Sei sulla pagina 1di 37

Bangalore Institute of Technology Water supply and Sanitation project

WATER SUPPLY AND SANITATION PROJECT

CONTENTS

1. Introduction 2

2. Objectives of planned water supply 4

3. Factors to be considered for water supply 4

4. Water quality standard for drinking water 6

5. Design period 7

6. Units of water treatment plant 8

7. Units of sewage treatment plant 9

8. Design of water treatment plant 11

9. Flow diagram of water treatment plant 26

10.Flow diagram of water supply scheme 28

11.Design of sewage treatment units 29

12.Flow diagram of sewage treatment plant 34

13.Bibliography 35

Extensive Survey Project Batch A2


1
Bangalore Institute of Technology Water supply and Sanitation project

1. INTRODUCTION

PLACE: - MELKOTE

In preparing schemes of water supply the duties of engineer are to collect all the
information that may prove useful for preparing plan and all the estimates of the project.

Before actual construction of water supply work is taken up in it is necessary to


prepare plan and the full schemes and also design the various component of the project.
The proper planning will ensure an economical and efficient functional scheme, which will
serve the various objectives in view efficient and with minimum expenditure and recurring
operational troubles

A WATER SUPPLY SCHEMES ESSENTIAL CONSISITS OF:

1) Works for collection of water.


2) Works for conveyance of water.
3) Works for treatment and purification of water and,
4) Works for distribution of water to the consumers.

In planning good water supply schemes a compromise between efficiency and


economic is generally decided and the schemes possessing at least defects and
professional advice and guidance is very essential for the schemes.

In the case of rural water supply schemes, Since the commutations are
generally small and poor and hence the various element of the scheme have to
be necessarily simple and comparatively cheaper requiring minimum skilled
supervision and maintenance .In the case, the sources are generally ground
water leading to special problems like fluorides, Iron, Sailing etc., One should
take of all these the problems while designing.

NECESSITY OF PLANNED WATER SUPPLY

Water is a chemical compound and may occur in a liquid form or in a solid form or
in a gaseous form .All these three form of water are extremely useful to man, providing
the luxuries and comforts, in addition to fulfilling his basic necessity of life .No life can
Extensive Survey Project Batch A2
2
Bangalore Institute of Technology Water supply and Sanitation project

exist without water since water is essential for life as air. It has been estimated that two
thirds of human body is constituted of water.

From the public health point of view, it is necessary that the water required for
their need must be invariably free from all type of impurities whether suspended or
dissolved in water and no risk should occur to the health of the public as a result of any
water contamination.

A public water supply or water works system has to be both from the point of view
of providing an adequate and reliable supply of water catering to all the public need
ensuring that the supply so made are not only portable but also fully protected against
every infection which might otherwise pollute water and cause outbreak of disease.

The planned water supply scheme should not only help in supplying wholesome
water to the people for drinking cooking, bathing etc.., so as to keep disease away and
there by promoting better health but it should also help in supplying water for fountains,
garden etc.., thus helping in maintaining better sanitation and beautification of
surrounding thereby reducing environmental pollution .The schemes should therefore
help in promoting wealth and welfare of the entire humanity as a whole.

Extensive Survey Project Batch A2


3
Bangalore Institute of Technology Water supply and Sanitation project

2. OBJECTIVES OF PLANNED WATER SUPPLY

1) To supply safe and wholesome water to consumers:


2) To supply water in adequate quantity, and
3) To make water easily available to the consumer so as to encourage
4) Personnel and base hold clean lines.

3. FACTOR TO BE CONSIDERED FOR WATER SUPPLY PROJECT


The various factors should be taken into consideration before designing any water supply
project is:

1. Population forecast.
2. Per capita supply.
3. Selection of source.
4. Quality requirement.
5. Distribution system.
6. Design period

I.POPULATION FORECAST
The recent population of a region is obtained by recent census figure and perspective
population as a result of growth, development, educational and industrial expansion etc..,
are estimated by followed methods.

i). ARITHMETICAL INCREASE METHOD:

This method is based upon assumption that the populations increase at a


constant rate i.e.., the rate of change of population with time (df/dt) is constant.

Thus dp/df =k

DP=>kdt.

Integrating between first and last available census we get,

Pe-Pf =k(te tf)

Where the suffix e and f represent the last and the first census
respectively. K represent average increase per census .This method gives
comparatively lower results.

ii). GEOMETRICAL INCREASE METHOD:

In this method, a graph is plotted from the available dates between time
and population. The curve is then smoothly extended unto the desired gear. This
Extensive Survey Project Batch A2
4
Bangalore Institute of Technology Water supply and Sanitation project

method however gives very approximate results, as the extensions of the curve
are done the intelligence of the designer

II.PER CAPITA DEMAND

It is the annual average amount of daily water required by one person and includes the
domestic use, Industrial and commercial use, public use, wastes, thefts etc.., It may be
therefore expressed as Liters per captia per day (LPCD).

