine(90%)]
Road way excavation in Soft rock including disposal upto 10 m and lift upto 1.5
31 0 278 286 0
m etc. all complete as per specification.[Manual]
Road way excavation in Soft rock including disposal upto 10 m and lift upto 1.5
32 1 287 309 1
m etc. all complete as per specification.[Manual(10%), Machine(90%)]
Road way excavation in Hard rock including disposal upto 10 m and lift upto
33 0 310 319 0
1.5 m etc. all complete as per specification.[Manual]
Road way excavation in Hard rock including disposal upto 10 m and lift upto
34 1 320 343 1
1.5 m etc. all complete as per specification.[Manual(5%), Machine(95%)]
Earthwork excavation in soft soil for drain and trenches including shoring,
35 0 344 352 0 struting, bracing, sheeting and disposal upto 10 m and lift upto 1.5 m etc. all
complete as per specification. [Manual]
Earthwork excavation in soft soil for drain and trenches including shoring,
36 0 353 367 0 struting, bracing, sheeting and disposal upto 10 m and lift upto 1.5 m etc. all
complete as per specification. [Manual(20%), Machine(80%)]
Earthwork excavation in Hard soil/Gravels/Boulder mixed soil for drain and
37 0 368 376 0 trenches including shoring, struting, bracing, sheeting and disposal upto 10 m
and lift upto 1.5 m etc. all complete as per specification. [Manual]
Earthwork excavation in Hard soil/Gravels/Boulder mixed soil for drain and
trenches including shoring, struting, bracing, sheeting and disposal upto 10 m
38 0 377 391 0
and lift upto 1.5 m etc. all complete as per specification. [Manual(20%),
Machine(80%)]
Earthwork excavation in soft rock for drain and trenches including shoring,
39 0 392 400 0 struting, bracing, sheeting and disposal upto 10 m and lift upto 1.5 m etc. all
complete as per specification
Formation of embankment including compaction in layers not exceeding 150
40 0 401 411 0 mm compacted depth, watering and haulage 10 m etc. all complete as per
specification (i)manual methods
Formation of embankment including compaction in layers not exceeding 150
41 1 412 441 1 mm compacted depth, watering and haulage 10 m etc. all complete as per
specification (ii)using equipments.
Excavation for foundation through all types of soil including relevant lift and
42 0 442 450 0 disposal upto 20m.
(a) Depth upto 1.5 m
Excavation for foundation through all types of soil including relevant lift and
43 0 451 459 0 disposal upto 20m.
(b) Depth 1.5 m upto 3 m
Excavation for foundation through all types of soil including relevant lift and
44 0 460 468 0 disposal upto 20m.
(c) Depth upto 3m upto 4.5 m
Excavation for foundation through all types of soil including relevant lift and
45 0 469 477 0 disposal upto 20m.
(d) Depth 4.5 m upto 6 m
Underwater Excavation for foundation through all types of soil including
46 0 478 488 0 relevant lift and disposal upto 20m and dewatering.
(a) Depth upto 1.5 m
Underwater Excavation for foundation through all types of soil including
47 0 489 499 0 relevant lift and disposal upto 20m.
(b) Depth 1.5 m upto 3 m
Underwater Excavation for foundation through all types of soil including
48 0 500 510 0 relevant lift and disposal upto 20m.
(c) Depth upto 3m upto 4.5 m
Underwater Excavation for foundation through all types of soil including
49 0 511 521 0 relevant lift and disposal upto 20m.
(d) Depth 4.5 m upto 6 m
Underwater Excavation for foundation through all types of soil including
50 0 522 532 0 relevant lift and disposal upto 20m.
(d) Depth 6.0m upto 7.0 m
Backfilling in layers in foundation pits,trenches etc with approved filter material
51 0 533 541 0 including compaction and watering etc complete,lead 10 m
a) Depth of foundation upto 1.5m
Backfilling in layers in foundation pits,trenches with common excavated
52 0 542 550 0 material etc including compaction and watering etc complete,lead 10 m
a) Depth of foundation upto 1.5m
Backfilling in layers in foundation pits,trenches etc including compaction and
53 0 551 559 0 watering etc complete,lead 10 m
b) Depth of foundation 1.5 m upto 3m
Backfilling in layers in foundation pits,trenches etc including compaction and
54 0 560 568 0 watering etc complete,lead 10 m
c) Depth of foundation upto 3m upto 4.5 m.
Backfilling in layers in foundation pits,trenches etc including compaction and
55 0 569 577 0 watering etc complete,lead 10 m
d) Depth of foundation 4.5 m upto 6m.
Excavation and disposal of slides manually haulage distance upto 50m a)Soft
56 0 578 586 0
soil
Excavation and disposal of slides manually haulage distance upto 50m
57 0 587 595 0
b) Hard soil
Excavation and disposal of slides manually haulage distance upto 50m
58 0 596 604 0
c)Soft Rock
Subgrade construction and preparation of formation in cutting (other than
59 0 605 615 1 0
rock excavation) including disposal of material upto10m .
Subgrade construction, preparation and formation of subgrade in rock cutting
60 0 616 626 0
with regulating course of natural materials.
Subgrade construction with loose untreated materials; preparation and
61 0 627 637 0
formation of subgrade in fill areas.
Preparation of sub-grade for rehabilitation or other similar works (filling or
62 0 638 646 0
cutting depth of 10 to 20 cm) in common soil.
Preparation of sub-grade for rehabilitation or other similar works (filling or
63 0 647 654 0
cutting depth of 10 to 20 cm) in gravel & boulder mixed soil.
Providing, laying, spreading, watering, levelling and compaction of natural
64 0 655 665 1 0 sand gravel subbase grading as per table 12.1 of standard specification lead
upto 10m.
Providing, laying and spreading of loose natural sand gravel subbase grading
0 666 676 0
as per table 12.1 of standard specification lead upto 10m. [Loose Gravel]
Providing, laying, spreading, watering, levelling and compaction of natural
65 0 677 696 0 sand gravel subbase grading as per table 12.1 of standard specification lead
upto 10m (for manual works).
Providing, laying, spreading, watering, levelling and compaction of crusher run
66 0 697 707 0
materials for subbase course grading SB1* lead upto 10m.
Providing, laying, spreading, watering, levelling and compaction of crusher run
67 0 708 716 0 materials for subbase course grading SB1* lead upto 10m.
( for manual works)
Providing, laying, spreading, watering, levelling and compaction of crusher run
68 0 717 728 0 materials for subbase course grading SB2*lead upto 10m.
(for machine works)
Providing, laying, spreading, watering, levelling and compaction of crusher run
69 0 729 738 0 materials for subbase course grading SB2*lead upto 10m.
(for manual works)
Providing, laying, spreading, watering, levelling and compaction of crusher run
70 0 739 750 0 materials for base course lead upto 10m.
(a) Machine works
Providing, laying, spreading, watering, levelling and compaction of crusher run
71 0 751 760 0 materials for base course lead upto 10m.
(b) For manual works.

Providing, laying, spreading, watering, levelling and compaction of waterbound


72 0 761 772 0
Macadam base course class D1* grading 1 or grading 2 lead upto 10m.

Providing, laying, spreading, watering, levelling and compaction of


73 0 773 783 0 Waterbound macadam subbase course class E1* lead upto 10 m
(b) Manual works.

