Sei sulla pagina 1di 22

2.

3 Systematic Safety Analysis (HAZOP) on Distillation Process in


Acetone Manufacturing Process
One of the commonly used safety analysis systems in process design is HAZOP. HAZOP
stands for Hazard and Operability Study. In typical scenarios, a HAZOP study is conducted by
a team comprising of specialists in different fields (varying from process engineers to plant
manager). The team uses a series of guide words to identify possible deviations from the
intended design or operation of a given process. After identifying such deviations, there then
comes about the discussion on how the deviations occur, consequences of these deviations,
reliability of existing safeguards in preventing or mitigating the issue and possibly
recommending additional safeguards into the system. In this report, the HAZOP study will be
conducted on the second distillation column (IPA Column, C-101).

2.3.1 PFD of Distillation


Before performing HAZOP on the distillation itself, a draft Process Flow Diagram (PFD) with
complete control loops are to be drawn. Following heuristics, there are to be these main control
loops in a distillation column set-up (with other considerations of the usage of cascade loops
and safety relief valves):

x Flowrate of feed
x Flowrate of reflux
x Level in distillation column
x Level in overhead accumulator
x Temperature of boil up return
x Pressure in distillation column
x Differential pressure across distillation column
The following is assumed:

x All control valves have a by-pass valve as well as isolation valves present but not drawn
into the PFD
x No proper level alarms for the process transmitter has been determined yet
x The pressure control systems are done separately through the use control valves PCV-101
and PCV-102
The preliminary PFD is shown in the following page.

40
PC
PC 102 PCV-102 To Flare
101
PT
102
PRV-101
PT PCV-101
101
LT
V-102
102

TT TC LC
101 101 102

TT
E-106 102

TC
TCV-102 102
FC FT FT FC
101 101 102 102
CWR CWS
Bottoms
from C-100 C-101
FCV-101

P-102
PD
FCV-102
101

P-103 IPA for


Recycle
TC
103 LCV-102

TT
103 FT FC
103 103
LT
101
Steam
Inlet
FCV-103
E-107
LC
101 Steam
Outlet
LCV-101 Water for
Discharge

Figure 2.3.1.1: PFD of Distillation Column C-101 with control loops

2.3.2 HAZOP of Distillation


In this HAZOP analysis, there will be three parameters evaluated; (1) Level, (2) Temperature
and (3) Pressure. These parameters have been associated with a series of guidewords, forming
a deviation. These deviations are as such and a HAZOP will be done for each of them (in the
following order):

1. High level in C-101 7. High temperature in V-102


2. Low level in C-101 8. Low temperature in V-102
3. No level in C-101 9. High pressure in C-101
4. High level in V-102 10. Low pressure in C-101
5. High temperature in C-101 11. High pressure in V-102
6. Low temperature in C-101 12. Low pressure in V-102
The HAZOP analysis made for the 12 deviations are presented in a table format per deviation
in the following pages.

41
Unit/Node IPA distillation column, C-101
Process Variable Level Guide Word More of
Deviation High level in C-101
Additional Safeguards
Cause(s) of Deviation Possible Consequences Existing Safeguards Available
Recommended
a) Install level transmitter with
level alarm high (LAH) to alert
operator when levels increase
a) With constant heating from pass the optimum settings.
High feed flow rate. More feed reboiler, the excess feed will not a) Level transmitter (LT-101) and b) Install composition analyser
entering distillation column be sufficiently heated so the controller (LC-101). (AI-101) to measure the top
purity of the product will be low. product composition.
c) Scheduled trips by field staff to
double check control panel values
with onsite instruments
a) Install composition analyser
a) Accumulation liquid inside C-
(AI-101) to measure the top
101.
LCV-101 fail close. Hence, result a) Flow transmitter (FC-102) and product composition.
b) Continuous heating of same
in no flow of bottom out. controller (FC-102) b) Scheduled trips by field staff
column liquid causing the purity
to double check control panel
of the product to remain low.
values with onsite instruments
Table 2.3.2.1: High level in C-101 HAZOP analysis