Total yearly water required of the city

=365 x DESIGN POPULATION x PER CAPTIA DEMAND

Per capita supply varies as per region and the people living standard in the
region.

For the rural area per capita should be selected as per the following criteria.

1) Where house connection are not contemplated and supply through hand
pumps or central stand post, per capita supply shall not be less than 40 lpcd.
2) Where the house connections are contemplated the supply shall be at
least 70 lpcd.
3) A minimum of 135-lpcd areas preferably 150 for all residence provided
with full flushing systems with modern sanitary.

III. SELECTION OF SOURCE

The following order of priority may be given in the choice of suitable source among the
various sources available.

a) Water that required no treatment except disinfections to meet water


quality standard and would be supplied by gravity.
b) Water that requires no treatment except disinfections to meet water
quality standard but would require pumping.
c) Water that requires simple treatment like chlorination.

IV.QUALITY REQUIREMENT

The water required for domestic uses, particularly the water required for drinking must be
colorless, odorless, and tasteless. It should be free from turbidity and excessive of toxic.
The maximum permissible limits for physical, chemical and bacteriological standards
should satisfy the drinking water standard as given by ISI in the table shown.

These limits in table are ideal and safe for public supplies, therefore in village they may
not be followed rigidly due to the shortage of funds for treatment or due to

Extensive Survey Project Batch A2


5
Bangalore Institute of Technology Water supply and Sanitation project

lack of development .However, bacterial quality should no where be relaxed as to


avoid serious water borne disease.

4. WATER QUALITY STANDARDS FOR DRINKING WATER

Type of Type of Permissible E Absolute Max.Limits Remarks


characteristics impurity limits

Physical 1.Turbidity 5 10 On silica scale.

2. Colour 10 20 On cobalt scale.

3. Taste and 01 03

odor Threshold no.

Chemical 1. pH value 6.6 8.0

2. Hardness 75mg/ltr 110mg/ltr Expressed as CaCo3


Equilatew/s.

As per WHO
3. Total solids 500mg/ltr 1500 mg/lit international STDs.

-do-
4. Mg & Na 500mg/ltr 1000mg/ltr -do-
5. Chlorides. 200mg/ltr 400mg/ltr -do-
6. Calcium. 75mg/ltr 200mg/ltr -do-
7. Iron. 1.0mg/ltr -do-
8. Fluorides. - 1.5mg/ltr

Biological & Coli form Nil 1Coliform colony per -


micro-organic Bacteria 100m/n of B coli is
ltd.to 0.3 mg/ltr1per
100me

Radiological Emitters Nil - -

After a complete treatment of water, it becomes necessary to distribute it to a number of


houses and public places by means of distribution network. The distribution system consistof
pipes of various sizes, valves, water pumps, distribution reservoirs, hydrants, stand posts

Extensive Survey Project Batch A2


6
Bangalore Institute of Technology Water supply and Sanitation project

etc.., The pipes carry water to each and every house,roads,streets,while are controlled by
valves. Mainly in village water flow will be designed as gravitational so the pumping is not
required.

5. DESIGN PERIOD

The water supply schemes include huge and costly structure such as dams,
reservoir, treatment plants ,penstock pipes etc.., which cannot be replaced are
increase in their capacities easily and conveniently .For example the water mines
laid underground including distribution system cannot be replaced or added without
digging the road and disturbing the traffic .In order to avoid this future complication
of expansion the various component of water supply scheme are purposely made
larger so as to satisfy the community needs for a reasonable number of years to
come.

This future period or number of years far which a provision is made designing the
capacities of various components of water supply scheme is known as DESIGN
PERIOD.

Such a scheme which is designed for a design period of say X year is supposed to
satisfactorily serve the community need up to the end of x years .The design period
should neither be too long nor too short .The design period cannot exceed the
useful life of the components structure . Here the design period for water supply
scheme is taken as 20 year.

Extensive Survey Project Batch A2


7
Bangalore Institute of Technology Water supply and Sanitation project

6. UNITS OF WATER TREATMENT PLANT

Design of intake well and screen:

The intake well is a circular or rectangular well with circular ends


located in a river bed, so that it always remains surrounded with water, even
during low flood stage. The well is built in masonry or concrete, and is raised
above the river HFL and covered at the top by wooden sleepers etc; as to make
it approachable from the river bank through a foot bridge arrangement.
Screens are generally provided in front of the intake works, so as to
exclude the large sized particles. Screens are normally inclined at about 45 -
60 to the horizontal, so as to increase the opening area to reduce the flow
velocity.
Pre-sedimentation Tank:

In order to remove the large sized and rapidly settleable solids to reduce
turbidity, it is proposed to construct a pre-sedimentation tank and raw water
storage.

