Sei sulla pagina 1di 6

Olympic Dam Operation An Overview of Underground

Design and Planning


S Uggalla1

INTRODUCTION In the current underground expansion the mining method will


essentially remain unchanged. The ore handling system will
Olympic Dam Operation is located in the Stuart Shelf Geological incorporate some recent advances in technology, improving
Province approximately 520 km north-north-west of Adelaide in efficiency and safety standards.
South Australia. It is estimated to be one of the worlds top five
copper orebodies by size and the biggest single occurrence of Major infrastructure excavations are designed by a team of
uranium. The deposit was discovered by Western Mining engineers attached to the Olympic Dam Expansion Project and a
Corporation in 1975. Exploration was based on a conceptual number of consulting groups. Once the expansion is fully
model for the formation of sediment hosted copper deposits completed it is expected to increase the current annual
together with gravity and magnetic anomalies. underground production level from 3.4 Mt to 9.0 Mt of ore by the
year 2000. Mine design engineers working for the Olympic Dam
The capital cost of the current expansion is estimated to be A$ Operation have recently completed a three year final design plan
1.64 billion. The underground expansion includes a total of 36 to achieve this target.
km of lateral development, a railway haulage system delivering
ore from a series of ore passes to a new crusher station and a Access to the existing mine is through the decline and Whenan
significant increase in ventilation capacity and mine services. shaft. The Whenan shaft was originally sunk as an exploration
access and later upgraded for hoisting. The 4 km long service
decline connecting to the Whenan shaft was later constructed to
accommodate the increase in service demand. The Robinson and
1. Mine Design Engineer, Olympic Dam Operation, Technical Services,
Western Mining Corporation, Roxby Downs SA. Sir Lindsay Clark shafts were developed at later stages to cater
for the hoisting during and following the expansion lead up.

FIG 1 - Location of Olympic Dam Mine.

Tenth Australian Tunnelling Conference 1999 Melbourne, Vic, 21 - 24 March 1999 127
S UGGALLA

