DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
1 27.1 Mobilization for test boring or observation well: Transportation
of materials, equipments, tools and plants and boring rig to work
site. Construction of derrick and dismantling the same. Cleaning
the site after completion of the work accepted by the Engineer.

1.00 set 7,534.00 7,534.00


2 Boring by using 100 mm dia cutter and 40 mm dia heavy type
G.I pipe having wall thickness 2.9 mm, outside diameter min
47.8 mm, weight 3.517 kg/m, capability to withstand 50 kg/cm2
and other equipments capable of drilling up to a depth 500 meter
by water jet system through all sorts of strata. Protection of
caving by supplying necessary casing pipe. Collection of soil
samples at every 3 meter interval and at every change of strata
and preserve them in a controlled environment for analysis and
laboratory test. Finally withdrawal of boring and casing pipes etc.
complete and accepted by the Engineer.

i) For borehole # 1
27.2.1 a) From 0.0 m to 50 m = 50 m 50.00 rm. 154.00 7,700.00
27.2.2 b) From 50 m to100 m = 50 m 50.00 rm. 177.00 8,850.00
27.2.3 c) From 100 m to 152 m = 52 m 52.00 rm. 203.00 10,556.00
27.2.4 d) From 152 m to 200 m = 48 m 48.00 rm. 234.00 11,232.00
ii) For borehole # 2( If necessary)
a) From 0.0 m to 50 m = 50 m 50.00 rm. 154.00 7,700.00
b) From 50 m to100 m = 50 m 50.00 rm. 177.00 8,850.00
c) From 100 m to 152 m = 52 m 52.00 rm. 203.00 10,556.00
d) From 152 m to 200 m = 48 m 48.00 rm. 234.00 11,232.00
3 Installation of tube-well fixture for observation well:
Supplying and lowering of 40/38 mm inside dia best quality
uPVC pressure tube well pipe having specific gravity 1.35 - 1.45,
wall thickness 2.5 mm - 3.0 mm, capability to withstand a
minimum hydrostatic pressure of 170 psi for 1 hr. fitted and fixed
in position with all accessories, uPVC sand trap of length 3.00
with uPVC strainer of desired slot installing in or at mid depth of
the most suitable water bearing strata. 38 mm dia G.I. pipe of
best quality of length 1.52 m with M.S. welded flat bar on each
side to prevent from rotation up to desired depth, fitting fixing the
best quality No. 6 C.I. head hand-pump etc including the cost of
solvent cement, socket adaptor, filling medium sand up to 18.00
m above strainer and the remaining portion with available soil
from boring etc. complete as per standard specification and
accepted by the Engineer.

a) For borehole # 1
27.3.3 (i) 38/40 mm dia water grade uPVC pipe having thickness 2.5-
3.00 mm. For bore hole # 1 150.00 rm. 141.00 21,150.00
27.3.4 (ii) 38/40 mm dia water grade uPVC strainer having wall
thickness 2.5-3.00 mm For bore hole # 1 50.00 rm. 175.00 8,750.00

file:///conversion/tmp/scratch/365023380.xls Page No-1


Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
27.31.1 iii) Fitting, fixing No.6 Hand pump set including all necessary
accessories etc. complete and accepted by the engineer.
1.00 each 2,738.00 2,738.00
27.3.2 iv) 38/40 mm dia heavy type GI pipe conforming to standerd BS-
1387 &BDS-1031 having chemical composition (in %) carbon
0.17-0.25, Manganese 0.95-1.2, sulphur 0.060 max,
Phosphorous 0.060 max, tensile properties : minimum Yield
strengh 188 Mpa, Minimum Tensile Strengh 313 Mpa and
marking for a) Manufactuer b) Material c) Wall thickness
d)Nominal outside dia e)Intended use etc. on the body of pipe
having wall thckness 2.90mm, weight 3.517 kg/m capability to
withstand 50 kg/sqcm hydraulic pressure.
1.52 rm. 680.00 1,033.60
27.3.5 v) 38/40 mm dia uPVC socket adapter 1.00 each 87.00 87.00
27.3.6 vi) Best qualily 38mm dia uPVC cap 1.00 each 66.00 66.00
b) For borehole # 2 ( If necessary)
27.3.4 (i) 38/40 mm dia water grade uPVC pipe having wall thickness
2.5-3.00 mm. For bore hole # 2. 150.00 rm. 161.00 24,150.00
27.3.5 (ii) 38/40 mm dia water grade uPVC strainer having wall
thickness 2.5-3.00 mm For bore hole # 2. 50.00 rm. 195.00 9,750.00
27.3.1 iii) Fitting, fixing No.6 Hand pump set including all necessaries
etc. complete and accepted by the engineer.For bore hole # 2. 1.00 each 2,938.00 2,938.00
27.3.2 iv) 38/40 mm dia heavy type GI pipe conforming to standerd BS-
1387 & BDS-1031 having chemical composition (in %) carbon
0.17-0.25, Manganese 0.95-1.20, sulphur 0.060 max,
Phosphorous 0.060 max, tensile properties : minimum Yield
strengh 188 Mpa, Minimum Tensile Strengh 313 Mpa and
marking for a) Manufactuer b) Material c) Wall thickness
d)Nominal outside dia e)Intended use etc. on the body of pipe
having wall thckness 2.90mm, weight 3.517 kg/m capability to
withstand 50 kg/sqcm hydraulic pressure.

1.52 rm. 680.00 1,033.60


27.3.5 v) 38/40 mm dia uPVC socket adapter. For bore hole # 2.
1.00 each 87.00 87.00
27.3.6 vi) Best qualily 38mm dia uPVC cap. For bore hole # 2. 1.00 each 66.00 66.00
4 27.3.9 Filling the top 0.60 m of the borehole around the top pipe with
sanitary seal of concrete of proportion 1:2:4 as per design
accepted by the engineer. 1.00 each 51.00 51.00
5 Complete development of the tube well to obtain sand and
turbidity free water at a satisfactory yield confirmed by tests as
per specification and accepted by the Engineer. Water sample
must be taken from 3 separate aquifers from three tube-well.
a) For borehole # 1 well beyond 200m depth
27.4.2.1 (i) Well up to 200meter depth, For 1 No. test tube-well. 200.00 rm. 35.57 7,114.00
27.4.2.2 (ii) Well beyond 200 meter depth, For 2 No. test tube-well. 30.00 rm. 53.35 1,600.50
b) For borehole # 2( If necessary)well beyond 200m depth

27.2.1 (i) Well up to 200 meter depth, For 2 No. test tube-well. 200.00 rm. 55.57 11,114.00
27.2.2 (ii) Well beyond 200 meter depth, For 1 No. test tube-well. 30.00 rm. 73.35 2,200.50

file:///conversion/tmp/scratch/365023380.xls Page No-2


Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
6 27.5 Furnishing design of a production well by testing of water and
soil samples from a test bores up to 350m depth collecting
samples of water from the best suitable aquifer, filling in
sterilized air-tight glass bottles having no air space inside;
collecting soil (sand, solids etc) at 3 m interval and at each
change of soil strata from the bores, arranging them in the cell of
a box in an orderly manner. carrying out test of water for (1) pH,
(2) CO2 (3) Chloride, (4) Fluoride, (5) Iron, (6) Manganese, (7)
Nitrate-Nitrogen, (8)Total alkalinity, (9) Total hardness, (10)
Arsenic, (11) Turbidity, followed by test reports along with
Bangladesh Standards of potable water and (12) Sieve analysis
on soils throughout a bore, leading to ascertain the best suitable
sustained aquifers, depths and slot sizes of strainer, types and
dia of tube well for specific yield, thickness of shrouding around
strainer, fineness modulus of shrouding materials, mechanical
units (pumps, compressor) for testing and operation of the tube
well, maintaining test bore functional till tube well installation,
testing etc. is finished, finally filling and sealing the

left over test bore permanently, including carrying water and soil
samples under direct responsibility of Engineer-in-charge to
BRTC, BUET or other reputed laboratory, approved by the
authority, submitting the report and design details all complete
and accepted by the Engineer and maintaining the mobilized
tools and plant at site till satisfactory test results are found (if not,
next test bore may be executed with the approval of concern
S.E. / Design Office)Total No. of test on water: 11 types of test x
1 test bore x one set sample (3 specimen) = 11 Nos. test (each
specimen 1.5 liter of water)Sieve analysis: min 9 Nos. Sample x
one test x One bore = 9 Nos. test (Samples are of 1 kg dry wt.
each)"There are about 55 (fifty-five) tests for potable water
Quality Standard according to Bangladesh Environment
Conservation Rules-12 (Schedule-3), 1997, under ECA 1995 of
Ministry of Environment and Forest. Therefore, additional test/
tests on water or sieve analysis of soil if required, other than the
above specified 12
(twelve) tests,