Cascade type Aerator:

Since the raw water does not contain too much color and odor, only nominal
aeration is proposed. This unit will help in maintaining the wanted oxygen levels in
water , remove dissolved iron , manganese, CO2 and H2S gases as well as color and
taste caused by volatile oils etc.

Combined Coagulation cum Sedimentation Tank:

It shall be constructed to allow formation of flocs and settlement of


particles. The fine colloidal particles present in water, gets attracted and absorbed in
these flocs, forming the bigger sized flocculated particles.

Rapid Gravity Filter:

Filter units shall be constructed to filter the sedimented water, as usual,


with provision of wash water tank. Rapid Gravity Filter is the best and most
economical and, therefore invariably used for treating public supplies, especially for
large towns and city. The treated water is not so much safe as obtained from slow
sand filter and need further treatment before they can be supplied to the public.

Chlorinator:

Extensive Survey Project Batch A2


8
Bangalore Institute of Technology Water supply and Sanitation project

Considering the remote area and difficulty in transporting and storing the
chlorine gas cylinders, it has been decided to use bleaching powder for disinfection
by providing gravity type of chlorinator. Bleaching powder mixed clear water will be
fed by gravity into clear water tank where contact period shall be more than half
hour, which is the acceptable limit.

7. UNITS OF SEWAGE TREATMENT PLANT


Primary Sedimentation Tank

The Clarification of sewage by the process of sedimentation can be affected by providing


conditions under which the suspended material present in sewage can settle out. This is
brought about in specially designed tanks called Primary Sedimentation Tanks.

Trickling Filters

Trickling filters are now almost universally adopted for giving secondary treatment to
sewage. These filters, also called as percolating filters or sprinkling filters, consist of tanks of
coarser filtering media, over which the sewage is allowed to sprinkle or trickle down, by
means of spray nozzles or rotary distributors. The percolating sewage is collected at the
bottom of the tank through a well designed under-drainage system. The purification of the
sewage is brought about manly by the aerobic bacteria, which form a bacterial film around
the particles of the filtering media. The action due to the mechanical straining of the filter
bed is much less. In order to ensure the large scale growth of the aerobic bacteria, sufficient
quantity of oxygen is supplied by providing suitable ventilation facilities in the body of the
filter; and also to some extent by the intermittent functioning of the filter.

Secondary Sedimentation Tank

A filter does remove only a very small percentage of the finely divided suspended
organic matter present in sewage, while the majority of this organic matter
undergoes a change of character, only due to the biological oxidation and
nitrification taking place in the filter. Due to this aerobic oxidation and nitrification
that takes place in the filter, the organic solids are converted into coagulated
suspended mass, which is heavier and bulkier, and would thus settle down by
gravity, if allowed to dos so in sedimentation tanks. The effluent of the filter is,

Extensive Survey Project Batch A2


9
Bangalore Institute of Technology Water supply and Sanitation project

therefore, passed through a sedimentation tank, called Secondary settling tank or


Humus Tank.

Sludge Digestion Tank

The sludge withdrawn from the sedimentation basins contains a lot of putrescible
organic matter, and if disposed of without any treatment, the organic matter may
decompose, producing foul gases and a lot of nuisance, pollution, and health
hazards. In order to avoid such pollutions, the sludge is, first of all, stabilized by
decomposing the organic matter under controlled anaerobic conditions, and then
disposed off suitably after drying on drying beds, etc. The process of stabilization is
called the sludge digestion; and the tank where the process is carried out is called
the sludge digestion tank.

Three distinct stages have been found to occur in the biological action involved in
the natural process of sludge digestion tank. These stages are:

(i) Acid fermentation;


(ii) Acid regression; and
(iii) Alkaline fermentation.

Sludge Drying Bed

Sludge drying beds are open beds of land, 45 to 60 cm deep, and consisting of about
30 to 45 cm thick graded layers of gravel or crushed stone varying in size from 15 cm
at bottom to 1.25 cm at top, and overlain by 10 to 15 cm thick coarse sand layer.
Open jointed under-drain pipes (15cm dia) @ 5 to 7 cm c/c spacing are laid below
the gravel layer in valleys, at a longitudinal slope of about 1 to 100. The beds are
about 15 X 30 m in plan, and are surrounded by brick walls rising about 1 meter
above the sand surface.