GEOLOGY AND RESERVES the Central Ore Reserves Database so that new additions or
modifications made to existing stopes will automatically be
The orebody extends over an area of 5 km by 3 km and reflected in the production schedule.
comprises of a number of ore zones. The ore consists of fine to All designs are currently done using the system as described
medium grain copper sulphides and pitch blende and is located above, thereby minimising the need for paper based designs.
beneath some 350 m of unmineralised sedimentary rock. Gold Assessment of three-dimensional models as well as preparation
and silver occur as minor compounds. An extensive drilling and evaluation of alternate design options are major advantages
programme has been carried out to ascertain the ore reserves. of this system.
Datamine software is used in the reserve estimation process.
Based on the ore reserve statement 1997, the orebody consists of
82 Mt of Proved Reserves and 484 Mt of Probable Reserves. Stope design parameters
Based on drill hole data a three-dimensional grid of blocks, 5 For the purpose of design and planning, the orebody has been
m 5 m 10 m, is generated throughout the orebody. Once this divided into a number of mining areas. These areas have been
process is completed contours can be generated for individual defined by their relative geographic locations. In each mining
metal concentrations and for total combined in situ dollar values. area, stopes are identified by different colours such as blue,
Based on long-term predictions of metal prices and exchange green, red, purple and brown.
rates, individual metal concentrations of each block are factored Once the underground diamond drilling and grade analysis
and added up to give a combined dollar value. Currently the $70 process is completed for each area a Datamine model is
in situ value contour is taken as the stope design cut-off value. generated. Based on this model, preliminary stopes, perimeter
The average dollar value of each stope has to be greater than $70 accesses and other infrastructures such as ore passes and
and Cu/S ratio should be greater than 1.4 to be included in the ventilation raises are designed.
Proved ore reserves. Sublevel open stoping is the mining method used to extract
ore. Intermediate level intervals vary from 30 - 60 m. Stope
DESIGN AND PLANNING length along strike is largely based on mineralisation, geological
structures, geotechnical issues such as in situ stress distribution,
Geotechnical considerations stope geometry and stope filling. The maximum transverse width
(across strike) and length has been determined as 60 m and 35 m
As the underground production expands to 9.0 Mtpa there will be respectively. A typical stope indicating planned development is
an increase in the intensity of mining activities. The mine will be shown in Figure 2.
extended deeper and the in situ stresses will increase. In this In general the stope crown is domed wherever possible to
aspect, understanding the geotechnical implications for design maximise crown stability. A flat crown with a span 10 m or
and planning is particularly important. To ensure the structural greater is supported by cable bolting. Perimeter drives are
integrity of the mine over the mine life a detailed geotechnical positioned a minimum of 15 m away from stopes.
program is being carried out. Based on the mine planning procedures, stopes are designed
The broad aim of the program is to: by mine design engineers in consultation with the area mine
a. achieve minimum stope wall and crown failures; geologist and presented to the operating personnel. The
presentation is required to gain formal approval from the
b. achieve minimum backfill failures; underground production, development and services departments.
The final document incorporating their recommendations will
c. enhance existing ground support systems; and
then be issued. This document will have the following details.
d. determine stope design guide lines so that issues associated A three-dimensional view of the stope with planned and
with mining induced stresses can be effectively managed. actual development;
Some of the areas under consideration are: development level plans indicating actual and planned
a. geotechnical and ground condition modelling; development;
a summary of lateral and vertical development;
b. stope sequence planning and numerical modelling;
stope sequencing in the area;
c. in situ stress measurements; design considerations detailing surrounding stopes and fill
d. review of ground support standards; masses;
e. stope performance reconciliation; and geological information showing Cu and U3O8 grades, Cu:S
ratio and structural controls (to be provided by the area mine
f. backfill performance. geologist);
These studies will help to improve stope performance by stope scheduling and concurrent activities;
minimising dilution while managing mining induced stresses. preliminary ground support designs;
drill and blast design layouts and firing sequence;
Computer aided mine design ventilation during development and production (to be
Olympic Dam Operation currently has a combined mine provided by the senior ventilation engineer); and
planning system using Microstation and Datamine software. preliminary backfill design.
Both of these software packages run on Unix workstations.
Considerable in-house programming has been undertaken to best
Stope sequencing
utilise the capabilities of both of these packages and to ensure the
efficient exchange of design information between them. Upon the completion of preliminary stope designs, the sequence
Datamine and Microstation can also be linked to the Geology of stope extraction is determined. The mining cost including
Database and survey files to extract drilling and survey filling and geotechnical consideration such as mining induced
information. stresses and their regional behaviour, are the key factors to be
Mine Works Planner software, together with few other built in considered at this stage. It is anticipated that XPAC software
programmes is currently used for planning and scheduling which is currently being introduced will improve possible
purpose. Arrangements are being made to link the schedule to sequencing maximising Net Present Value.

128 Melbourne, Vic, 21 - 24 March 1999 Tenth Australian Tunnelling Conference 1999
OLYMPIC DAM OPERATION

FIG 2 - A stope with planned and actual development.

FIG 3 - A typical stope sequence.

Tenth Australian Tunnelling Conference 1999 Melbourne, Vic, 21 - 24 March 1999 129
S UGGALLA

