Project Name : Shared RF antenna System

Apr
Time
W3
NO Description Percent (%)
21 23 24 25
Day Jumat Sabtu Minggu Senin
I Jasa
1 Survey 2 2.00% 1.00% 1.00%
2 Planning 3 10.00% 3.33% 3.33%
3 Implementation 8 35.00%
4 VSWR,DTF,BER. 2 5.00%
5 Comissioning 1 3.00%
6 SSV 2 5.00%
7 Optimization 7 5.00%
8 Acceptance 5 10.00%

II Material
1 Mounting 1 1.00%
2 Rack 2 2.00%
3 Feeder 3 5.00%
4 Connector 1 2.00%
5 Antenna 1 7.00%
6 Diplexer 1 3.00%
7 Combiner 1 5.00%
100.00%
Planing Progress
Value Cummulative 1% 2% 5% 9%
Actual Progress 1% 2% 5% 9%
2016
Apr
W4 W1
26 27 28 29 30 1 2 3 4 5
Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis

3.33%
4.38% 4.38% 4.38% 4.38% 4.38% 4.38% 4.38% 4.38%
2.50%

1.00%
1.00% 1.00%
1.67% 1.67% 1.67%
2.00%
7.00%
3.00%
5.00%

13% 18% 24% 30% 36% 42% 63% 68% 72% 75%
13% 18% 24% 30% 36% 42% 63% 68% 72% 75%
2016
May 2016
W2
6 7 8 9 10 11 12 13 14 15
Jumat Sabtu Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu

2.50%
3.00%
0.025 0.025
0.71% 0.71% 0.71% 0.71% 0.71% 0.71%

77% 80% 83% 85% 86% 86% 87% 88% 89% 89%
77% 80% 83% 85% 86% 86% 87% 88% 89% 89%
Total Progress

W3
16 17 18 19 20 21
Senin Selasa Rabu Kamis Jumat Sabtu

0.71%
0.02 2.00% 2.00% 0.02 0.02

90% 92% 94% 96% 98% 100%


90% 92% 94% 96% 98% 100% 100%
Project Name : MORAN & MOCN Excercise

Apr
Time
NO Description
Percent W3 W4
(%) 21 23 24 25 26
Day Jumat Sabtu Minggu Senin Selasa
I Jasa
1 1 0.70% 0.70%
2 4 7.20% 1.80% 1.80% 1.80% 1.80%
3 6 27.00%
4 3 19.80%
5 2 2.80%
6 5 4.30%
7 0.60%

II Material
1 2 14.30%
2 1 5.80%
3 4 10.80%
4 1 1.60%
5 1 3.50%

100.00%
Planing Progress 0.70% 1.80% 1.80% 1.80% 1.80%
Value Cpumulative 1% 3% 4% 6% 8%
Actual Progress 1% 3% 4% 6% 8%
2016
Apr
W4 W1
27 28 29 30 1 2 3 4 5 6
Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Jumat

4.50% 4.50% 4.50% 4.50% 4.50% 4.50%


6.60% 6.60% 6.60%
1.40%

7.10%

4.50% 4.50% 4.50% 4.50% 4.50% 4.50% 6.60% 6.60% 6.60% 8.60%
12% 17% 21% 26% 30% 35% 42% 48% 55% 63%
12% 17% 21% 26% 30% 35% 42% 48% 55% 63%
2016
May 2016
W2 W3
7 8 9 10 11 12 13 14 15 16
Sabtu Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin

1.40%
0.90% 0.90% 0.90% 0.90%

7.10%
5.80%
2.70% 2.70% 2.70% 2.70%
1.60%

8.60% 5.80% 2.70% 2.70% 2.70% 2.70% 0.90% 0.90% 0.90% 2.50%
72% 78% 80% 83% 86% 89% 89% 90% 91% 94%
72% 78% 80% 83% 86% 89%
Total Progress

W3
17 18 19 20 21
Selasa Rabu Kamis Jumat Sabtu

0.90%
0.30% 0.30%

3.50%

4.30% 0.30% 1.00% 0.60% 0.10%


98% 98% 99% 100% 100%

89%
Project Name : Enhancement Phase 1
SUBRING Cipinang Muara - Pul

Apr
Time
NO Description
Percent W3 W4
(%) 21 23 24 25 26
Day Jumat Sabtu Minggu Senin Selasa
I Jasa
1 Survey 1 0.70% 0.70%
2 Permit 4 7.20% 1.80% 1.80% 1.80% 1.80%
3 Trenching 6 27.00%
4 Borring 3 19.80%
5 Roding HD 2 2.80%
6 Pulling Kabe 5 4.30%
7 Splicing 0.60%
8 Terminasi 2 1.30%
9 OTDR 3 0.10%

II Material
1 HDPE 2 14.30%
2 Perbaikan 1 5.80%
3 Handhole 4 10.80%
4 Closure 1 1.60%
5 OTB 1 3.50%

100.00%
Planing Progress 0.70% 1.80% 1.80% 1.80% 1.80%
Value Cpumulative 1% 3% 4% 6% 8%
Actual Progress 1% 3% 4% 6% 8%
2016
Apr
W4 W1
27 28 29 30 1 2 3 4 5 6
Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Jumat

4.50% 4.50% 4.50% 4.50% 4.50% 4.50%


6.60% 6.60% 6.60%
1.40%

7.10%

4.50% 4.50% 4.50% 4.50% 4.50% 4.50% 6.60% 6.60% 6.60% 8.60%
12% 17% 21% 26% 30% 35% 42% 48% 55% 63%
12% 17% 21% 26% 30% 35% 42% 48% 55% 63%
2016
May 2016
W2 W3
7 8 9 10 11 12 13 14 15 16
Sabtu Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin

1.40%
0.90% 0.90% 0.90% 0.90%

7.10%
5.80%
2.70% 2.70% 2.70% 2.70%
1.60%

8.60% 5.80% 2.70% 2.70% 2.70% 2.70% 0.90% 0.90% 0.90% 2.50%
72% 78% 80% 83% 86% 89% 89% 90% 91% 94%
72% 78% 80% 83% 86% 89%
Total Progress

W3
17 18 19 20 21
Selasa Rabu Kamis Jumat Sabtu

0.90%
0.30% 0.30%
0.60% 0.60%
0.10%

3.50%

4.30% 0.30% 1.00% 0.60% 0.10%


98% 98% 99% 100% 100%

89%