may be carried out for public interest as per direction of the


design engineer on actual payment including profit, VAT and all
other charges.
27.5.1 a) For borehole # 1 furnishing design considering 1 no
test 1.00 each 42,223.00 42,223.00
27.5.1 b) For borehole # 2( If necessary) 1.00 each 42,223.00 42,223.00
7 27.7.2 Mobilization: Preparation for installation of tube-well and
transportation of complete boring equipments, labour and
materials to the work site and remove the materials after
completion of the works. Installation of drilling rig and
accessories, making arrangements for electricity, water, labour
shed, site office and stores, digging mud pit etc, leveling,
dressing and clearing of the site as per original condition and a
testing for discharge using minimum 1000 liter water tub etc. all
complete as per specifications and accepted by the Engineer.Up
to 200m depth.
1.00 Per set 37,824.00 37,824.00

file:///conversion/tmp/scratch/365023380.xls Page No-3


Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
8 27.8 Preparation and making gravel pack around the tube well
fixtures with supply of designed graded pea gravels free from
any substance harmful to pipe and health confirmed by test
(Passing through 10 mesh and retained on 40 mesh) including
sieving, washing etc. complete as per standard specification and
accepted by the Engineer. (The rate is inclusive of the cost of
extra amount required for caving and extra depth below the tube
well fixtures, shrouding should not be more than 15 m above the
strainer and measurement should be allowed from bottom of the
tube-well fixture to top of the gravel pack)

35.00 cum. 4,087.00 143,045.00


9 27.9 Making a sanitary seal up to a minimum depth of 6 meter from
G.L. or as specified including the supply of approved quality of
cement, sand and khoa (12 mm down graded) in ratio (1:1:5:3)
as per standard specification and accepted by the Engineer.
4.10 cum. 7,982.00 32,726.20
10 27.49 Boring: Execution of 800 mm dia boring through all sorts of
strata by reverse circulation or any other approved method
(Method other than reverse circulation is to be applied only for
wells deeper than 152 meter). For boring 800 mm dia vertical
hole up to designed depth and collection of soil samples at every
3 meter interval and at every change of formation including
sinking and withdrawing necessary casing pipe and all
necessary arrangements complete as per specification and
accepted by the Engineer. (Measurement will be allowed form
G.L. to bottom of the blind pipe and the rate is required for
caving and siltation)

27.49.1 From 0 m to 50 m = 50 m 50.00 rm. 2,137.00 106,850.00


27.49.2 From 50 m to 100 m = 50 m 50.00 rm. 2,308.00 115,400.00
27.49.3 From 100 m to 152 m = 52 m 52.00 rm. 2,504.00 130,208.00
27.49.4 From 152 m to 200 m = 48 m 48.00 rm. 2,730.00 131,040.00
27.49.5 From 200 m to 250 m = 50 m 50.00 rm. 2,989.00 149,450.00
11 Supplying the following tube-well fixtures and Pipes conforming
to standard BS-1387 & BDS -1031, having chemical composition
(in %) carbon 0.17-0.25, manganese 0.95-1.20, sulphur 0.060
max ,Phosphorous 0.060 max, Tensile properties : Minimum
Yield strength 188 MPa Minimum strengh 313 MPa and marking
for a) Manufacturer b) Material c) Wall thickness d) Nominal out
side dia e) Intended use etc. on the body of the pipe at working
site as per standard practice and accepted by the engineer.

27.50.1 a) 200 mm dia MS cap 6 mm thick for blind pipe / sand trap. 1.00 each 1,581.00 1,581.00
MR b) 3m long 200 mm dia heavy type GI pipe (National tube or
equivalent) with one end sealed with welded 6mm thick steel
plate ( Bail plug) and other end with thread and socket joint or
similar.
3.00 rm. 31,834.00 95,502.00
MR c) 200 mm dia strainer of Slot as per design including taging
4 Nos 12 mm dia MS rod continuously. Stainless steel strainer
of continuous slot .The stainer shall be Johnson (foreign made)
or equivalent product having a minimum weight of 12.3 kg per
meter. Based on design of Tube well.
50.00 rm. 34,500.00 1,725,000.00

file:///conversion/tmp/scratch/365023380.xls Page No-4


Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
27.50.2 200 mm dia 6 mm thick tube well pipe and blank G.I. pipe of wt.
33.45 kg per meter can withstand minimum 700 psi hydraulic
pressure. 15.00 rm. 8,005.00 120,075.00
27.50.4 200 mm x 450 mm dia 6 mm thick M.S. reducer.
1.00 rm. 15,118.00 15,118.00
MR 450 mm dia 6 mm thick M.S. housing pipe (Seamless)
87.00 rm. 31,500.00 2,740,500.00
12 27.51 Complete installation of 200 mm dia deep tubewell fixtures
such as expanded top pipes, reducer, tube well pipes, strainer,
blind pipe, pipe caps etc. fitting,and fixing socket ,welded and
additional welding with fibre and placing in position with proper
size MS centralizer @ 3 metre c/c in strainer position including
blind pipe etc. complete as per standard practice and accepted
by the Engineer.
160.00 rm. 383.00 61,280.00
13 27.52 Complete development of the tube well by suitable air
compressor and pump of suitable capacity by alternate surging
and pumping until satisfactory yield, sand free water and the
turbidity condition is reached using necessary quantity of calgon
and conducting step draw down test before and after the
development as per specification and accepted by the Engineer.
(Development should be started within 24 hours of completion of
shrouding).

27.52.1 Wells up to 200 m depth 1.00 each 38,647.00 38,647.00


14 MR Collection of water samples (Post Development) 3 hours after
continuous pumping in 1.5L clean plastic mineral water bottles
(acidified 1 bottle and completely filled non-acidified 5 bottles) as
per standard practice and direction of the Engineer-in-Charge.
Transportation of the water samples on the same day of
collection from the field to BUET laboratory with proper
identification/depth and direction of the Engineer-in-Charge for
water Quality test as per following specification. (Ref:
Technical Specification, Clause # 7A.8)

1.00 L.S 35,000.00 35,000.00


15 27.53 Long term pumping test of the well by turbine/submersible
pump of required capacity through testing & measuring
equipment including supply of all materials for determining flow
and yield for 72 hours. Conducting draw down and recovery test
etc. complete as per standard practice and direction of the
Engineer-in-Charge. (Ref: Technical Specification, Clause #
7A.6.1.2)
72.00 hours 1,044.00 75,168.00
16 27.54 Disinfections of the well including supply of sufficient quantity of
bleaching powder (33% strength) chlorinated water having 150
ppm available free chlorine complete as per standard
specification and accepted by the Engineer.
1.00 each 2,211.00 2,211.00
17 27.55 Filling of the borehole around the tube well from top of the
shrouding up to the bottom of sanitary seal by withdrawn
selected soil or local clay free from any substances harmful to
pipes and health as per standard specification and accepted by
the Engineer.
90.00 rm. 43.00 3,870.00
18 MR Water jetting / positive back wash air lift development using
fresh water etc. All completer as per specification and direction
of the E/C. 45.00 rm. 8,500.00 382,500.00

file:///conversion/tmp/scratch/365023380.xls Page No-5


Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
19 27.64 Supplying the following tube-well fixtures at working site as
per standard practice and accepted by the Engineer.(The
quantity of materials will be decided on the basis of final design
of production Tube well)

