Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
ThyssenKrupp Uhde
2
Table of contents
1. Company profile 3
6. Recent references 27
3
1. Company profile
With its highly specialised workforce of more than 4,500 employees
and its international network of subsidiaries and branch offices, Uhde,
a Dortmund-based engineering contractor, has to date successfully
completed over 2,000 projects throughout the world.
Ever since the company was established in 1921, Uhde In recent years, ammonia plant technology has under-
has been involved in the design and construction of gone radical developments in terms of both design and
ammonia plants and has played a leading role in the equipment. In order to improve plant efficiency, efforts
development of ammonia technology. As far back as have had to be focused on reducing power consump-
1928, the first ammonia plant to use an Uhde propri- tion, improving process heat recovery, minimising stack
etary process went on-stream at the site of the Mont- losses and cutting energy consumption for CO2 removal.
Cenis coal mine at Herne-Sodingen. The plant had an
output of 100 mtpd of ammonia and comprised four Uhdes objective of making a substantial improvement
reactors with a capacity of 25 mtpd each, the loop oper- in energy efficiency has relied heavily on experience and
ating at a pressure of 100 bar. involved a broad spectrum of technical expertise including
a technical review of process design, engineering design,
The fact that the first Uhde-engineered ammonia reac- research and development and the evaluation of operat-
tors were equipped with an internal heat exchanger and ing data. Equally important has been the enhancement
a synthesis loop with an integrated two-stage refrigera- of plant operability and reliability. Hence, much attention
tion unit deserves a special mention. Unfortunately, this has been paid to past successful experience and proven
efficient system was soon considered outdated, and it energy-saving features.
was not until the seventies that these design principles
were taken up again. In 1998, Uhde joined forces with Synetix, now Johnson
Matthey Catalysts (JMCatalysts), to further improve the
Rising energy prices have posed an increasing challenge Uhde ammonia process. This partnership builds on the
for ammonia plant designers since this period. As early traditional strengths of the two companies and takes
as 1968, Uhde took up the challenge and engineered a advantage of JM Catalysts know-how in catalysis, am-
plant with an energy consumption of only 7.8 Gcal per monia plant operation and support services together
tonne of ammonia. with Uhdes experience in design, engineering and project
execution. The partnership allows strong collaboration
This natural gas-based plant with a capacity of 880 mtpd between JM Catalysts and Uhde engineers so that the
incorporated the following essential elements for reduc- Uhde ammonia process can be further optimised to take
ing energy consumption: best advantage of the latest high-performance catalysts
from JM Catalysts, thus improving efficiency and lowering
Maximum heat recovery from the primary reformer cost.
flue gas by cooling it to 135C at the stack inlet.
The most recent successful implementations of the Uhde
Preheating of the combustion air for the primary ammonia process include a plant in Turkmenistan with
reformer. a capacity of 600 mtpd, a 2,000 mtpd plant for Qatar
Fertiliser Co. (QAFCO) in Mesaieed, Qatar, and five
Generation of 125 bar steam from process waste 1,200 mtpd plants in Egypt, where three more 1,200
heat downstream of the secondary reformer and in mtpd plants based on the Uhde ammonia process are
the ammonia synthesis unit. also under construction.
High-pressure steam superheating with waste A new milestone in ammonia technology has now been
process heat downstream of the secondary reformer. achieved with the plant built for Saudi Arabian Fertilizer
Company (SAFCO) in Al Jubail, Saudi Arabia. It is the
Three-bed ammonia reactor with heat exchangers first plant to be based on the "Uhde Dual Pressure Pro-
between catalyst beds. cess" and, with a single-train capacity of 3,300 mtpd, it
is by far the worlds largest ammonia plant. It has been
All subsequent ammonia plants designed by Uhde have in operation since 2006. A second plant of this type is
incorporated most of these low-energy features. now under construction in Ras As Zawr, Saudi Arabia.
5
The adjacent block diagram of an Uhde The following process areas have under-
ammonia plant shows the conventional se- gone major modifications in order to achieve
quence of process steps that form the basis these figures:
of most present-day ammonia processes.
However, ammonia processes cannot be The steam reforming section including
judged solely on the basis of a block dia- its waste heat recovery system.
gram. A more detailed scrutiny of the facts
and figures shows that what appears to The CO2 removal unit.
be a conventional set-up is in fact a most
up-to-date ammonia plant concept. The ammonia synthesis unit.