Providing, laying, spreading, watering, levelling and compaction of waterbound


74 0 784 795 0 Macadam base course class D1* grading 1 or grading 2 lead upto 10m.
(a) Machine works

Providing, laying, spreading, watering, levelling and compaction of waterbound


75 0 796 806 0 Macadam base course class D1* grading 1 or grading 2 lead upto 10m.
(B) Manual works

Providing, laying, spreading, watering, levelling and compaction of natural


76 0 807 818 0 sand gravel wearing course class -1 / class -2 lead upto 10m. For machine
works

Providing, laying, spreading, watering, levelling and compaction of natural


77 0 819 828 0
sand gravel wearing course class -1/class -2 lead upto 10m for manual works.
Providing and spraying bituminous tack coat MC30/MC70 including cleaning
78 0 829 839 1 0
the road surface using wire, brushes, broom etc. before applying tack coat.
Providing and spraying bituminous tack coat MC30/MC70 including cleaning
79 0 840 849 0 the road surface using wire, brushes, broom etc. before applying tack coat,
using manual methods.
Providing and spraying bituminous prime coat MC30/MC70 including cleaning
80 0 850 860 0
the road surface using wire, brushes, broom etc. before applying prime coat.
Providing and spraying bituminous prime coat MC30/MC70 including cleaning
81 0 861 870 0 the road surface using wire, brushes, broom etc. before applying prime coat,
using manual methods.
Laying of single / double / multiple bituminous coats for surface dressing using
82 0 871 881 0 river gravels, shingles or broken stone chips including compaction
I) Bituminous binder for surface dressing( mass work).
Laying of single / double / multiple bituminous coats for surface dressing using
83 0 882 892 0 river gravels, shingles or broken stone chips including compaction
I) Bituminous binder for surface dressing( Patch work).
Laying of single / double / multiple bituminous coats for surface dressing using
84 0 893 902 0 river gravels, shingles or broken stone chips including compaction --
II) Cutter for bitumen grade 80/100.
Laying of single / double / multiple bituminous coats for surface dressing using
85 0 903 912 0 river gravels, shingles or broken stone chips including compaction --
III) Chipping for surface dressing for 1st coat size or second coat size.
Laying of single / double / multiple bituminous coats for surface dressing using
86 0 913 923 0 river gravels, shingles or broken stone chips including compaction --
IV) Production of percorated chipping.
87 0 924 937 0 Providing and laying semi-grouting with compaction 50mm thickness.
88 0 938 951 0 Providing and laying semi-grouting with compaction 75mm thickness.
89 0 952 965 0 Providing and laying full grouting with compaction 50 mm thicknes.
90 0 966 978 0 Providing and laying sand seal.
91 0 979 992 0 Providing, mixing and laying slurry seal with fine slurry mix.
92 0 993 1006 0 Providing, mixing and laying slurry seal with normal slurry mix.
93 0 1007 1020 0 Providing, mixing and laying slurry seal with coarse slurry mix.
94 0 1021 1031 0 Providing, mixing, laying and compaction of premix carpet.
95 0 1032 1045 0 Providing, mixing, and laying asphalt concrete with compaction.
Supplying and erecting traffic sign in place including 50mm dia. Steel tube,
2mm. thick steel plate, cement concrete, painting, writing and supporting steel
96 0 1046 1058 1 0
angle nut and bolit etc. complete a) 60cm. Dia. Circular, 60cm. equilateral
traingle and 60cm.x 45cm. rectangular shaped sign (single post).
Supplying and erecting traffic sign in place including 50mm dia. Steel tube,
2mm. thick steel plate, cement concrete, painting, writing and supporting steel
97 0 1059 1071 0
angle nut and bolit etc. complete b) 1.2m.x 0.75m. Size bigger traffic sign with
back support and two or more post.
Supplying and applying paint for Road marking including cleaning, watering,
98 0 1072 1081 0 brooming etc. all complete (10cm. wide strip)
a) Two coats over old painted surface
Supplying and applying paint for Road marking including cleaning, watering,
99 0 1082 1091 0 brooming etc. all complete (10cm. wide strip)
b) More than two coats over new bitumin surface
Supplying and placing R.C.C. kilometer post including excavation, back filling,
100 0 1092 1104 0 painting and writing etc. all complete as per specification
a) Standard KM post placed at each kilometer.
Supplying and placing R.C.C. kilometer post including excavation, back filling,
101 0 1105 1117 0 painting and writing etc. all complete as per specification
b) Bigger kilometer post (placed at each 5 km.)

Supplying and fixing in place R.C.C. delineator and guard post including
102 0 1118 1129 0
excavation, back filling, painting and erection etc. all complete as per drawing.

