PROCEDURE FOR
HAZARD IDENTIFICATION & RISK
ASSESSMENT
TABLE OF CONTENTS
1.0 PURPOSE 3
2.0 SCOPE 3
3.0 REFERENCE 3
4.0 ABBREVIATIONS AND DEFINITIONS 3
5.0 PROCESS DESCRIPTION 4
5.1 Initial Hazard Review 4
5.2 Hazard & Risk Identification 4
5.3 Identification of hazards 6
5.4 Establishing Controls 7
6.0 DOCUMENTATION / RECORDS 10
1.0 PURPOSE
To establish, document, implement and maintain a documented procedure for hazard identification &
risk assessment
Page 2 of 10
Mobile Business Company Ltd.
QHSE SYSTEM PROCEDURE
Procedure No. Title Rev No Rev Date
MBZ/HIRA/QHSESP/09 HAZARD IDENTIFICATION & RISK ASSESSMENT 00 01.11.2014
2.0 SCOPE
This procedure covers initial hazard review, risk assessment, evaluation and assessment criteria and
determination of significant risks.
3.0 REFERENCE
MBZ/QHSESM/01 : QHSE System Manual
MBZ/COD/QHSESP/01 : Procedure for Control of Documents
MBZ/COR/QHSESP/02 : Procedure for Control of Records
MBZ/IA/QHSESP/06 : Procedure for Internal Audit
MBZ/ELC/QHSESP/11 : Procedure for Evaluation of Legal Compliance
4.2 DEFINITIONS
Refer QHSE Manual MBZ/QHSESM/01, OHSAS 18001:2007 for list of definitions
Page 3 of 10
Mobile Business Company Ltd.
QHSE SYSTEM PROCEDURE
Procedure No. Title Rev No Rev Date
MBZ/HIRA/QHSESP/09 HAZARD IDENTIFICATION & RISK ASSESSMENT 00 01.11.2014
The HSE team members conduct an IHR by studying all the locations/process areas/activities. The IHR
serves as the basis for identification of preliminary hazards and risks across locations/process
areas/activities. The IHR will be maintained with all respective HSE team members. The IHR consists of
following parameters
Work Activity Hazard Penetration Hazard Machinery Hazard
Dust Hazard Thermal Hazard Electrical Hazard
Fire and Explosion Hazard Chemical Hazard Biological Hazard
Physical Hazard Psychological Hazard Work Environment Hazard
Confined Spaces Hazard Occupational Hazard Ergonomics & Human Behaviour
The data is collected reflecting all the above parameters. This will be documented in the IHR report by
the respective team member. The data collected will be maintained as an input for identification of
hazards and risks at locations/process areas/activities.
Methods:
The HSE team member can either go to the respective locations/process areas/activities to collect the
data or can interact with respective area supervisor / worker to collect the data, Where if they are
involved in the activities / location/ process area, it is the responsibility of the concerned team member
to identify.
Page 4 of 10
Mobile Business Company Ltd.
QHSE SYSTEM PROCEDURE
Procedure No. Title Rev No Rev Date
MBZ/HIRA/QHSESP/09 HAZARD IDENTIFICATION & RISK ASSESSMENT 00 01.11.2014
I. Routine and non routine activities: Routine activities are such as performing an operation or a
process / projects sites. Non-routine activities are such as maintenance or support. The routine and
non-routine activities are indicated in the risk assessment sheet.
II. Contractors and visitor related activities: The contractor activities include man-power, electrical and
mechanical, and other special services. The hazards identification will be covered for routine
operations and contractors activities.
III. Human behavior, capabilities and other human factors: This includes negligence, attitude of people
performing work, knowledge and competence for performing the jobs, safety violations, not wearing
PPE etc.
IV. Hazards and risk originated outside the work place affecting health and safety of persons at the
workplace
V. Hazards created in the vicinity of the work place from work related activities: Focusing the nature
and type of industry located near the vicinity of AGAMEP site locations, analyzing the complexity of
the processes, significant hazards are identified.
VI. Infrastructure, equipment and materials at the workplace provided by customers / contractors.
VII. Temporary changes made and associated impacts towards operations, processes and activities
VIII. The HSE Team will be responsible to make sure that hazards are considered and necessary actions
are taken.