Extensive Survey Project Batch A2


10
Bangalore Institute of Technology Water supply and Sanitation project

8. DESIGN OF WATER TREATMENT PLANT

Calculation of water Demand

1. Minimum domestic water consumption as per IS- 1172-1993 required


water = 200 lit/hd/day

2. Parks-3.5lit/ sq m/day

3. Schools & colleges (day)- 45lit/hd/day

4. For Mattas 45lit/hd/day

Assumed area of park -10,000 sq m


No of Schools & Colleges -5no, and having 200 students for each
No of mattas 15no, Capacity of each 80members

Water required

Domestic - 200*25,000 =50,00,000lit/day


Parks - 10,000*3.5 = 35,000lit/day
Schools & Colleges - 5*200*45 = 45,000lit/day
For Mattas 15*45*80 = 54,000lit/day
Total = 51,34,000lit/day

Maximum water Demand = 1.5*5134 = 7701Cum/day

Discharge = 7701.0/(24*60*60)

= 0.0891Cum/sec

Extensive Survey Project Batch A2


11
Bangalore Institute of Technology Water supply and Sanitation project

DESIGN OF RAISING MAIN


Using Leas formula for most economical diameter

D=0.972Q to 1.22Q

D=23.81cm to 29.8cm

Hence provide 30 cm pipe

Velocity = Q/A = 0.0891/0.00706

= 1.26m/sec

DESIGN OF PUMPS

Calculations of total head:-

H=Hs + Hd + Hf

Hs = Section head

Hd = Delivery head

Hf = Head loss due to friction

Hs = 952.0-944.5=7.5m

Hd = 961.0-952.0=9.0m

Hf = 4flv2/2gd

= 0.025*50*1.262/2*9.81*0.3

= 0.337m

Total Head H= 16.5+0.337= 16.837

Adding 0.05% as Minor losses = 16.837*1.05= 17.679m

Break Horse power:-

Extensive Survey Project Batch A2


12
Bangalore Institute of Technology Water supply and Sanitation project

BHP = wQH/ *.735

= 9.81*0.0891*17.67/0.65*0.735

= 32.34 ~ 35Hp

Design of Primary Sedimentation tank:-


Discharge = 7701cumec/day

Detention time = 3hours

Depth of sedimentation tank = 2.5m

Specific gravity = 2.65

Velocity Vs = 0.23mm/sec

Volume of water to be treated / hour = 7701/24

= 320.87cumec / hour

The Raw water to be treated for a detention period = 7701*3/24

= 962.62cumec

Circular sedimentation tank:-

Depth of sedimentation tank = 2.5m

Surface Area = 962.62

2.5

= 385.05sq m

Diameter of circular tank = 22.14m

Effective settling zone = 22.04


Extensive Survey Project Batch A2
13
Bangalore Institute of Technology Water supply and Sanitation project

= 11.07

Provide 20% of Diameter of tank for Inlet zone = 4.43m

Surface flow rate = 7701

385.05

= 20m/day

Horizontal flow velocity = 20

86400

= 0.00023m/sec

Weir loading = 7701/2*13.285

= 92.258cumec/m/day

Inlet velocity = Q = a*v

0.0891 = *22.142*v/4

V = 0.00023m/sec

Sludge collecting capacity, assume suspended solid particles in water 300mg/lit

Sludge collection = 7701*106*300/105

= 2310lit/day

Extensive Survey Project Batch A2


14
Bangalore Institute of Technology Water supply and Sanitation project

Inlet pipe

Provide 0.15m dia

Q = a*v

0.0891 = *.0152*v/4

V = 5.04m/sec

V = 2gH

H = v2 /2g

H = 5.042/2*9.81

H = 1.29m

Design of raw storage tank

Capacity of water to be stored on tank approximately one day demand of water.

Quantity of water should be stored on tank = 7701Cum

Depth of water stored in a tank =4.5m

Provide circular tank. D = dia of the tank

D = 4*A/

D = 4*1711.32/

D = 46.67m

Extensive Survey Project Batch A2


15
Bangalore Institute of Technology Water supply and Sanitation project

Design of inlet well

Providing an oblong shaped inlet well, with openings provided at 3 levels.

The openings shall be fitted with bar screens made of 20mm dia steel bars of 50mm
openings. Let the velocity through the bar screens be limited to 0.16m/s.

The area of openings required at each level = Q/v

= 0.133/.16

= 0.831sq m

Let us provide 1m height of screen openings; then the clear length of the openings
required = 0.831m

No. of openings required = 0.831/0.05 = 17no

No. of bars=17

Length occupied by 20mm dia bars = 17*0.02= 0.34m

Total length of screen = 0.831+0.34 = 1.171 1.2m

Design of pipe connecting intake well to jack well.

Therefore, Q=0.133cumec

V=0.16met/sec

Area of pipe = Q/V

= 0.133/0.16

= 0 .831m2
Extensive Survey Project Batch A2
16
Bangalore Institute of Technology Water supply and Sanitation project

Therefore, d = 4*0.831/

d = 1.028m

Provide jack well dia = 10m.