Providing , Preparing and Installing form work including necessary supports


103 1 1130 1141 1 1 and removing after completion for foundation and footings
(a) using timber ( soft wood) - Class F1 finish.
Providing , Preparing and Installing form work including necessary supports
104 0 1142 1153 0 and removing after completion ---For Vertical plain surface [class F2 finish]
height upto 3 m
Providing , Preparing and Installing form work including necessary supports
105 0 1154 1165 0 and removing after completion ---For Vertical plain surface [class F2 finish]
height upto 3 m upto 6m.
Providing , Preparing and Installing form work including necessary supports
106 0 1166 1176 0 and removing after completion ---For Vertical plain surface [class F2 finish]
height upto 6 m upto 9m.
Providing , Preparing and Installing form work including necessary supports
107 0 1177 1189 0 and removing after completion ---For Vertical curved surface [class F2 finish]
height upto 3.0 m.
Providing , Preparing and Installing form work including necessary supports
108 0 1190 1201 0 and removing after completion ---For Vertical curved surface [class F2 finish]
height 3.0 m upto 6.0 m.
Providing , Preparing and Installing form work including necessary supports
109 0 1202 1213 0 and removing after completion ---For Vertical curved surface [class F2 finish]
height 6.0 upto 9.0m.
Providing , Preparing and Installing form work including necessary supports
110 0 1214 1224 0 and removing after completion ---For slab structure [class F2 finish] using
timber planks. (Falsework not included)
Providing , Preparing and Installing form work including necessary supports
111 0 1225 1235 0 and removing after completion ---For slab and beam structure [class F2 finish]
using timber planks. (Falsework not included)
Providing, and assembling in position falsework for the construction of RCC
superstructure and removal after completion including necessary design and
112 0 1236 1246 0
drawings as per specification.
A) For Slabs and Box culverts , using timber for height 2m ~ 4m
Providing, and assembling in position falsework for the construction of RCC
superstructure and removal after completion including necessary design and
113 0 1247 1257 0
drawings as per specification.
A) For RCC beam bridges , using timber for height 3m ~ 6m
Providing and fixing in positions, 75 mm diameter drainage spouts with
114 0 1258 1266 0
necessary hardware.
Providing and installing Expansion Joints and tarfelt sheet including all
115 0 1267 1275 1 0 necessaary axilliary and incidental works etc. complete as per drawing and
specification.
Providing and fixing in positions,reinforced elastomeric bearing pad per
116 0 1276 1284 0
drawing and instructions.
Providing and placing machine mixed M10/40 cement concrete for the
117 0 1285 1299 1 0 foundation and footing etc. including compaction, curing, testing and lead
30m. etc. all complete as per specification and drawing.
Providing and placing machine mixed M15/40 cement concrete for the
118 1 1300 1315 1 foundation and footing etc. including compaction, curing, testing and lead
30m. etc. all complete as per specification and drawing.
Providing and placing machine mixed M20/40 cement concrete for the
119 0 1316 1331 0 foundation and footing etc. including compaction, curing, testing and lead
30m. etc. all complete as per specification and drawing.
Providing and placing machine mixed M20/20 cement concrete for the
120 1 1332 1346 1 foundation and footing etc. including compaction, curing, testing and lead
30m. etc. all complete as per specification and drawing.
Providing and placing machine mixed M25/20 cement concrete for the
121 0 1347 1361 0 foundation and footing etc. including compaction, curing, testing and lead
30m. etc. all complete as per specification and drawing.
Providing and placing manually mixed M10/40 cement concrete for the
122 0 1362 1374 0 foundation and footing etc. including compaction, curing, testing and lead
30m. etc. all complete as per specification and drawing.
Providing and placing manually mixed M15/40 cement concrete for the
123 0 1375 1388 0 foundation and footing etc. including compaction, curing, testing and lead
30m. etc. all complete as per specification and drawing.
Providing and placing manually mixed M20/40 cement concrete for the
124 0 1389 1402 0 foundation and footing etc. including compaction, curing, testing and lead
30m. etc. all complete as per specification and drawing.
Providing and placing manually mixed M20/20 cement concrete for the
125 0 1403 1415 0 foundation and footing etc. including compaction, curing, testing and lead
30m. etc. all complete as per specification and drawing.
Providing and placing manually mixed M25/20 cement concrete for the
126 0 1416 1428 0 foundation and footing etc. including compaction, curing, testing and lead
30m. etc. all complete as per specification and drawing.
Providing and placing machine mixed M15/40 cement concrete for abutment,
127 0 1429 1444 0 pier, wall, etc. including compaction, curing, testing and lead 30m. etc. all
complete as per specification and drawing.
Providing and placing machine mixed M20/40 cement concrete for abutment,
128 0 1445 1460 0 pier, wall, etc. including compaction, curing, testing and lead 30m. etc. all
complete as per specification and drawing.
Providing and placing machine mixed M20/20 cement concrete for abutment,
129 0 1461 1475 0 pier, wall, etc. including compaction, curing, testing and lead 30m. etc. all
complete as per specification and drawing.
Providing and placing machine mixed M25/20 cement concrete for abutment,
130 0 1476 1490 0 pier, wall, etc. including compaction, curing, testing and lead 30m. etc. all
complete as per specification and drawing.
Providing and placing machine mixed M20/20 cement concrete for the
131 0 1491 1505 0 superstructure, deckslab, girder etc. including compaction, curing, testing and
lead 30m. etc. all complete as per specification and drawing.
Providing and placing machine mixed M25/20 cement concrete for
132 0 1506 1520 0 superstructure, deckslab, girder, etc. including compaction, curing, testing and
lead 30m. etc. all complete as per specification and drawing.
Providing and placing manually mixed non structural cement concrete
133 0 1521 1533 0 [ cement (1): sand (4) : aggregate (8) ] including compaction, curing, testing
and lead 30m. etc. all complete as per specification and drawing.
Providing and placing manually mixed non structural cement concrete
134 0 1534 1546 0 [ cement (1): sand (3) : aggregate (6) ] including compaction, curing, testing
and lead 30m. etc. all complete as per specification and drawing.
Providing and placing manually mixed non structural cement concrete
135 0 1547 1559 0 [ cement (1): sand (2) : aggregate (4) ] including compaction, curing, testing
and lead 30m. etc. all complete as per specification and drawing.
Providing and laying Reinforcement ( diameter upto 8 mm) including cutting,
136 0 1560 1569 0 bending, binding, fixing in position and lead 30m. etc. all complete as per
specification and drawing.
Providing and laying Reinforcement ( diameter above 8 mm and upto 16 mm)
137 1 1570 1579 1 including cutting, bending, binding, fixing in position and lead 30m. etc. all
complete as per specification and drawing.
Providing and laying Reinforcement ( diameter above 16 mm) including
138 0 1580 1589 0 cutting, bending, binding, fixing in position and lead 30m. etc. all complete as
per specification and drawing.
Fabrication of hexagonal mesh type 100mm x 120 mm Gabion boxes /
mattresses with diapharagms, with binding wire 12 swg, mesh wire 10 swg and
selvedged wire 8 swg , including rolling, cutting and weaving ; assembling
Gabion boxes mattresses, palcing in position including stretching, forming
139 0 1590 1645 1 0
compartments; tying with bracing wires and tie wires; tying down the lid
complete; and providing and filling stone / boulder in gabion boxes /
mattresses etc. including dressing, beding, bonding and all transporation as
per specification.
Providing and laying grouted stone pitching in protection work with stone size
140 0 1646 1656 0
not less than 0.01 m3 and cement : sand motar (1:3) lead 30m, lift 1.5m
141 0 1657 1665 0 Providing, laying and fixing of Geo-textile (filter fabrics), lead 30m
Providing and placing concrete with 60% M 15/40 concrete and 40%
142 1 1666 1681 1 boulders/stones as per specification Lead 30m, lift 1.5m , using concrete mixer
and vibrator.
Providing and placing concrete with 60% M 15/40 concrete and 40%
143 0 1682 1695 0 boulders/stones as per specification Lead 30m, lift 1.5m , without using
concrete mixer and vibrator.
Providing and placing plum-concrete with 70% M 15/40 concrete and 30%
144 0 1696 1711 0 boulders/stones as per specification. Lead 30m, lift 1.5m using concrete
mixer and vibrator.
Providing and placing concrete with 70% M 15/40 concrete and 30%
145 0 1712 1725 0 boulders/stones as per specification Lead 30m, lift 1.5m , without using
concrete mixer and vibrator.
Providing and laying brick masonry in manual mixed cement mortar 1:4
146 0 1726 1737 1 0
including preparation of mortar as per specification, lead 30 m.
Providing and applying 20mm thick cement plaster including mortar mixing,
147 0 1738 1749 0 scaffolding, curing etc. complete as per specification lead 30 m (manual
mixing)
Providing, laying and levelling of dry stone masonry works in the foundation
148 1 1750 1760 1
all complete.
Providing and laying dry stone masonry (coursed rubble) including dressing
149 0 1761 1770 1 0
etc. complete as per specification, lead 30m.
Providing and laying Random rubble stone masonry in cement mortar
150 0 1771 1783 0 [ cement(1) : sand(3)] including scaffolding, curing, preparation of mortar etc.
complete, masoned height 0-5m, lead 30m (machine mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar
151 1 1784 1796 1 [ cement(1) : sand(4)] including scaffolding, curing, preparation of mortar etc.
complete, masoned height 0-5m, lead 30m (machine mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar
152 0 1797 1809 0 [ cement(1) : sand(6)] including scaffolding, curing, preparation of mortar etc.
complete, masoned height 0-5m, lead 30m (machine mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar
153 0 1810 1821 0 [ cement(1) : sand(3)] including scaffolding, curing, preparation of mortar etc.
complete, masoned height 0-5m, lead 30m (manual mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar
154 0 1822 1833 0 [ cement(1) : sand(4)] including scaffolding, curing, preparation of mortar etc.
complete, masoned height 0-5m, lead 30m (manual mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar
155 0 1834 1845 0 [ cement(1) : sand(6)] including scaffolding, curing, preparation of mortar etc.
complete, masoned height 0-5m, lead 30m (manual mixing), mortar 35%
Providing and laying Coursed rubble stone masonry in cement mortar
156 0 1846 1858 0 [ cement(1) : sand(3)] including scaffolding, curing, preparation of mortar etc.
complete, masoned height 0-5m, lead 30m (machine mixing), mortar 30%
Providing and laying Coursed rubble stone masonry in cement mortar
157 0 1859 1871 0 [ cement(1) : sand(4)] including scaffolding, curing, preparation of mortar etc.
complete, masoned height 0-5m, lead 30m (machine mixing), mortar 30%
Providing and laying Coursed rubble stone masonry in cement mortar
158 0 1872 1884 0 [ cement(1) : sand(6)] including scaffolding, curing, preparation of mortar etc.
complete, masoned height 0-5m, lead 30m (machine mixing), mortar 30%

Providing, mixing, and Pointing cement mortar over rubble masonry works in
159 0 1885 1897 0 cement mortar [ cement(1) : sand(1)] including scaffolding, curing, preparation
of mortar etc. complete, masoned height 0-5m, lead 30m (machine mixing).

