Single Station Automated Cell
n=1, w=0
Characteristics
Labor cost < manned station
Easiest and least expensive among automated systems
Production rate > manned station
First step in implementing automated system
2
Part Storage Subsystem
UT = npTc
UT = Unattended time of operation of the manufacturing cell (min)
np = designed part storage capacity (pc)
Tc = cycle time of the automated workstation (min/pc)
Tc = Tm + Ts
Tc= Cycle time, Tm= machining process time, Ts= worker service time
One part storage: Tc = Max{Tm, Ts} + Tr
Tr= responding time
If Ts>Tm, machine experiences forced idle time
3
Application of Single Station Cells
Manned Cells Automated Cells
CNC machining center for + Part carousel + APC
single products
Worker: Execute part program,
load/unload part
CNC turning center single for + Part storage + robot
products
Worker: Execute part program,
load/unload part
Above for mixed products + Automatic part program
Worker: Select part program download
Cluster of two CNC turning + Part storage + robot
center
One worker can work on both machines
Assembly by worker Assembly by robot
4
Mill-Turn Center