27.64.2 75 mm dia 4.85 mm thick tube well pipe and blank G.I. pipe 3.00 rm. 1,328.00 3,984.00
27.64.7 Centralizer made with 12 mm dia M.S. rod of approved design 20.00 each 364.00 7,280.00
MR 500 mm dia M.S. cap of 6 mm thick for housing pipe covering.
1.00 each 5,000.00 5,000.00
20 MR Verticality test of the well including supplying verticality test
equipment, labour, etc. after sinking of the well but before
placement of the shrouding materials and after completion of the
well including rectification of any deviation from the specified
limit etc. all complete as per specification and direction of the
Engineer-in-Charge. (Ref: Technical Specification, Clause #
7A.5.3).
1.00 L.S 25,000.00 25,000.00
21 MR Making a clay seal above the filter pack with clay balls made of
50% local puddled clay (clay mixed with 3-5% puddloo) and 50%
bentonite as per specification and direction of the Engineer- in
Charge and as per attached Drawing (Up to 10m of housing
pipe).
1.00 L.S 25,000.00 25,000.00
Sub-Total Tk. 6,471,844.40
02 Number Tk. 12,943,688.80
Add 5% Contingency Tk. 647,184.44
Grand Total Tk. 13,590,873.24
Say Tk. 13,590,900.00

file:///conversion/tmp/scratch/365023380.xls Page No-6


BANGLADESH UNIVERSITY OF ENGINEERING AND TECHNOLOGY, DHAKA.
Name of Work : INSTALLATION OF 200mmX450mm DIA DEEP TUBE WELL AT ANYWHERE WITHIN BUET CAMPUS.
( TUBE WELL B )
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
1 27.1 Mobilization for test boring or observation well: Transportation
of materials, equipments, tools and plants and boring rig to work
site. Construction of derrick and dismantling the same. Cleaning
the site after completion of the work accepted by the Engineer. 1.00 set 7,034.00 7,034.00
2 Boring by using 100 mm dia cutter and 40 mm dia heavy type
G.I pipe having wall thickness 2.9 mm, outside diameter min
47.8 mm, weight 3.517 kg/m, capability to withstand 50 kg/cm2
and other equipments capable of drilling up to a depth 500 meter
by water jet system through all sorts of strata. Protection of
caving by supplying necessary casing pipe. Collection of soil
samples at every 3 meter interval and at every change of strata
and preserve them in a controlled environment for analysis and
laboratory test. Finally withdrawal of boring and casing pipes etc.
complete and accepted by the Engineer.

i) For borehole # 1
27.2.1 a) From 0.0 m to 50 m = 50 m 50.00 rm. 154.00 7,700.00
27.2.2 b) From 50 m to100 m = 50 m 50.00 rm. 177.00 8,850.00
27.2.3 c) From 100 m to 152 m = 52 m 52.00 rm. 203.00 10,556.00
27.2.4 d) From 152 m to 200 m = 48 m 48.00 rm. 234.00 11,232.00
ii) For borehole # 2( If necessary)
a) From 0.0 m to 50 m = 50 m 50.00 rm. 154.00 7,700.00
b) From 50 m to100 m = 50 m 50.00 rm. 177.00 8,850.00
c) From 100 m to 152 m = 52 m 52.00 rm. 203.00 10,556.00
d) From 152 m to 200 m = 48 m 48.00 rm. 234.00 11,232.00
3 Installation of tube-well fixture for observation well:
Supplying and lowering of 40/38 mm inside dia best quality
uPVC pressure tube well pipe having specific gravity 1.35 - 1.45,
wall thickness 2.5 mm - 3.0 mm, capability to withstand a
minimum hydrostatic pressure of 170 psi for 1 hr. fitted and fixed
in position with all accessories, uPVC sand trap of length 3.00
with uPVC strainer of desired slot installing in or at mid depth of
the most suitable water bearing strata. 38 mm dia G.I. pipe of
best quality of length 1.52 m with M.S. welded flat bar on each
side to prevent from rotation up to desired depth, fitting fixing the
best quality No. 6 C.I. head hand-pump etc including the cost of
solvent cement, socket adaptor, filling medium sand up to 18.00
m above strainer and the remaining portion with available soil
from boring etc. complete as per standard specification and
accepted by the Engineer.

a) For borehole # 1
27.3.3 (i) 38/40 mm dia water grade uPVC pipe having thickness 2.5-
3.00 mm. For bore hole # 1 150.00 rm. 141.00 21,150.00
27.3.4 (ii) 38/40 mm dia water grade uPVC strainer having wall
thickness 2.5-3.00 mm For bore hole # 1 50.00 rm. 175.00 8,750.00
27.31.1 iii) Fitting, fixing No.6 Hand pump set including all necessary
accessories etc. complete and accepted by the engineer.
1.00 each 2,738.00 2,738.00

file:///conversion/tmp/scratch/365023380.xls 7 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
27.3.2 iv) 38/40 mm dia heavy type GI pipe conforming to standerd BS-
1387 &BDS-1031 having chemical composition (in %) carbon
0.17-0.25, Manganese 0.95-1.2, sulphur 0.060 max,
Phosphorous 0.060 max, tensile properties : minimum Yield
strengh 188 Mpa, Minimum Tensile Strengh 313 Mpa and
marking for a) Manufactuer b) Material c) Wall thickness
d)Nominal outside dia e)Intended use etc. on the body of pipe
having wall thckness 2.90mm, weight 3.517 kg/m capability to
withstand 50 kg/sqcm hydraulic pressure.
1.52 rm. 680.00 1,033.60
27.3.5 v) 38/40 mm dia uPVC socket adapter 1.00 each 87.00 87.00
27.3.6 vi) Best qualily 38mm dia uPVC cap 1.00 each 66.00 66.00
b) For borehole # 2 ( If necessary)
27.3.4 (i) 38/40 mm dia water grade uPVC pipe having wall thickness
2.5-3.00 mm. For bore hole # 2. 150.00 rm. 141.00 21,150.00
27.3.5 (ii) 38/40 mm dia water grade uPVC strainer having wall
thickness 2.5-3.00 mm For bore hole # 2. 50.00 rm. 175.00 8,750.00
27.3.1 iii) Fitting, fixing No.6 Hand pump set including all necessaries
etc. complete and accepted by the engineer.For bore hole # 2. 1.00 each 2,738.00 2,738.00
27.3.2 iv) 38/40 mm dia heavy type GI pipe conforming to standerd BS-
1387 & BDS-1031 having chemical composition (in %) carbon
0.17-0.25, Manganese 0.95-1.20, sulphur 0.060 max,
Phosphorous 0.060 max, tensile properties : minimum Yield
strengh 188 Mpa, Minimum Tensile Strengh 313 Mpa and
marking for a) Manufactuer b) Material c) Wall thickness
d)Nominal outside dia e)Intended use etc. on the body of pipe
having wall thckness 2.90mm, weight 3.517 kg/m capability to
withstand 50 kg/sqcm hydraulic pressure.

1.52 rm. 680.00 1,033.60


27.3.5 v) 38/40 mm dia uPVC socket adapter. For bore hole # 2.
1.00 each 87.00 87.00
27.3.6 vi) Best qualily 38mm dia uPVC cap. For bore hole # 2. 1.00 each 66.00 66.00
4 27.3.9 Filling the top 0.60 m of the borehole around the top pipe with
sanitary seal of concrete of proportion 1:2:4 as per design
accepted by the engineer. 1.00 each 51.00 51.00
5 Complete development of the tube well to obtain sand and
turbidity free water at a satisfactory yield confirmed by tests as
per specification and accepted by the Engineer. Water sample
must be taken from 3 separate aquifers from three tube-well.
a) For borehole # 1 well beyond 200m depth
27.4.2.1 (i) Well up to 200meter depth, For 1 No. test tube-well. 200.00 rm. 35.57 7,114.00
27.4.2.2 (ii) Well beyond 200 meter depth, For 2 No. test tube-well. 30.00 rm. 53.35 1,600.50
b) For borehole # 2( If necessary)well beyond 200m depth

