Sei sulla pagina 1di 9

Covalence

Raychem
Corrosion Protection Group

PROCEDURE
FOR
HTLP-80 HEAT SHRINK SLEEVES
WITH S1301M EPOXY OVER
3LPE COATED PIPES
Raychem RPG Ltd

SCOPE

1. GENERAL

2. MATERIAL AND EQUIPMENT

3. BEVELING OF LINE COATING EDGES

4. SURFACE PREPARATION

5. CUTTING OF SLEEVE CORNERS

6. EPOXY PRIMER MIXING

7. PREHEAT OF GIRTH WELD AREA

8. PRIMING OF GIRTH WELD AREA

9. SLEEVE INSTALLATION & POST HEATING

10. VISUAL INSPECTION CRITERIA

11. HOLIDAY INSPECTION TEST

12. ADHESION PEEL STRENGHT TEST

Procedure: HTLP-80 Heat Shrink Sleeves with S1301M Epoxy over 3LPE Coated Pipes
Sheet: 2 of 9
Raychem RPG Ltd

1. GENERAL

This installation procedure details the application of Raychem HTLP-80 Heat


shrink sleeve system. The HTLP-80 heat shrink sleeve system comprises of
HTLP-80 sleeve applied over S1301M epoxy.

1A. Reference: EN 12068, DIN 30672.

2. MATERIAL AND EQUIPMENT

1. HTLP80 sleeve with closure patch suitable for required dia pipe.
2. S1301M Epoxy Part A.
3. S1301M Epoxy Part B
4. Applicator Pad with Mixing Cup & Stick.
5. Gas torch with LPG Cylinder
6. Straight Rollers
7. Wet Film Gauge
8. Pyrometer with flat surface probe
9. Peel Strength Gauge
10. Holiday detector
11. Hygro Meter

3. BEVELLING OF POLYETHYLENE COATING EDGES

If not factory beveled, bevel the line coating edges on both sides of the
weld bead to approximately 15.

The ends of existing mill coating shall be inspected. Unbounded portions


of the coating shall be removed and then suitably trimmed. Portions
where parent coating is removed shall be thoroughly beveled, and
cleaned as specified.

Procedure: HTLP-80 Heat Shrink Sleeves with S1301M Epoxy over 3LPE Coated Pipes
Sheet: 3 of 9
Raychem RPG Ltd

4. SURFACE PREPARATION

o Clean exposed steel area and adjacent pipe coating (100mm before
shrinking) that will be covered by the HTLP 80 sleeve from all dust,
dirt, moisture, grease or other contaminations.
o If Humidity is greater than 85 % and pipe temperature is below or
equal to 30c compared to dew point than coating should be stopped.
Also when design pipe Temperature goes below 10 0c, it shall be
stopped.
o If necessary, use a non-contaminating solvent such as Xylene.
o Using copper slag clean blast only the bare steel part of the girth
weld area to SA 2 and a roughness profile (anchor pattern)
between 50 to 70 microns.
o Sweep blast adjacent PE line coating up to 100 mm only to create a
rough surface.
o Abrade the R -95 Coated pipe with Emery Paper (50 mesh size) to
create rough surface and adjacent PE coating upto 100mm on either
side.

Remove carefully all remaining abrasive dust and loose particles after
blast cleaning.

5. CUTTING OF SLEEVE CORNERS

The corners of the underlying end should be cut by 15 x 50 mm, prior


to wrapping sleeve around the joint.
15 mm

Underlaying end 50 mm

6. EPOXY PRIMER MIXING

The S1301M epoxy has to be applied only on the steel surface. (THE
EPOXY HAS NOT TO BE APPLIED ON THE PE)

Mix Part A and Part B in a cup. The mixing has to be done thoroughly
for 30 -60 seconds till homogeneous mass is obtained i.e. the
hardener shall mix completely with resin. The color of hardener shall
not visible or float over the resin.

