SUMMARY SHEET

BOQ - SUMMARY
No. Description Amount
1 SITE MANAGEMENT 220,000.00
Site management cost for concrete works 120,000.00
Site management cost for Finishing works 100,000.00
2 GROUND WORKS 193,450.00
Ground works 193,450.00
3 FOUNDATION WORK 677,572.50
Concrete Works 677,572.50
4 GROUND FLOOR 782,420.50
Concrete Works 332,155.00
Masonry , plastering & finishing work 450,265.50
5 FIRST FLOOR 957,730.50
Concrete Works 341,662.50
Masonry , plastering & finishing work 616,068.00
6 SECOND FLOOR 919,820.50
Concrete Works 324,135.00
Masonry , plastering & finishing work 595,685.50
7 THIRD FLOOR 919,820.50
Concrete Works 324,135.00
Masonry , plastering & finishing work 595,685.50
8 FOURTH FLOOR 919,820.50
Concrete Works 324,135.00
Masonry , plastering & finishing work 595,685.50
9 MISCELLANEOUS WORK 275,000.00 275,000.00
TOTAL FOR CONCRETE 2,637,245.00
TOTAL FOR MASONRY, PLASTERING & FINISHING 2,953,390.00
TOTAL FOR MISCELLANEOUS WORK 275,000.00

SUB TOTAL 5,865,635.00

6% OF G.S.T 351,938.10

GRAND TOTAL 6,217,573.10

DURATION
Building completion

Page 1