42
Unit/Node IPA distillation column, C-101
Process Variable Level Guide Word Less of
Deviation Low level in C-101
Additional Safeguards
Cause(s) of Deviation Possible Consequences Existing Safeguards Available
Recommended
a) Install level transmitter with
level alarm low (LAL) to alert
operator when levels decreases
pass the optimum settings.
a) Top and bottom product b) Scheduled trips by field staff
Low feed flow rate. Lesser feed collected will be lowered that a) Level transmitter (LT-101) and to double check control panel
entering distillation column. will cause the demands of client controller (LC-101) values with onsite instruments
to not be met. c) Install a safety interlock
system which will cause a
solenoid block valve to activate
when column level is past the
low-low limit
a) Install temperature indicator
a) Temperature of top product
with temperature alarm high
will increase, as there is no reflux
(TAH) to indicate high alarm of
to cool down the vapour. More
a) Temperature transmitter (TT- top product.
FCV-102 fail closed, hence cooling of top product is
101) and controller (TC-101). b) Install composition analyser
resulting in no reflux entering C- required.
b) Flow transmitter (FC-102) and (AI-101) to measure the
101, causing lesser level. b) Separation efficiency in the
controller (FC-102) composition of the top product.
column and top and bottom
c) Scheduled trips by field staff to
products stream composition will
double check control panel values
be affected
with onsite instruments
Table 2.3.2.2: Low level in C-101 HAZOP analysis

43
Unit/Node IPA distillation column, C-101
Process Variable Level Guide Word No
Deviation No level in C-101
Additional Safeguards
Cause(s) of Deviation Possible Consequences Existing Safeguards Available
Recommended
a) Steam continues to flow to
reboiler so heating continues.
a) Flow transmitter (FT-101) and a) Install parallel pump along P-
With no feed to heat, the vapour
P-102 pump fail. No feed will controller (FC-101) 102 in case one fails.
inside the column will be heated
enter the distillation column. b) Pressure differential indicator b) Pressure relief valve (PRV) to
causing the pressure to increase
(PD-101) relief excess pressure.
overheating the reboiler at the
same time.
a) Steam continues to flow to
reboiler so heating continues.
With no feed to heat, the vapour
inside the column will be heated
a) Pressure relief valve (PRV) to
causing the pressure to increase.
FCV-101 fail closed, line relief excess pressure.
b) Feed in the pipeline between
blockage due to presence of b) Install minimum flowrate line
P-102 and FCV-101 will a) Flow transmitter (FT-101) and
impurities (like corrosion for P-102.
accumulate and increase the controller (FC-101).
product). No feed will enter the c) Addition of pump strainers for
pressure causing the pipeline to
distillation column. P-102 to remove any addition
eventually burst and release
impurities.
chemicals into the atmosphere.
c) Pump will continue to pump
feed and do work that will cause
the pump to overheat.
Table 2.3.2.3: No level in C-101 HAZOP analysis

44
Unit/Node Reflux drum, V-102
Process Variable Level Guide Word More of
Deviation High level in V-102
Additional Safeguards
Cause(s) of Deviation Possible Consequences Existing Safeguards Available
Recommended
a) More cooling of distillate
product entering E-106 so more
condensate will be formed. As
a) Install temperature indicator
such greater increase of flow rate a) Temperature transmitter (TT-
with temperature low alarm
of condensate into V-102. 102) and controller (TC-102) to
(TAL) to alert operator of low
TCV-102 fail open. Increased b) Higher flow rate of condensate measure the temperature of outlet
temperature in discharge stream.
cooling water into E-106 will cause the temperature to be stream of E-106.
b) Scheduled trips by field staff
lower in the outlet stream of E- b) Pressure transmitter (PT-102)
to double check control panel
106. and controller (PC-102)
values with onsite instruments
c) Pressure in V-102 will
decrease due to lesser vapour
flow into the reflux drum
a) Pressure in V-102 build-up due a) Install Pressure indicator with
to high level inside, hence result a) Pressure transmitter (PT-102) pressure high alarm (PAH) to
LCV-102 fail closed. Result
in vessel from bursting. and controller (PC-102) alert the operator of the high
lesser flow out of V-102, hence
b) Releasing of top product to b) Pressure relief valve (PRV- pressure in V-102.
level increase.
environment, which can cause 101) b) Regular inspection and
fire when there ignition patrolling of the area.
Table 2.3.2.4: High level in V-102 HAZOP analysis

