TABLE OF CONTENTS
1. GENERAL 3
2. SCOPE 3
3. DEFINITIONS AND ABBREVIATION. 3
4. SAFETY 3
5. PREPARATION. 3
5.1. Quality Control. .................................................................................................................3
5.2. Material Control .................................................................................................................4
6. PROCEDURE 4
7. RECORD. 4
APPENDIX A: UNDERGROUND GRP PIPE INSTALLATION PROCEDURE 5
the agreed upon right of use.
1. GENERAL
- This procedure is built based on method/ procedure issued by NUOVA SGUASSERO SRL,
the Vendor of GRP piping.
2. SCOPE
- This procedure describes the general requirements for UNDERGROUND PIPES fabrication,
installation and inspection in respect with GRP materials only
- In addition to, the information contained in this procedure, SUBCONTRACTOR will carry out
fabrication/ installation work to meet the requirements of drawings, technical specifications,
standards and codes, as set out in the contract, should there be any conflict between this
procedure and contract document, the latter shall govern.
- Direct instruction of Vendor at site will be strickly following.
3. DEFINITIONS AND ABBREVIATION.
Owner: Petrovietnam Fertilizer and Chemical Corporation (PVFCCo).
Contractor: Consortium of Technip Italia S.P.A and Petrovietnam Technical
Services Corporatio
Subcontractor: Southern Petroleum Construction J.S.C (Alpha Ecc).
Vendor: Nuova Sguassero S.r.l
QA/QC: Quality Assurance / Quality Control
Fabrication team: a body, who has responsibility to fabricate and install pipe works
4. SAFETY
- Fabrication team shall ensure that all fabrication and installation activities on safe, effective
and timely operation in strictly compliance with Project HSE Plan
- Fabrication team shall work closely with HSE personnel to ensure the safe, effective
performance of the activities by all members
- To ensure a safe working environment for all personnel through the whole of the project
period including sub-contractors, equipment vendors
- All personnel working at fabrication site shall participate weekly HSE meetings and
Superintendents and/or Supervisors shall conduct tool-box meeting daily for direct
workforces to ensure safe performance for installation activities of GRPs Underground pipe
works
- All equipment, tools used for installation works shall be valid calibrated certificates in
accordance with Project safety rules and all lifting equipment with suitable color code. To
ensure equipment, tools shall be calibrated and inspected periodically in accordance with
Equipment Protection & Preservation Procedure.
5. PREPARATION.
5.1. Quality Control.
- Contractor will supervise the works executed by Subcontractor to ensure compliance with
specification requirements and the relevant codes and standards.
the agreed upon right of use.
- All procedures such as butt and strap lamination, butt and branch welding, Site Material
Management Procedure etc shall be available at fabrication area or in hand prior to
commencement of the works.
2539
Project N
00
Unit
PP
AMMONIA PLANT REVAMP PROJECT
Document Code
0
Rev.
5/5
Page
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 1 OF 18
Rev. 1
CONTENT
Page
1 HANDLING 4
2 INSPECTION 8
3 EXCAVATION 9
4 INSTALLATION 10
5 JOINTING PIPE 11
6 BACKFILL 16
7 COMPACTING 17
8 SPECIAL INDICATIONS 17
9 HYDROTEST 18
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 3 OF 18
Rev. 1
INTRODUCTION
The excellent corrosion resistance and many other benefits of GRP pipe can be realized if the
pipe is properly installed.
GRP pipe is designed considering the bedding and pipe zone backfill support that will result
from this recommended installation procedure.
These instructions are easy to follow and to monitor. A good indication of the quality of
the installation achieved is immediately verifiable by measuring the vertical diametrical
deflection of the buried pipe and by inspecting the pipe shape.
Bulges, flat areas or other abrupt changes of curvature are not permitted.
The installation procedures here outlined, when carefully followed, will help to assure a
proper, long-lasting installation.
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 4 OF 18
Rev. 1
1 HANDLING
1.1 GRP pipes are generally supplied in lengths of 12 m. Being these much lighter than
steel, cast iron or concrete, they are therefore easier to move. Any how it is advisable to
follow the handling instructions detailed below:
Lift the bar using slings of hemp, nylon or similar, with abundant section, but never
Rope
steel cables nor chain. Slings may consist of single lifting point at centerline, or in two lifting
points connected to an equalizer at a distance of 3 m from the ends.
Rope
In the second instance, the movement will be more secure with an overall time advantage
and a correct execution of the handling and installation operations.
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 5 OF 18
Rev. 1
- Ensure that the ground is flat and free from stones or other things that may cause damage by
impact during discharging:
- Pipes of small/medium diameter (up to ND 600/800) laid out in a single layer, may be laid
directly on the ground.
