SAUDI ARAMCO ID/PID FORM REV 1 - 010109 REV 6 COS 03/31/2012

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
REFRIGERANT/ PIPING SATIP-K-001-07 30-Apr-13 HVAC
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

See See
1.1 Brazing Procedures See SATIP-S-060-08 Copper Piping
Remarks Remarks
See See
1.2 Brazer Qualifications See SATIP-S-060-08 Copper Piping
Remarks Remarks

2.0 MATERIAL RECEIVING

Refrigerant SAIC- SAIC-


2.1
Handling, storage and Preservation K-4025 K-4025 W S Weekly Inspection by Contractor QA/QC

Refrigerant SAIC- SAIC- Saudi Aramco shall be notified on initial delivery for
2.2
Receiving Inspection K-4025 K-4025 H W each location

3.0 INSTALLATION

Refrigerant Piping (Copper), Fittings


SAIC- SAIC- Saudi Aramco shall be notified on start of this activity
3.1 and Support Lay-Out
K-4026 K-4026 H W for each building or zone
Inspection

See SATIP S-060-08 Copper Piping

Refrigerant (Copper) Piping See See Copper piping is the most common type of pipe used
3.2
Inspection Remarks Remarks in Saudi Aramco Projects for Refrigerant Piping. Iron
and steel Piping shall be approved by CSD for
intended use.

Air Moving/Cooling Valve and


Apparatus Arrangement Installation
SAIC- SAIC- Saudi Aramco shall be notified on start of this activity
3.3 Inspection (Applicable to Direct
K-4027 K-4027 H W for each building or zone
Expansion Units)
Inspection

Also see SATIP-A-004-02 (Pressure testing ) for the


requirements of Pressure gauge, pressure relief valve
SATR- SATR-
3.4 Refrigerant Piping Pressure Test
K-4003 K-4003 H H setting and any other applicable requirements.
Note: Factory charged and sealed refrigerant tubing
shall not be field tested

Page 1 of 2
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 REV 6 COS 03/31/2012
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
REFRIGERANT/ PIPING SATIP-K-001-07 30-Apr-13 HVAC
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

SATR- SATR-
3.5 Refrigerant Piping Vacuum Testing
K-4004 K-4004 H H

See SATIP-N-001-01 Cold Insulation


See See
3.6 Pipe Insulation and SATIP-N-001-02 Hot Insulation
Remarks Remarks
as applicable

4.0 PRE-COMMISSIONING

4.1 Not Applicable

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1 adjust the levels of Saudi Aramco participation based upon the Contractors performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 2 of 2