Design of Cascade Aerator:

Water requirement = 7.70 MLD

Q= 0.0891m/s

Provide 3 steps, dia ratio 1:2:3.

Depth of wall =0.75m

Diameter of weir proposed

Top = 1m

Middle = 2m

Bottom = 3m

Sedimentation aided with coagulation tank:


Average daily consumption = Volume of water treated per day =7701 m3

Assume detention period of 4hrs.

Quantity of water to be treated = 7701*4/24 = 1283.5m3

.. Capacity of tank = 1283.5 m3 1284m3

Assuming depth of water in tank = 4m , we have,

Plan area = Breadth*L ength= capacity/depth

= 1284/4 = 321m3

Take Breadth = 9m

.. length = 321/9 = 35.67m 36m

Settling tank dimension = 36x9x4

Providing an extra depth of 0.5m at the starting tank ,I,e; a depth of 4.5 at the start and
providing a slope of 1in30 along the length.

Extensive Survey Project Batch A2


17
Bangalore Institute of Technology Water supply and Sanitation project

We get, 4.5+37/30 = 5.7m, at the end.

Design of flocculation chamber:

In addition to 15m length of settling tank, the floc chamber at the entry has to be provided
as half the depth of the sedimentation tank

I.e. 2.5/2 =1.25 m

1.5 m

Detention time = 20 minutes

= 0.08912060

= 106.92cum

Surface area = 106.92/1.5

= 71.28m2

Provide rectangular chamber 1:2ratio

Width of chamber = 6m

Length of chamber = 12m

Thus, floc chamber is of size 6.0 m 12m 1.5m.

Coagulation sedimentation plant:

Coagulant added is Alum.

Given pH=8

Extensive Survey Project Batch A2


18
Bangalore Institute of Technology Water supply and Sanitation project

The coagulant added : ALUM

Alkalinity of water is 4.5mg/lit of CaCO3(nat)

Quantity of water treated =7.701 MLD

Quantity of filter ALUM required at 20 mg/lit = 20 x 7.701 x 106 mg/day

=20 x 7.701 = 154 kg/day

Thus the following chemical reaction will take place:

Al2(SO4)3.18H2O+3Ca(HCO3)22AL(OH)3+3CaSO4+18H20+6CO2

CaCO3+H2O+CO2Ca(HCO3)2
CaCO3CaO+CO2

The molecular weight shall be:

AL2(SO4)3.18H20={(2x27)+3x(32+(16x4))+18x((1x2)+16)}=666gm

Ca(HCO3)2=40+(1+12+48)x2=162gm

CaO=40+16=56gm

It is clear that from the above equations 3x100parts of CaO3 will produce the same alkalinity
as that off 660mg of ALUM

Quantity of CaCO3 required to produce the same alkalinity which is equal to 20mg/litre

=>(3x100x20)/666=9.01mg/lit

The natural alkalinity available in CaCO3 =4.5mg/lit

Additional alkaline required to be added to form the lime=40.5mg/lit of CaCO3

Thus the above equation clearly states that 40 parts of CaCO3 produce by 56 parts of CaO.

Therefore CaO required = (4.5 x 56)/100 = 2.52 mg/lit

But Quick lime required =(2.52 x 100)/80 = 3.156 mg/lit

The quantity of lime required for treatment = 7.701 x 106 x 3.156 mg/day

= 24.30 kg/day

And, from above result,

Extensive Survey Project Batch A2


19
Bangalore Institute of Technology Water supply and Sanitation project

the quantity of alum =154 kg/day

or, alum = 154/(24 x 3600) = 0.0018kg/sec.

This coagulant is dispensed using a dry feeding device. These are in the form of a tank with a
hopper bottom. Agitating plates are placed inside the tank so as to prevent the arching the
coagulant. The coagulant is in the powdered form and is allowed to fall in the mixing basin.
Its dose is regulated by the speed of a toothed wheel or a helical screw. The speed of the
toothed wheel or the helical screw is controlled by connecting it to a venturi device installed
in the raw water pipes bringing the water to the mixing basin.

Mixing the coagulant in a mixing basin with baffle walls.


Design:

Assume Velocity of flow = 0.3 m/sec

Detention time = 30min.

Volume of water to be treated per day = 7701m3/day

.. Volume of water required to be treated in 30min = Capacity of tank = 7701*30/(24*60)

= 160.43 m3

Length of flow = velocity*Detention period

= 0.3*30*60 = 540m

The required c/s between each baffle is assumed to be 0.5m.