- Pipes of bigger diameters shall have at least 2 supports each, at a distance of approx. 3 m
from the ends: use wooden tables not less than 25 cm wide, piling in such a way as not to lay
the ends on the ground.
When pipes are delivered on site in bundles, crates or other packing, they may be stored
without unpacking.
Rubber ring gaskets should be stored in the shade in their original packaging and not under
direct sunlight.
The gaskets must be protected from exposure to greases and oils which are petroleum
derivatives, and from solvents and other deleterious substances.
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 6 OF 18
Rev. 1
1.4 TRANSPORT
If it is necessary to transport pipes at the job site, it is best to use the original packing when
loading the truck. If this material is no longer available, support all pipe sections on flat
timbers spaced with a maximum overhang of 2 m. chock the pipes to maintain stability and
separation. Insure no contact between pipes occur, so vibrations during transport will not
cause abrasion.
Maximum stack height is approx. 2 m. Strap pipe to the vehicle over the support points using
pliable straps or ropes. Never use steel cables nor chains without adeguate padding to protect
the pipe from abrasion.
Pipes may be nested (smaller diameter pipes inside of larger sizes). To reduce transportation
cost. These pipes have generally special packing and may require non-standard procedures for
unloading, handling and transporting.
Non-standard practices, if required, will be supplied prior to shipment. Regardless, the
following general procedure should always be followed:
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 7 OF 18
Rev. 1
1.5.1 Always lift the nested bundle using at least two pliable straps. Limitations, if any, for
spacing between straps and lifting locations will be specified for each project.
Insure that the lifting slings have sufficient capacity for the bundle weight.
1.5.2 Nested pipes are usually best stored in the transport packaging. Stacking of these
packages should not occur unless otherwise specified.
1.5.3 Nested pipe bundles can only be safely transported in the original transport packaging.
Special requirements, if any, for support, configuration and/or strapping to the vehicle, will be
specified for each project.
1.5.4 Package removal and denesting of the inside pipes is best accomplished at a destining
station. Typically, this consists of three or four fixed cradles to fit the outside diameter of the
largest pipe of the bundle. Inside pipes, starting with the smallest size, may be removed by
lifting slightly with an inserted padded boom to suspend the section and carefully move it out
of the bundle without touching the other pipe. When weight, length and/or equipment
limitations preclude the use of this method. The procedure for sliding the inside pipe out of
the bundle will be recommended for each project.
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 8 OF 18
Rev. 1
2. INSPECTION ON SITE
2.1 Upon arrival on site, check wether the pipes had been securely fixed on the truck. In the
event of doubt, regarding the integrity of the packing or of the fixing, carefully inspect the bar
along the entire length and particularly at the ends, in order to identify possible damages
caused by impact, such as faults or cracking of the heads or areas of delamination (pale or mat
stains) on the pipe walls. If in doubt, immediately inform the carrier, the supplier's forwarding
department and put the bars aside.
2.2 If during unloading or handling on site a bar should fall down or be subjected to impact,
inspect it as detailed in 2.1; in case of doubt, set the pipe aside: The eventual repair may be
made on site by supplier's staff.
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 9 OF 18
Rev. 1
3. EXCAVATION
3.2 SUB-TRENCH
In case of not stable soils, the trench excavation should be deeper; a bed of gravel to support
the pipe should be provided.
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 10 OF 18
Rev. 1
4. INSTALLATION
Once excavation completed, the pipe bed shall consist of approx. 20 cm sand or fine granular
material to be brought to grade along the entire length of the section to be installed. At each
joint location, the bed must be slightly excavated to accommodate the larger outside diameter
of the bell (Bell&Spigot joint). The pipe section must receive continuous support and not rest
on the bell. Alignment and levelling of the pipes must be carried out so that, during the
nesting of bell and spigot the misalignment is not grater than 0.5.
If due to unstable soils sinking of foundations, anchor blocks or manholes are impossible,
flexible joints should be provided for a distance not exceeding 2 pipe diameters.
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 11 OF 18
Rev. 1
5. JOINTING
5.1.1 Sling pipe to be jointed at its point of balance using a textile band sling at least 100 mm
wide. Thoroughly clean interior of bell of installed pipe and exterior of spigot of pipe to be
jointed.
5.1.4 Clean gasket with dry cloth checking that it is not damaged (no pits, scratches, cuts are
permitted as leakages may occur), then lubricate.
5.1.5 Put the gaskets into the proper grooves and smear a thin film of lubricant over them.
5.1.7 Position pipe to be jointed just clear from trench bottom and enter spigot into bell until
contact is made.