45
Unit/Node IPA distillation column, C-101
Process Variable Temperature Guide Word More of
Deviation High temperature in C-101
Additional Safeguards
Cause(s) of Deviation Possible Consequences Existing Safeguards Available
Recommended
a) With a faulty control valve
a) Install another control valve
(FCV-103), there could be an
that works independently and can
increase in steam flow rate into
be used as a backup control valve
the reboiler (E-107) which will
in case FCV-103 fails.
then result in higher vapour a) Cascade control, TC-103, to
b) Separate TAH and TAHH to
production. control the steam flow rate
Faulty control valve (FCV-103) trip the steam entering the
b) Higher vapour production will entering the reboiler.
resulting in an excess heating of reboiler in the case of excess
result in an increase in overall b) PC-101 located at the top of
stripping section using reboiler E- heating in stripping section.
pressure, and may over pressurise the distillation column, C-101, to
107. c) Install pressure relief valve at
condenser E-106 and reflux drum control the pressure entering the
the top of the distillation column,
V-102. reflux drum, V-102.
C-101, to appropriately relieve
c) The over pressurisation will
excess pressure before entering
consequently cause E-106 and V-
condenser and reflux drum to
102 to rupture and burst,
prevent over pressurisation.
releasing flammable content.
a) Faulty control valve (FCV- a) Install another pump (parallel
102) or/and P-103 failure may a) PC-101 located at the top of configuration) that is used as a
Little or no rectifying reflux cause little or no reflux flow into the distillation column, C-101, to backup pump in case P-103 fails.
stream to provide cooling of the C-101. control the pressure entering the b) Install another control valve
vapour stream. This could be due b) This will result in a higher reflux drum, V-102. that works independently and can
to pump failure (P-103) or/and yield of vapour product due to b) Cascade control, TC-101, to be used as backup control valve
faulty control valve (FCV-102). absence of rectifying reflux control the reflux flow rate into in case FCV-102 fails.
stream to cool the vapour stream C-101.
sufficiently.

46
c) Higher vapour production will c) Install pressure relief valve at
result in an increase in overall the top of the distillation column,
pressure, and may over pressurise C-101 to appropriately relieve
the E-106 and V-102. excess pressure before entering
d) The over pressurisation will condenser and reflux drum to
consequently cause E-106 and V- prevent from over pressurisation.
102 to rupture and burst,
releasing flammable content.
a) Higher temperature resulted
from the reboiler E-104 (located
at the bottom of C-100) will
a) Install temperature transmitter
cause the temperature of the feed
(TT) with TAH at the inlet of C-
entering to be high, which may
101 to detect and alert the high
consequently lead to higher
temperature flow that is entering
pressure and temperature in
High intermediate temperature C-101.
transfer line and eventually in
from bottoms of C-100 (due to None. b) Install pressure relief valve at
column C-101.
reboiler E-104). the top of the distillation column,
b) This increases the likelihood
C-101 to appropriately relieve
of C-101 to rupture and burst due
excess pressure so as to protect
to the high inlet pressure entering
the column from being over
the column.
pressurised and rupture.
c) Isopropyl alcohol, being
flammable, may cause fire or
explosion when ignited.
Table 2.3.2.5: High temperature in C-101 HAZOP analysis

47
Unit/Node IPA distillation column, C-101
Process Variable Temperature Guide Word Less of
Deviation Low temperature in C-101
Additional Safeguards
Cause(s) of Deviation Possible Consequences Existing Safeguards Available
Recommended
a) With a faulty control valve
(FCV-103), there could be a
decrease in steam flow rate into
a) Install another control valve
the reboiler (E-107) which will
that works independently and can
then result in lesser vapour
a) Cascade control, TC-103, to be used as a backup control valve
production.
control the steam flow rate in case FCV-103 fails.
b) Lesser vapour product will
Faulty control valve (FCV-103) entering the reboiler. b) Ensure regular checks and
lead to reduced separation
resulting in little or no heating of b) LT-102 to indicate the low maintenance of the control valve.
efficiency in C-101, hence
stripping section using reboiler E- level in V-102 due to lesser c) Separate LAL and LALL to
resulting in a lower amount of
107. product present in V-102. trip LCV-102 in order to stop
IPA available to recycle.
c) Minimum flow line on pump outflow of IPA for recycle and
c) Lesser vapour product will
P-103 to prevent cavitation. prevent the level in V-102 from
also mean that the level in V-102
dropping even further which may
drops. This may consequently
cause pump P-103 to cavitate.
cause pump P-103 to damage or
cavitate due to insufficient level
in reflux drum V-102.
a) Faulty control valve (FCV-
a) Cascade control, TC-101, to a) Install another control valve
102) or/and pump failure could
Excess cooling provided by control the amount of reflux that works independently and can
result in large amount of reflux
rectifying reflux stream. This stream entering the column C- be used as a backup control valve
stream entering C-101.
could be due to pump failure (P- 101. in case FCV-102 fails.
b) The excess cooling provided
103) or/and faulty control valve b) LT-102 to indicate the low b) Ensure regular checks and
by the large amount of reflux
(FCV-102). level in V-102 due to lower maintenance of the control valve.
stream will result in lower yield
product present in V-102.
of vapour product.

