GL C.5 - G.5 b. EPS Cladding 10.00 c. Rasping/Grooving 7.00 d. Base Coat 10.00 e. Finisher Applicatio 10.00
3 FRONT ELEVATION a. Scaffolding Install 5.00
GL J - L b. EPS Cladding 7.00 c. Rasping/Grooving 5.00 d. Base Coat 7.00 e. Finisher Applicatio 7.00
4 RIGHT SIDE ELEVATION a. Scaffolding Install 7.00
GL 4 - 8.3 b. Light Gauge Frami 10.00 c. Ficem Board 10.00 d. EPS Cladding 10.00 e. Rasping/Grooving 7.00 f. Base Coat 10.00 g. Finisher Applicatio 10.00
5 RIGHT SIDE ELEVATION a. Scaffolding Install 5.00
GL 8.3 - 10 b. EPS Cladding 7.00 c. Rasping/Grooving 5.00 d. Base Coat 7.00 e. Finisher Applicatio 7.00
6 LEFT SIDE ELEVATION a. Scaffolding Install 5.00
GL 8 - 10 b. EPS Cladding 7.00 c. Rasping/Grooving 5.00 d. Base Coat 7.00 e. Finisher Applicatio 7.00
7 LEFT SIDE ELEVATION a. Scaffolding Install 7.00
GL 4 - 8 b. EPS Cladding 10.00 c. Rasping/Grooving 7.00 d. Base Coat 10.00 e. Finisher Applicatio 10.00 PURCHASE ORDER AREA