SL. Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Signing of Contract Agreement
1 byCPC
Submission of detail Project
2 SchedulebyContractor
3 ApprovalofProjectSchedule
HandingoverLandtoContractor
4
5 MobilizationAdvance
Approval of Sub Vendor/sub
6 contractor
7 LevellingofLand
8 SoilInvestigation
9 MasterPlanPreparation
Submission of Drawing
10 submissionschedule
11 SubmissionofDrawing
12 DrawingApproval
Submission of Inspection
13 schedule
14 Inspectionofmaterials
15 Despatchofmaterials
16 SubstationLayout
GISINFOCITYII PACKAGENO23/201213 1/4
Construction Power and water
17 Supply
Construction of Boundary wall,
SiteStore,SiteOffice&Security
18 shedetc.
19 Control Room With Office
20 Building
FoundationofColumn
21 ErectionofColumnandBeam
22 FoundationofEquipment
Erection of Equipment
23 Structures
Bus Bar Stringing, Jumpering,
24 EquipmentConnection
25 InstallationofEquipment
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
26 EarthmatLayingandEarthing
27 CableTrench
28 CableLayingandTermination
Foundation&ErectionofStation
29 Transformer
Sand & Metal spreading / Site
30 surfacing
31 TransformerFoundation
32 ErectionofTransformer.

GISINFOCITYII PACKAGENO23/201213 2/4


Supply&ErectionofFirefighting
33 system
34 SwitchYardIllumination
35 SwitchYardFencing
36 A/csystem
37 ErectionofC.R.Panel
38 Installation of Battery with
Charger
Erection of A.C.D.B. and
39 D.C.D.B.
InstallationofFOTSEquipments
40
41 IlluminationofControlRoom
42 Road
43 Quarters
Drainage system/Rain
44 harvesting
45 Plantation
46 Testing
47 Inspection
48 Metering
49 Commissioning
Material Reconciliation &
50 handingoverofS/s

GISINFOCITYII PACKAGENO23/201213 3/4


WORKSCHEDULE/BARCHARTFOR220KV&132KVTRANSMISSIONLINEPROJECTCOMPLETIONPERIOD:24MONTHS

GISSUBSTATION_INFOCITYII PACKAGENO23/201213 4/4