.. Depth of water in the basin = 0.29/0.5 = 0.58

0.6m

The clear opening between end of each baffle is kept equal to 1.5 times the distance
between baffles = 1.5*0.5 = 0.75m

Assume clear with of clear compartment as 9m.

Effective length of each channel = clear width of each compartment (2*0.5 of clear
opening)

= 9 (0.5*2*0.75)

= 8.25m

.. No. of channels = Total flow length/eff. Flow length of each channel


Extensive Survey Project Batch A2
20
Bangalore Institute of Technology Water supply and Sanitation project

= 540/8.25 = 65.45

66

.. The total no. of channels =66 ; and 66/2 = 33 in each half.

Clear length of tank excluding baffle walls and side walls = No. of channels x distance b/w
baffles

= 33*0.5 =16.5m

Assume thickness of baffle = 7.5cm

.. Overall inside length of tank = 16.5 + ( (7.5/100) x no. of baffles)

= 16.5 + ( (7.5/100) x (33-1))

= 18.9m 19m.

Sludge treatment:
The sludge collected from the primary and secondary sedimentation tanks gets stored in a
large storage tank. From here it is taken to the sludge drying beds. Once the water from the
sludge drains into the channel after passing through the sand and gravel layers over a period
of one week, the dry sludge is taken out manually and transported elsewhere.

Design of sludge drying beds

Quantity of sludge generated per day = 2310 litres/day

= 2.310m3/day

Height at the starting of the sludge bed = 2.5m

.. Cross sectional area of the bed = 4.5/2.5 = 1.8m2

Assuming width to be 1.2m, we have,

Length of the bed = 1.8/1.2 = 1.5m

Providing a sand layer of depth 1.5m and a gravel layer of depth 1.5m, we have,

Total height at the start of the sludge bed = 2.5+1.5+1.5 = 5.5m

Providing a gradient of 1in10 along the width, we have,

Depth at the end of 1.2m ,i.e, depth at the channel transporting the water from the sludge
beds

= (2.5+1.2/10)+1.5+1.5

= 2.62+1.5+1.5 = 5.62m
Extensive Survey Project Batch A2
21
Bangalore Institute of Technology Water supply and Sanitation project

Now there will be 3 such units on the either side of the channel.

Design of Rapid sand filters:

General provisions
1. Required flow of filtered water = 7.701 MLD

2. Quantity of back wash water used = 3% of filter output

3. Time lost during back washing = 30 minutes

4. Design rate of filtration = 500lit/sq.m/hr.

5. Length to width ratio =1:2.5

6. Under drainrage system = central manifold.

Filter media

Fine grain - (3.5mm-5mm)

Coars grain - (3mm-6mm)

Fine sand - (0.52mm effective size)

Filter water required per hour = 320.87cum/hr

Design flow for filter after accounting for backwash water (3%) & washing time
(20min)

= 320.87(1+0.03)24/23.5

= 337.53cum/hr

Plan of filter required = 337.53/.5

= 675.06 sq m

Generally the plan area of filter unit is kept as 10 sq m to 80 sq m

Provide 1 unit if 80 sq m

Size of tank 12.65m 6.35m.

Extensive Survey Project Batch A2


22
Bangalore Institute of Technology Water supply and Sanitation project

Hence provide 8 filter unit

Now, let a manifold and lateral system be provided below the filter bed, for receiving
the filtered water and to allow back washing for cleaning the filter. This consists of central
manifold pipe with laterals having perforations at the bottom.

.. Total area of perforations = 0.2% * filter area

= (0.2/100)*(6.35*12.65) m2

= 0.16 m2

Assuming the area of each lateral = 2 times the area of perforations

Total area of laterals = 2*Total area of perforations

= 2*0.1.6 m2 = 0.32 m2

Assuming the area of manifold to be about twice the area of laterals,

The area of manifold = 2*0.32 = 0.64m2

.. Dia of manifold (d) is given by,

/4*d2 = 0.64

.. d = 0.7m

Hence, use a 70 cm dia manifold pipe laid lengthwise along the centre of the filter bottom.
Laterals running perpendicular to manifold (widthwise) emanating from the manifold may
be laid at a spacing of say 15cm. The number of laterals is then given as,

= 12.65/0.15 = 84.33 say 85

On the either side of manifold. Hence use 170 laterals in all, in each unit.

Now, length of each lateral = (width of filter/2) (Dia of manifold/2)

= (6.35/2) (0.7/2)

= 2.82m

Now, adopting 13mm dia perforations in the laterals, we have,

Total area of perforations = 0.16

= 1600cm2 = x*(/4)*(1.3)2

Where x = Total no. of perforations in all 170 laterals.