Stope filling with cement aggregates (CAF) is a major The short-term scheduling is performed by operations on a
component of the mining cost. Primary stopes in many situations rolling three month basis and linked to the five year schedule.
need to be filled with 100 per cent CAF. For this reason smaller There is also a 12-day forecast for production bogging
primary stopes and larger secondary stopes are designed as (mucking, drilling, blasting and development) which details ore
standard practice. This is particularly important in areas where
sources and tonnages on a shift by shift basis.
the orebody is relatively narrow.
Once primary stopes are extracted there are a number of
alternate secondary stopes which are under pillar stress Ventilation
condition. These stopes will be subjected to a large and changing Effective ventilation is a major consideration in a successful
mining stresses. It is essential to understand the behaviour of in extraction strategy. Owing to the presence of uranium, the
situ stress in determining the successful extraction sequence of current underground mining practices at the Olympic Dam
the orebody. Wherever possible larger stopes along the main Operation is primarily governed by the ventilation resources. The
stress axis will be extracted first. This will effectively shadow the
principal contaminants in the underground are heat, diesel fumes,
extraction of smaller stopes. The stope sequence needs to be
designed to manage such effects. dust and radiation products. To create a satisfactory working
environment a number of ventilation design standards have been
The selection of primary/secondary stopes and their sequence established by the Olympic Dam Mine. The overall design
is essential with consideration given to the presence of structural
criteria are summarised in Table 1.
features and infrastructure in the area. Currently only a few
major geological structures have been identified at Olympic The mine operates under negative pressure with several Return
Dam. Air Raises located on the surface exhausting air from
underground.
Mine scheduling The overall ventilation requirement for the Olympic Dam mine
after the expansion will be 2915 m3/s.
Mine scheduling plays an important role in the design process.
In terms of ventilation the entire mine has been regionalised
The current production scheduling at the Olympic Dam Mine is
mainly based on a combination of Copper and Uranium grades, allocating a specific intake (fresh air) and exhaust (return air)
Cu/S ratio, ventilation and ore pass usage. The interaction of raise for each ventilation district. These intake and exhaust raises
mining activities on each stope has to be carefully analysed to are linked via perimeter drives and stope drill drives. Based on
ensure efficiency in the production cycle. the current mining standards each ventilation district has the
capacity to operate between one to four producing stopes at a
In scheduling, each stope is taken as an individual project with
the start and finish of production being the over-riding drive of time. Ventilation control in each district is achieved by the use of
all other activities. A five year production schedule is produced regulators, temporary parachutes, shotcrete barricades and
in a spread sheet format using the area stoping sequence trees. ventilation doors. The ventilation network has been designed
This information is then used in the scheduling package to such that stopes act under negative pressure with air being drawn
incorporate other activities such as development, drilling, from draw points (when open) and drill levels and exhaust
production and filling. through main ventilation returns.

TABLE 1
Mine ventilation design criteria.

Requirement Design criterion Reason


Minimum air velocity in all transport and personnel 0.5 m/s Heat control, diesel exhaust dilution
access openings (eg 15 m3/s for 30 m2 development)
Minimum air velocity in ore producing areas (not 1 m/s Control of radon decay products
including mined out areas which will be sealed and (eg 30 m3/s for 30 m2 development)
kept under negative pressure)
Minimum air velocity in development 0.5 m/s Heat and control of radon decay products
(eg 15 m3/s for 30 m2 development)
Maximum air velocity in horizontal or decline intake Unlimited
airways where employees travel or work
Range of air velocity in horizontal or decline intake 4 to 6 m/s Economic design
airways where employees travel or work
Maximum air velocity in downcast service shaft 10 m/s Movement of conveyances
Maximum air residence time after radon contact with 12 minutes Control of radon decay products
uranium ore in production areas before reaching
return airways
Velocity in downcast air shaft Up to 25 m/s Drag constraints
Velocity in upcast air shaft Below 7 m/s or above 12 m/s Raindrop entrainment
Re-entry time after blasting > 30 minutes Fumes dilution/removal
Ventilating air per kW of rated diesel engine power 0.040 m3/s Diesel exhaust dilution

Except where > 6 m/s and settled dust may become airborne, appropriate dust suppression measures must be taken.
(Source: Radiation management plan for mining engineering and ventilation control).
The overall ventilation for the Olympic Dam mine after expansion will be 2915 m3/s.

130 Melbourne, Vic, 21 - 24 March 1999 Tenth Australian Tunnelling Conference 1999
OLYMPIC DAM OPERATION

Drilling and blasting Mass Quality was ascertained. Virgin stress tests were carried out
to assess any significant influence of regional stress on the
Down holes are drilled (102 mm) by Atlas Copco Simba 4356S crusher complex.
electric hydraulic drilling rigs. Normal down hole parameters are
3.0 m burden and 4.0 m toe spacing. Up-hole rings are dumped
Hoisting
20 forward and drilled to 89 mm diameter by Solomatic jumbos
with 2.5 m burden and 3.5 m toe spacing. A powder factor of Crushed ore from the two fine ore bins will be discharged into
0.25 kg of explosives per tonnes of ore is generally maintained. two conveyors via two vibrating feeders. Ore will then be hoisted
Stope slots are opened up by firing into a 1.4 m diameter raise to surface by the newly constructed Sir Lindsay Clark shaft
bore hole. Ring designs are generated by the planning engineers which is equipped with a double compartment four rope hoisting
in consultation with the drill and blast engineer using the system. The skips are designed for bottom discharge with a
Datamine Rings package. payload of 36.5 tonnes (21.5 m3)