The total consumption figure (feed+fuel+ Assuming the reader to be familiar with the
electric power) per metric ton of am monia fundamentals of ammonia technology,
produced is in the range of 6.6 to 7.2 Gcal attention in the following sections has been
(27.6-30.1 GJ), depending on local con- restricted to those aspects specific to the
ditions (e.g. cooling water temperature) and Uhde low-energy concept.
project-specific requirements (such as the
natural gas price, etc.).
Desulphurisation
Fuel Process steam
Combustion
Primary reformer
air
Process air
Secondary reformer
HP steam
superheated
BFW
CO shift
CO2
CO2 removal
Methanation
Syngas compressor
HP steam to
superheater
Product
Refrigeration NH3 synthesis
NH3
Block diagram
of an Uhde ammonia plant
8
Primary and secondary The following modifications to conventional plant Increase in the feed/steam mixture preheat tem-
reformer of the AFC
designs have contributed to improvements in overall perature. This reduces the firing requirements in the
ammonia plant in Egypt.
efficiency: primary reformer by shifting the heat transfer duty
from the radiant section to the convection section.
Shift of part of the reforming reaction from the
primary to the secondary reformer as a result of the Decrease in the steam-to-carbon ratio to 3.0. This
following measure: includes an adequate safety margin against the
formation of carbon deposits on the primary refor-
Installation of a purge gas recovery unit, by means mer catalyst. Reducing the admixture of steam to
of which hydrogen is recycled to the suction side of the feed results in less heat being absorbed in the
the syngas compressor, thereby allowing operation primary reformer radiant section and therefore lower
of the secondary reformer with excess air while the fuel consumption. Nevertheless, the steam-to-gas
hydrogen-to-nitrogen ratio of the make-up gas is ratio is high enough to minimise by-product forma-
kept close to 3:1. tion in the HT shift through the use of commercially
proven catalysts.
Preheating of the process air for the secondary
reformer to a higher temperature (540C). Shifting The process data of the reforming section are
part of the reaction to the secondary reformer leads summarised below:
to lower operating temperatures in the primary re-
former and therefore to fuel savings. Steam/carbon ratio 3.0
Feed/steam, primary reformer inlet C 530-580
Optimum use of the reduced primary reformer load
Pressure, primary reformer exit bar 39-43
is achieved by increasing the reformer pressure to
about 40 bar whilst maintaining the estimated life- Methane, primary reformer exit vol.% 10-13
time of the reformer tubes at 100,000 hours. This
Methane, secondary reformer exit vol.% 0.3-0.6
step entails a reduction in overall energy consump-
tion as the aggregate power required for the com- Process air temperature C 520-600
pressors is reduced. Combustion air temperature C 250-440
125 bar steam, superheated C 530-540
Stack temperature C 120-180
9
Special mention should be made of an essential item A superheater of this type was installed by Uhde for the
of equipment in the steam reforming section: the steam first time in the Gewerkschaft Victor plant, which went
superheater, located in the process train downstream of on stream in 1970. This same design configuration was
the secondary reformer. also used for the CIL plant in Canada (on-stream since
1985) and is now the superheater of choice in all of the
In a low-energy plant, the objective is to recover as ammonia plants recently built by Uhde. On the one hand,
much heat as possible from the convection section for this arrangement provides the necessary flexibility to
direct process use, thereby reducing the fuel require- adapt the plant to any given set of process requirements,
ment. This reduces the heat available in the convection and on the other, it enables the steam system to operate
section for superheating HP steam. The balance of the safely under any normal, or abnormal, operating con-
energy required for this purpose is therefore recovered ditions.
in the superheater downstream of the secondary re-
former. The duty of this superheater is in the range An internal bypass in the evaporation section permits
of 15 to 40% of the heat available between secondary the shifting of heat transfer duty between the evapora-
reformer exit and HT shift inlet, depending on the pro- tor and the steam superheater. In normal operation, the
cess parameters selected. internal bypass remains partially open. By closing it, the
gas temperature at the superheater inlet can be re-
The lower the consumption figure, the more process gas duced, thus increasing steam generation. This is impor-
heat is utilised to superheat the HP steam, whereas the tant in overcoming partial plant failures, e.g. in the case
total HP steam generated is reduced. In other words: of a loss of steam production in the ammonia synthesis
fuel savings also reduce the net energy export. section.