Providing, mixing, and Pointing cement mortar over rubble masonry works in
160 0 1898 1910 0 cement mortar [ cement(1) : sand(2)] including scaffolding, curing, preparation
of mortar etc. complete, masoned height 0-5m, lead 30m (machine mixing).
Providing, mixing, and Pointing cement mortar over rubble masonry works in
161 0 1911 1923 0 cement mortar [ cement(1) : sand(3)] including scaffolding, curing, preparation
of mortar etc. complete, masoned height 0-5m, lead 30m (machine mixing).

Removal of old paints by sand blasting, cleaning and repairing of metal


162 0 1924 1934 1 0
surfaces for the application of new paints as per specification.
Double coat whitewash on new surface including supply of materials all
163 0 1935 1946 0
complete
Single coat whitewash on old surface including supply of materials all
164 0 1947 1958 0
complete
Single coat enamel paint/ readymade emulsion paint with primer including
165 0 1959 1971 0
supply of materials all complete.
Restoration of rain cuts in embankment slopes including watering and
166 0 1972 1981 1 0
compaction etc. all complete lead 10 m.
Maintenance of earthen shoulders by making irregularities even to the required
167 0 1982 1991 0
level including watering and compaction etc. all complete lead 10m.
Maintenance of gravel shoulders and gravel carriageway by repairing pot
168 0 1992 2001 0 holes and making iregularities even to the required level including watering
and compaction etc. all complete lead 10m.
Repair of potholes and damaged bituminous surface including cleaning,
169 0 2002 2015 0 brooming, and rolling etc all complete using hot premix material for 20mm
shallow patching.
170 0 2016 2024 1 0 Providing and installing Railing including Railing Posts -- 100 mm dia
171 0 2025 2033 0 Providing and installing Railing including Railing Posts -- 50 mm dia
172 0 2034 2042 0 Providing and installing Railing including Railing Posts -- 38 mm dia
Summary (Checklist)

Specification Rate
S.N. Norms No Description Unit
Clause No. ( NRs.)
A ACTIVITY GROUP 2 : SITE CLEARANCE
Clearing and grubbing of forest including uprooting, carrying and disposing of vegetation, grass,
1 2.01.a 201 bush, spaling and trees of girth upto 300 mm (measured at a height of 1m above the ground level), m2 23.09
lead 10m for (a) Trees and spaling less than 15 numbers per 100 sq. m.
Clearing and grubbing of forest including uprooting, carrying and disposing of vegetation, grass,
2 2.01.b 201 bush, spaling and trees of girth upto 300 mm (measured at a height of 1m above the ground level), m2 30.80
lead 10m for (a) Trees and spaling more than 15 numbers per 100 sq. m.

3 2.02 201 Clearing of grass, removing roots breaking sods, levelling the surface and disposal 10 m. m2 17.70

Feeling and uprooting of bamboo, clearing the area, stacking of bamboo, and disposing of wastes to
4 2.03 201 10 m. (Voulme of the excavated area should be measured)
m3 2155.79

Feeling trees (the girth measured at a height of 1m above the ground level) including cutting of trunks
5 2.04.a 201 and branches, removing the roots, stacking serviceable materials to 10m distance and back filling the no 708.33
depression/pits. (a) above 300 mm to 600 mm.
Feeling trees (the girth measured at a height of 1m above the ground level) including cutting of trunks
6 2.04.b 201 and branches, removing the roots, stacking serviceable materials to 10m distance and back filling the no 2694.74
depression/pits. (b) above 600 mm to 900 mm.
Feeling trees (the girth measured at a height of 1m above the ground level) including cutting of trunks
7 2.04.c 201 and branches, removing the roots, stacking serviceable materials to 10m distance and back filling the No 7506.76
depression/pits. (c) above 900 mm to 1800 mm.
Feeling trees (the girth measured at a height of 1m above the ground level) including cutting of trunks
8 2.04.d 201 and branches, removing the roots, stacking serviceable materials to 10m distance and back filling the No 12318.80
depression/pits. (d) above 1800 mm to 2400 mm.
Feeling trees (the girth measured at a height of 1m above the ground level) including cutting of trunks
9 2.04.e 201 and branches, removing the roots, stacking serviceable materials to 10m distance and back filling the No 30797.00
depression/pits. (e) above 2400 mm to 3000 mm.
Feeling trees (the girth measured at a height of 1m above the ground level) including cutting of trunks
10 2.04.f 201 and branches, removing the roots, stacking serviceable materials to 10m distance and back filling the No 60600.79
depression/pits. (e) above 3000 mm.
11 2.05 201,909 Dressing and levelling of the construction surface including cutting and filling of small undulation. m2 7.69
Excavation of top soil (sub grade) and carrying away from construction site, lead 10m and thickness
12 2.06 201,1003 upto 100mm.
m2 123.19

13 2.07 201,2800 Spreading, shaping and light compacting of top soil on slopes. m2 38.49

Dismantling Bridge, culvert and other structures including stockpiling the reusable materials and
14 2.08.01 202 diposal of usable materials within 50 m lead for m3 1129.42
(a) Plain cement concrete, 1:4:8 or leaner mix
Dismantling Bridge, culvert and other structures including stockpiling the reusable materials and
15 2.08.02 202 diposal of usable materials within 50 m lead for m3 1822.35
(b) Plain cement concrete, 1:3:6 or richer mix
Dismantling Bridge, culvert and other structures including stockpiling the reusable materials and
16 2.08.03 202 diposal of usable materials within 50 m lead for m3 2553.78
(c) Reinforced cement concrete work
Dismantling Bridge, culvert and other structures including stockpiling the reusable materials and
17 2.08.05 202 diposal of usable materials within 50 m lead for m3 1835.38
(e) Random rubble masonry in cement mortar
Excavation of metalled road and removal of all materials including soling and screening, sorting out
18 2.15.a 202 reusable materials and disposing unusable materials upto 20m lead m3 695.53
(a) Water bound macadam materials including soling / sub-base.
Excavation of metalled road and removal of all materials including soling and screening, sorting out
19 2.15.b 202 reusable materials and disposing unusable materials upto 20m lead m3 1873.52
(b)Bitumenous Materials

Dismantling of RCC pipes (excluding excavation and refilling).


20 2.17.i 202 i) upto 600 mm dia.
m 318.27

Dismantling of RCC pipes (excluding excavation and refilling).