27.2.1 (i) Well up to 200 meter depth, For 2 No. test tube-well. 200.00 rm. 35.57 7,114.00
27.2.2 (ii) Well beyond 200 meter depth, For 1 No. test tube-well. 30.00 rm. 53.35 1,600.50

file:///conversion/tmp/scratch/365023380.xls 8 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
6 27.5 Furnishing design of a production well by testing of water and
soil samples from a test bores up to 350m depth collecting
samples of water from the best suitable aquifer, filling in
sterilized air-tight glass bottles having no air space inside;
collecting soil (sand, solids etc) at 3 m interval and at each
change of soil strata from the bores, arranging them in the cell of
a box in an orderly manner. carrying out test of water for (1) pH,
(2) CO2 (3) Chloride, (4) Fluoride, (5) Iron, (6) Manganese, (7)
Nitrate-Nitrogen, (8)Total alkalinity, (9) Total hardness, (10)
Arsenic, (11) Turbidity, followed by test reports along with
Bangladesh Standards of potable water and (12) Sieve analysis
on soils throughout a bore, leading to ascertain the best suitable
sustained aquifers, depths and slot sizes of strainer, types and
dia of tube well for specific yield, thickness of shrouding around
strainer, fineness modulus of shrouding materials, mechanical
units (pumps, compressor) for testing and operation of the tube
well, maintaining test bore functional till tube well installation,
testing etc. is finished, finally filling and sealing the

left over test bore permanently, including carrying water and soil
samples under direct responsibility of Engineer-in-charge to
BRTC, BUET or other reputed laboratory, approved by the
authority, submitting the report and design details all complete
and accepted by the Engineer and maintaining the mobilized
tools and plant at site till satisfactory test results are found (if not,
next test bore may be executed with the approval of concern
S.E. / Design Office)Total No. of test on water: 11 types of test x
1 test bore x one set sample (3 specimen) = 11 Nos. test (each
specimen 1.5 liter of water)Sieve analysis: min 9 Nos. Sample x
one test x One bore = 9 Nos. test (Samples are of 1 kg dry wt.
each)"There are about 55 (fifty-five) tests for potable water
Quality Standard according to Bangladesh Environment
Conservation Rules-12 (Schedule-3), 1997, under ECA 1995 of
Ministry of Environment and Forest. Therefore, additional test/
tests on water or sieve analysis of soil if required, other than the
above specified 12
(twelve) tests,

may be carried out for public interest as per direction of the


design engineer on actual payment including profit, VAT and all
other charges.
27.5.1 a) For borehole # 1 furnishing design considering 1 no
test 1.00 each 32,223.00 32,223.00
27.5.1 b) For borehole # 2( If necessary) 1.00 each 32,223.00 32,223.00
7 27.7.2 Mobilization: Preparation for installation of tube-well and
transportation of complete boring equipments, labour and
materials to the work site and remove the materials after
completion of the works. Installation of drilling rig and
accessories, making arrangements for electricity, water, labour
shed, site office and stores, digging mud pit etc, leveling,
dressing and clearing of the site as per original condition and a
testing for discharge using minimum 1000 liter water tub etc. all
complete as per specifications and accepted by the Engineer.Up
to 200m depth.
1.00 Per set 37,824.00 37,824.00

file:///conversion/tmp/scratch/365023380.xls 9 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
8 27.8 Preparation and making gravel pack around the tube well
fixtures with supply of designed graded pea gravels free from
any substance harmful to pipe and health confirmed by test
(Passing through 10 mesh and retained on 40 mesh) including
sieving, washing etc. complete as per standard specification and
accepted by the Engineer. (The rate is inclusive of the cost of
extra amount required for caving and extra depth below the tube
well fixtures, shrouding should not be more than 15 m above the
strainer and measurement should be allowed from bottom of the
tube-well fixture to top of the gravel pack)
35.00 cum. 3,087.00 108,045.00
9 27.9 Making a sanitary seal up to a minimum depth of 6 meter from
G.L. or as specified including the supply of approved quality of
cement, sand and khoa (12 mm down graded) in ratio (1:1:5:3)
as per standard specification and accepted by the Engineer.
4.10 cum. 7,982.00 32,726.20
10 27.49 Boring: Execution of 800 mm dia boring through all sorts of
strata by reverse circulation or any other approved method
(Method other than reverse circulation is to be applied only for
wells deeper than 152 meter). For boring 800 mm dia vertical
hole up to designed depth and collection of soil samples at every
3 meter interval and at every change of formation including
sinking and withdrawing necessary casing pipe and all
necessary arrangements complete as per specification and
accepted by the Engineer. (Measurement will be allowed form
G.L. to bottom of the blind pipe and the rate is required for
caving and siltation)

27.49.1 From 0 m to 50 m = 50 m 50.00 rm. 1,137.00 56,850.00


27.49.2 From 50 m to 100 m = 50 m 50.00 rm. 1,308.00 65,400.00
27.49.3 From 100 m to 152 m = 52 m 52.00 rm. 1,504.00 78,208.00
27.49.4 From 152 m to 200 m = 48 m 48.00 rm. 1,730.00 83,040.00
27.49.5 From 200 m to 250 m = 50 m 50.00 rm. 1,989.00 99,450.00
11 Supplying the following tube-well fixtures and Pipes conforming
to standard BS-1387 & BDS -1031, having chemical composition
(in %) carbon 0.17-0.25, manganese 0.95-1.20, sulphur 0.060
max ,Phosphorous 0.060 max, Tensile properties : Minimum
Yield strength 188 MPa Minimum strengh 313 MPa and marking
for a) Manufacturer b) Material c) Wall thickness d) Nominal out
side dia e) Intended use etc. on the body of the pipe at working
site as per standard practice and accepted by the engineer.

27.50.1 a) 200 mm dia MS cap 6 mm thick for blind pipe / sand trap. 1.00 each 1,581.00 1,581.00
MR b) 3m long 200 mm dia heavy type GI pipe (National tube or
equivalent) with one end sealed with welded 6mm thick steel
plate ( Bail plug) and other end with thread and socket joint or
similar.
3.00 rm. 31,834.00 95,502.00
MR c) 200 mm dia strainer of Slot as per design including taging
4 Nos 12 mm dia MS rod continuously. Stainless steel strainer
of continuous slot .The stainer shall be Johnson (foreign made)
or equivalent product having a minimum weight of 12.3 kg per
meter. Based on design of Tube well.
50.00 rm. 24,500.00 1,225,000.00
27.50.2 200 mm dia 6 mm thick tube well pipe and blank G.I. pipe of wt.
33.45 kg per meter can withstand minimum 700 psi hydraulic
pressure. 15.00 rm. 7,005.00 105,075.00

file:///conversion/tmp/scratch/365023380.xls 10 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
27.50.4 200 mm x 450 mm dia 6 mm thick M.S. reducer.
1.00 rm. 13,118.00 13,118.00
MR 450 mm dia 6 mm thick M.S. housing pipe (Seamless)
107.00 rm. 21,500.00 2,300,500.00
12 27.51 Complete installation of 200 mm dia deep tubewell fixtures
such as expanded top pipes, reducer, tube well pipes, strainer,
blind pipe, pipe caps etc. fitting,and fixing socket ,welded and
additional welding with fibre and placing in position with proper
size MS centralizer @ 3 metre c/c in strainer position including
blind pipe etc. complete as per standard practice and accepted
by the Engineer.
160.00 rm. 383.00 61,280.00
13 27.52 Complete development of the tube well by suitable air
compressor and pump of suitable capacity by alternate surging
and pumping until satisfactory yield, sand free water and the
turbidity condition is reached using necessary quantity of calgon
and conducting step draw down test before and after the
development as per specification and accepted by the Engineer.
(Development should be started within 24 hours of completion of
shrouding).

27.52.1 Wells up to 200 m depth 1.00 each 38,647.00 38,647.00


14 MR Collection of water samples (Post Development) 3 hours after
continuous pumping in 1.5L clean plastic mineral water bottles
(acidified 1 bottle and completely filled non-acidified 5 bottles) as
per standard practice and direction of the Engineer-in-Charge.
Transportation of the water samples on the same day of
collection from the field to BUET laboratory with proper
identification/depth and direction of the Engineer-in-Charge for
water Quality test as per following specification. (Ref:
Technical Specification, Clause # 7A.8)