Steam reforming
and CO shift
Fuel HP steam
Secondary
reformer
Steam drum
Reformer HP steam
Desulphurisation superheater
Process
gas cooler
HP steam
Feed
MP steam
LT shift HT shift
Process air
Combustion air
Various chemical and physical absorption systems are The design selected incorporates a two-stage absorber.
available for the removal of CO2, e.g. aMDEA, Benfield, Most of the CO2 is removed in the lower part using a
Amine Guard and Selexol. Uhde has used all these pro- semi-lean solution that has been regenerated in a two-
cesses in the past and has the experience of many years stage flash loop without any need for stripping energy.
of commercial operation. The lowest energy consumption Final purification to the ppm range then takes place in
is achieved using the activated aMDEA process licensed the upper part of the absorber with a relatively small por-
by BASF. The key to these energy savings is that the tion of the total circulating solvent. It is only this portion
solution is primarily regenerated by flashing rather than that has to be thermally regenerated by a stripping pro-
steam stripping. cess in a reboiling column. This process scheme permits
a reduction in the specific energy consumption of the
The activated aMDEA process uses a solution of N-me- CO2 recovery system to 1,340 kJ/Nm3 of CO2 (13,000
thyldiethanolamine and water with a special activator as BTU/lb mole of CO2).
Flash
vessel
Stripper
aMDEA CO2
removal system Process gas
the solvent. As the aMDEA solution isotherms for CO2 In addition, the process offers the following advantages:
are between those of a typical chemical solvent and a
physical solvent, this process combines the benefits of High CO2 recovery rate (> 96%) and CO2 purity
both chemical and physical CO2 removal processes. (> 99% by volume).
No toxic solvents.
No crystallisation problems.
11
The most fundamental improvements to earlier designs magnetitebased catalysts in all three beds. The first of
have been effected in the ammonia synthesis unit. the three beds will typically be filled with prereduced
catalyst to accelerate the initial start-up.
The main feature of this unit is its high conversion rate
which is achieved by a large catalyst volume. In order to Depending on the site-specific and project-specific con-
minimise reactor size and cost while keeping the pres- ditions, the three catalyst beds are arranged in either
sure drop low, the large catalyst volume requires: one or two ammonia reactors.
The use of small grain-size catalyst. Designs with one ammonia reactor and one waste heat
boiler cannot optimally exploit the reaction heat for the
Application of the radial-flow concept in the generation of high-pressure steam. However, optimum
ammonia reactor. heat recovery can be achieved if an additional waste heat
boiler is introduced between the second and third bed.
HP steam
This arrangement improves the gas-side temperature of
the boilers and provides an additional advantage in that
it permits a higher boiler feed water temperature at the
Purge
Ammonia
converter
C.W.
NH3
BFW (liquid)
Make-up gas Syngas compressor
Ammonia synthesis
Uhde has always advocated three-bed reactors with high boiler inlet, which means that the preheating of the boiler
ammonia conversion rates per pass. Therefore, the Uhde feed water can be enhanced by using the low-level heat
ammonia synthesis unit is based on a three-bed reactor available in other plant sections, for example downstream
system, each bed with a radial flow. A high-conversion of the LT shift.
synthesis loop offers considerable advantages since the
recycle gas quantity is considerably reduced and, conse- The effect of a two-boiler system on high-pressure steam
quently, power requirements for the circulator are lower generation is significant:
and heat exchanger surfaces smaller. Refrigeration re- it is increased from 1.1 to 1.5 t/t of ammonia. The pro-
quirements also decrease overproportionately because cess parameters of the synthesis loopdesign are shown
most of the ammonia produced is condensed upstream below:
of the loop chiller.