48
c) Lesser vapour production will c) Minimum flow line on pump c) Separate LAL and LALL to
lead to reduced separation P-103 to prevent cavitation. trip LCV-102 in order to stop
efficiency which consequently outflow for IPA recycle and
results in a lower amount of IPA prevent the level in V-102 from
available for recycle. dropping even further which may
d) Low level in V-102 may also cause pump P-103 to cavitate.
cause pump to damage due to
insufficient level in reflux drum
V-102.
a) Install temperature transmitter
a) Lower temperature of liquid
(TT) with TAL at the inlet of C-
feed would result to a lower
101 to detect and alert the low
generation of vapour from
temperature feed flow that is
reboiler E-107. a) TC-103 to control steam
Low intermediate temperature entering C-101.
b) The lower feed temperature heating into reboiler E-107
from bottoms of C-100 (due to b) Separate LAL and LALL to
entering will lead to reduced b) TC-101 to control the flowrate
reboiler E-104). trip LCV-102 in order to stop
separation efficiency in C-101. of cool reflux into column
outflow of IPA for recycle and
c) Lesser vapour generated would
prevent the level in V-102 from
result to a lower liquid level in V-
dropping even further which may
102.
cause pump P-103 to cavitate.
Table 2.3.2.6: Low temperature in C-101 HAZOP analysis

49
Unit/Node Reflux drum, V-102
Process Variable Temperature Guide Word More of
Deviation High temperature in V-102
Additional Safeguards
Cause(s) of Deviation Possible Consequences Existing Safeguards Available
Recommended
a) With a faulty control valve
(TCV-102), there could be little
or no condensation in E-106 due
to lesser or no flow of cooling
water into the condenser E-106,
this will consequently result in
greater vapour product in reflux a) PC-102 located at the top of
a) Install another control valve
drum V-102. the reflux drum, V-102, to
that works independently and can
Faulty control valve (TCV-102) b) There could be a possibility of control the pressure in V-102 by
be used as a backup control valve
resulting in little or no over pressurisation in V-102 due sending the excess pressure to
in case TCV-102 fails.
condensation in E-106. to the reduced condensation at flare.
b) Ensure regular checks and
the top of the distillation column, b) PRV-101 to relieve excess
maintenance of the control valve.
C-101. This may eventually pressure in V-102.
cause V-102 to rupture and burst,
releasing flammable isopropyl
alcohol into the atmosphere.
c) The release of isopropyl
alcohol may cause fire or
explosion if ignited.
a) With a faulty control valve
a) Cascade control, TC-103, to a) Install another control valve
Faulty control valve (FCV-103) (FCV-103), there could be an
control the steam flow rate that works independently and can
resulting in an excess heating of increase in steam flow rate into
entering the reboiler. be used as a backup control valve
stripping section using reboiler E- the reboiler (E-107) which will
in case FCV-103 fails.
107. then result in higher vapour
production.

50
b) Higher vapour production will b) PC-101 located at the top of b) Separate TAH and TAHH to
result in more vapour present in the distillation column, C-101, to trip the steam entering the
V-102 which may result in an control the pressure entering the reboiler in the case of excess
increase in overall pressure and reflux drum, V-102. heating in stripping section.
eventually lead to V-102 over
pressurisation.
c) The over pressurisation may
cause V-102 to rupture and burst,
releasing flammable isopropyl
alcohol into the atmosphere.
a) Higher temperature resulted
from the reboiler E-104 (located
at the bottom of C-100) will lead
to higher pressure and a) Install temperature transmitter
temperature in transfer line and (TT) with TAH at the inlet of C-
eventually in column C-101. 101 to detect and alert the high
b) With a higher temperature of temperature flow that is entering
feed inlet, more vapour is likely C-101.
to be produced and hence a) PC-101 located at the top of b) Install pressure relief valve at
High intermediate temperature
collected in V-102. the distillation column, C-101, to the top of C-101 to appropriately
from bottoms of C-100 (due to
c) This will then result in an control the pressure entering the relieve pressure so as to protect
reboiler E-104).
increase in vapour product reflux drum, V-102. the column from being over
entering the condenser E-106 and pressurised and rupture.
reflux drum V-102, causing these c) Install temperature transmitter
equipment to over pressurise. with TAH to indicate and alert
d) Over pressurisation of E-106 the high temperature stream
and V-102 will cause equipment entering V-102.
to rupture and burst. Flammable
isopropyl alcohol may cause fire
or explosion.
Table 2.3.2.7: High temperature in V-102 HAZOP analysis