1.00 L.S 35,000.00 35,000.00


15 27.53 Long term pumping test of the well by turbine/submersible
pump of required capacity through testing & measuring
equipment including supply of all materials for determining flow
and yield for 72 hours. Conducting draw down and recovery test
etc. complete as per standard practice and direction of the
Engineer-in-Charge. (Ref: Technical Specification, Clause #
7A.6.1.2)
72.00 hours 1,044.00 75,168.00
16 27.54 Disinfections of the well including supply of sufficient quantity of
bleaching powder (33% strength) chlorinated water having 150
ppm available free chlorine complete as per standard
specification and accepted by the Engineer.
1.00 each 2,211.00 2,211.00
17 27.55 Filling of the borehole around the tube well from top of the
shrouding up to the bottom of sanitary seal by withdrawn
selected soil or local clay free from any substances harmful to
pipes and health as per standard specification and accepted by
the Engineer.
90.00 rm. 43.00 3,870.00
18 MR Water jetting / positive back wash air lift development using
fresh water etc. All completer as per specification and direction
of the E/C. 45.00 rm. 8,500.00 382,500.00
19 27.64 Supplying the following tube-well fixtures at working site as
per standard practice and accepted by the Engineer.(The
quantity of materials will be decided on the basis of final design
of production Tube well)

file:///conversion/tmp/scratch/365023380.xls 11 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
27.64.2 75 mm dia 4.85 mm thick tube well pipe and blank G.I. pipe 3.00 rm. 1,328.00 3,984.00
27.64.7 Centralizer made with 12 mm dia M.S. rod of approved design 20.00 each 364.00 7,280.00
MR 500 mm dia M.S. cap of 6 mm thick for housing pipe covering.
1.00 each 5,000.00 5,000.00
20 MR Verticality test of the well including supplying verticality test
equipment, labour, etc. after sinking of the well but before
placement of the shrouding materials and after completion of the
well including rectification of any deviation from the specified
limit etc. all complete as per specification and direction of the
Engineer-in-Charge. (Ref: Technical Specification, Clause #
7A.5.3).
1.00 L.S 25,000.00 25,000.00
21 MR Making a clay seal above the filter pack with clay balls made of
50% local puddled clay (clay mixed with 3-5% puddloo) and 50%
bentonite as per specification and direction of the Engineer- in
Charge and as per attached Drawing (Up to 10m of housing
pipe).
1.00 L.S 25,000.00 25,000.00
Sub-Total Tk. 5,200,544.40
Add 5% Contingency Tk. 260,027.22
G. Total = Tk. 5,460,571.62
Say Tk. 5,460,600.00

ABSTRACT
DEEP TUBE WELL A Tk. 5,460,600.00
DEEP TUBE WELL B Tk. 5,460,600.00
GRAND TOTAL Tk. 10,921,200.00

file:///conversion/tmp/scratch/365023380.xls 12 of 27
BANGLADESH UNIVERSITY OF ENGINEERING AND TECHNOLOGY, DHAKA.
Name of Work : INSTALLATION OF 200mmX450mm DIA DEEP TUBE WELL AT ANYWHERE WITHIN BUET CAMPUS.
( TUBE WELL A )
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
1 Mobilization for test boring or observation well: Transportation 1.00 set
of materials, equipments, tools and plants and boring rig to work
site. Construction of derrick and dismantling the same. Cleaning
the site after completion of the work accepted by the Engineer.

2 Boring by using 100 mm dia cutter and 40 mm dia heavy type


G.I pipe having wall thickness 2.9 mm, outside diameter min
47.8 mm, weight 3.517 kg/m, capability to withstand 50 kg/cm2
and other equipments capable of drilling up to a depth 500 meter
by water jet system through all sorts of strata. Protection of
caving by supplying necessary casing pipe. Collection of soil
samples at every 3 meter interval and at every change of strata
and preserve them in a controlled environment for analysis and
laboratory test. Finally withdrawal of boring and casing pipes etc.
complete and accepted by the Engineer.

i) For borehole # 1

a) From 0.0 m to 50 m = 50 m 50.00 rm.

b) From 50 m to100 m = 50 m 50.00 rm.

c) From 100 m to 152 m = 52 m 52.00 rm.

d) From 152 m to 200 m = 48 m 48.00 rm.

ii) For borehole # 2( If necessary)

a) From 0.0 m to 50 m = 50 m 50.00 rm.

b) From 50 m to100 m = 50 m 50.00 rm.

c) From 100 m to 152 m = 52 m 52.00 rm.

d) From 152 m to 200 m = 48 m 48.00 rm.

file:///conversion/tmp/scratch/365023380.xls 13 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
3 Installation of tube-well fixture for observation well:
Supplying and lowering of 40/38 mm inside dia best quality
uPVC pressure tube well pipe having specific gravity 1.35 - 1.45,
wall thickness 2.5 mm - 3.0 mm, capability to withstand a
minimum hydrostatic pressure of 170 psi for 1 hr. fitted and fixed
in position with all accessories, uPVC sand trap of length 3.00
with uPVC strainer of desired slot installing in or at mid depth of
the most suitable water bearing strata. 38 mm dia G.I. pipe of
best quality of length 1.52 m with M.S. welded flat bar on each
side to prevent from rotation up to desired depth, fitting fixing the
best quality No. 6 C.I. head hand-pump etc including the cost of
solvent cement, socket adaptor, filling medium sand up to 18.00
m above strainer and the remaining portion with available soil
from boring etc. complete as per standard specification and
accepted by the Engineer.

a) For borehole # 1

(i) 38/40 mm dia water grade uPVC pipe having thickness 2.5- 150.00 rm.
3.00 mm. For bore hole # 1

(ii) 38/40 mm dia water grade uPVC strainer having wall 50.00 rm.
thickness 2.5-3.00 mm For bore hole # 1

iii) Fitting, fixing No.6 Hand pump set including all necessary 1.00 each
accessories etc. complete and accepted by the engineer.

iv) 38/40 mm dia heavy type GI pipe conforming to standerd BS- 1.52 rm.
1387 &BDS-1031 having chemical composition (in %) carbon
0.17-0.25, Manganese 0.95-1.2, sulphur 0.060 max,
Phosphorous 0.060 max, tensile properties : minimum Yield
strengh 188 Mpa, Minimum Tensile Strengh 313 Mpa and
marking for a) Manufactuer b) Material c) Wall thickness
d)Nominal outside dia e)Intended use etc. on the body of pipe
having wall thckness 2.90mm, weight 3.517 kg/m capability to
withstand 50 kg/sqcm hydraulic pressure.

v) 38/40 mm dia uPVC socket adapter 1.00 each

vi) Best qualily 38mm dia uPVC cap 1.00 each

b) For borehole # 2 ( If necessary)

(i) 38/40 mm dia water grade uPVC pipe having wall thickness 150.00 rm.
2.5-3.00 mm. For bore hole # 2.

(ii) 38/40 mm dia water grade uPVC strainer having wall 50.00 rm.
thickness 2.5-3.00 mm For bore hole # 2.

file:///conversion/tmp/scratch/365023380.xls 14 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
iii) Fitting, fixing No.6 Hand pump set including all necessaries 1.00 each
etc. complete and accepted by the engineer.For bore hole # 2.

iv) 38/40 mm dia heavy type GI pipe conforming to standerd BS- 1.52 rm.
1387 & BDS-1031 having chemical composition (in %) carbon
0.17-0.25, Manganese 0.95-1.20, sulphur 0.060 max,
Phosphorous 0.060 max, tensile properties : minimum Yield
strengh 188 Mpa, Minimum Tensile Strengh 313 Mpa and
marking for a) Manufactuer b) Material c) Wall thickness
d)Nominal outside dia e)Intended use etc. on the body of pipe
having wall thckness 2.90mm, weight 3.517 kg/m capability to
withstand 50 kg/sqcm hydraulic pressure.

v) 38/40 mm dia uPVC socket adapter. For bore hole # 2. 1.00 each

vi) Best qualily 38mm dia uPVC cap. For bore hole # 2. 1.00 each

4 Filling the top 0.60 m of the borehole around the top pipe with 1.00 each
sanitary seal of concrete of proportion 1:2:4 as per design
accepted by the engineer.

5 Complete development of the tube well to obtain sand and


turbidity free water at a satisfactory yield confirmed by tests as
per specification and accepted by the Engineer. Water sample
must be taken from 3 separate aquifers from three tube-well.

a) For borehole # 1 well beyond 200m depth

(i) Well up to 200meter depth, For 1 No. test tube-well. 200.00 rm.

(ii) Well beyond 200 meter depth, For 2 No. test tube-well. 30.00 rm.

b) For borehole # 2( If necessary)well beyond 200m depth

(i) Well up to 200 meter depth, For 2 No. test tube-well. 200.00 rm.

