Following are the observations related to E, I &A scope of work as detailed out in TS No-

DGM/PCC/TK/2017/428 Dated 05.08.17, issued by MECON:

S. Page /Clause No As per TS BSPs Observations


No
1 P-27/07.02.VI . Contractor will May please clarify, as commissioning spares
ensure that the make for free issue items is not in the scope of
of commissioning contractor.
spare for free
issue items..
2 P-51/07.16.58 contractor will May please clarify, in which tender discussion
note that no major MOM this point is appearing.
modification..
3 P-51/07.16.62 ..However any
Please refer pt. no-35 of pre bid clarification
change in load
issued to bidders and incorporate it as a
list separate point under clause 07.16 as it is
relevant for URM, BRM & FWPH areas. Pt no-
35 of pre bid clarification is quoted here as
Please note that all the required MCC/PCC
panels has been supplied based on the approved
drive list by previous supplier (M/s MBE).
However any change in drive list shall be
suitably taken care by the bidder
4 P-122/08.03.02.02 Fire Fighting PHs In the tender document, column titled distance
between source & FWPH and distance
mentioned were not given. May please
provide/clarify in which tender discussion
MOM this point is appearing.
5 P-123/08.03.02.02 .Increase/Decrease This clause was not there in the tender
in route length is document. May please provide/clarify in which
required post order tender discussion MOM this point is appearing.
stage..
6 P-129/08.03.03.01 Total 30 nos. of Please mention PKG no. under which supply of
telephone sets.. telephone sets is envisaged.
7 P-132/08.03.03.01 Interconnectivity This clause was not there in the tender
of pump houses. document. May please provide/clarify in which
tender discussion MOM this point is appearing.
9 P-133/08.03.03.01 ..However any Same observation as in pt no-3 above.
change in load
list
10 P-134/08.03.03.02 .Complete Please include cable bridges also as it is
illumination.. appearing in MOM dtd 18.10 & 26.10.16 with
other bidders.
11 P-136/08.03.03.02 Total 30 nos. of Same observation as in pt no-6 above
telephone sets..
12 P-140/08.03.03.03 Out of 20 nos. 16 Please correct the voltage rating vis--vis no.
nos. are.. of VCBs.
13 P-146/Cable & .Further above Supply of copper cables of relevant
cabling philosophy cables will be.. sizes for incomers of panels located in
WTP-1 & 2 (MLDB & PDB only) and
in WTP-5 area (MCC, MCP, and
MLDB & PDB) is in the scope of TK
contractor.
Please note that laying, testing and
commissioning of only 3.5 C x 240 sq
mm. cu cable between WTP-7 & WTP-
5 (MCC & MCP only) is excluded
from scope of work of TK contractor.
(Refer Table C Annexure VI) &
MECONs e-mail to party dated
17.12.16.
Laying testing and termination of all
other cables is in the scope of TK
contractor. (Refer Table C Annexure
VI) & MECONs e-mail to party dated
17.12.16
Supply of minimum 5100 meters of 3.5
C x 240 sq. mm. cu cable and supply of
shortfall 3.5 C X120 sq mm cu. Cable
is in the scope of TK contractor.

May please correct in CTS.


14 P-229/08.07.02 Sl. No- 8,9,10,11 Please note that power supply to the cranes
mentioned under sl. no- 8, 9, 10, 11 shall be
from PDB which is under scope of TK
contractor. Extending power supply from this
board to cranes shall also be scope of TK
contractor,
15 P-231/08.07.02 Sl. No- 17,19,20 Same observation as point no- 14 above.
16 P-252/08.10.02 Web Based System As confirmed by M/s TPL vide e-mail dated
04.11.16, minimum 7 nos. of OPC servers &
minimum 7 nos. of hardware firewall is
considered.
Please include minimum word in the given
table.
17 P-513/ Table C Table To be removed as supply, erection, testing and
Annexure VI pt no- commissioning of UPS, Battery & ACDB for
49 URM & BRM is in the scope of TK contractor.
18 P-163/08.03.13.01 One no plant wide Please mention PKG no. under which supply of
network switch Ethernet switch is envisaged.
19 General Cooling Tower Scope of work related to electrics of cooling
towers in URM & BRM is not covered in this
CTS. May please clarify.