21 2.17.ii 202 ii) above 600 mm dia.
m 626.24

Dismantling gabion works including stockpiling the reusable materials and disposal of reusable
22 2.18 202 materials within 50m lead.
m3 872.98

B ACTIVITY GROUP 7 : PIPE DRAINS, PIPE CULVERTS AND CONCRETE CHANNELS

Providing, jointing and laying HDP pipes (110 mm/125mm outer diameter) with or without collar etc.
23 7.01.a 701 complete in place as per specification.
m 141.90

Proving and laying RCC pipes of diameter 600 mm (internal) with or without collars jointed with stiff
24 7.02.i 701 mixture of cement mortar in the proportion of m 8854.60
1 : 2 ( 1 cement : 2 fine sand ) , lead upto 100m.
Proving and laying RCC pipes of diameter 750 mm (internal) with or without collars jointed with stiff
25 7.02.ii 701 mixture of cement mortar in the proportion of 1 : 2 ( 1 cement : 2 fine sand ) , lead upto 100m. m 11800.70
Proving and laying RCC pipes of diameter 900 mm (internal) with or without collars jointed with stiff
26 7.02.iii 701 mixture of cement mortar in the proportion of 1 : 2 ( 1 cement : 2 fine sand ) , lead upto 100m.
m 15434.59

C ACTIVITY GROUP 9 : EARTHWORKS

Road way excavation in soft soil including disposal upto 10 m and lift upto 1.5 m etc. all complete as
27 9.01.a 905 per specification [Manual] m3 577.44

Road way excavation in soft soil including disposal upto 10 m and lift upto 1.5 m etc. all complete as
28 9.01.a 905 per specification. [Manual(10%), Machine(90%)] m3 96.89

Road way excavation in Hard soil / Gravel / Boulder mixed soil including disposal upto 10 m and lift
29 9.01.b 905 upto 1.5 m etc. all complete as per specification.[Manual] m3 769.93
Road way excavation in Hard soil / Gravel / Boulder mixed soil including disposal upto 10 m and lift
30 9.01.b 905 upto 1.5 m etc. all complete as per specification.[Manual(10%), Machine(90%)] m3 112.69
Road way excavation in Soft rock including disposal upto 10 m and lift upto 1.5 m etc. all complete
31 9.01.c 905 as per specification.[Manual]
m3 2117.29
Road way excavation in Soft rock including disposal upto 10 m and lift upto 1.5 m etc. all complete
32 9.01.c 905 as per specification.[Manual(10%), Machine(90%)] m3 245.97
Road way excavation in Hard rock including disposal upto 10 m and lift upto 1.5 m etc. all complete
33 9.01.c 905 as per specification.[Manual]
m3 9239.10
Road way excavation in Hard rock including disposal upto 10 m and lift upto 1.5 m etc. all complete
34 9.01.c 905 as per specification.[Manual(5%), Machine(95%)]
m3 507.50
Earthwork excavation in soft soil for drain and trenches including shoring, struting, bracing,
35 9.02.a 905 sheeting and disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification. [Manual]
m3 692.93
Summary (Checklist)
Specification Rate
S.N. Norms No Description Unit
Clause No. ( NRs.)
Earthwork excavation in soft soil for drain and trenches including shoring, struting, bracing,
36 9.02.a 905 sheeting and disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification. m3 107.92
[Manual(20%), Machine(80%)]
Earthwork excavation in Hard soil/Gravels/Boulder mixed soil for drain and trenches including
37 9.02.b 905 shoring, struting, bracing, sheeting and disposal upto 10 m and lift upto 1.5 m etc. all complete as per m3 1154.89
specification. [Manual]
Earthwork excavation in Hard soil/Gravels/Boulder mixed soil for drain and trenches including
38 9.02.b 905 shoring, struting, bracing, sheeting and disposal upto 10 m and lift upto 1.5 m etc. all complete as per m3 265.31
specification. [Manual(20%), Machine(80%)]
Earthwork excavation in soft rock for drain and trenches including shoring, struting, bracing, sheeting
39 9.02.c 905 and disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification
m3 2309.78

Formation of embankment including compaction in layers not exceeding 150 mm compacted depth,
40 9.05.a 909 watering and haulage 10 m etc. all complete as per specification (i)manual methods m3 800.68

Formation of embankment including compaction in layers not exceeding 150 mm compacted depth,
41 9.05.b 909 watering and haulage 10 m etc. all complete as per specification (ii)using equipments.
m3 445.68

Excavation for foundation through all types of soil including relevant lift and disposal upto 20m.
42 9.07.01.a 907 (a) Depth upto 1.5 m m3 1539.85

Excavation for foundation through all types of soil including relevant lift and disposal upto 20m.
43 9.07.01.b 907 (b) Depth 1.5 m upto 3 m
m3 2309.78

Excavation for foundation through all types of soil including relevant lift and disposal upto 20m.
44 9.07.01.c 907 (c) Depth upto 3m upto 4.5 m
m3 3079.70

Excavation for foundation through all types of soil including relevant lift and disposal upto 20m.
45 9.07.01.d 907 (d) Depth 4.5 m upto 6 m m3 3657.14
Underwater Excavation for foundation through all types of soil including relevant lift and disposal upto
46 9.07.1.a 907 20m and dewatering. m3 1847.82
(a) Depth upto 1.5 m
Underwater Excavation for foundation through all types of soil including relevant lift and disposal upto
47 9.07.01.b 907 20m. m3 3695.64
(b) Depth 1.5 m upto 3 m
Underwater Excavation for foundation through all types of soil including relevant lift and disposal upto
48 9.07.01.c 907 20m. m3 5851.43
(c) Depth upto 3m upto 4.5 m
Underwater Excavation for foundation through all types of soil including relevant lift and disposal upto
49 9.07.01.d 907 20m. m3 6948.55
(d) Depth 4.5 m upto 6 m
Underwater Excavation for foundation through all types of soil including relevant lift and disposal upto
50 9.07.01.e 907 20m. m3 9033.14
(d) Depth 6.0m upto 7.0 m
Backfilling in layers in foundation pits,trenches etc with approved filter material including
51 9.10.a 908 compaction and watering etc complete,lead 10 m m3 3846.67
a) Depth of foundation upto 1.5m
Backfilling in layers in foundation pits,trenches with common excavated material etc
52 9.10.a 908 including compaction and watering etc complete,lead 10 m m3 877.71
a) Depth of foundation upto 1.5m
Backfilling in layers in foundation pits,trenches etc including compaction and watering etc
53 9.10.b 908 complete,lead 10 m m3 1247.28
b) Depth of foundation 1.5 m upto 3m
Backfilling in layers in foundation pits,trenches etc including compaction and watering etc
54 9.10.c 908 complete,lead 10 m m3 1616.84
c) Depth of foundation upto 3m upto 4.5 m.
Backfilling in layers in foundation pits,trenches etc including compaction and watering etc
55 9.10.d 908 complete,lead 10 m m3 1986.41
d) Depth of foundation 4.5 m upto 6m.