Ore handling Cavity monitoring system


Current ore handling practice is that trucks are loaded near stope Once a stope is mucked to empty, the stope void is surveyed
draw points and trucked to grizzlies. With the new system, ore using the Cavity Monitoring System (CMS). This is a system
from each stope will be tipped by a LHD directly to an ore pass developed by the Canadian Company, Noranda Technology
which is connected to a surge bin. . Centre. The CMS system consists of a laser unit in a motorised
head that is capable of being pushed 4 - 5 m into the stope. Once
Design of underground ore pass and rail haulage system the instrument is set up it can locate up to 50 000 points on
concentric 3600 circles. The CMS has the capacity to pick up
The Ore Pass System is a major component of the expansion stope voids up to 100 m in height when the visibility within the
project. It comprises 13 ore passes and 50 finger passes. stope is clear. The major advantage of the system is that it gives a
Tramming distance, the amount of ore to be fed through each of true volume of the void allowing stope reconciliation and stope
the ore pass and the stoping configuration were the three main performance evaluation.
criteria considered in designing the ore pass system. Ore from From the mine planning and design point of view CMS offers
each of the stope will be tipped through a grizzly consisting of the following advantages:
four panels of 1.2 m 1.2 m size into a 3.0 m diameter ore pass. Based on the CMS survey stope over-break and under-break
A portable rock breaker will be used to break over sized material. can be accurately estimated and adjacent stopes can be
Each ore pass is connected to a 4.5 m diameter surge bin below redesigned. This will be particularly helpful at the ring
which will have a capacity of around 1000 tonnes. The surge bin design stage to optimise stope recovery.
will be between 60 - 80 m high. Stope crown over-break can be clearly identified. This will
An automated rail haulage system will be installed on 64L be helpful in assessing crown support requirement in nearby
(-740 mRL) for ore transportation from surge bins to the crusher. stopes.
This is based on the LKAB Kiruna Mine which is the largest Possible sources of stope dilution can be identified.
underground iron ore mine in the world. The rail haulage system
will be totally computer controlled with no personnel travelling
Stope back filling
on the train. Once a surge bin exceeds a set minimum level of ore
the train will be directed to the respective ore chute. In the Olympic Dam Operation stope back filling plays a critical
Owing to the nature of the orebody, ore passes have been role in stope sequencing and the design process . Following the
designed at varied angles. The minimum dip angle has been set extraction, depending on the individual circumstances, stopes are
at 65. No ground support requirement for the ore passes has been filled with CAF and underground mullock. A typical CAF
mixture will have 57 per cent of crushed rock by wet weight,
anticipated at this stage. Owing to radiation and ventilation
26.5 per cent of deslimed mill tailings and sands, 2.5 per cent of
issues all ore passes have been designed in the fresh air side of cement, five per cent of pulverised fly ash and nine per cent
the mine and operate under negative pressure. Normally an ore neutralised tailings liquor producing a nominal fill strength of 3
pass can have three to five tipping points. Only one tipping point Mpa. Specific CAF mix designs exist to allow strengths to be
can be active at any one time. A top exhaust ventilation system delivered from 1.0 Mpa to 5.0 Mpa. The CAF plant has been
will be used to control reverse flow resulting from tipping into an upgraded and will continuously mix CAF in a pug mill at 6000
ore pass. m3/day.
Initially there will be two trains in operation, each containing Filling cost is a significant portion of the mining cost. The
14 cars, with a nominal capacity of 400 tonnes per train. Each possibility of reducing this cost while maintaining the minimum
mine car will have a capacity of 14 cubic metres. The rail system fill strength for the given stope geometry is currently being
will have a 1670 tonnes per hour haulage capacity. investigated. Some of the areas under investigation are CAF mix,
stope geometry CAF strength and continuous CAF delivery
Primary crushing systems. An overall review is being conducted to identify areas
where the non cemented fill proportion can be increased.
Based on the current design parameters a single train load of ore Regular communication between the engineers of the mine
can be unloaded into the dump station at a rate of 3000 design and backfill departments is essential to ensure maximum
tonnes/hour. This ore will be fed to the Gyratory crusher at the utilisation of resources and to get any cost benefit out of fill
base of the dump station directly. The Gyratory crusher will have placement.
a design capacity of 2000 tonnes/hour and crush to a maximum CAF production prior to the plant upgrade was a batching
size of 300 mm. process. After a predetermined mixing time fill mixture is
Design of the crusher station is one of the major tasks discharged into dump trucks with a holding capacity of 12 m3
undertaken by the underground expansion project. Prior to the which transport the fill to the stope fill hole. The existing plant
commencement of the excavation a detailed geotechnical has the capacity of 75 m3/hr while the new plant will have
evaluation was carried out in collaboration with Australian maximum a capacity of 350 m3/hr and will operate at 300 m3/hr.
Mining Consultants and Barrett, Fuller and Partners. As a part of This is achieved by continuous mixing in a Pug Mill with
the program a series of underground holes were drilled and Rock discharge in to CAF surge bins for loading in to CAF delivery

