Our Project Plan

Shown as a Gantt Box Chart


31-May 14-Jun 28-Jun 12-Jul 26-Jul 9-Aug 23-Aug 6-Sep

Project Kickof

Gather Requirements

Design Module 1

Design Module 2

Develop

Test

Implement

Task Start Best Case Realistic Worst Case BC


Project Kickof 1-Jun-16 5-Jun-16 9-Jun-16 14-Jun-16 4
Gather Requirements 6-Jun-16 13-Jun-16 18-Jun-16 23-Jun-16 7
Design Module 1 11-Jun-16 17-Jun-16 20-Jun-16 27-Jun-16 6
Design Module 2 11-Jun-16 16-Jun-16 19-Jun-16 26-Jun-16 5
Develop 20-Jun-16 29-Jun-16 15-Jul-16 22-Jul-16 9
Test 21-Jul-16 27-Jul-16 29-Jul-16 5-Aug-16 6
Implement 8-Aug-16 14-Aug-16 16-Aug-16 23-Aug-16 6

42521
31-May-16 40413
How to use this?

1) Set up your project plan using the


table in row 6
2) Just enter first 5 columns of dates
9-Aug 23-Aug 6-Sep 3) Last 3 columns are calculated. Do
not mess with them.
4) If you have Excel 2007 or above, the
calculated columns should
automatically update when you add
new rows to the table.
6) The chart now shows the project
plan as a Gantt Box Chart
7) Adjust horizontal / date axis scaling
and major units to see dates clearly.

For more info. visit:

http://chandoo.org/wp/2010/07/09/g
antt-box-chart-proposal/
http://chandoo.org/wp/2010/07/12/g
antt-box-chart/
R W
4 5
5 5
3 7
3 7
16 7
2 7
2 7