Table I
Activity Duration (days) Cost (Rs.) Slope
Normal Crash Normal Crash
A 3 1 8000 8400
B 5 3 3000 4600
C 4 4 9000 9000
D 6 4 7800 9000
E 7 5 10000 11000
A D
4
3 6
B
1 2 5
5
E
C
3
4 7
Critical activities are B and E.
D
A
4
3 6
B
1 2 5
5
E
C
3
4 6
Critical activities are B, D and E.
B
1 4 5
4
C E
3
4 6
Critical activities are B, C, D and E.
Decision: Crash Activity D and E together by one day @ 1100 per day.
A D
2
3 5
B
1 4 5
4
C E
3
4 5
Summary
53000
48000
43000
38000
Cost in Rs.
Direct Cost
33000
Indirect Cost
28000
Total Cost
23000
18000
13000
8000
12 11 10 9
Project Duration