.. x = 1600*(/4)*(1/1.3) = 966.64 say 967


Extensive Survey Project Batch A2
23
Bangalore Institute of Technology Water supply and Sanitation project

.. No. of perforations in each lateral = 967/170 = 5.68 say 6.

.. area of perforations per lateral = 6*((/4)*(1.3)2) cm2

= 7.96 cm2 .

Now, area of each lateral = 2*Area of perforations per lateral

= 2*7.96

=15.92cm2

.. Dia of each lateral = (15.92*(/4))

= 3.53cm

Hence, use 170 laterals each of 3.53cm dia, @ 15cm c/c, each having 4 perforations of
13mm size, with 70cm dia manifold.

Disinfection process:
Chlorination:

Assume the chlorine dosage rate to disinfect water be 3PPM.

Therefore, chlorine requirement = Avg quantity of water dosage

=7.701106310-6

= 23.10 kg/day

Generally chlorine is stored for 3 months

Therefore chlorine for 3 month = 23.1090

=2079kg

Therefore no. of chlorine cylinder required = 12+1 stand by.

Design of the raising main:


Using the empirical formula given Lea, dia of the pipe= 0.972 to1.22Q

Q = 7.701 MLD

Q = 0.0891

D = 1.220.089
Extensive Survey Project Batch A2
24
Bangalore Institute of Technology Water supply and Sanitation project

= 36.4 cm

40 cm

Therefore provide 30cm dia pipe

.. area of pipe = 0.07m2

.. velocity = Q/A = 0.0

= 1.27m/s

Design of pump.
To pump water from the treatment plant to water storage tank (over head tank)

H = Hs + Hd + Hf

Hs= 3m

Hd = 100m

Hf = 4flv2/2gd

= 4*.0075*1250*1.272/(2*9.81*.3)

= 10.27m

Total head = 3 + 100 + 10.27 = 113.3m

Brake horse power of the pump (BHP)


Assume efficiency of pump as 0.65

BHP = WQH/*0.735

= (9.81*0.0891*113.3)/(0.65*0.735)

BHP =207.28H.P.

Assume the capacity of pump available in the market : 50H.P, 100H.P, 150H.P, 200H.P,
250H.P, 500H.P, 750H.P, 1000H.P,

.. BHP provide = 250H.P

Extensive Survey Project Batch A2


25
Bangalore Institute of Technology Water supply and Sanitation project

Design of clean water reservoir:


Treated water is stored in clear water reservoir = 7.701 MLD

Since the pumping from clear water reservoir to distribution tank is for 24 hrs,
detention period of 24hr is provided in clear water reservoir to ensure 24 hr supply
capacity of clear reservoir.

Capacity of clear water reservoir = 7.70124/24

=7.701 MLD

= 7701cum

Assuming effective depth = 4.50m

Plan area required =7701/4.5

= 1711.3

Provide circular tank

Area = D2/4

1711.33 = D2/4

D = 46.6

.. D = 47m

Design of overhead tank:


Assuming following pattern of % draw off from daily supply

7.00am-8.00am 30% = 2.31MLD

8.00am-5.00pm 35% = 2.69MLD

5.00pm-6.30pm 30% = 2.31LD

6.30pm-7.00am 5% = 0.385MLD

Total storage req. = 7.7MLD

Providing 3 hrs of static storage

Capacity = 7.710003/24

Extensive Survey Project Batch A2


26
Bangalore Institute of Technology Water supply and Sanitation project

= 962.5cum

Assume depth = 4.5

Dia = 16.5

Therefore dia of overhead tank= 9m and depth =3m and distribution mains are designed
for peak demand i.e. for 2.69 MLD and diameter of main is 25cm.

Extensive Survey Project Batch A2


27
Bangalore Institute of Technology Water supply and Sanitation project

9.Flow diagram of water treatment plant

Extensive Survey Project Batch A2


28
Bangalore Institute of Technology Water supply and Sanitation project

10. FLOW DIAGRAM OF WATER SUPPLY SCHEME

Extensive Survey Project Batch A2


29
Bangalore Institute of Technology Water supply and Sanitation project

11. DESIGN OF SEWAGE TREATMENT UNITS

Quantity of water supplied = 7.701MLD

Assuming 80% of supplied water becomes sewage

=0.87.701106

=6.16MLD

Assuming detention period = 2hr

Quantity of sewage to be treated in 2hr i.e. capacity of tank

Q =6.162/24

= 0.513 MLD

= 513.4cum

Now, assuming flow velocity = 0.3m/min

The length of tank req. = vel. Of flow detention period

= 0.3260

= 36m

c/s area of the tank req.= capacity of tank/length of tank

= 513.4/36

= 14.26m2

Assume effective depth = 3mc

The width of tank = area of c/s /depth

= 14.26/3

= 4.75m

Assume free board = 0.5m

Overall depth =4.75+0.5 = 5.25m

Extensive Survey Project Batch A2


30
Bangalore Institute of Technology Water supply and Sanitation project

Therefore dimensions of primary sedimentation tank are 36 m 4.75m 5.25m.

