+ Percent Complete Type defines the actual progress of an
activity. The option has three types — Duration, Physical, and
Units. Under the fixed price type contract, Physical is
recommended.
HOW DO P6 USERS SELECT DURATION TYPES?
Duration type determines the relations between remaining duration, units
assigned to activity, and remaining units per time as follows:
+ Fixed Units/Time — This is used if the activity has fixed
productivity output per time period. When the duration of an
activity with this type increases, the amount of budgeted labour
units also increases while resource units per time remain
constant.
+ Fixed Units — This is used when the amount of the units is
fixed. Decreased units per time causes the activity duration to
increase. When a user updates the duration or units per time, the
units remain constant.
+ Fixed Duration and Units/Time — This is used when the
duration and resource performance have constraints.
+ Fixed Duration & Units — This is used when the duration and
the amount of the resources have constraints.
In order to choose the appropriate duration type in accordance with
schedule management tactics, schedulers must first understand following
formula:
Ore aa Ca me
Seu on ee Red
quantity of resources (not the quantity of deliverables).
In the implementation phase:
+ When duration is shortened, performance (Units/Time) should
increase in order to complete the planned quantities (Units) on
time [1].
+ When performance decreases, duration will increase [2].
+ When the quantity decreases, duration will decrease because a
client will probably require to complete the tasks earlier [3].On the other hand:
+ When duration increases, performance will decrease [4].
+ When performance increases, duration will decrease [5].
+ When the quantity increases, performance should increase
because a client generally will require to complete the tasks on
time by increasing performance [6].
In the perspective of mentioned above, Fixed Units seems more desirable.
Figure 35 demonstrates the correlation between duration, performance
(units/time), and quantity (units). The basis activity is A0000 (Original)
with 12 days, 32 units/time, and 384 hours (units).
Figure 35 — Changes according to duration types
ae iat
i
i
However, in terms of schedule management, Fixed Units is not a good
choice because:
+ Doubled Units/Time does not always mean double performance
and schedulers do not care changes of Units/Time but those of
durations or units.
+ Durations or units should not be changed unexpectedly because
successor activity owners can hardly follow up predecessor
activities’ change. The duration of the activity with Fixed
Duration & Units type only will not change when units change,
and vice versa.To conclude, Fixed duration & units is recommended in the
implementation phase, and is commonly used in managing schedules.
HOW DO P6 USERS CHOOSE PERCENT COMPLETE
TYPES?
Percent Complete is an estimate of the amount of work that has been
completed on an activity. In Primavera P6, each activity must have one of
the following Percent Complete types:
+ Duration — Used when progress for the activity can best be
reported based on original planned work days and scheduled
work days remaining. In other words, if an activity had an
original duration of 10 working days, and it is estimated that
there are four work days remaining, the activity is estimated to
be 60 % complete. This is computed as:
Creu headed olen) Eker}
Pee Me neues nna Tea
+ Physical — Used for activities whose progress can be assessed
most accurately based on the complete of deliverables. This is
calculated as:
+ Units — Used when actual work effort accomplished and actual
work effort remaining can be used to accurately represent
progress for the activity. For example, if an activity was allotted
100 hours of work and the contractor has spent 30 hours, the
activity is estimated at 30 % complete. This is computed as:(ire Cho Onno nr tna)
PO ee tr U enna
Cee ea aa nes at
Each activity must have one of the Percent Complete types in accordance
with its task types. So, what type of Percent Complete should be assigned
to each activity? To answer the question, it is necessary to consider the
client’s point of view. Duration and units are not usually important for
clients because:
* Duration is not what the client wants to get, although Duration
can be an element of the client’s requirements.
* Units are the quantity of resources that a contractor will spend.
On the other hand, there are some contract types that require
monitoring units to estimate payment.
“Physical” in Primavera P6 represents deliverable for which the client has
made contract and the client will pay in accordance with complete of
deliverables. Progress data of “Physical” indicates EV in EVM in case of
that Physical is selected in Activity complete option. Figure 36 illustrates
the relations of progress data and deliverables. As previously mentioned,
what client wants to get is the information about completed quantities
(completed deliverables) on time and it will be indicated by means of
EVM ~ EV and PV. PV is calculated from schedule (actually, activities
loaded with resources) and EV comes directly from Activity
that is indicated from one of Physical, Units, and Duration. For instance,
if an activity has Physical for its Percent Complete type, value of Physical
will be that of Activity complete for the activity. When schedule is
updated, values of completed deliverables, spent units, and elapsed time
will be progress of Physical, Units, and Duration respectively. In
conclusion, “Physical” of Percent Complete is frequently recommended
in construction projects.