H2/N2 ratio, methanation exit 2.95
Studies on innovative high-activity precious-metalbased Synthesis loop pressure bar 140-210
catalysts have revealed that no economic advantage can
be gained through their use in view of the uncertainty of NH3 reactor inlet vol.% 3-5
future prices for the precious metals required. Further- NH3 reactor outlet vol.% 20-25
more, due to the different physical properties operational
HP steam generation t/t NH3 1.1-1.5
problems can be expected. For maximum reliability and
cost-effectiveness Uhde therefore uses only well-proven Number of reactors 1 or 2
12
HP steam header
112 bar, 530 C
Turbine syngas compressor
Steam drum
125 bar
Process gas
NH3
Process gas synthesis Process gas
LP steam header
The diagram shows the heat management system The superheated steam is expanded in the highpressure
underlying Uhdes low-energy ammonia plant concept, part of the syngas compressor turbine and fed to the
the essence of which is the optimum utilisation of medium-pressure system.
process waste heat for the generation of superheated
high-pressure steam. Medium-pressure steam at 49 bar, 415C, is used as
process steam or for the following equipment:
High-pressure boiler feed water is heated in a first step
downstream of the LT shift; the stream is then split into Condensing turbine driving the syngas
two, one part-stream going to the ammonia synthesis compressor.
unit and the other to the HT shift for further preheating.
Condensing turbine driving the process air
High-pressure steam is only generated from process compressor / alternator.
waste heat at two locations:
Back-pressure turbine driving the boiler feed
Downstream of the secondary reformer. water pump.
In the ammonia synthesis unit. Depending on the plant requirements, the process air
compressor turbine or the refrigeration compressor
Superheating of high-pressure steam takes place turbine can be fed with HP-steam. All other machines
downstream of the secondary reformer and in the are driven by electric motors.
primary reformer convection bank.
13
Chemical plant capacities have for a long time been nia process. The high synthesis loop pressure is
taking on ever greater dimensions. The reason lies in achieved through a combination of the chilled second
the reduction of the specific production costs through casing of the syngas compressor and a slightly
economies of scale. More than ever before, the plant elevated front-end pressure. In this conventional am-
construction sector is facing the challenge of exploiting monia synthesis loop the remaining two thirds of the
this advantage while at the same time continuing to total ammonia is produced.
employ proven technologies and equipment.
Technology highlights
Uhde and Johnson Matthey Catalysts have risen to this
challenge and developed a process based on existing Well-proven magnetite-based catalysts can be used
technology which now enables ammonia plants to pro- in all stages of the new process.
duce very large capacities. This new process (see flow-
sheet) delivers a capacity of 3,300 mtpd using well- Energy efficiency is improved by 4% compared to the
tried and tested equipment. It also provides the basis conventional Uhde process.
for even larger plants (e.g. 4,000-5,000 mtpd).
A high conversion rate in the high-pressure synthesis
The first plant based on this process is the SAFCO IV loop combined with the reduced production require-
ammonia plant in Al-Jubail, Saudi Arabia. With a ca- ment results in reduced piping sizes in the high-pres-
pacity of 3,300 mtpd it is by far the largest ammonia sure loop. Standard piping can be used for capacities
plant worldwide. The plant has been in operation since of 4,000 mtpd and more.
2006. Engineering for the next plant using the dual-
pressure process is ongoing. The syngas compressor of a 3,300 mtpd dual-
pressure plant is the same size as that in current
The key innovation in Uhdes new dual-pressure ammo- 2,000 mtpd ammonia plants; several reference
nia process is an additional medium-pressure once- compressors are in operation.
through ammonia synthesis connected in series with
the conventional high-pressure ammonia synthesis loop Only 2/3 of the hydrogen recovered from the purge
as follows: gas has to be recompressed to the loop; 1/3 is con-
verted to ammonia in the once-through synthesis.
1. The once-through ammonia synthesis involves the
compression of the make-up gas in a two-stage The process design is extremely flexible with a large
inter-cooled compressor. This is the low-pressure number of process parameters available to optimise
(LP) casing of the syngas compressor. The pressure the use of catalyst and machinery.
at the discharge of the compressor is about 110 bar.
At this pressure the three-bed, inter-cooled, once- It is now possible to achieve a synthesis capacity of
through converter produces approximately one third about 3,300 mtpd of ammonia using conventional
of the total ammonia output. The syngas-ammonia equipment and catalysts that have proved to be reliable
mixture leaving this converter is cooled and 85% of and efficient in existing plants.
the ammonia produced is separated from the gas as
liquid. There are no major deviations from proven process
conditions.