51
Unit/Node Reflux drum, V-102
Process Variable Temperature Guide Word Less of
Deviation Low temperature in V-102
Additional Safeguards
Cause(s) of Deviation Possible Consequences Existing Safeguards Available
Recommended
a) With a faulty control valve
(TCV-102), there could an
excessive condensation in E-106
a) Install another control valve
due to more flow of cooling
that works independently and can
water into the condenser E-106.
be used as a backup control valve
This will result in lesser vapour
in case TCV-102 fails.
product entering the reflux drum a) LT-102 to indicate the low
b) Ensure regular checks and
Faulty control valve (TCV-102) V-102. level in V-102 due to lower
maintenance of the control valve.
resulting in an excess b) Lesser vapour production will product present.
c) Separate LAL and LALL to
condensation in E-106. lead to reduced separation b) Minimum flow line on pump
trip LCV-102 in order to stop
efficiency, hence resulting in a P-103 to prevent cavitation.
outflow for IPA recycle and
lower amount of IPA available to
prevent the level in V-102 from
recycle.
dropping even further which may
c) Low level in V-102 may also
cause pump P-103 to cavitate.
result in pump damage due to
insufficient level in reflux drum
V-102.

52
a) With a faulty control valve
(FCV-103), there could be a
a) Install another control valve
decrease in steam flow rate into
that works independently and can
the reboiler (E-107) which will
a) Cascade control, TC-103, to be used as a backup control valve
then result in lesser vapour
control the steam flow rate in case FCV-103 fails.
production.
Faulty control valve (FCV-103) entering the reboiler. b) Ensure regular checks and
b) Lesser vapour production will
resulting in little or no heating of b) LT-102 to indicate the low maintenance of the control valve.
lead to reduced separation
stripping section using reboiler E- level in V-102 due to lower c) Separate LAL and LALL to
efficiency, hence resulting in a
107. product present in V-102. trip LCV-102 in order to stop
lower amount of IPA available
c) Minimum flow line on pump outflow for IPA recycle and
for recycle.
P-103 to prevent cavitation. prevent the level in V-102 from
c) Low level in V-102 may also
dropping even further which may
cause pump P-103 to damage due
cause pump P-103 to cavitate.
to insufficient level in reflux
drum V-102.
Table 2.3.2.8: Low temperature in V-102 HAZOP analysis

53
Unit/Node IPA distillation column, C-101
Process Variable Pressure Guide Word More of
Deviation High Pressure in C-101
Additional Safeguards
Cause(s) of Deviation Possible Consequences Existing Safeguards Available
Recommended
a) Reboiler E-107 may overheat a) Install a high pressure alarm
Malfunctioning of FCV-103, and get damaged due to the (PAH) that is independent of PC-
leaving the control valve at full suddenly increase in steam 101 and its control loop. Hence,
open position. With an increased a) Basic Process Control System:
flowrate. operator can intervene during
flow of hot steam, the reboiler E- PCV-101 will open to relieve
b) Over-pressurization in column high pressure situations.
107 duty increases. As such, pressure in the column C-101
C-101 is unsafe and may rupture b) Incorporate a safety interlock
there will be more vapourisation when PT-101 reads a high
if pressure continues to build-up. system to cut off steam flow into
of the liquid in the column, pressure in the column.
c) Increased pressure may affect the reboiler E-107 if the pressure
resulting in a pressure increase in
the separation in the column and in column C-101 increases past
the IPA Column C-101.
hence, reduce C-101s efficiency. the high-high limit set.
a) Over-pressurization in column a) Install a high pressure alarm
The inlet stream from P-102 C-101 is unsafe and may rupture (PAH) that is independent of PT-
contains the bottoms from C-100. if pressure continues to build-up. 101. Hence, operator can
It may overheat and enter column b) Increased pressure may affect a) Basic Process Control System: intervene during high pressure
C-101 as hot vapour instead of the separation in the column and PCV-101 will open to relieve situations.
hot liquid. Hence, the influx of hence, reduce C-101s efficiency. pressure in the column C-101 b) Incorporate a heat exchanger
hot vapour in C-101 will build up c) High pressure may also when PT-101 reads a high after column C-100 and before
in the column, resulting in a damage condenser E-106 as hot pressure in the column. column C-101 to cool the
pressure increase in IPA column vapour will enter at pressure incoming bottoms from C-100.
C-101. much higher than operating Hence, inlet stream of C-101 will
levels. not enter as vapour.