Procedure: HTLP-80 Heat Shrink Sleeves with S1301M Epoxy over 3LPE Coated Pipes
Sheet: 4 of 9
Raychem RPG Ltd

7. PREHEATING OF FIELD JOINT

Make sure that all necessary items are in close proximity before you
start.
Proper arrangements are to be made during windy and rain
conditions to protect the field joint surface from moisture and dirt/
dust.
Preheat the joint area with a slow flame moving in a paintbrush
motion.
Preheat the steel surface to between 70C to 80C, & the
adjacent PE line coating to between 60C to 70. This is very
important to bond properly to the PE line coating.
Check the temperatures using a digital pyrometer with a flat
temperature sensor.
To avoid excessively fast curing of epoxy do not preheat the steel
higher than 85C.
The sleeve needs to be shrunk while the epoxy is still wet.

8. PRIMING OF GIRTH WELD AREA

Apply the S1301M epoxy on the steel surface and include a couple of
mm of chamfered polyethylene edges, in order to cover all bare metal.
In order to achieve the required wet film thickness, apply the S1301M
epoxy primer over the weld seams first.
Then apply the S1301M over the main steel body.
S1301M epoxy should not be applied on the adjacent PE line coating
The S1301M epoxy applied to the steel should be a wet.
For field joint coating applications of S1301M Brush Grade, disposable
tools such as applicator pads should be used to apply the coating.

9. SLEEVE INSTALLATION

The following steps are to be followed while applying HTLP -80


sleeves over PE.

The shrink sleeve shall be applied immediately after the S1301M


application without waiting.
Wrap the HTLP 80 sleeve centrally around the girth weld.

Procedure: HTLP-80 Heat Shrink Sleeves with S1301M Epoxy over 3LPE Coated Pipes
Sheet: 5 of 9
Raychem RPG Ltd

Position the leading edge of the sleeve onto the pipe between the 10
and 2 O'clock position.
Preheat the underside of the leading edge of the sleeve with a LPG /
Propane flame, and press firmly down onto the top of the joint area.
The sleeve should be wrapped loosely around the joint leaving a small
gap of 30-40 mm between the bottom of the joint and the sleeve as
indicated below. Sleeve overlap onto itself should be minimum 50 mm.
Apply closure patch centrally over sleeve overlap area.
While heating press down and smooth the closure patch with a gloved
hand to ensure good bonding and eliminate air entrapment.
Using LPG gas torches adjust flame length as required.
Begin at one end of the sleeve and heat circumferentially all around the
pipe until sleeve conforms to the pipe; then continue to the other end of
the sleeve with a constant paint brush motion until the sleeve is fully
recovered. Alternately, shrinking can be started from the middle and
shrunk first towards one end and then towards the other, from the
middle.
The embossed pattern on the sleeve ( dimpled PCI Permanent
Change Indicator) of the backing should disappear and a smooth
backing profile should be seen as illustrated below :

Dimples still visible = more heat Smooth profile = O.K

Till 4 dia of pipe one insulator for heating the sleeve is recommended.
Two insulators are required for pipe sizes > 4 dia.

Procedure: HTLP-80 Heat Shrink Sleeves with S1301M Epoxy over 3LPE Coated Pipes
Sheet: 6 of 9
Raychem RPG Ltd

9.1. SLEEVE POSTHEATING

Immediately after the sleeve has been fully shrunk, post heat the
sleeve area overlapping the polyethylene line coating well with the LPG
torch until it passes the finger test as indicated below.
Adhesive not bonded yet = More heat Adhesive does bond = OK

After post heating and while the adhesive is still liquid, roll the entire
sleeve with a straight hand roller to remove any air voids if necessary.

Start rolling from the weld bead towards the ends, forcing possible air
enclosures out of the sleeve.

Special attention should be given circumferential weld beads, and also


to transition to the mill coating and the patch area.

When the adhesive is too viscous and rolling difficult, reheat the area
again.

Rolling does not affect the properties of the sleeve; it only helps to work
out possible entrapped air.