2. The remaining syngas is then compressed in the
high-pressure (HP) casing of the syngas compressor The front-end of the plant is very similar to the current
to the operating pressure of the ammonia synthesis Uhde design except that it operates at a pressure of
loop (up to 210 bar). Since the syngas has been about 3 bar higher, a process condition which is well
cooled down the HP casing can operate at a much within Uhdes proven long-term design and operating
lower temperature than in the conventional ammmo- experience.
15
Off-gas
Second
ammonia
converter PGR unit
LP HP Once-through Ammonia
casing casing ammonia converters from
Note: Molecular HP loop
sieves (dryers) CW
not shown
NH3 NH3 chiller
chiller
HP
steam
H 2O
CW
Make-up gas from front-end NH3 chiller Ammonia from once-through conversion NH3
A good process alone is not sufficient. Primary reformer with a cold outlet manifold system.
Secondary reformer
Burners
Process air
Catalyst bed
Gas outlet
The primary reformer is a furnace in which a multiplicity Small number of burners (in comparison with a
of tubes filled with catalyst are heated by burning fuel. side-fired reformer).
The process gas temperature required at the outlet of
the catalystfilled tubes is about 800C at a pressure of Internally-insulated cold outlet manifold system made
approximately 45 bar. Inevitably, the service life of com- from carbon steel and located externally under the
ponents such as the reformer tubes is limited. Material reformer bottom.
deterioration occurs through the combined effects of
creep, alternating thermal and mechanical stresses, ex- Internally-insulated reformer tube-to-manifold con-
ternal and internal oxidation and carburisation. nection which operates at moderate temperatures.
Consequently, the furnace designer is faced with two Each tube row is connected to a separate outlet
main tasks: manifold.
Firstly, to minimise the number of components sub- Advantages of the Uhde reformer:
ject to wear and tear due to the combined effects of
high temperatures and pressures. No high-alloy outlet pigtails and/or outlet manifolds
or risers which work at creep conditions.
Feed/steam
Secondly, to allow as smooth and safe an operation
as possible. Minimum number of components exposed to the
severe process conditions.
Furnace arch The following main features show Uhdes approach to
fulfilling the above requirements: Uniform temperature profile over the entire length
Reformer tube
of the reformer tube with the lowest possible peak
Top-firing for an optimum uniformity of the tube skin temperature, resulting in optimum utilisation of the
Fire box
temperature profile. reformer tube material.
Catalyst grid
The process gas outlet temperature is monitored for
each tube row and is adjustable during operation for
Skin temperature
profile optimum reformer performance and temperature
Bellow
uniformity.
Gas conducting tube Almost unlimited service life of the Uhde outlet mani-
fold system with no maintenance required other than
Shop weld
painting.
Field weld
Carbon steel
Considerable operational allowance of the outlet
Refractory manifold system with regard to process gas tem-
perature and pressure.
300 600 900 More than 60 reformers of this type have so far been
Skin temperature [C]
Outlet manifold designed and constructed since 1966. All have given
excellent performance. The two largest units are
equipped with 630 and 960 tubes, respectively.
The burners.
Features of the Uhde process gas cooling train Advantages of the horizontal fire-tube boiler:
Tube inlets protected by ferrules to limit the head flux No heated dead ends on water side where debris
at the tube inlet. can settle.
Double layer refractory lining for the inlet and, if Low metal temperatures at and near tubesheets due
necessary for the outlet chamber with high duty bricks to efficient insulation and ferrules.
on the hot surface.
Simple and reliable process gas temperature control.
Internal gas bypass for temperature control with
steam cooled damper blades. Easy access for inspection and maintenance.
Steam drum mounted on top of the boiler and Low erection costs due to shop assembly of boiler
supported by downcomers and risers. and drum.
Process gas inlet and outlet at the bottom. Coil designed for high mechanical flexibility.
Preferably vertical arrangement of the super- Thermal expansions compensated within the coil.
heating coil.
Safe metal temperatures maintained by efficient
Pressure shell in contact with the cooled process bypass control.
gas only.
Temperature of the pressure-bearing shell governed
Internal bypass for temperature control. by cooled outlet gas.