54
a) Install a high pressure alarm
Malfunctioning of FCV-102,
(PAH) that is independent of PT-
leaving the control valve at full a) Over-pressurization in column
101. Hence, operator can
close position. Hence, there will C-101 is unsafe and may rupture
a) Basic Process Control System: intervene during high pressure
be no reflux flow from reflux if pressure continues to build-up.
PCV-101 will open to relieve situations.
drum V-102. With no reflux b) With no reflux, the purity of
pressure in the column C-101 b) Incorporate a safety interlock
flow, there is no liquid to the distillate will be affected.
when PT-101 reads a high system to cut off steam supply to
condense the rising vapours. As Hence, the column C-101
pressure in the column. reboiler E-107 to stop
such, the accumulation of vapour efficiency in separating IPA from
vapourisation. Interlock activates
will result in high pressure in C- water will be reduced.
when pressure pass the high-high
101.
limit set.
Table 2.3.2.9: High Pressure in C-101 HAZOP analysis

55
Unit/Node IPA distillation column, C-101
Process Variable Pressure Guide Word Less of
Deviation Low Pressure in C-101
Additional Safeguards
Cause(s) of Deviation Possible Consequences Existing Safeguards Available
Recommended
a) Install a low pressure alarm
Malfunctioning of PCV-101,
(PAL) that is independent of PT-
leaving the control valve at full a) Reduced pressure may affect
101. Hence, operator can
close position. Hence, with the the separation in the column and
a) Basic Process Control System: intervene during low pressure
control valve fully closed, vapour hence, reduce C-101s efficiency.
LCV-102 will open in an attempt situations.
will all condense as it passes b) With all the vapour top
to reduce the level in reflux drum b) BPCS: Control valve to
through condenser E-106. As product being condensed, level in
V-102 when LT-102 reads a high increase steam flowrate to
such, vapour is unable to build up reflux drum, V-102, will increase
level in the reflux drum. reboiler E-107 when pressure is
in IPA column C-101. This will drastically and continue to build-
low. It can be set to work
result in a low pressure scenario up.
alongside FC-103 using a selector
in column C-101.
control scheme.
a) Basic Process Control System:
Malfunctioning of FCV-103, a) Reduced pressure may affect PCV-101 will open in an attempt
leaving the control valve at full the separation in the column and to prevent hot vapour from being
close position. With no flow of hence, reduce C-101s efficiency. condensed in E-106. As such, a) Install a low pressure alarm
hot steam, the reboiler E-107 b) With no vapourisation, there vapour should accumulate to try (PAL) that is independent of PT-
duty decreases. As such, there be will be no top product being to increase the pressure. 101. Hence, operator can
no vapourisation of the liquid in formed. The liquid level in b) Basic Process Control System: intervene during low pressure
the column, resulting in low column C-101 will start to build- LVC-101 will open in an attempt situations.
pressure in IPA Column C-101. up. Hence, resulting in high level to reduce the level in column C-
in column. 101 when LT-101 reads a high
level in the column.
Table 2.3.2.10: Low Pressure in C-101 HAZOP analysis