5.1.8 Push spigot into bell using a tirfor or other equipment that will not misalign the pipes
during nesting.
C TIRFOR
one on each side
E nylon or rope
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 12 OF 18
Rev. 1
5.1.9 Medium or big diameter pipes can be jointed using backhoe or buldozzer but attention
have to be payd in order to maintain alignment and not to damage the bell.
C backhoe or buldozzer
D plywood
5.1.10 Perform the test of the O-Ring tightness (nipple test), as indicated in chapter 9.
5.1.11 Once the O-Ring tightness test has been successfully performed, insert the locking key
to assure the joint.
Consider that, as indicated in the document no. PD-01-DS-005, the locking key is formed
with no. 2 nylon bars from ND 900 till ND 1600, and no. 3 nylon bars for ND > 1600.
In this case the following procedure has to be attended for the each bars introduction:
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 13 OF 18
Rev. 1
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 14 OF 18
Rev. 1
5.2.2 Ensure the gasket is clean and undamaged. Do not use defective gaskets.
5.2.3 Position gasket on flange face and secure in position with small strips of adhesive tape,
if not full face.
5.2.5 Insert bolts, washers and nuts. All hardware must be clean and lubricated to avoid
incorrect tightening. Washers must be used on all GRP flanges.
5.2.6 Using a torque wrench, tighten all bolts to half the torque given in our specs following
standard flange bolt tightening sequences.
5.2.7 Repeat tightening, raising the bolt torque to the value given in our specs.
Butt & Strap weldings, conical adhesive joints and couplings can be use for pipe to pipe and
pipe to fitting connection. Ask our technical service dept. for complete documentation.
When two or more pipes are installed parallel in the same trench, spacing between pipes
shall be as indicated below.
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 15 OF 18
Rev. 1
bed - min. 15 cm
5.4.2 CROSS-OVERS
When two pipes intersect, so that one crosses over the other, vertical spacing between
pipes and installation for the bottom pipe shall be as indicated below.
Gravel
or
Sand
BED
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 16 OF 18
Rev. 1
6. BACKFILL
This operation shall be carried out immediately after pipe laying and hydrotest; if impossible,
provide for an accurate re-checking of the alignment before backfill. The embedment material
should be of the same type as the trenchbed for at least 20 cm. The compactation of the
embedment shall be 90% Proctor Standard. Native backfill material may be used to backfill
the remaining trench. Material containing stones or other object larger than 50 mm, frozen
soil, debris or other foreign materials shall not be allowed within 30 cm around the pipe.
During backfill protect the pipe against falling stones and blows from the compactor. Proceed
as indicated below.
Backfill
DN / 2 max 300 mm
Bed: min.15 cm
Foundation: min.15 cm
(if required)
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 17 OF 18
Rev. 1
7. COMPACTING
If the embedment material does not permit to get the degree of compacting required, suitable
equipment like vibrators with beating plate shall be used.
The embedment shall be compacted normally in layers of 20/40 cm thickness in relation to the
pipe diameter. In order to ensure conformity with the requirements of the project, periodic
controls shall be carried out of the compacting quality by means of measuring of the
ovalization of the installed pipe.
If reduction of the vertical diameter should be higher than 3% on the short term, the
compacting shall have to be increased.
CORRECT
C Correct bedding:
pipe frimly supported
WRONG
D Poor bedding:
pipe badly supported
8. SPECIAL INDICATIONS
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot
Doc. PD-01-SP-47
DATE 18-07-2002
SHEET 18 OF 18
Rev. 1
9. HYDROTEST
9.1.1 Fix drilled bolt D on the bell by connecting nut C with gasket B keeping bolt D firm
with an Allen wrench and fastening C with another wrench. The exceeding part of the bolt D
has to be cut away.
9.1.2Connect pump to the nut C with two hexagonal wrenches. Tightness shall be obtained by
teflon tape.
9.2 Hydrotest
9.2.1 The test consists in pumping water or air, better water, into the gap between the two O-
rings through the bolt D up to the required test pressure. Wait for some minute. If pressure
remains constant, tightness is ok.
9.2.2 Disassemble the connection to the pump E and close the nipple with the cap A. (see fig.
G).
If hydrotest fails, (pressure decreases) it means that joint has not been correctly assembled.
Diassemble the joint and re-assemble it with new O-rings as per para 5.1
Mod. DC2/GB - Rev. 0 (12/95) This document is the property of N. SGUASSERO S.p.A. who will safeguard its rights according to the civil and penal provisions of the law.
C:\PC-Luca\Documenti\Specifiche_SP\SpecificaPosa\PD01SP47E_R0.dot