Fertiliser complex of The demand for energy-efficient Features of the Features of the
EFC in Ain Shukna ammonia production dictates the single-converter design: two-converter design:
(near Suez), Egypt.
following criteria for the design
Capacities: of the ammonia synthesis unit: Heat exchanger between Location of the first two
1,200 mtpd of ammonia catalyst beds for indirect catalyst beds in the first
1,925 mtpd of urea High conversion rates and cooling of synthesis gas; converter vessel and of the
2,000 mtpd granulation unit therefore large catalyst consequently, highly-efficient third bed in the second
volume. temperature control. converter vessel.
Maximum utilisation of Radial flow from outside to Radial flow from outside to
reaction heat for the genera- inside through all catalyst inside through all catalyst
tion of high-pressure steam. beds. beds.
Low pressure drop in the Design adaptable to full-bore Simple U-tube heat ex-
loop. or drawn-in top closure of changer between first and
converter, depending on pro- second catalyst beds for
Such criteria, in turn, ject constraints. indirect cooling of the
call for the: synthesis gas.
Heat exchangers extractable
Use of small grain-size without removal of cartridge. Design adaptable to full-bore
catalyst. or drawn-in top closure of
An externally-arranged BFW converter, depending on
Application of the radial-flow preheater/HP steam boiler project constraints.
principle. downstream of the third bed.
Second bed
Second bed
Third bed
Left:
Three-bed ammonia
converter, radial flow
Right:
Ammonia converter I, radial flow,
catalyst beds 1 and 2
Third bed
BFW inlet
Ammonia converter II ,
radial flow, catalyst bed 3 Gas Gas outlet HP Steam boiler
inlet
Capacities:
2,000 mtpd of ammonia
3,200 mtpd of urea
3,500 mtpd granulation unit
Utilities
Cooling water ( T = 10 K) .......................mt ............... 120 .......to.. 260
Demineralised water (net cons.) ...............mt ................... 0.65 ..to...... 0.75
Effluents
Treated process condensate(3) ..................mt ................... 0.85 ..to ..... 1.15
Product Quality
Ammonia content ...................................% by wt. ........ 99.8 ....to...100.0
Water content .......................................% by wt. ........ 0.0 ....to...... 0.2
Oil content ............................................ppm by wt. ...............max. ... 5
(1)
expressed as lower heating value of natural gas per ton of ammonia
(2)
electric power and steam export converted into fuel equivalents
(3)
routed back to the demineralisation unit for re-use
All consumption figures are per metric ton of liquid ammonia and serve as general information only.
Local climatic conditions and gas composition may have a considerable influence on the performance figures.
26
Uhde is dedicated to providing its customers with a Uhdes policy is to ensure utmost quality in the im-
wide range of services and to supporting them in their plementation of its projects. We work worldwide to
efforts to succeed in their line of business. the same quality standard, certified according to:
DIN/ISO 9001/EN29001.
With our worldwide network of local organisations and
experienced local representatives, as well as first-class We remain in contact with our customers even after
backing from our head office, Uhde has the ideal quali- project completion. Partnering is our byword.
fications to achieve this goal.
By organising and supporting technical symposia, we
We at Uhde place particular importance on interacting promote active communication between customers,
with our customers at an early stage to combine their licensors, partners, operators and our specialists. This
ambition and expertise with our experience. enables our customers to benefit from the development
of new technologies and the exchange of experience as
Whenever we can, we give potential customers the well as troubleshooting information.
opportunity to visit operating plants and to personally
evaluate such matters as process operability, main- We like to cultivate our business relationships and learn
tenance and on-stream time. We aim to build our future more about the future goals of our customers. Our
business on the confidence our customers place in us. after-sales services include regular consultancy visits
which keep the owner informed about the latest devel-
Uhde provides the entire spectrum of services asso- opments or revamping options.
ciated with an EPC contractor, from the initial feasibility
study, through financing concepts and project manage- Uhde stands for tailor-made concepts and international
ment right up to the commissioning of units and grass- competence. For more information contact one of the
roots plants. Uhde offices near you or visit our website:
Utilities/offsites/infrastructure
Procurement/inspection/transportation services
Commissioning
6. Recent references
E Engineering
P Procurement
C Construction
Uhde
Friedrich-Uhde-Strasse 15
44141 Dortmund, Germany
Tel.: +49 231 5 47-0 Fax: +49 231 5 47-30 32 www.uhde.eu