56 9.11.a 908 Excavation and disposal of slides manually haulage distance upto 50m a)Soft soil m3 461.96

Excavation and disposal of slides manually haulage distance upto 50m


57 9.11.b 908 b) Hard soil
m3 615.94

Excavation and disposal of slides manually haulage distance upto 50m


58 9.11.c 908 c)Soft Rock
m3 1231.88

C ACTIVITY GROUP 10 : SUB GRADES

Subgrade construction and preparation of formation in cutting (other than rock excavation) including
59 10.01 1003 disposal of material upto10m . m3 139.74

Subgrade construction, preparation and formation of subgrade in rock cutting with regulating course
60 10.02 1003 of natural materials.
m3 195.09

Subgrade construction with loose untreated materials; preparation and formation of subgrade in fill
61 10.03 1003 areas. m3 553.06

Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20
62 10.05.a 1003 cm) in common soil.
m2 115.48

Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20
63 10.05.b 1003 cm) in gravel & boulder mixed soil.
m2 230.98

C ACTIVITY GROUP 12 : SUB-BASE, BASE

Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase
64 12.01 1201 grading as per table 12.1 of standard specification lead upto 10m. m3 1814.52

Providing, laying and spreading of loose natural sand gravel subbase grading as per table 12.1 of
65 12.02 1201 standard specification lead upto 10m. [Loose Gravel]
m3 1312.58

Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase
66 12.02 1201 grading as per table 12.1 of standard specification lead upto 10m (for manual works). m3 2491.77

Providing, laying, spreading, watering, levelling and compaction of crusher run materials for subbase
67 12.03 1202 course grading SB1* lead upto 10m. m3 3708.50

Providing, laying, spreading, watering, levelling and compaction of crusher run materials for subbase
68 12.04 1202 course grading SB1* lead upto 10m. m3 4639.33
( for manual works)
Providing, laying, spreading, watering, levelling and compaction of crusher run materials for subbase
69 12.05 1202 course grading SB2*lead upto 10m. m3 3708.50
(for machine works)
Providing, laying, spreading, watering, levelling and compaction of crusher run materials for subbase
70 12.06 1202 course grading SB2*lead upto 10m. m3 4647.38
(for manual works)
Summary (Checklist)
Specification Rate
S.N. Norms No Description Unit
Clause No. ( NRs.)
Providing, laying, spreading, watering, levelling and compaction of crusher run materials for base
71 12.07 1202 course lead upto 10m. m3 3453.09
(a) Machine works
Providing, laying, spreading, watering, levelling and compaction of crusher run materials for base
72 12.08 1202 course lead upto 10m. m3 4472.47
(b) For manual works.
Providing, laying, spreading, watering, levelling and compaction of waterbound Macadam base
73 12.09 1203 course class D1* grading 1 or grading 2 lead upto 10m.
m3 4072.64

Providing, laying, spreading, watering, levelling and compaction of Waterbound macadam subbase
74 12.10 1203 course class E1* lead upto 10 m m3 5094.86
(b) Manual works.
Providing, laying, spreading, watering, levelling and compaction of waterbound Macadam base
75 12.11 1203 course class D1* grading 1 or grading 2 lead upto 10m. m3 3886.64
(a) Machine works
Providing, laying, spreading, watering, levelling and compaction of waterbound Macadam base
76 12.12 1203 course class D1* grading 1 or grading 2 lead upto 10m. m3 4887.56
(B) Manual works
Providing, laying, spreading, watering, levelling and compaction of natural sand gravel wearing
77 12.13 1205 course class -1 / class -2 lead upto 10m. For machine works
m3 1789.2

Providing, laying, spreading, watering, levelling and compaction of natural sand gravel wearing
78 12.14 1205 course class -1/class -2 lead upto 10m for manual works. m3 2895.63

C ACTIVITY GROUP 13 : BITUMINOUS SURFACE AND BASE COURSE

Providing and spraying bituminous tack coat MC30/MC70 including cleaning the road surface using
79 13.01 1301, 1302 wire, brushes, broom etc. before applying tack coat.
Ltr 164.11

Providing and spraying bituminous tack coat MC30/MC70 including cleaning the road surface using
80 13.02 1301, 1302 wire, brushes, broom etc. before applying tack coat, using manual methods. Ltr 146.96

Providing and spraying bituminous prime coat MC30/MC70 including cleaning the road surface using
81 13.03 1301, 1302 wire, brushes, broom etc. before applying prime coat.
Ltr 164.11

Providing and spraying bituminous prime coat MC30/MC70 including cleaning the road surface using
82 13.04 1301, 1302 wire, brushes, broom etc. before applying prime coat, using manual methods.
Ltr 146.96

Laying of single / double / multiple bituminous coats for surface dressing using river gravels, shingles
83 13.05.01 1301, 1303 or broken stone chips including compaction Ltr 141.58
I) Bituminous binder for surface dressing( mass work).
Laying of single / double / multiple bituminous coats for surface dressing using river gravels, shingles
84 13.05.02 1301, 1303 or broken stone chips including compaction Ltr 160.30
I) Bituminous binder for surface dressing( Patch work).
Laying of single / double / multiple bituminous coats for surface dressing using river gravels, shingles
85 13.05.03 1301, 1303 or broken stone chips including compaction -- Ltr 88.04
II) Cutter for bitumen grade 80/100.
Laying of single / double / multiple bituminous coats for surface dressing using river gravels, shingles
86 13.05.04 1301, 1303 or broken stone chips including compaction -- Mt 3638.85
III) Chipping for surface dressing for 1st coat size or second coat size.
Laying of single / double / multiple bituminous coats for surface dressing using river gravels, shingles
87 13.05.05 1301, 1303 or broken stone chips including compaction -- m3 6442.28
IV) Production of percorated chipping.

88 13.06.01 1301, 1304 Providing and laying semi-grouting with compaction 50mm thickness. m2 848.52

89 13.06.02 1301, 1304 Providing and laying semi-grouting with compaction 75mm thickness. m2 1127.31

90 13.06.03 1301, 1304 Providing and laying full grouting with compaction 50 mm thicknes. m2 1024.17

91 13.07 1301, 1305 Providing and laying sand seal. m2 115.59

92 13.08.01 1301, 1306 Providing, mixing and laying slurry seal with fine slurry mix. m2 159.74

93 13.08.02 1301, 1306 Providing, mixing and laying slurry seal with normal slurry mix. m2 176.6

94 13.08.03 1301, 1306 Providing, mixing and laying slurry seal with coarse slurry mix. m2 203.89

95 13.09 1307, 1308 Providing, mixing, laying and compaction of premix carpet. m3 14970.01

96 13.1 1307, 1308 Providing, mixing, and laying asphalt concrete with compaction. m3 16258.87

ACTIVITY GROUP 15 : TRAFFIC SIGNS AND ROAD MARKING


Supplying and erecting traffic sign in place including 50mm dia. Steel tube, 2mm. thick steel plate,
97 15.01.a 1501 cement concrete, painting, writing and supporting steel angle nut and bolit etc. complete a) 60cm. no 672.88
Dia. Circular, 60cm. equilateral traingle and 60cm.x 45cm. rectangular shaped sign (single post).
Supplying and erecting traffic sign in place including 50mm dia. Steel tube, 2mm. thick steel plate,
98 15.01.b 1501 cement concrete, painting, writing and supporting steel angle nut and bolit etc. complete b) 1.2m.x no 2396.38
0.75m. Size bigger traffic sign with back support and two or more post.
Supplying and applying paint for Road marking including cleaning, watering, brooming etc. all
99 15.02.a 1502 complete (10cm. wide strip) m 31.86
a) Two coats over old painted surface
Supplying and applying paint for Road marking including cleaning, watering, brooming etc. all
100 15.02.b 1502 complete (10cm. wide strip) m 55.09
b) More than two coats over new bitumin surface
Supplying and placing R.C.C. kilometer post including excavation, back filling, painting and writing
101 15.03.a 1503 etc. all complete as per specification no 2483.34
a) Standard KM post placed at each kilometer.
Supplying and placing R.C.C. kilometer post including excavation, back filling, painting and writing
102 15.03.b 1503 etc. all complete as per specification no 5506.11
b) Bigger kilometer post (placed at each 5 km.)
Supplying and fixing in place R.C.C. delineator and guard post including excavation, back filling,
103 15.04 1504 painting and erection etc. all complete as per drawing.
no 1228.28

ACTIVITY GROUP 18 : FASLEWORK, FORMWORK & SURFACE FINISH FOR CONCRETE STRUCTURES
Summary (Checklist)
Specification Rate
S.N. Norms No Description Unit
Clause No. ( NRs.)
Providing , Preparing and Installing form work including necessary supports and removing after
104 18.01 1804, 1805 completion for foundation and footings m2 475.53
(a) using timber ( soft wood) - Class F1 finish.