Tenth Australian Tunnelling Conference 1999 Melbourne, Vic, 21 - 24 March 1999 131
S UGGALLA

trucks of 15 m3 capacity. CAF is delivered to a rock dropper hole equipment such as LHDs can be more challenging than the track
which delivers to the top of the stope. Underground pipe work bound train system. Such a system however will relax some of
reticulation is currently testing with a view to establish a the existing ventilation standards improving system efficiency.
continuous delivery from the CAF plant in the longer term.
Stopes with combined CAF and rock filling will require a Availability of geological/geotechnical data in the design
detailed back fill design. Such designs are performed using process
Datamine Guide software. Assumptions made in such designs
are: Currently, preliminary on screen designs and stope sequencing
are determined with a limited geological and geotechnical data.
1. CAF rill angle =15; It is anticipated that in the future data will be available in an
2. mullock/rock rill angle = 37; on-screen format so that the design engineers can optimise the
final stope design taking into account this information.
3. CAF hole to be generated immediately beneath the fill hole;
4. rock fill cone generated at the tipping point; and Understanding the complexity of the orebody
5. leave 10 m CAF wall against adjacent stope/s to be extracted. Owing to the large size and complexity of the deposit it is
essential to understand the varying geological and geotechnical
Stope review characteristics in term of different mining areas. Mine designs
including ring designs can then be modified to suit local
Every effort is made to utilise information and experience conditions improving blasting efficiency while maximising
acquired during the production life of a stope in order to improve output.
the future design and planning process. Once the CMS is
completed, the mine design engineer will investigate factors such
as stope over-break/under-break, crown failure, stress related ACKNOWLEDGEMENT
problems, geological structure evaluations and variation of ring The author wishes to thank the management of the Olympic Dam
grades against actual tonnes produced. They will also collate Mine for the permission to publish this report. The input to this
information relating to drilling, blasting, ventilation, paper by personnel from the Technical Services Department is
development, drainage, concurrent activities that took place, also acknowledged.
draw point condition, ground support strategy adopted,
fragmentation, remote loader layout, trucking path, raise drilling,
CMS survey location and backfill process. Information gathered REFERENCES
is presented to both planning and operating personnel. Following Adriana, P, 1998. Three modern metal mines using rail system, World
the meeting, the mine design engineer will issue a Mining Equipment, 5:40-41.
recommendation/action statement. To ensure such a process is Cope, B, 1996. Geotechnical Programme (Internal Document).
successful, each relevant officer will need to maintain a record of Hardcastle and Richards, 1997. Engineering specification for Automated
events that took place within his/her area of responsibility. Underground Rail Haulage system (Internal Document), pp 1-21.
Jones, G, 1995. Optec gives MIM a head start on production, Australian
Future developments Mining, 9:60-61
Kinhill Engineers Pty Ltd, 1997. Olympic Dam Operation Environmental
Impact Statement (Internal Document) pp 1-10.
Tele-remoting
Olympic Dam Operation, 1998. Mine Planning Guide Lines (Internal
Ore from the stope is currently mucked using conventional Documents).
loader units. Remote loading is used only to allow retrieval from Olympic Dam Operation, 1993. Geology and Mining Technical Hand
the open stope areas to some distance away from the operator. It Book, pp 1-42.
is likely that this technology will be improved to a remote Philpott, S, 1997. Geotechnical Programme Requirement (Internal
control operator station system where the operator can be Document).
centrally located. Automation and remote control of mobile Western Mining Corporation, 1997. Ore Reserve Statement, pp 1-9.

132 Melbourne, Vic, 21 - 24 March 1999 Tenth Australian Tunnelling Conference 1999

Potrebbero piacerti anche