(ii) Well beyond 200 meter depth, For 1 No. test tube-well. 30.00 rm.

file:///conversion/tmp/scratch/365023380.xls 15 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
6 Furnishing design of a production well by testing of water and
soil samples from a test bores up to 350m depth collecting
samples of water from the best suitable aquifer, filling in
sterilized air-tight glass bottles having no air space inside;
collecting soil (sand, solids etc) at 3 m interval and at each
change of soil strata from the bores, arranging them in the cell of
a box in an orderly manner. carrying out test of water for (1) pH,
(2) CO2 (3) Chloride, (4) Fluoride, (5) Iron, (6) Manganese, (7)
Nitrate-Nitrogen, (8)Total alkalinity, (9) Total hardness, (10)
Arsenic, (11) Turbidity, followed by test reports along with
Bangladesh Standards of potable water and (12) Sieve analysis
on soils throughout a bore, leading to ascertain the best suitable
sustained aquifers, depths and slot sizes of strainer, types and
dia of tube well for specific yield, thickness of shrouding around
strainer, fineness modulus of shrouding materials, mechanical
units (pumps, compressor) for testing and operation of the tube
well, maintaining test bore functional till tube well installation,
testing etc. is finished, finally filling and sealing the

left over test bore permanently, including carrying water and soil
samples under direct responsibility of Engineer-in-charge to
BRTC, BUET or other reputed laboratory, approved by the
authority, submitting the report and design details all complete
and accepted by the Engineer and maintaining the mobilized
tools and plant at site till satisfactory test results are found (if not,
next test bore may be executed with the approval of concern
S.E. / Design Office)Total No. of test on water: 11 types of test x
1 test bore x one set sample (3 specimen) = 11 Nos. test (each
specimen 1.5 liter of water)Sieve analysis: min 9 Nos. Sample x
one test x One bore = 9 Nos. test (Samples are of 1 kg dry wt.
each)"There are about 55 (fifty-five) tests for potable water
Quality Standard according to Bangladesh Environment
Conservation Rules-12 (Schedule-3), 1997, under ECA 1995 of
Ministry of Environment and Forest. Therefore, additional test/
tests on water or sieve analysis of soil if required, other than the
above specified 12
(twelve) tests,

may be carried out for public interest as per direction of the


design engineer on actual payment including profit, VAT and all
other charges.
a) For borehole # 1 furnishing design considering 1 no 1.00 each
test

b) For borehole # 2( If necessary) 1.00 each

7 Mobilization: Preparation for installation of tube-well and 1.00 Per set


transportation of complete boring equipments, labour and
materials to the work site and remove the materials after
completion of the works. Installation of drilling rig and
accessories, making arrangements for electricity, water, labour
shed, site office and stores, digging mud pit etc, leveling,
dressing and clearing of the site as per original condition and a
testing for discharge using minimum 1000 liter water tub etc. all
complete as per specifications and accepted by the Engineer.Up
to 200m depth.

file:///conversion/tmp/scratch/365023380.xls 16 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
8 Preparation and making gravel pack around the tube well 35.00 cum.
fixtures with supply of designed graded pea gravels free from
any substance harmful to pipe and health confirmed by test
(Passing through 10 mesh and retained on 40 mesh) including
sieving, washing etc. complete as per standard specification and
accepted by the Engineer. (The rate is inclusive of the cost of
extra amount required for caving and extra depth below the tube
well fixtures, shrouding should not be more than 15 m above the
strainer and measurement should be allowed from bottom of the
tube-well fixture to top of the gravel pack)

9 Making a sanitary seal up to a minimum depth of 6 meter from 4.10 cum.


G.L. or as specified including the supply of approved quality of
cement, sand and khoa (12 mm down graded) in ratio (1:1:5:3)
as per standard specification and accepted by the Engineer.

10 Boring: Execution of 800 mm dia boring through all sorts of


strata by reverse circulation or any other approved method
(Method other than reverse circulation is to be applied only for
wells deeper than 152 meter). For boring 800 mm dia vertical
hole up to designed depth and collection of soil samples at every
3 meter interval and at every change of formation including
sinking and withdrawing necessary casing pipe and all
necessary arrangements complete as per specification and
accepted by the Engineer. (Measurement will be allowed form
G.L. to bottom of the blind pipe and the rate is required for
caving and siltation)

From 0 m to 50 m = 50 m 50.00 rm.

From 50 m to 100 m = 50 m 50.00 rm.

From 100 m to 152 m = 52 m 52.00 rm.

From 152 m to 200 m = 48 m 48.00 rm.

From 200 m to 250 m = 50 m 50.00 rm.

11 Supplying the following tube-well fixtures and Pipes conforming


to standard BS-1387 & BDS -1031, having chemical composition
(in %) carbon 0.17-0.25, manganese 0.95-1.20, sulphur 0.060
max ,Phosphorous 0.060 max, Tensile properties : Minimum
Yield strength 188 MPa Minimum strengh 313 MPa and marking
for a) Manufacturer b) Material c) Wall thickness d) Nominal out
side dia e) Intended use etc. on the body of the pipe at working
site as per standard practice and accepted by the engineer.

a) 200 mm dia MS cap 6 mm thick for blind pipe / sand trap. 1.00 each

file:///conversion/tmp/scratch/365023380.xls 17 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
b) 3m long 200 mm dia heavy type GI pipe (National tube or 3.00 rm.
equivalent) with one end sealed with welded 6mm thick steel
plate ( Bail plug) and other end with thread and socket joint or
similar.

c) 200 mm dia strainer of Slot as per design including taging 50.00 rm.
4 Nos 12 mm dia MS rod continuously. Stainless steel strainer
of continuous slot .The stainer shall be Johnson (foreign made)
or equivalent product having a minimum weight of 12.3 kg per
meter. Based on design of Tube well.

200 mm dia 6 mm thick tube well pipe and blank G.I. pipe of wt. 15.00 rm.
33.45 kg per meter can withstand minimum 700 psi hydraulic
pressure.
200 mm x 450 mm dia 6 mm thick M.S. reducer. 1.00 rm.

450 mm dia 6 mm thick M.S. housing pipe (Seamless) 107.00 rm.

12 Complete installation of 200 mm dia deep tubewell fixtures 160.00 rm.


such as expanded top pipes, reducer, tube well pipes, strainer,
blind pipe, pipe caps etc. fitting,and fixing socket ,welded and
additional welding with fibre and placing in position with proper
size MS centralizer @ 3 metre c/c in strainer position including
blind pipe etc. complete as per standard practice and accepted
by the Engineer.

13 Complete development of the tube well by suitable air


compressor and pump of suitable capacity by alternate surging
and pumping until satisfactory yield, sand free water and the
turbidity condition is reached using necessary quantity of calgon
and conducting step draw down test before and after the
development as per specification and accepted by the Engineer.
(Development should be started within 24 hours of completion of
shrouding).

Wells up to 200 m depth 1.00 each

14 Collection of water samples (Post Development) 3 hours after 1.00 L.S


continuous pumping in 1.5L clean plastic mineral water bottles
(acidified 1 bottle and completely filled non-acidified 5 bottles) as
per standard practice and direction of the Engineer-in-Charge.
Transportation of the water samples on the same day of
collection from the field to BUET laboratory with proper
identification/depth and direction of the Engineer-in-Charge for
water Quality test as per following specification. (Ref:
Technical Specification, Clause # 7A.8)

15 Long term pumping test of the well by turbine/submersible 72.00 hours


pump of required capacity through testing & measuring
equipment including supply of all materials for determining flow
and yield for 72 hours. Conducting draw down and recovery test
etc. complete as per standard practice and direction of the
Engineer-in-Charge. (Ref: Technical Specification, Clause #
7A.6.1.2)

16 Disinfections of the well including supply of sufficient quantity of 1.00 each


bleaching powder (33% strength) chlorinated water having 150
ppm available free chlorine complete as per standard
specification and accepted by the Engineer.

file:///conversion/tmp/scratch/365023380.xls 18 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
17 Filling of the borehole around the tube well from top of the 90.00 rm.
shrouding up to the bottom of sanitary seal by withdrawn
selected soil or local clay free from any substances harmful to
pipes and health as per standard specification and accepted by
the Engineer.

18 Water jetting / positive back wash air lift development using 45.00 rm.
fresh water etc. All completer as per specification and direction
of the E/C.
19 Supplying the following tube-well fixtures at working site as
per standard practice and accepted by the Engineer.(The
quantity of materials will be decided on the basis of final design
of production Tube well)

75 mm dia 4.85 mm thick tube well pipe and blank G.I. pipe 3.00 rm.