Providing , Preparing and Installing form work including necessary supports and removing after
105 18.02.1.a.i 1804, 1805 completion ---For Vertical plain surface [class F2 finish] height upto 3 m
m2 654.83

Providing , Preparing and Installing form work including necessary supports and removing after
106 18.02.1.a.ii 1804, 1805 completion ---For Vertical plain surface [class F2 finish] height upto 3 m upto 6m. m2 786.28

Providing , Preparing and Installing form work including necessary supports and removing after
107 18.02.1.a.iii 1804, 1805 completion ---For Vertical plain surface [class F2 finish] height upto 6 m upto 9m. m2 982.58

Providing , Preparing and Installing form work including necessary supports and removing after
108 18.02.02.a.i 1804, 1805 completion ---For Vertical curved surface [class F2 finish] height upto 3.0 m. m2 881.79

Providing , Preparing and Installing form work including necessary supports and removing after
109 18.02.02.a.ii 1804, 1805 completion ---For Vertical curved surface [class F2 finish] height 3.0 m upto 6.0 m.
m2 1045.09

Providing , Preparing and Installing form work including necessary supports and removing after
110 18.02.02.a.iii 1804, 1805 completion ---For Vertical curved surface [class F2 finish] height 6.0 upto 9.0m.
m2 1318.90

Providing , Preparing and Installing form work including necessary supports and removing after
111 18.04.a 1804, 1805 completion ---For slab structure [class F2 finish] using timber planks. (Falsework not included)
m2 769.75
Providing , Preparing and Installing form work including necessary supports and removing after
112 18.05.a 1804, 1805 completion ---For slab and beam structure [class F2 finish] using timber planks. (Falsework not m2 1138.50
included)
Providing, and assembling in position falsework for the construction of RCC superstructure and
113 18.08.1.a.ii 1803 removal after completion including necessary design and drawings as per specification. m2 3719.10
A) For Slabs and Box culverts , using timber for height 2m ~ 4m
Providing, and assembling in position falsework for the construction of RCC superstructure and
114 18.08.2.a.ii 1804, 1805 removal after completion including necessary design and drawings as per specification. m2 7408.30
A) For RCC beam bridges , using timber for height 3m ~ 6m

ACTIVITY GROUP 19 : BEARINGS AND EXPANSION JOINTS (BRIDGES, SLABS ETC.)

115 19.01 1901 Providing and fixing in positions, 75 mm diameter drainage spouts with necessary hardware. nos 1244.76

Providing and installing Expansion Joints and tarfelt sheet including all necessaary axilliary and
116 19.02 1901 incidental works etc. complete as per drawing and specification.
m2 187.85

117 19.02 1901 Providing and fixing in positions,reinforced elastomeric bearing pad per drawing and instructions. nos 0.00

ACTIVITY GROUP 20 : CONCRETE FOR STRUCTURES

Providing and placing machine mixed M10/40 cement concrete for the foundation and
118 20.01.a.01 2000 footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per m3 11819.76
specification and drawing.
Providing and placing machine mixed M15/40 cement concrete for the foundation and
119 20.01.a.02 2000 footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per m3 12521.71
specification and drawing.
Providing and placing machine mixed M20/40 cement concrete for the foundation and
120 20.01.a.03 2000 footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per m3 13701.89
specification and drawing.
Providing and placing machine mixed M20/20 cement concrete for the foundation and
121 20.01.a.04 2000 footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per m3 13879.65
specification and drawing.
Providing and placing machine mixed M25/20 cement concrete for the foundation and
122 20.01.a.05 2000 footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per m3 14802.46
specification and drawing.
Providing and placing manually mixed M10/40 cement concrete for the foundation and footing etc.
123 20.01.b.01 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and m3 12532.31
drawing.
Providing and placing manually mixed M15/40 cement concrete for the foundation and footing etc.
124 20.01.b.02 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and m3 13234.26
drawing.
Providing and placing manually mixed M20/40 cement concrete for the foundation and footing etc.
125 20.01.b.03 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and m3 14558.68
drawing.
Providing and placing manually mixed M20/20 cement concrete for the foundation and footing etc.
126 20.01.b.04 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and m3 14792.43
drawing.
Providing and placing manually mixed M25/20 cement concrete for the foundation and footing etc.
127 20.01.b.05 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and m3 15793.54
drawing.
Providing and placing machine mixed M15/40 cement concrete for abutment, pier, wall, etc. including
128 20.02.a.i 2000 compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 17145.94
Providing and placing machine mixed M20/40 cement concrete for abutment, pier, wall, etc. including
129 20.02.a.iii 2000 compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 18326.12
Providing and placing machine mixed M20/20 cement concrete for abutment, pier, wall, etc. including
130 20.02.a.iii 2000 compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 18503.88
Providing and placing machine mixed M25/20 cement concrete for abutment, pier, wall, etc. including
131 20.02.a.iv 2000 compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 19444.37
Providing and placing machine mixed M20/20 cement concrete for the superstructure, deckslab,
132 20.03.a.ii 2000 girder etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification m3 16102.77
and drawing.
Providing and placing machine mixed M25/20 cement concrete for superstructure,
133 20.03.a.ii 2000 deckslab, girder, etc. including compaction, curing, testing and lead 30m. etc. all complete as m3 17230.68
per specification and drawing.
Providing and placing manually mixed non structural cement concrete [ cement (1): sand (4) :
134 20.06.b.1 2000 aggregate (8) ] including compaction, curing, testing and lead 30m. etc. all complete as per m3 11159.53
specification and drawing.
Providing and placing manually mixed non structural cement concrete [ cement (1): sand (3) :
135 20.06.b.02 2000 aggregate (6) ] including compaction, curing, testing and lead 30m. etc. all complete as per m3 12141.11
specification and drawing.
Providing and placing manually mixed non structural cement concrete [ cement (1): sand (2) :
136 20.06.b.03 2000 aggregate (4) ] including compaction, curing, testing and lead 30m. etc. all complete as per m3 14149.32
specification and drawing.
Summary (Checklist)
Specification Rate
S.N. Norms No Description Unit
Clause No. ( NRs.)
Providing and laying Reinforcement ( diameter upto 8 mm) including cutting, bending, binding, fixing
137 20.07.01 2000 in position and lead 30m. etc. all complete as per specification and drawing.
mt 132077.5

Providing and laying Reinforcement ( diameter above 8 mm and upto 16 mm) including cutting,
138 20.07.02 2000 bending, binding, fixing in position and lead 30m. etc. all complete as per specification and drawing.
mt 126603.5

Providing and laying Reinforcement ( diameter above 16 mm) including cutting, bending, binding,
139 20.07.03 2000 fixing in position and lead 30m. etc. all complete as per specification and drawing.
mt 123889.5

ACTIVITY GROUP 24 : MISCELLANEOUS STRUCTURES


Fabrication of hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms,
with binding wire 12 swg, mesh wire 10 swg and selvedged wire 8 swg , including rolling, cutting and
weaving ; assembling Gabion boxes mattresses, palcing in position including stretching, forming
140 24.02.01 2401 compartments; tying with bracing wires and tie wires; tying down the lid complete; and providing and
m3 4844.41
filling stone / boulder in gabion boxes / mattresses etc. including dressing, beding, bonding and all
transporation as per specification.