10. VISUAL INSPECTION CRITERIA

The inspection of the joint shall be done after the cool down of the sleeve
and the substrate to ambient temperature. The sleeve shall be visually
inspected for the following points.
The weld bead profile contour shall be visible through the sleeve.
The ends of the sleeve shall be firmly bonded to the mill coating.
There shall be no upstanding edges.

Procedure: HTLP-80 Heat Shrink Sleeves with S1301M Epoxy over 3LPE Coated Pipes
Sheet: 7 of 9
Raychem RPG Ltd

Adhesive flow shall be evident at both edges of sleeve around entire


circumference of pipe / sleeve.
The sleeve shall be smooth; there will be no dimples, cold spots,
bubbles, punctures, burn holes or any signs of holidays.
There shall be no signs of entrapment of foreign materials in the
underlying adhesive.
Sleeve shall overlap minimum 50mm onto the adjacent PE line coating
on each side of joint.

11. HOLIDAY INSPECTION TEST

After complete cooling down, each sleeve shall pass holiday detection test.
Holiday inspection shall be done using a voltage setting can go upto 25kv.
The holiday test shall be carried out after 4 hrs.

12. ADHESION PEEL STRENGHT TEST

One out of every 50 sleeves, or alternatively one out of each days


production (whichever is lower) shall be subjected to a manual peel
test. The peel test shall be done after 24 hrs.

Peel strength inspection shall be done at a sleeve temperature of around


23C or 60C in order to compare with Owners specification; both the
substrate and the sleeve shall be at this temperature.

Strips of 25 mm x 200 mm shall be cut perpendicular to the pipe axis,


either at 9 or 3 o'clock position as per EN12068, in the area between
the circumferential weld bead and the line coating and on the line
coating.

Manually remove the first 20-30 mm of the leading edge of the strip by
using a screwdriver or chisel, make sure that the initial adhesive bond
line cut is essentially centered within the adhesive layer or towards the
epoxy primer layer.

Attach the peel gauge to the leading edge of the test strip and fasten
clamp.

Holding the test gauge with both hands exert a steady force with a
pulling speed of approximately 100 mm/min, and an angle of 90 to the
circumference of the pipe. Note the pull value on the Peel Test Gauge.

Procedure: HTLP-80 Heat Shrink Sleeves with S1301M Epoxy over 3LPE Coated Pipes
Sheet: 8 of 9
Raychem RPG Ltd

The peel strength of the coating in Newtons / cm is the pull value in Kg


x 9.81/ 2.5.

The peel strength at 23C shall exceed 35N/cm and at 60C 5 N/cm

For peel test conducted at different temperature between these two


temperature values, the peel strength recorded will exceed the values
given in the following table.

PEEL VALUE Vs. TEMPERATURE CHART

Temperature in Peel Value Peel value in ( N/cm)


(C) in Kg
23 9.0 35
30 7.75 30
35 6.5 25
40 5.0 20
45 3.8 15
50 2.5 10
55 2.0 7.5
60 1 5

13. SLEEVE REPAIR PROCEDURE

Sleeves damaged during Adhesion (Peel) Testing shall be repaired as


follows:

Cut repair patch from a roll of PERP80, approximately 50mm larger in


each direction than the area to be repaired.
Lightly abrade the area all around the damage with a 60 mesh Emery
paper.
Abrade area extending at least 25mm beyond the area to be covered by
the PERP repair patch.
Preheat the damaged area with a propane torch with a gentle flame.
If damage is deep down to the steel, the void area should be filled with
S1137 PERP Filler Mastic.
Preheat the repair patch with a LPG gas torch on the adhesive side till
soft and shiny.
While adhesive is still soft, apply the patch centrally over the damaged
area.
Carefully heat and roll the PERP80 patch with a roller until the surface
becomes smooth, and the adhesive is visible all around the PERP80.

Procedure: HTLP-80 Heat Shrink Sleeves with S1301M Epoxy over 3LPE Coated Pipes
Sheet: 9 of 9

Potrebbero piacerti anche