Centralizer made with 12 mm dia M.S. rod of approved design 20.00 each

500 mm dia M.S. cap of 6 mm thick for housing pipe covering. 1.00 each

20 Verticality test of the well including supplying verticality test 1.00 L.S
equipment, labour, etc. after sinking of the well but before
placement of the shrouding materials and after completion of the
well including rectification of any deviation from the specified
limit etc. all complete as per specification and direction of the
Engineer-in-Charge. (Ref: Technical Specification, Clause #
7A.5.3).

21 Making a clay seal above the filter pack with clay balls made of 1.00 L.S
50% local puddled clay (clay mixed with 3-5% puddloo) and 50%
bentonite as per specification and direction of the Engineer- in
Charge and as per attached Drawing (Up to 10m of housing
pipe).

Total (Tk)

file:///conversion/tmp/scratch/365023380.xls 19 of 27
BANGLADESH UNIVERSITY OF ENGINEERING AND TECHNOLOGY, DHAKA.
Name of Work : INSTALLATION OF 200mmX450mm DIA DEEP TUBE WELL AT ANYWHERE WITHIN BUET CAMPUS.
( TUBE WELL B )
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
1 Mobilization for test boring or observation well: Transportation 1.00 set
of materials, equipments, tools and plants and boring rig to work
site. Construction of derrick and dismantling the same. Cleaning
the site after completion of the work accepted by the Engineer.

2 Boring by using 100 mm dia cutter and 40 mm dia heavy type


G.I pipe having wall thickness 2.9 mm, outside diameter min
47.8 mm, weight 3.517 kg/m, capability to withstand 50 kg/cm2
and other equipments capable of drilling up to a depth 500 meter
by water jet system through all sorts of strata. Protection of
caving by supplying necessary casing pipe. Collection of soil
samples at every 3 meter interval and at every change of strata
and preserve them in a controlled environment for analysis and
laboratory test. Finally withdrawal of boring and casing pipes etc.
complete and accepted by the Engineer.

i) For borehole # 1

a) From 0.0 m to 50 m = 50 m 50.00 rm.

b) From 50 m to100 m = 50 m 50.00 rm.

c) From 100 m to 152 m = 52 m 52.00 rm.

d) From 152 m to 200 m = 48 m 48.00 rm.

ii) For borehole # 2( If necessary)

a) From 0.0 m to 50 m = 50 m 50.00 rm.

b) From 50 m to100 m = 50 m 50.00 rm.

c) From 100 m to 152 m = 52 m 52.00 rm.

d) From 152 m to 200 m = 48 m 48.00 rm.

file:///conversion/tmp/scratch/365023380.xls 20 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
3 Installation of tube-well fixture for observation well:
Supplying and lowering of 40/38 mm inside dia best quality
uPVC pressure tube well pipe having specific gravity 1.35 - 1.45,
wall thickness 2.5 mm - 3.0 mm, capability to withstand a
minimum hydrostatic pressure of 170 psi for 1 hr. fitted and fixed
in position with all accessories, uPVC sand trap of length 3.00
with uPVC strainer of desired slot installing in or at mid depth of
the most suitable water bearing strata. 38 mm dia G.I. pipe of
best quality of length 1.52 m with M.S. welded flat bar on each
side to prevent from rotation up to desired depth, fitting fixing the
best quality No. 6 C.I. head hand-pump etc including the cost of
solvent cement, socket adaptor, filling medium sand up to 18.00
m above strainer and the remaining portion with available soil
from boring etc. complete as per standard specification and
accepted by the Engineer.

a) For borehole # 1

(i) 38/40 mm dia water grade uPVC pipe having thickness 2.5- 150.00 rm.
3.00 mm. For bore hole # 1

(ii) 38/40 mm dia water grade uPVC strainer having wall 50.00 rm.
thickness 2.5-3.00 mm For bore hole # 1

iii) Fitting, fixing No.6 Hand pump set including all necessary 1.00 each
accessories etc. complete and accepted by the engineer.

iv) 38/40 mm dia heavy type GI pipe conforming to standerd BS- 1.52 rm.
1387 &BDS-1031 having chemical composition (in %) carbon
0.17-0.25, Manganese 0.95-1.2, sulphur 0.060 max,
Phosphorous 0.060 max, tensile properties : minimum Yield
strengh 188 Mpa, Minimum Tensile Strengh 313 Mpa and
marking for a) Manufactuer b) Material c) Wall thickness
d)Nominal outside dia e)Intended use etc. on the body of pipe
having wall thckness 2.90mm, weight 3.517 kg/m capability to
withstand 50 kg/sqcm hydraulic pressure.

v) 38/40 mm dia uPVC socket adapter 1.00 each

vi) Best qualily 38mm dia uPVC cap 1.00 each

b) For borehole # 2 ( If necessary)

(i) 38/40 mm dia water grade uPVC pipe having wall thickness 150.00 rm.
2.5-3.00 mm. For bore hole # 2.

(ii) 38/40 mm dia water grade uPVC strainer having wall 50.00 rm.
thickness 2.5-3.00 mm For bore hole # 2.

file:///conversion/tmp/scratch/365023380.xls 21 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
iii) Fitting, fixing No.6 Hand pump set including all necessaries 1.00 each
etc. complete and accepted by the engineer.For bore hole # 2.

iv) 38/40 mm dia heavy type GI pipe conforming to standerd BS- 1.52 rm.
1387 & BDS-1031 having chemical composition (in %) carbon
0.17-0.25, Manganese 0.95-1.20, sulphur 0.060 max,
Phosphorous 0.060 max, tensile properties : minimum Yield
strengh 188 Mpa, Minimum Tensile Strengh 313 Mpa and
marking for a) Manufactuer b) Material c) Wall thickness
d)Nominal outside dia e)Intended use etc. on the body of pipe
having wall thckness 2.90mm, weight 3.517 kg/m capability to
withstand 50 kg/sqcm hydraulic pressure.

v) 38/40 mm dia uPVC socket adapter. For bore hole # 2. 1.00 each

vi) Best qualily 38mm dia uPVC cap. For bore hole # 2. 1.00 each

4 Filling the top 0.60 m of the borehole around the top pipe with 1.00 each
sanitary seal of concrete of proportion 1:2:4 as per design
accepted by the engineer.

5 Complete development of the tube well to obtain sand and


turbidity free water at a satisfactory yield confirmed by tests as
per specification and accepted by the Engineer. Water sample
must be taken from 3 separate aquifers from three tube-well.

a) For borehole # 1 well beyond 200m depth

(i) Well up to 200meter depth, For 1 No. test tube-well. 200.00 rm.

(ii) Well beyond 200 meter depth, For 2 No. test tube-well. 30.00 rm.

b) For borehole # 2( If necessary)well beyond 200m depth

(i) Well up to 200 meter depth, For 2 No. test tube-well. 200.00 rm.

(ii) Well beyond 200 meter depth, For 1 No. test tube-well. 30.00 rm.

file:///conversion/tmp/scratch/365023380.xls 22 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
6 Furnishing design of a production well by testing of water and
soil samples from a test bores up to 350m depth collecting
samples of water from the best suitable aquifer, filling in
sterilized air-tight glass bottles having no air space inside;
collecting soil (sand, solids etc) at 3 m interval and at each
change of soil strata from the bores, arranging them in the cell of
a box in an orderly manner. carrying out test of water for (1) pH,
(2) CO2 (3) Chloride, (4) Fluoride, (5) Iron, (6) Manganese, (7)
Nitrate-Nitrogen, (8)Total alkalinity, (9) Total hardness, (10)
Arsenic, (11) Turbidity, followed by test reports along with
Bangladesh Standards of potable water and (12) Sieve analysis
on soils throughout a bore, leading to ascertain the best suitable
sustained aquifers, depths and slot sizes of strainer, types and
dia of tube well for specific yield, thickness of shrouding around
strainer, fineness modulus of shrouding materials, mechanical
units (pumps, compressor) for testing and operation of the tube
well, maintaining test bore functional till tube well installation,
testing etc. is finished, finally filling and sealing the

left over test bore permanently, including carrying water and soil
samples under direct responsibility of Engineer-in-charge to
BRTC, BUET or other reputed laboratory, approved by the
authority, submitting the report and design details all complete
and accepted by the Engineer and maintaining the mobilized
tools and plant at site till satisfactory test results are found (if not,
next test bore may be executed with the approval of concern
S.E. / Design Office)Total No. of test on water: 11 types of test x
1 test bore x one set sample (3 specimen) = 11 Nos. test (each
specimen 1.5 liter of water)Sieve analysis: min 9 Nos. Sample x
one test x One bore = 9 Nos. test (Samples are of 1 kg dry wt.
each)"There are about 55 (fifty-five) tests for potable water
Quality Standard according to Bangladesh Environment
Conservation Rules-12 (Schedule-3), 1997, under ECA 1995 of
Ministry of Environment and Forest. Therefore, additional test/
tests on water or sieve analysis of soil if required, other than the
above specified 12
(twelve) tests,

may be carried out for public interest as per direction of the


design engineer on actual payment including profit, VAT and all
other charges.
a) For borehole # 1 furnishing design considering 1 no 1.00 each
test

b) For borehole # 2( If necessary) 1.00 each

7 Mobilization: Preparation for installation of tube-well and 1.00 Per set


transportation of complete boring equipments, labour and
materials to the work site and remove the materials after
completion of the works. Installation of drilling rig and
accessories, making arrangements for electricity, water, labour
shed, site office and stores, digging mud pit etc, leveling,
dressing and clearing of the site as per original condition and a
testing for discharge using minimum 1000 liter water tub etc. all
complete as per specifications and accepted by the Engineer.Up
to 200m depth.