Design of trickling filter:

Assume BOD =150 ppm

Total BOD present in sewage to be treated per day = 6.16150

= 924kg

Assume organic loading = 1500kg/ha-m/day

Volume of filtering media req. = 92410000/1500

= 6160 cum

Assuming effective depth = 2m.

We have

The surface area of filter req. = 6160/2

= 3080sqm

Using 15 m dia circular trickling filter units

Area of each unit = 176.71 sq m

No of units req = 3080/176.71

= 18 nos

Check for Hydraulic loading

Assume Hydraulic loading = 25ML/ha/day

Surface area required = total sewage to be treated per day/hydraulic loading per day

= 6.1610000/25

= 2464sqm

Surface area chosen 3080sqm >2464sqm, therefore safe.

Extensive Survey Project Batch A2


31
Bangalore Institute of Technology Water supply and Sanitation project

Design of sec. Sedimentation tank:


Assume detention period = 1.5hr

We have capacity of tank = 6.16(1.5/24)

= 0.385

capacity of tank = 385cum

Volume of each conical tank=V= (1/3) (d2/4) depth

Using 2 numbers of 5.0m depth of each tank, we have total volume required for all
2

Tanks = 385/5

= 77sq m

Therefore dia d = 9.9m

10m

Hence use 2 tanks with Dia of 10m and height of 5.0m and 1 stand by.

Design of Sludge digestion tank:


Assuming suspended solids in raw sewage = 300 ppm.

Moisture content = 85%

Therefore suspended solids in 6.16MLD of sewage flowing per day

= 3006.16106/106

= 1848 kg

Assuming that 65% solids are removed in primary settling tank, we have

Wt of solids removed in primary settling tank = 0.651848

= 1201.2 kg/day

Assuming that the fresh sludge has o m c of 95%, we have 5 kg of dry solids make
100 kg of wet sludge

And 1201.2 kg of dry solid will make = (100/5)1201.2

= 24024kg of wet sludge/day

Extensive Survey Project Batch A2


32
Bangalore Institute of Technology Water supply and Sanitation project

Assuming the sp.gr. Of wet sludge =1.02

i.e. unit wt = 1020 kg/cum

The volume of raw sludge produced per day = V1 = 24024/1020

= 23.55 cum/day

Now, the volume of digested sludge V2 at 85% m c is given by

V2= V1 [100-P1/100-P2]

= 23.55[100-95/100-85]

V2 = 7.85cum/day

Now, assuming the digestion period as 30 days, we have the capacity of required
Digestion tank = [v1-2(v1-v2)/3]t

= [23.55-2(23.55-7.85)/3]30

= 392.5 cum

Provide 5m depth cylindrical tank

C/s area of tank = 392.5/5

= 78.5 sq m

Dia of tank= d = 10 m

Disposal of digested sludge:

Volume of wet sludge from sewage = 23.55cum

And let it spread in 20 cm layer on under drained bed then,

Area of bed required = 23.55/0.2

= 117.75 sqm/day

Under Indian tropical condition , the bed get dried about 10 days and hence taking 2
weeks as Avg drying time = 52/2

= 26 times in an year

Therefore area of bed required per year = 117.75365/26

= 1653.03 sq m
Extensive Survey Project Batch A2
33
Bangalore Institute of Technology Water supply and Sanitation project

Making 100% allowance for space for storage, repair, and resting of beds etc, we
have

The total required area of beds = 2*1653.03

= 3306.06sqm

Using 1025 m beds we have no of beds required = 3306.06/(10*25)

No of beds required = 13.22

No of beds required 14beds

Provide 14 beds with size as

Area = 3306.06/14

= 236.15 sq m

Using width = 10m

Length = 236.15/10

=23.61m

Provide 14 no of (1023.61) m beds.

Extensive Survey Project Batch A2


34
Bangalore Institute of Technology Water supply and Sanitation project

12. FLOW DIAGRAM OF SEWAGE TREATMENT PLANT

Extensive Survey Project Batch A2


35
Bangalore Institute of Technology Water supply and Sanitation project

13. BIBLIOGRAHY

Environmental Engineering 1 S K GARG

Environmental Engineering 1 B C PUNMIA & ASHOK JAIN

Environmental Engineering II S K GARG

Environmental Engineering II B C PUNMIA & ASHOK JAIN

Extensive Survey Project Batch A2


36
Bangalore Institute of Technology Water supply and Sanitation project

Extensive Survey Project Batch A2


37

Potrebbero piacerti anche