Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
blunders
Offer to investors
The proposed highway was offered to international investors in May 2011, to be
built as a privately financed toll road on BOT (build, own & transfer) basis. The
investor was expected to design the road over the pre-selected corridor, acquire
land, pay compensation and construct related facilities. The design and
construction would be under the supervision was awarded to Australian
consultant SMEC Engineering in December 2012.
RDAs estimate
The Northern Expressway was expected to be constructed in two phases: Phase 1
48.2 km section from Kadawatha to Ambepussa estimated at Rs. 70 b; Phase 2
50.7 km section between Ambepussa and Katugastota was priced at Rs. 90 b.
Award of contract
In July 2012, Cabinet approved the award the construction of 100km Kandy
Expressway under Build Own Transfer (BOT) system to two Chinese companies,
China Merchant Holdings and China Merchant Huajin Investment Company and a
MOU was signed. The website of China Merchant Huajin Investment Company
noted under China company lands 1 b USD highway project in Sri Lanka.
The first 45 km of the Expressway traverse a flat terrain, the next 15 km a rolling
terrain and the balance 38 km hilly terrain and the route had been approved by
the CEA in 2008. A significant feature of the second section of expressway is the
inclusion of 10 tunnels, two of length of around 400 m and eight of length of
around 30-225 m. The Chinese agreed to construct the Kadawatha-Ambepussa
section for a 35-year BOT period and construction was expected to begin in
August 2012. The Chinese indicated that the second sector, Ambepussa-Kandy,
would require a longer period.
Shifting to Enderamulla
In the original trace prepared by the Consultant the first 0-10 km was on firm
ground. But in July 2012 when villagers near Gampaha protested against their loss
of property, Minister Felix Perera agreed to relocate the route. The road
commencement was shifted from Kadawatha to Enderamulla and join the original
route at Mirigama, increasing the distance by five kms. The amended route from
Enderamulla continued via Ragama, Gampaha, Veyangoda to Mirigama with a
sharp right turn to Ambepussa. The principle of avoiding built-up areas was
adopted for the entire alignment. The new route not only included villagers
concerns, but also accommodated wishes of politicians.
Enderamulla is surrounded by marshes and the amended route ran parallel to the
railway line, traversing over paddy, marshy and uncultivated lands. Marshes on
the diverted route necessitated nine km of viaducts (overhead road). Viaducts
cost over six times the cost of a firm-ground road and the increased costs altered
the financial viability of the project, and the Chinese investor was no longer
interested.
Changes to Kandy route
In March 2013, Mahinda Rajapaksa during a visit to Kandy reviewing progress
noted problems in land acquisitions in Kegalle, Rambukkana had delayed
implementation of the project. Rajapaksa directed the expressway be built
through Kurunegala and Galagedara. This diversion pushed the highway nearly
20km northwards and increased the highway length and the costs. Rajapaksa had
a soft corner for Kurunegala, as noted by the decision to contest from Kurunegala
District, abandoning Hambantota, after losing the presidency.
Inauguration of Northern Expressway
With the route change, the contract was awarded to Australian consultant SMEC
to select a suitable road corridor to link the highway with the Northern Province,
with a link to Kandy. The highway to allow speeds up to 100 kmph.
nStage 1 Enderamulla to Meerigama 37.1km
nStage 2 Meerigama to Kurunegala 39.7km and Ambepussa link (9.3km)
nStage 3 Pothuhera to Galagedara (Kandy) 32.5km
nStage 4 Kurunegala to Dambulla 60.3km
The revised Northern Expressway intended to connect Enderamulla with
Pothuhera and continue to Katugastota and Gannoruwa. In addition, highway
commencing from Pothuhera will pass through Kurunegala, Galewela and
Dambulla. The road will have interchanges at Gampaha, Veyangoda, Mirigama,
Nakalgamuwa, Pothuhera, Dambokka, Kurunegala, Rideegama and Melsiripura.
Under revised Expressway, distance wise Enderamulla to Kandy became 120km,
whereas in the earlier proposal Kadawatha-Kandy was only 98.9km.
RDA engineers allege the consultancy award to SMEC without calling other
quotations and the price of Rs. 1 billion was excessive. They also claim the route
was deliberately moved over paddy fields/marshlands, necessitating a large
number of overpasses and excessive earth-fills.
In November 2014, prior to Presidential elections, Mahinda Rajapaksa re-launched
the construction by laying a foundation stone at the Senkadagala entrance and
also awarded the Stage I of the contract to Metallurgical Group Corporation of
China (MCC).
Changes to Outer Circular Road
The last section is OCH Phase III from Kadawatha to Kerawalapitiya (9.63 km) had
been awarded to MCC in January 2013 for Rs. 66.69 billion with a loan wfrom
Chinese Exim Bank. The OCH 3 is a four-lane highway with provision to expand to
six lanes to accommodate traffic leading to Kandy Expressway commencing from
Enderamulla.
Earlier, the 54km stretch Kadawatha to Ambepussa was priced by the RDA at Rs.
70 billion. But shifting the commencement from Kadawatha to Enderamulla
moved the highway into flood plains and embankments had to be made larger, so
the RDA Engineers revised the Enderamulla to Mirigama estimate to Rs. 100
billion. But the price of contractor, MCC, was Rs. 29 billion higher.
Expressway under Yahapalanaya Government
The new Government appointed a committee of three ministers to determine the
future of the Kandy Expressway. The Committee recommended in March 2015 to
bring back the commencement of the Expressway from Enderamulla to
Kadawatha, also renaming it as the Central Expressway. The biggest change was
the possibility of reducing costs of OCH 3 by approximately Rs. 24 billion (or 30%)
by removing the provision to widen the road to six lanes and the redundancy of
the Enderamulla interchange. The Committee recommended that with the savings
from OCR 3, Kadawatha to Kossinna (five km) sector could be built. The highway
beyond Mirigama would be left unchanged from previous Government proposals.
The new Government too failed to investigate the massive project in detail and
blindly accepted modifications made by the Rajapaksa Government. They failed to
obtain opinions of educated persons in road construction and contract
management prior to taking decisions. Politicians were only interested in filling
their pockets and contracts for all three sectors was awarded on negotiated basis.
If the Chinese offer in 2012 was accepted, the people would be enjoying the
highway by now, without loans or interest payments. The present highway will
cost an additional Rs. 150 billion and interest on loans would be payable.
Extending the highway by 30 km means every vehicle will consume additional two
litres of petrol on every trip to Kandy one-way forever. The proposed overpriced
Kandy Expressway is the consequence of a series of political blunders and public