56
Unit/Node Reflux Drum, V-102
Process Variable Pressure Guide Word Less of
Deviation High Pressure in V-102
Additional Safeguards
Cause(s) of Deviation Possible Consequences Existing Safeguards Available
Recommended
a) Install a high pressure alarm
Malfunctioning of PCV-101, (PAH) that is independent of PT-
leaving the control valve at full a) Pressure Relief Valve (PRV- 102. Hence, operator can
open position. Hence, with the 101) is installed to relief excess intervene during high pressure
control valve fully opened, a) Over-pressurization in reflux pressure in reflux drum V-101. situations.
vapour will by-pass the drum V-102 is dangerous and 2) Basic Process Control System: b) Install a rupture disc for reflux
condenser E-106 and begin to may rupture if pressure continues PCV-102 will open in an attempt drum V-102 that is in parallel
accumulate in V-102. As such, to build-up. to reduce pressure in V-102 when with PRV-101. This rupture disc
vapour is builds up in reflux PT-102 reads a high pressure in will rupture only at a higher
drum and result in a high pressure the reflux drum. pressure when the PRV-101
scenario in reflux drum V-102. cannot relief the pressure
sufficiently.
a) Install a high pressure alarm
Malfunctioning of FCV-103, (PAH) that is independent of PT-
leaving the control valve at full a) Over-pressurization in reflux a) Pressure Relief Valve (PRV- 102. Hence, operator can
open position. With an increased drum V-102 is dangerous and 101) is installed to relief excess intervene during high pressure
flow of hot steam, the reboiler E- may rupture if pressure continues pressure in reflux drum V-101. situations.
107 duty increases. As such, to build-up. b) Basic Process Control System: b) Install a rupture disc for reflux
there will be more vapourisation b) Reboiler E-107 may overheat PCV-102 will open in an attempt drum V-102 that is in parallel
of the liquid in the column, and get damaged due to the to reduce pressure in V-102 when with PRV-101. This rupture disc
resulting in more vapour suddenly increase in steam PT-102 reads a high pressure in will rupture only at a higher
accumulated in V-102. Hence, flowrate. the reflux drum. pressure when the PRV-101
the high pressure V-102. cannot relief the pressure
sufficiently.

57
a) Install a high pressure alarm
Malfunctioning of PCV-102,
(PAH) that is independent of PT-
leaving the control valve at full
102. Hence, operator can
close position. Hence, vapour is
a) Over-pressurization in reflux intervene during high pressure
trapped in V-102. This results in a) Pressure Relief Valve (PRV-
drum V-102 is dangerous and situations.
an accumulation of hot vapour in 101) is installed to relief excess
may rupture if pressure continues b) Install a rupture disc for reflux
V-102 that will build-up pressure pressure in reflux drum V-101.
to build-up. drum V-102 that is in parallel
over time such that there will be
with PRV-101. This rupture disc
high pressure in reflux drum V-
will rupture only at a higher
102.
pressure.
Table 2.3.2.11: High Pressure in V-102 HAZOP analysis

58
Unit/Node Reflux Drum, V-102
Process Variable Pressure Guide Word Less of
Deviation Low Pressure in V-102
Additional Safeguards
Cause(s) of Deviation Possible Consequences Existing Safeguards Available
Recommended
Malfunctioning of PCV-102,
leaving the control valve at full
open position. Hence, vapour will a) Install a low pressure alarm
a) A large amount of product will
continuously leave the reflux (PAL) that is independent of PT-
be lost. This is because the top
drum at a fast rate. With the loss No existing safeguard available. 102. Hence, operator can
vapour product is continuously
of vapour, vapour is unable to intervene during low pressure
sent to the flare to be burnt off.
build up in reflux drum V102. situations.
This will result in a low pressure
scenario in reflux drum V-102.
Malfunctioning of FCV-103,
a) Basic Process Control System: a) Install a low pressure alarm
leaving the control valve at full
a) With no vapourisation, there LVC-101 will open in an attempt (PAL) that is independent of PT-
close position. With no flow of
will be no top product being to reduce the level in column C- 102. Hence, operator can
hot steam, the reboiler E-107
formed. The liquid level in 101 when LT-101 reads a high intervene during low pressure
duty decreases. As such, there be
column C-101 will start to build- level in the column. situations.
no vapourisation of the liquid in
up. Hence, resulting in high level b) Basic Process Control System: b) Install a low level alarm (LAL)
the column. Thus, no vapour will
in column. LCV-102 will close in an that is independent of LT-102.
build up in the reflux drum V-
b) No top product being formed attempted to increase the level in Hence, operator can intervene
102. This will result in a low
means level in V-101 will drop. reflux drum when LT-102 reads a during low level in reflux drum
pressure scenario in reflux drum
low level in the reflux drum. situations.
V-102.
Table 2.3.2.12: Low Pressure in V-102 HAZOP analysis