2403(5), Providing and laying grouted stone pitching in protection work with stone size not less than 0.01 m3
141 24.04 m3 9074.50
2406 -5(b) and cement : sand motar (1:3) lead 30m, lift 1.5m

142 24.09 2404,3110 Providing, laying and fixing of Geo-textile (filter fabrics), lead 30m m2 181.07

Providing and placing concrete with 60% M 15/40 concrete and 40% boulders/stones as per
143 24.14.01.a 2406; 2, 4 specification Lead 30m, lift 1.5m , using concrete mixer and vibrator. m3 9278.82

Providing and placing concrete with 60% M 15/40 concrete and 40% boulders/stones as per
144 24.14.01.b 2406; 2, 4 specification Lead 30m, lift 1.5m , without using concrete mixer and vibrator. m3 9752.51

Providing and placing plum-concrete with 70% M 15/40 concrete and 30% boulders/stones as per
145 24.14.02.a 2406; 2, 4 specification. Lead 30m, lift 1.5m using concrete mixer and vibrator. m3 9937.45

Providing and placing concrete with 70% M 15/40 concrete and 30% boulders/stones as per
146 24.14.02.b 2406; 2, 4 specification Lead 30m, lift 1.5m , without using concrete mixer and vibrator. m3 10469.09

ACTIVITY GROUP 25 : BRICKWORKS FOR STRUCTURES

Providing and laying brick masonry in manual mixed cement mortar 1:4 including preparation of
147 25.02.b 2502,3,4,5,7 mortar as per specification, lead 30 m.
m3 14100.94

Providing and applying 20mm thick cement plaster including mortar mixing, scaffolding, curing etc.
148 25.06.b 2502,2510 complete as per specification lead 30 m (manual mixing) m2 484.60

ACTIVITY GROUP 26 : MASONRY WORK FOR STRUCTURES

26.01, 6.05
149 2602, 2603 Providing, laying and levelling of dry stone masonry works in the foundation all complete. m3 3045.32
old

2602, 2603, Providing and laying dry stone masonry (coursed rubble) including dressing etc. complete as per
150 26.01 m3 4671.88
2068 specification, lead 30m.

Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(3)] including
2602, 2603,
151 26.03.a scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (machine m3 10986.42
2607 mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(4)] including
2602, 2603,
152 26.03.b scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (machine m3 10400.81
2607 mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(6)] including
2602, 2603,
153 26.03.c scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (machine m3 9517.43
2607 mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(3)] including
154 26.04.a 2607 scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (manual m3 11590.18
mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(4)] including
155 26.04.b 2607 scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (manual m3 11004.57
mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(6)] including
156 26.04.c 2607 scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (manual m3 10121.2
mixing), mortar 35%
Providing and laying Coursed rubble stone masonry in cement mortar [ cement(1) : sand(3)] including
157 26.05.a 2600 scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (machine m3 11509.41
mixing), mortar 30%
Providing and laying Coursed rubble stone masonry in cement mortar [ cement(1) : sand(4)] including
158 26.05.b 2600 scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (machine m3 10923.79
mixing), mortar 30%
Providing and laying Coursed rubble stone masonry in cement mortar [ cement(1) : sand(6)] including
159 26.05.c 2600 scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (machine m3 10040.42
mixing), mortar 30%
Providing, mixing, and Pointing cement mortar over rubble masonry works in cement mortar
2602, 2603,
160 26.07.a [ cement(1) : sand(1)] including scaffolding, curing, preparation of mortar etc. complete, masoned m2 343.85
2610 height 0-5m, lead 30m (machine mixing).
Providing, mixing, and Pointing cement mortar over rubble masonry works in cement mortar
2602, 2603,
161 26.07.b [ cement(1) : sand(2)] including scaffolding, curing, preparation of mortar etc. complete, masoned m2 306.76
2610 height 0-5m, lead 30m (machine mixing).
Providing, mixing, and Pointing cement mortar over rubble masonry works in cement mortar
2602, 2603,
162 26.07.c [ cement(1) : sand(3)] including scaffolding, curing, preparation of mortar etc. complete, masoned m2 287.99
2610 height 0-5m, lead 30m (machine mixing).

ACTIVITY GROUP 27 : REPAIR OF STRUCTURES

Removal of old paints by sand blasting, cleaning and repairing of metal surfaces for the application of
163 27.07 2713 new paints as per specification.
m2 1375.31

164 Double coat whitewash on new surface including supply of materials all complete m2 49.31

165 Single coat whitewash on old surface including supply of materials all complete m2 33.25

Single coat enamel paint/ readymade emulsion paint with primer including supply of materials all
166 complete.
m2 197.12

ACTIVITY GROUP 29 : MAINTENANCE WORKS


Summary (Checklist)
Specification Rate
S.N. Norms No Description Unit
Clause No. ( NRs.)
Restoration of rain cuts in embankment slopes including watering and compaction etc. all complete
167 29.01 2902 lead 10 m.
m3 680.49

Maintenance of earthen shoulders by making irregularities even to the required level including
168 29.02 2903 watering and compaction etc. all complete lead 10m. m2 174.59

Maintenance of gravel shoulders and gravel carriageway by repairing pot holes and making
169 29.03 2904 iregularities even to the required level including watering and compaction etc. all complete lead 10m.
m2 400.66

Repair of potholes and damaged bituminous surface including cleaning, brooming, and rolling etc all
170 29.04.b.i 2905 complete using hot premix material for 20mm shallow patching. m2 475.20

ACTIVITY GROUP 31: MISCELLANEOUS WORKS

171 31.01.a 3105 Providing and installing Railing including Railing Posts -- 100 mm dia m 2556.19

172 31.01.b 3105 Providing and installing Railing including Railing Posts -- 50 mm dia m 1071.46

173 31.01.c 3105 Providing and installing Railing including Railing Posts -- 38 mm dia m 779.24
During Site Visit Soil was found Mixed type ( mixture of Boulder
mixed Soil, Soft Soil and Soft Rock ) having Following Proportion
and which is used in the calculation of quantities

S.N Type of Soil Percentage Rate/m3 Weightage


1 Soft Soil 50 96.89 48.445
2 Boulder Mixed Soil 30 112.69 33.807
3 Soft Rock 20 245.97 49.194
Total 131.446

Unit Rate of Mixed Soil cutting pre m3 131.446


4.01) Providing and placing machine made gabion and mattresses of hexagonal mesh size 100 mm x 120 mm with mesh wire 3
mm , selvedge wire 3.9 mm and lacing wire 2.4 mm including stone placing, all complete
a) Using new stones
Specification Clause No:
Unit: m3 Norm: 24.01.02 (a) (b), 24.02.01 (a) (b), 24.02.04
2401 Amount in
Rate
S.N. Description Unit Quantity NRs Remarks
NRs. NRs.
A Labour Cost
Stretching
Unskilled Labour md 1.040 650.00 676.00
and Binding
Unskilled Labour md 2.250 650.00 1,462.50 Stone Filling
Skilled Labour md 0.750 870.00 652.50 Stone Filling

Sub Total 1 2,791.00


B Material Cost
Machine made gabion m2 16.000 258.00 4,128.00
Stone m3 3.300 1317.00 4,346.10

Sub Total 2 8,474.10


C Equipment Cost

Sub Total 3
D Other Cost
Material Testing Cost (1% of Material Cost) 84.74

Sub Total 4 84.74


E Sub Total (A+B+C+D) 11,349.84
F Contractor's Overhead and Profit Cost (15%) 1,702.48
G Total (E+F) 13,052.32 per 3 m3
4,350.77