IX. Updates on legal and other requirements
X. Design of work areas, processes, installations, machinery/equipment, operating procedures, work
instructions, including their adaptation to human capabilities: The safety hazards should be
considered while designing the work areas or installation of new machinery / equipment.
XI. Mobilization of projects: Job safety analysis will be submitted as per the client requirements. Where
Representative there is no such requirement exists, risk assessment will be carried out by the site
safety officer and project team involved / appointed for the project.
XII. In case of the applicability to legal requirements the HSE team member shall consult with HR /
Management Representative and suitably mark the applicability. The hazards and risks shall be
reviewed by the HSE team member / Management Representative on following conditions:
Change in layout
Change of any raw-materials / chemicals used
Page 5 of 10
Mobile Business Company Ltd.
QHSE SYSTEM PROCEDURE
Procedure No. Title Rev No Rev Date
MBZ/HIRA/QHSESP/09 HAZARD IDENTIFICATION & RISK ASSESSMENT 00 01.11.2014
(b) Probability (P) This indicates how frequent an hazard occurs (this table remains applicable for
Aspect Impact Determination also)
(c) Rating The rating indicates the multiplication score of severity, probability and
present control. This value is considered to be as Risk Priority Number (RPN)
Page 6 of 10
Mobile Business Company Ltd.
QHSE SYSTEM PROCEDURE
Procedure No. Title Rev No Rev Date
MBZ/HIRA/QHSESP/09 HAZARD IDENTIFICATION & RISK ASSESSMENT 00 01.11.2014
Page 7 of 10
Mobile Business Company Ltd.
QHSE SYSTEM PROCEDURE
Procedure No. Title Rev No Rev Date
MBZ/HIRA/QHSESP/09 HAZARD IDENTIFICATION & RISK ASSESSMENT 00 01.11.2014
Page 8 of 10
Mobile Business Company Ltd.
QHSE SYSTEM PROCEDURE
Procedure No. Title Rev No Rev Date
MBZ/HIRA/QHSESP/09 HAZARD IDENTIFICATION & RISK ASSESSMENT 00 01.11.2014
Competent/
3 Certified / skilled workers deployed for the process
Trained Personnel
Material Safety
4 Display of material safety data sheets at process / work areas
Data Sheets
Master/ regular health checkup, pre-employment health checkup, Inbuilt
5 Medical Plan
occupational health center
Performance
Monitoring and measurement tests such as ambient air quality, water quality, noise
6 monitoring/
and stack monitoring, fork lift and lifting tackles certifications, calibration etc.,
measurement
Work Permits/ Hot , cold, confined spaces, height, work permit and legal compliance and
7 Compliance to monitoring
rules
Hierarchy of controls
While establishing controls or making changes to existing controls, the hierarchy of assigning to a control could be
as follows:
(a) Elimination: Initially the hazards are considered for elimination. Methods and steps will be taken to eliminate
the hazards at source
(b) Substitution: Substituting methodologies are considered in case if the hazards could not be eliminated
(c) Engineering controls: The controls related to changes in machine design or process design is adopted
(d) Administrative controls: The activities could be supervised and governed by procedures or authorized personnel
(e) Personnel protection: Personnel protection is also considered for additional protection of employees
Before arriving at new controls, the existing controls followed will be studied. The control methods listed in this
document applies for assessment. Additional controls apart for this, if any is decided, the same will be documented
in the significant risk assessment report
Communicating and Reviewing Hazards Risks and Controls for Significant Hazards
The HSE Team Member shall circulate the Hazards Identification and Risk Assessment Register and List of
Significant Hazards Register to respective Department Managers/Heads.
Page 9 of 10
Mobile Business Company Ltd.
QHSE SYSTEM PROCEDURE
Procedure No. Title Rev No Rev Date
MBZ/HIRA/QHSESP/09 HAZARD IDENTIFICATION & RISK ASSESSMENT 00 01.11.2014
At the minimum the HSE Team Members shall review Hazards Identification and Risk Assessment Register and
List of Significant Hazards Register based on following conditions:
Change in layout
New project and need for submission for job safety analysis.
Note 2: The review should be carried out once in a year or based on the above change takes place
whichever is earlier.
Page 10 of 10