59
2.3.3 PFD of distillation process after HAZOP
From the HAZOP analysis performed on the 12 deviations, the required safeguards to be built
onto the current preliminary PFD is as such (with further considerations made through
observation and evaluation) with reference to the preliminary column PFD:

x Introduce a parallel pump configuration for feed pump P-102


x Introduce a parallel pump configuration for reflux pump P-103
x Install a minimum flowline for feed pump P-102
x Introduce a strainer each for all pumps
x Introduce a pressure relief valve (sized for two-phase flow) immediately at the top outlet
of the column C-101, venting off to flare
x Introduce a rupture disc parallel to the pressure relief valve at the reflux tank which will
lead to the flare
x Introduce a composition analyser for feed, top product (before the pipeline splits between
distillate and reflux lines) and bottom product
x Install separate transmitters to provide alarm signals (from their Basic Process Control
System, BPCS, counter parts) for the following process parameters
Pressure of column C-101 (For high and low)
Pressure in reflux tank V-102 (For high and low)
Level in column C-101 (For high and low)
Level in reflux tank V-102 (For high and low)
Temperature of vapour boil-up after reboiler E-107 (For high only)
Temperature of top vapour flow out from column C-101 (For high only)
Temperature of condensed fluid flow after condenser E-106 (For high and low)
x Install a temperature transmitter (and indicator) along the feed inlet line with alarms set
at high and low limits
x Installer safety interlock systems for the following process parameters
Low-low level switch for column C-101 which activates a solenoid valve that blocks
liquid flow out of reboiler
Low-low level switch for reflux tank V-102 which will switch off all reflux pumps
High-high pressure switch for column C-101 which activates a solenoid valve that
blocks steam flow into the reboiler
High-high temperature switch for vapour boil-up flow from reboiler E-107 which
activates a solenoid valve that blocks steam flow into the reboiler
x Ensure there are scheduled trips to ensure that all equipment are in proper operating
conditions, to confirm if reading transmitted is that on-site, and to perform regular control
valve stroke checks
x Employ a split range pressure controller scheme that controls PCV-101 and PCV-102
rather than to use two separate control schemes

60
Main discussion pointers
The main two recommendations from the HAZOP analysis that were not considered are the
employment of a heat exchanger to cool the feed stream and to introduce additional back-up
control valves parallel to their original ones. The former would be relatively unnecessary due
to the fact that heat is generally lost over flow distance. Implementation of a heat exchanger
would result to excessive energy and utility demands. If it is critically demanded that the stream
is to be cooled, an exposed section of the piping coiled up as a heating coil can be implemented
so as to exchange heat to the surroundings. For the latter idea, the idea of using extra control
valves may cause confusions during operations which can result to miscommunications and
process upsets. Also the idea of using a low selector switch between PC-101 (column pressure
regulator) and TC-103 (temperature control of vapour outlet from reboiler) to then act as the
master control for cascade controller FC-103 (steam inlet flow into reboiler) is not advisable.
This is because the pressure in the column has its own BPCS to operate thus providing two
conflicting signals may result to producing a vapour flowrate that is not desired; ultimately
affecting the purity of the outlet streams.
The edited overall IPA column PFD with all these considerations is presented as such:

PAH
PRV-101 PIT PIT PC To Flare
101 PAL
101 101

PCV-101B
PCV-101A PRV-102

PAH
TAH TAH PIT
TIT E-106 TIT 102
LAH
102 103 TAL LIT
PAL

102
TIT TIC V-102 LAL

102 102
TIT
PSHH
103 LIT
101
102
LSLL
TC 102
TCV-103 103 LC
102

CWR CWS
II
FC FIT FIT FC
101 101 102 102 P-103A

AIT
C-101 102
FCV-101 P-103B
Bottoms AIT TIT
TAH

from C-100 P-102A 101 101 TAL IPA for


FCV-102 HV-102
PDI Recycle
101

LCV-102
P-102B TSHH III
104
TC
TIT
TAH
TIT 104
104 104
LAH FIT FC
LIT
103 103
101 LAL

LIT Steam
101 Inlet
LSLL FCV-103 UZV-101
101
E-107

Steam
LC Outlet
101 HV-101 LCV-101
I

Water for
AIT Discharge
103

Figure 2.3.3.1: Edited PFD of C-101 with consideration of performed HAZOP analysis

61

Potrebbero piacerti anche