file:///conversion/tmp/scratch/365023380.xls 23 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
8 Preparation and making gravel pack around the tube well 35.00 cum.
fixtures with supply of designed graded pea gravels free from
any substance harmful to pipe and health confirmed by test
(Passing through 10 mesh and retained on 40 mesh) including
sieving, washing etc. complete as per standard specification and
accepted by the Engineer. (The rate is inclusive of the cost of
extra amount required for caving and extra depth below the tube
well fixtures, shrouding should not be more than 15 m above the
strainer and measurement should be allowed from bottom of the
tube-well fixture to top of the gravel pack)

9 Making a sanitary seal up to a minimum depth of 6 meter from 4.10 cum.


G.L. or as specified including the supply of approved quality of
cement, sand and khoa (12 mm down graded) in ratio (1:1:5:3)
as per standard specification and accepted by the Engineer.

10 Boring: Execution of 800 mm dia boring through all sorts of


strata by reverse circulation or any other approved method
(Method other than reverse circulation is to be applied only for
wells deeper than 152 meter). For boring 800 mm dia vertical
hole up to designed depth and collection of soil samples at every
3 meter interval and at every change of formation including
sinking and withdrawing necessary casing pipe and all
necessary arrangements complete as per specification and
accepted by the Engineer. (Measurement will be allowed form
G.L. to bottom of the blind pipe and the rate is required for
caving and siltation)

From 0 m to 50 m = 50 m 50.00 rm.

From 50 m to 100 m = 50 m 50.00 rm.

From 100 m to 152 m = 52 m 52.00 rm.

From 152 m to 200 m = 48 m 48.00 rm.

From 200 m to 250 m = 50 m 50.00 rm.

11 Supplying the following tube-well fixtures and Pipes conforming


to standard BS-1387 & BDS -1031, having chemical composition
(in %) carbon 0.17-0.25, manganese 0.95-1.20, sulphur 0.060
max ,Phosphorous 0.060 max, Tensile properties : Minimum
Yield strength 188 MPa Minimum strengh 313 MPa and marking
for a) Manufacturer b) Material c) Wall thickness d) Nominal out
side dia e) Intended use etc. on the body of the pipe at working
site as per standard practice and accepted by the engineer.

a) 200 mm dia MS cap 6 mm thick for blind pipe / sand trap. 1.00 each

file:///conversion/tmp/scratch/365023380.xls 24 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
b) 3m long 200 mm dia heavy type GI pipe (National tube or 3.00 rm.
equivalent) with one end sealed with welded 6mm thick steel
plate ( Bail plug) and other end with thread and socket joint or
similar.

c) 200 mm dia strainer of Slot as per design including taging 50.00 rm.
4 Nos 12 mm dia MS rod continuously. Stainless steel strainer
of continuous slot .The stainer shall be Johnson (foreign made)
or equivalent product having a minimum weight of 12.3 kg per
meter. Based on design of Tube well.

200 mm dia 6 mm thick tube well pipe and blank G.I. pipe of wt. 15.00 rm.
33.45 kg per meter can withstand minimum 700 psi hydraulic
pressure.
200 mm x 450 mm dia 6 mm thick M.S. reducer. 1.00 rm.

450 mm dia 6 mm thick M.S. housing pipe (Seamless) 107.00 rm.

12 Complete installation of 200 mm dia deep tubewell fixtures 160.00 rm.


such as expanded top pipes, reducer, tube well pipes, strainer,
blind pipe, pipe caps etc. fitting,and fixing socket ,welded and
additional welding with fibre and placing in position with proper
size MS centralizer @ 3 metre c/c in strainer position including
blind pipe etc. complete as per standard practice and accepted
by the Engineer.

13 Complete development of the tube well by suitable air


compressor and pump of suitable capacity by alternate surging
and pumping until satisfactory yield, sand free water and the
turbidity condition is reached using necessary quantity of calgon
and conducting step draw down test before and after the
development as per specification and accepted by the Engineer.
(Development should be started within 24 hours of completion of
shrouding).

Wells up to 200 m depth 1.00 each

14 Collection of water samples (Post Development) 3 hours after 1.00 L.S


continuous pumping in 1.5L clean plastic mineral water bottles
(acidified 1 bottle and completely filled non-acidified 5 bottles) as
per standard practice and direction of the Engineer-in-Charge.
Transportation of the water samples on the same day of
collection from the field to BUET laboratory with proper
identification/depth and direction of the Engineer-in-Charge for
water Quality test as per following specification. (Ref:
Technical Specification, Clause # 7A.8)

15 Long term pumping test of the well by turbine/submersible 72.00 hours


pump of required capacity through testing & measuring
equipment including supply of all materials for determining flow
and yield for 72 hours. Conducting draw down and recovery test
etc. complete as per standard practice and direction of the
Engineer-in-Charge. (Ref: Technical Specification, Clause #
7A.6.1.2)

16 Disinfections of the well including supply of sufficient quantity of 1.00 each


bleaching powder (33% strength) chlorinated water having 150
ppm available free chlorine complete as per standard
specification and accepted by the Engineer.

file:///conversion/tmp/scratch/365023380.xls 25 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
17 Filling of the borehole around the tube well from top of the 90.00 rm.
shrouding up to the bottom of sanitary seal by withdrawn
selected soil or local clay free from any substances harmful to
pipes and health as per standard specification and accepted by
the Engineer.

18 Water jetting / positive back wash air lift development using 45.00 rm.
fresh water etc. All completer as per specification and direction
of the E/C.
19 Supplying the following tube-well fixtures at working site as
per standard practice and accepted by the Engineer.(The
quantity of materials will be decided on the basis of final design
of production Tube well)

75 mm dia 4.85 mm thick tube well pipe and blank G.I. pipe 3.00 rm.

Centralizer made with 12 mm dia M.S. rod of approved design 20.00 each

500 mm dia M.S. cap of 6 mm thick for housing pipe covering. 1.00 each

20 Verticality test of the well including supplying verticality test 1.00 L.S
equipment, labour, etc. after sinking of the well but before
placement of the shrouding materials and after completion of the
well including rectification of any deviation from the specified
limit etc. all complete as per specification and direction of the
Engineer-in-Charge. (Ref: Technical Specification, Clause #
7A.5.3).

21 Making a clay seal above the filter pack with clay balls made of 1.00 L.S
50% local puddled clay (clay mixed with 3-5% puddloo) and 50%
bentonite as per specification and direction of the Engineer- in
Charge and as per attached Drawing (Up to 10m of housing
pipe).

Total (Tk)

TOTAL
DEEP TUBE WELL A

DEEP TUBE WELL B

Total Taka (In figure)-------------------------------------------------


(In Words)-------------------------------------------------
N.B. Rate must be quoted both in figures and in
words.
SIGNATURE OF THE CONTRACTOR.
ADDRESS.

..

..

file:///conversion/tmp/scratch/365023380.xls 26 of 27
Sl.
DESCRIPTION OF ITEMS QTY. UNIT RATE (TK.) AMOUNT (TK)
No.
..

Chief Engineer
BUET, Dhaka.
SAE (C-5) SDE (C-3) XEN (C-2) SE (C-1)

file:///conversion/tmp/scratch/365023380.xls 27 of 27

Potrebbero piacerti anche